descriptions of the procedure of measurement and valuation of variation. In PWD 203A (Rev. 10/83), clause 25 (b) refers to the measurement and valuation of variation.
(i) The rates in the Bills of Quantities after adjustment if necessary as provided in Clause 26 (d) hereof, shall determine the valuation of work of similar character and executed under similar conditions as work priced therein: (ii) The said rates, where work is not of similar character or executed similar conditions as aforesaid, shall be the basis of rates for the same, so far as may be reasonable, failing which a fair valuation thereof shall be made by the S.O.; (iii) The rates in the Bills of Quantities shall determine the valuation of items omitted, provided that if the omission substantially vary the conditions under which any remaining items of work are carried out, the rates of such remaining items shall be valued under rule (ii) of this clause.
Clause 24 in GCW form provides the procedures for adjustment of the Contract Price in very simple manner: Adjustment of the Contract Price shall be determined through consultations between the Owner and the Contractor. However, if an agreement on adjustment to the Contract Price is not reached between the Owner and the Contractor within ( ) days of initiating consultations, the Owner shall determine the adjustment of the Contract Price, and the Owner shall notify the Contractor of the adjustment.
We observe that there is no detailed procedure to settle the contractors claim of additional payment in GCW, whilst the PWD 203A (Rev. 10/83) provides the detailed procedure in which the contractor has to give the notice of his intention of claim and is given time to submit full particulars of all claims until 3 months after practical completion of the Work.
As to the settlement of an extension of time, the PWD 203A (Rev. 10/83) Clause 43 provides, the S.O. shall so soon as he is able to estimate the length of the delay beyond the date or time aforesaid make in writing a fair reasonable extension of time for completion of the Work The GCW Article 23 provides that Any adjustment of the Construction Period shall be determined through consultations between the Owner and the Contractor.
In short, PWD 203A (Rev. 10/83) provides detailed rule of change or claim in the Conditions of Contract. On the contrary, GCW does not provide the procedure of change or claim. It seems that there is a large extent of flexibility of the procedure in GCW, whilst flexibility of the procedure is limited in PWD 203A (Rev. 10/83).
In Japan, the Government and the Contractor often have opportunities to enter a contract again and again. In such a business environment, the both parties acknowledge the business practice to reach an agreement of Change of Contract Sum which is not mentioned in the Conditions explicitly. In practice, more often than not, the Government plays a leading role in changing the Contract Sum. As has been described previously, the PM is the representative of the Government. There is no third party in contractual relationship in GCW. In such a case, people may think that there would be many disputes because the government or PM would be likely to make a decision always favorable to the government. But the mutual-trust has been historically formed between the Government and the Contractor. In other words, the Contractor believe that all the Governments decisions should be made not on the basis of the Governments own benefit or the Contractors benefit but on the basis of social benefits, and that the Government has the ability to make correct decisions. On the other hand, the Government believes that the Contractor meekly obeys the Government decisions. It has been believed that this mutual-trust relationship is always guaranteed by the long-term business relationship between the Government and the Contractor in the domestic construction market. As far as such a relationship exists, GCW form can be said to be efficient. But, the question of transparency should be asked as to validity of variations.
Having said as above, however, it is not to say that there exists no mutual-trust relationship in Malaysia. Negotiations are held in PDW 203A (Rev. 10/83) when new prices or rates must be fixed in case of the situation mentioned in Clause 25 (b) (ii) and (iii). To reach an agreement by negotiations, the mutual-trust relationship between the parties is necessary.
4 Conclusion
This paper identified the specific characteristics of PWD 203A (Rev. 10/83) in Malaysia and GCW in Japan by comparing the procedures of variation. Standard forms of Contract are usually revised so as to suit for the domestic specific situation at times. The significant characteristic of PWD 203A (Rev. 10/83) is the administrative provisions. While it is often the case with public works that the government interferes the decision of the S.O. or Superintendent or the Engineer, a standard form of contract seldom provides explicitly the governments right to interfere or to limit the S.O.s power. The authors point out that this aspect may have impact on the S.O.s ability to practice the concept of impartiality. On the other hand, a characteristic of GCW is that the provisions are very simple and the flexibility of procedure of fixing the measurement and valuation of varied work is extremely large.
In this paper, differences of only variation procedure are investigated. The real purpose of the comparative study of the standard forms of contract is to explore the substantial difference in philosophy or business practice in each country which is not mentioned in the forms of contracts. In the future, through comparative studies in other aspects, the reason why each characteristic of a contract form has been formed must be proven from the viewpoints of history, culture and business practices.