0 évaluation0% ont trouvé ce document utile (0 vote)
15 vues4 pages
JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Rev. As of 27 Dec 2010 Positive Negative 1 Main Substation: Additional Access fromswitchgear Roomto Cable Space Access fromoutdoor only.
JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Rev. As of 27 Dec 2010 Positive Negative 1 Main Substation: Additional Access fromswitchgear Roomto Cable Space Access fromoutdoor only.
JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Rev. As of 27 Dec 2010 Positive Negative 1 Main Substation: Additional Access fromswitchgear Roomto Cable Space Access fromoutdoor only.
Log List for SH Comments (Building Works) Rev.2 As of 27 Dec 2010 Positive Negative 1 Main Substation: Additional Access fromSwitchgear Roomto Cable Space Access fromoutdoor only Complete by providing - an access fromswitchgear roomto cable room D-6E0-134A-001 MAIN SUBSTATION FLOOR PLAN 0 2,772 2 Main Substation: Additional Double Swing Door Single Door only - double swing door on north switchgear room D-6E0-134A-001 MAIN SUBSTATION FLOOR PLAN 0 68,857 3 Main Substation: Additional Fire Wall between HV Area and LV Area One Roomfor HV &LV Switchgear - Additional fire wall between HV area and LV area without door to be provided. D-6E0-134A-001 MAIN SUBSTATION FLOOR PLAN 0 44,956 As per M-GT-J Y/SHY-0026 Rev.1 4 Main Substation: Dedicated CO2 Cylinder Shed One CO2 Cylinder Shed for HV &LV Switchgear Room - Dedicated CO2 Cylinder Shed to be provided. D-6E0-134A-001 MAIN SUBSTATION FLOOR PLAN 0 43,451 As per M-GT-J Y/SHY-0026 Rev.1 5 Main Substation: Additional Desk space No Space for a Desk Provide one desk , one desktop computer and two printers for Essential Room Space to be verified D-6E0-134A-001 MAIN SUBSTATION FLOOR PLAN 1 8,819 Hadji-san requested it on 24 MAR 2010. 6 Main Substation: Additional Wall for Cable Space Wire Mesh Fence Cable space area should be closed against sand storm. Wire mesh for cable space area is inacceptable D-6E0-134A-002 MAIN SUBSTATION ELEVATION AND SECTION 0 88,120 7 Main Substation: Additional Rain Water Downspout No Rain Water Downspout - provide on the water the rainwater discharge system D-6E0-134A-002 MAIN SUBSTATION ELEVATION AND SECTION 0 9,575 8 Main Substation: Additional Ceramic Tile Walkway in Cable Space Backfilling only provide for cable space floor sand and ceramic tile for walkway D-6E0-134A-003 MAIN SUBSTATION FINISHING SCHEDULE (INTERIOR AND EXTERIOR) 0 48,360 9 Main Substation: Additional Panic Bar for Doors External Single Door only SD1, SD3, SD4 - equipped with bar panic system D-6E0-134A-004 MAIN SUBSTATION DOOR AND WINDOW SCHEDULE 0 1,656 10 Main Substation: Change of Door Width (900mm) 850mmW - SD-2, SD-3, SD-5, SD-6 change width (W) of doors 900 instead 850. D-6E0-134A-004 MAIN SUBSTATION DOOR AND WINDOW SCHEDULE 1 933 Clarified with Hadji-san on 03 MAR 2010 11 Main Substation: Additional Split AC for Essential Room Central HVAC only - Split AC with essential power for Essential Roomto be provided D-6E0-134A-004 MAIN SUBSTATION DOOR AND WINDOW SCHEDULE 1 19,557 Requested by Hadji-san on 02 MAR 2010 12 Laboratory: Additional Concrete Apron No Apron Complete by providing: - concrete paving around the building D-5L0-134L-001 LABORATORY FLOOR PLAN 0 5,320 Also requested by M-GT-J Y/SHY-0017 13 Laboratory: RC Wall for Cylinder Sheds Concrete Block provide wall of cylinder shed in Reinforced concrete. D-5L0-134L-001 LABORATORY FLOOR PLAN 0 791 14 Laboratory: Additional Canopy No Canopy - Provide RC canopy D-5L0-134L-001 LABORATORY FLOOR PLAN 1 3,254 Hadji-san requested it on 03 MAR 2010. 15 Laboratory: Additional False Ceiling for Chemical and Product Storage Room No False Ceiling - complete by providing ceiling for chemical and product storage room. D-5L0-134L-002 LABORATORY ELEVATION AND SECTION 0 3,836 16 Laboratory: Raise of Floor Elevation (GL+450mm) GL+300mm - Reviewthe elevation of building (at least 2 steps/ground level) D-5L0-134L-002 LABORATORY ELEVATION AND SECTION 0 64,229 Revised by SH E-mail on 17 DEC 2001 17 Laboratory: Additional Rain Water Downspout No Rain Water Downspout - define on the drawing the rainwater discharge system D-5L0-134L-002 LABORATORY ELEVATION AND SECTION 0 4,276 18 Laboratory: Additional Panic Bar for doors No Panic Bar - Complete by providing panic bars to BD/1 and BD/2 D-5L0-134L-004 LABORATORY DOOR AND WINDOW SCHEDULE 0 2,208 19 Laboratory: Change of Door Width (900mmW) 850mmW - Change the width of door 900 instead of 850mm. D-5L0-134L-004 LABORATORY DOOR AND WINDOW SCHEDULE 1 386 Clarified with Hadji-san on 03 MAR 2010 20 Laboratory: Additional Failure Alarmfor RoomPressurization No alarm - Addition of signal failure of the BLDG pressurization systemshall signal a visual &audible alarmin LAB (locally) D-5L-134L-051 LABORATORY BASIC HVAC FLOW SCHEME 1 3,673 C-GT-SHY/J Y-0977 21 Laboratory: Additional Visual and Audible Alarm Not specified - alarmshall be visual and audible D-5L-134L-051 LABORATORY BASIC HVAC FLOW SCHEME 2 1,842 22 Main Control Building: Additional RC Apron No Apron - provide concrete paving around the building D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 0 4,788 Also requested by M-GT-J Y/SHY-0017 23 Main Control Building: Change Type of Interior Wall (Steel Partition) Dry Wall Partition - change the dry wall partition in steel partition with phonic insulation D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 0 76,123 24 Main Control Building: Additional LowPartition Wall for Urinals No Partition - Lowpartition walls between urinals to be provided. (Common Comments for all toilets) D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 0 1,582 25 Main Control Building: Additional Canopy for Main Entrance No Canopy - Canopy to be provided for main entrance. (Common comment for Administration BLDG) D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 0 4,880 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 And Hadji-san requested RC canopy on 03 MAR 2010. 26 Main Control Building: Additional Automatic Fire Extinguishing System for UPS Room&TelecomRoom Indoor Hose Station only - Automatic Fire Extinguishing Systemto be applied to UPS Room&TelecomRoomin unmanned buildings" (MCB &ADM) D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 0 57,949 As per M-GT-J Y/SHY-0045 27 Main Control Building: Additional Hot Water Supply to Sink for Mess Room No Hot Water - Provide one sink with cold &hot water service for Mess Room D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 1 2,312 Hadji-san requested it on 17 MAR 2010. Only Hot water service is additional as Kitchen Sink +Cold water service are part of original concept. 28 Main Control Building: Additional Emergency Corridor &Exit Door No Dedicated Emergency Corridor &Exit Door - Provide corridor &emergency exit door D-5C0-134B-001 MAIN CONTROL BUILDING FLOOR PLAN 2 23,949 C-GT-SHY/J Y-0943 29 Main Control Building: Additional False Ceiling for Rack Room No False Ceiling Complete by providing: - Ceiling for rack room D-5C0-134B-002 MAIN CONTROL BUILDING ELEVATION AND SECTION 0 47,495 30 Main Control Building: Additional Panic Bar for doors No Panic Bar Provide BD/1 panic bar system D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 0 1,104 31 Main Control Building: Change of Door Size (1800mmW x 2200mmH) 1700mmW x 2100mmH - BD-2 change in 1800 x 2500 D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 1 874 32 Main Control Building: Change of Door Width (900mW) 850mmW - SD-2 change in 900 x 2100 instead 850 x 2100 D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 1 196 33 Main Control Building: Change of Door Width (900mmW) 850mmW - WD-1 change 900 x 2100 instead 850 x 2100 D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 1 202 34 Main Control Building: Change of Door Width (900mmW) 850mmW - WD-3 change in 900 instead 850mm D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 1 202 35 Main Control Building: Change of Door Width (900mmW) 800mmW - WD-6 change in 900 instead 800 D-5C0-134B-005 MAIN CONTROL BUILDING DOOR AND WINDOW SCHEDULE 1 101 36 Administration RC Building: Additional Apron No Apron - concrete paving around the building D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 7,595 Also requested by M-GT-J Y/SHY-0017 37 Administration Building: Change of RoomLayout (2 Offices with 2 Secretary Offices) 2 Offices change the (02) open offices in (02) offices with (02) secretary office. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 35,183 38 Administration Building: Change of RoomLayout (2 Offices with 2 Secretary Offices) 3 Offices - change the three offices in First floor in (01) office with (01) secretary office (01) office with (01) secretary office D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 17,133 39 Administration Building: Additional Windows No Window - External Windows to be added for Classroom-1 &2. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 9,017 40 Administration Building: Additional Windows No Window - External windows to be added for the newoffices instead of Open Office-1 &2. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 158,729 41 Administration Building: Change of RoomLayout (2 Offices) One Open Office - Open Office-1 to be change to 2 Offices for 2 persons each. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 17,591 42 Administration Building: Change of RoomLayout (1 MGR Office with 1 Secretary Room) One Open Office - Open Office-2 to be changed to HSE Safety Manager Roomand one Secretary Room. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 17,591 43 Administration Building: Additional LowPartition Wall for Urinals No LowPartition Wall - Lowpartition walls between urinals to be provided. (Common Comments for all toilets) D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 336 Remarks Hadji-san agreed that double leaf doors to be 1700mmand not 1800mmon 03 MAR 2010. Serial No. Description Original Contractual Requirements SH Comments Reference Document Proposed Change Amount (USD) 1 / 4 JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Positive Negative Remarks Serial No. Description Original Contractual Requirements SH Comments Reference Document Proposed Change Amount (USD) 44 Administration Building: Additional Automatic Fire Extinguishing System for UPS Room&TelecomRoom Indoor Hose Station only - Automatic Fire Extinguishing Systemto be applied to UPS Room&TelecomRoomin unmanned buildings" (MCB &ADM) D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 0 140,481 As per M-GT-J Y/SHY-0045 45 Administration Building: Additional Desk Space No Space for a Desk - Provide desk for TelecomSupervisors (Two persons) D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 1 2,487 46 Administration Building: Additional Ablution &Prayer Room No Ablution &Prayer Room - Toilet area (G FL) , provide toilet, ablution and prayer room. D-BID-134P-001 ADMINISTRATION BUILDING FLOOR PLAN 2 8,714 C-GT-SHY/J Y-1006 47 Administration Building: Raise of Floor Elevation (GL+500mm) GL+300mm Reviewthe floor level (FL) at least four (04) steps from the ground level D-BID-134P-002 ADMINISTRATION BUILDING ELEVATION AND SECTION 0 7,554 48 Administration Building: Additional Faade No Faade - Make more proposal for faade and provide Faade D-BID-134P-002 ADMINISTRATION BUILDING ELEVATION AND SECTION 1 15,338 49 Administration Building: Additional Glass Curtain Wall around Main Entrance Concrete Block Curtain Wall around Main Entrance ( including HVAC capacity up ) D-BID-134P-002 ADMINISTRATION BUILDING ELEVATION AND SECTION 1 58,565 based on M-GT-J Y/SHY-0144 50 Administration Building: Additional Skylight Flat Roof without Skylight Skylight ( including HVAC capacity up ) D-BID-134P-002 ADMINISTRATION BUILDING ELEVATION AND SECTION 1 55,776 based on M-GT-J Y/SHY-0144 51 Administration Building: Additional Windows and HVAC Thermal Load Windows for MGT Roomonly WindowArea Increase fromFEED Design ( including HVAC Capacity up ) D-BID-134P-002 ADMINISTRATION BUILDING ELEVATION AND SECTION 1 78,087 based on M-GT-J Y/SHY-0144 52 Administration Building: Additional Panic Bar for Doors No Panic Bar SD/1, SD/2, SD/3 with panic bar system D-BID-134P-005 ADMINISTRATION BUILDING DOOR AND WINDOW SCHEDULE 0 1,656 53 Administration Building: Change of Main Entrance Door Height (2500mmH) 2100mmH - The main door height AD-1 shall be 2,500mm D-BID-134P-005 ADMINISTRATION BUILDING DOOR AND WINDOW SCHEDULE 1 1,495 54 Unit IB Substation: Additional Access fromSwitchgear Roomto Cable Space Access fromoutdoor only Provide access fromthe switchgear roomto the cable space D-BID-134A-001 UNIT IB SUBSTATION FLOOR PLAN 0 630 55 Unit IB Substation: Additional Airlock One Airlock provide airlock for the entrance deck D-BID-134A-001 UNIT IB SUBSTATION FLOOR PLAN 0 3,135 56 Unit IB Substation: Change of HVAC Equipment Location (on ground) On roof change location of HVAC outdoor units (on floor instead of roof). D-BID-134A-001 UNIT IB SUBSTATION FLOOR PLAN 0 23,205 57 Unit IB Substation: Additional Rain Water Downspout No Rain Water Downspout complete by providing the rainwater discharge system D-BID-134A-002 UNIT IB SUBSTATION ELEVATION AND SECTION 0 4,676 58 Unit IB Substation: Additional Ceramic Tile Walkway in Cable Space Backfilling only Provide walkway in cable space with sand and ceramic tile D-BID-134A-003 UNIT(IB) SUBSTATION FINISHING SCHEDULE (INTERIOR AND EXTERIOR) 0 9,979 59 Unit IB Substation: Additional panic Bar for Doors External Single Door only SD/1, SD/2, SD/3, SD/4 should be equipped with panic bar system D-BID-134A-004 UNIT(IB) SUBSTATION DOOR AND WINDOW SCHEDULE 0 2,760 60 Unit IB Substation: Change of Door Width (900mmW) 850mmW - SD-2, SD-3, SD-5, SD-6 change the width of doors 900 instead 850mm. D-BID-134A-004 UNIT(IB) SUBSTATION DOOR AND WINDOW SCHEDULE 1 586 Hadji-san agreed that SD-6 was not applicable on 03 MAR 2010. 61 Safety Building: Change of RoomLayout Refer to contract drawing Reviewcompletely the drawing and submit a floor plan on ground-floor D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 2,706 62 Safety Building: Change of HVAC Equipment Location (on ground) On roof Provide on HVAC systemwith outdoor units on ground (instead of roof) D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 23,205 63 Safety Building: Change of Shutter Type to Sectional Shutter Rolling Shutter Provide sectional doors instead Roller Shutter D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 5,635 64 Safety Building: Change of Door Type (Steel Door) Wooden Door Provide steel doors instead wood doors D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 11,302 65 Safety Building: Change of Door Type to Steel Door AluminumDoor Change AD-1 in SD-1 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 732 66 Safety Building: Change of Door Type to Steel Door AluminumDoor Change AD-2 in SD-2 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 518 67 Safety Building: Additional Windows No Window Windows should be provided for nurse's and doctor's room(reviewthe position) D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 8,003 68 Safety Building: Additional Access to Roof Fans No Permanent Access Provide access to roof fan by inside D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 1,205 Clarification on 08 J AN 2010 69 Safety Building: Additional LowPartition Wall for Urinals No LowPartition Wall - Lowpartition walls between urinals to be provided. (Common Comments for all toilets) D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 336 70 Safety Building: Additional RC Apron No Apron Concrete paving on the area around the building D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 14,385 As per M-GT-J Y-SHY-0017 71 Safety Building: Increase of Fire Car Garage (359m2) 15.5mx 19.0m=295m2 Trailer mounted lighting equipment and trailer mounted pump to be added. D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 252,787 As per M-GT-J Y/SHY-0045 Rev.1 72 Safety Building: Change of WindowSize (1600mmWx1200mmH(2nos)&1200mmWx1200 mmH(1nos)) 900mmW x 1200mmH (3nos) - Command Room: the windowshall be 1600 x 1200 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 3,112 73 Safety Building: Change of WindowSize (900mmW x 1200mmH) No Window - Office-6 : windowshall be 1600 x 1200 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 1,556 74 Safety Building: Additional Sofa Space No Salon - provide furniture for Salon (Sofa) D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 13,018 75 Safety Building: Additional Door Single Door for Corridor - provide double leaf door similar to SD-6 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 3,965 76 Safety Building: Additional Ceramic Tile and Rain Water Sewer for Court No Pave - the court shall be provided with ceramic tile and rainwater sewer D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 5,203 77 Safety Building: Additional Canopy No Canopy - Provide sunshade canopy D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 7,066 Hadji-san agreed not to provide canopy for Substations on 03 MAR 2010. 78 Safety Building: Additional Rain Water Downspout No Rain Water Downspout Showon the drawing the rainwater discharge D-BID-134F-002 SAFETY BUILDING ELEVATION AND SECTION 0 4,075 79 Safety Building: Additional Windows Translucent Panel Provide fixed windows instead translucent panel D-BID-134F-002 SAFETY BUILDING ELEVATION AND SECTION 0 5,135 80 Safety Building: Additional Panic Bar No Panic Bar SD-4 should be equipped with anti-panic door D-BID-134F-005 SAFETY BUILDING DOOR AND WINDOW SCHEDULE 0 552 81 Safety Building: Change WindowSize 900mmW x 1200mmH - office-5 : windows shall be 1600 x 1200 D-BID-134F-005 SAFETY BUILDING DOOR AND WINDOW SCHEDULE 1 1,556 82 Safety Building: Additional Emergency Split AC for First Aid Room Central HVAC only - Provide emergency HVAC type SAC for First Aid Room D-BID-134F-051 SAFETY BUILDING BASIC HVAC FLOW SCHEME 1 50,321 83 Warehouse: Additional Windows Translucent Panel - fixed windows instead translucent panels D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 34,237 84 Warehouse: Additional Rolling Shutter No Shutter - Additional one rolling shutter for 10 ton truck to be provided on the east wall between grid-B and grid-C. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 2,413 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 85 Warehouse: Additional Windows One Wooden Door and No Window - One WD-1 to be deleted and one windowto be added for Office. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 7,132 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 86 Warehouse: Additional Interior Wall, False Ceiling and Mechanical Ventilation for Drawer/Cupboard/Bin R k Interior Fence Wall, No False Ceiling and Natural Ventilatio - Fence for Drawer/Cupboard/B.W Rack to be changed to solid wall and false ceiling &mechanical ventilation to be added for Drawer/Cupboard/Bin Rack. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 23,537 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 Mechanical Ventilation to be added. 2 / 4 JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Positive Negative Remarks Serial No. Description Original Contractual Requirements SH Comments Reference Document Proposed Change Amount (USD) 87 Warehouse: Additional Office One Office only - One office to be added for a material controller. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 34,833 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 88 Warehouse: Additional RC Apron No Apron Concrete paving on the area around the building D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 7,140 As per M-GT-J Y-SHY-0017 89 Warehouse: Additional Canopy No Canopy - Provide sunshade canopy D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 2,874 Hadji-san agreed not to provide canopy for Substations on 03 MAR 2010. 90 Warehouse: Additional Lay down Area No Lay down Area outdoor - Provide lay down area outside D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 40,887 Hadji-san requested on 17 MAR 2010 91 Warehouse: Additional Space for Big Truck No Indoor Space for Track - Consider access of big truck (13mL) inside of BLDG D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 12,829 Hadji-san requested on 17 MAR 2010 92 Warehouse: Additional Access for Roof Fan No Permanent Access for Roof Fan - provide access to fan roof D-BID-134N-002 WAREHOUSE ELEVATION AND SECTION 0 3,099 93 Warehouse: Change of Roof Type (Flat Roof) Steel Sheet Slope Roof - roof for warehouse shall be considered as a technical roof (access for fans) D-BID-134N-002 WAREHOUSE ELEVATION AND SECTION 1 1,504 C-GT-SHY/J Y-1015 94 Warehouse: Additional Panic Bar for Doors No Panic Bar - provide panic bar systemfor SD/2 D-BID-134N-004 WAREHOUSE DOOR AND WINDOW SCHEDULE 0 1,104 95 Warehouse: Change of WindowWidth (1200mmW) 900mmW - AW-1 to be 1200x1200 instead of 900x1200 D-BID-134N-004 WAREHOUSE DOOR AND WINDOW SCHEDULE 1 724 C-GT-SHY/J Y-1019 96 EP Maintenance Building: Deletion of Corridor Corridor Reviewthe access to offices 6,7,8 by warehouse . Remove corridor (office 1 to 5) to offices (6 to 8) D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 -1,021 97 EP Maintenance Building: Additional Access for Roof Fans No Permanent Access for Roof Fan Provide access to roof and roof fan D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 2,135 98 EP Maintenance Building: Additional LowPartition Wall for Urinals No LowPartition Wall for Urinals - Lowpartition walls between urinals to be provided. (Common Comments for all toilets) D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 1,582 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 99 EP Maintenance Building: Additional RC Apron No Apron Concrete paving on the area around the building D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 10,336 As per M-GT-J Y-SHY-0017 100 EP Maintenance Building: Additional Locker Roomwith Shower No Locker Roomwith Shower - Locker Roomwith shower to be added D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 39,642 Requested by Hadji-san on 04 MAR 101 EP Maintenance Building: Additional Canopy No Canopy - Provide sunshade canopy D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 0 3,593 Hadji-san agreed not to provide canopy for Substations on 03 MAR 2010. 102 EP Maintenance Building: Relocation of Toilet/Locker Shower/Prayer Room (Exterior Zone) Interior Zone - Reviewlocation of toilet / Locker Shower / Prayer Room D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 1 57,957 Tanabe-san e-mail on 16 Apr 2010 103 EP Maintenance Building: Additional Windowfor Locker and Prayer Room No Window - Small windows shall be provided for locker and prayer room D=BID-134M-101 EP MAINTENANCE SHOP FLOOR PLAN 1 2,292 104 EP Maintenance Building: Additional Windows Translucent Panel Provide fixed windows instead translucent panel on north and south elevation D-BID-134M-102 EP MAINTENANCE SHOP ELEVATION AND SECTION 0 40,499 105 EP Maintenance Building: Raise of Floor Elevation (GL+180mm) GL+150mm Reviewthe elevation : at least three steps / ground floor D-BID-134M-102 EP MAINTENANCE SHOP ELEVATION AND SECTION 0 141,361 106 Metering House: Change of HVAC Equipment Location (on ground) On roof Provide outdoor HVAC on ground instead of roof, with shelter D-360-134Z-001 METERING HOUSE PLAN, ELEVATION AND SECTION 0 9,931 107 Metering House: Change of Door Size (1200mmHx2400mmH) 1200mmW x 2100mmH Reviewthe width and height of SD-1 (1200 x 2100) insufficient to allowaccess of material and equipment D-360-134Z-001 METERING HOUSE PLAN, ELEVATION AND SECTION 0 1,450 108 Metering House: Additional Rain Water Downspout No Rain Water Downspout Showon the drawing the rainwater evacuation (drainage) (rainwater discharge) D-360-134Z-001 METERING HOUSE PLAN, ELEVATION AND SECTION 0 2,049 109 Metering House: Additional RC Apron No Apron Concrete paving on the area around the building D-360-134Z-001 METERING HOUSE PLAN, ELEVATION AND SECTION 0 1,918 As per M-GT-J Y-SHY-0017 110 Metering House: Additional Panic Bar for Doors No Panic Bar Provide anti-panic bar for outdoors SD-1 and SD-2 D-360-134Z-003 METERING HOUSE DOOR AND WINDOW SCHEDULE 0 1,656 111 Metering House: Additional Ceramic Tiles for Air Lock Floor Hardener - provide ceramic tile in the air lock D-360-134Z-003 METERING HOUSE DOOR AND WINDOW SCHEDULE 1 487 112 Maintenance Building: Additional RC Apron No Apron Complete by concrete paving around the building D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 13,273 Also requested by M-GT-J Y/SHY-0017 113 Maintenance Building: Change of Corridor Width (1850mmW) 1200mmW Reviewthe width of corridor (1200mm) at least > 1500mm D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 1,246 114 Maintenance Building: Additional Access for Roof Fans No Permanent Access for Roof Fan Provide access to roof and roof fan D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 3,443 115 Maintenance Building: Additional Windows Translucent Panel Provide fixed windows for: - garage - open general machinery - open area workshop - assembly welding area D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 21,827 116 Maintenance Building: Additional Electrical &Instrumentation Mechanic Roomin Garage Garage Divide the garage in electrical and instrumentation area, add an other roomsimilar to mechanic room D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 60,249 117 Maintenance Building: Additional LowPartition Wall for Urinals No LowPartition Wall for Urinals - Lowpartition walls between urinals to be provided. (Common Comments for all toilets) D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 1,582 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 118 Maintenance Building: Additional Interior Wall Showers in Toilet - provide wall separation between toilet and showers. D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 336 As per M-GT-J Y/SHY-0097 dated 22 FEB 2010 119 Maintenance Building: Additional Canopy No Canopy - Provide sunshade canopy D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 0 4,491 Hadji-san agreed not to provide canopy for Substations on 03 MAR 2010. 120 Maintenance Building: Additional LowPartition Wall for Urinals No LowPartition Wall for Urinals - wall separation for urinals shall be provided D-BID-134M-001 MAINTENANCE BUILDING FLOOR PLAN 1 1,582 C-GT-SHY/J Y-1012 121 Maintenance Building Additional Windows Translucent Panel Provide fixed windows instead translucent panel D-BID-134M-002 MAINTENANCE BUILDING ELEVATION AND SECTION 0 28,246 122 Maintenance Building Raise of Floor Elevation (GL+180mm) GL+150mm - Reviewelevation of building / ground floor (at least three steps) D-BID-134M-002 MAINTENANCE BUILDING ELEVATION AND SECTION 0 76,651 123 Maintenance Building: Additional False Ceiling No False Ceiling Complete by providing ceiling to: - mechanic room - electrical workshop - instrument workshop - test room D-BID-134M-003 MAINTENANCE BUILDING FINISHING SCHEDULE(INTERIOR) 0 21,037 124 Maintenance Building: Additional Panic Bar for Doors No Panic Bar - Provide panic bar systemfor all doors to outside: SD/2, SD/3, SD/1, SD/10 D-BID-134M-005 MAINTENANCEBUILDING DOOR AND WINDOW SCHEDULE 0 2,208 125 Maintenance Building: Additional Split AC for Spare Room No Air-conditioning - AC to be provided for Spare Room D-BID-134M-051 MAINTENANCE BUILDING BASIC HVAC FLOW SCHEME 0 15,423 Requested by Hadji-san on 04 MAR 2010 126 Main Gate House: Additional RC Apron No Apron Provide concrete paving around the building D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 0 4,195 127 Main Gate House: Change Gate Type (Motorized Slide Gate) Swing Gate Provide motorized sliding gate D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 0 41,360 128 Main Gate House: Additional Space for Card Reader, Scanner and Frame Detector Card Reader was located outdoor and Scanner &Frame Detector was not considered. Remove the card reader into the gate house and provide a scanner inside the gate house D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 0 210,553 3 / 4 JOB Code : 0-5353-20 PJ Name : Gassi Touil Project Log List for SH Comments (Building Works) Positive Negative Remarks Serial No. Description Original Contractual Requirements SH Comments Reference Document Proposed Change Amount (USD) 129 Main Gate House: Installation of Additional Frame Detector and Scanner Frame detector &scanner were not considered. - One frame detector and one scanner to be supplied by SH. D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 0 4,826 As per M-GT-JY/SHY-0045 Installation Only 130 Main Gate House: Additional Window No Window - add window400x400 for toilet D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 1 107 131 Main Gate House: Additional Paving No Paving - add paved area D-BID-134G-001 MAIN GATE HOUSE PLAN, ELEVATION AND SECTION 1 8,950 132 Main Gate House: Additional Panic Bar for Doors No Panic Bar Provide SD/1, SD/2 with panic bar D-BID-134G-003 MAIN GATEHOUSE DOOR AND WINDOW SCHEDULE 0 1,656 133 Plant Gate House: Additional RC Apron No Apron Provide concrete paving around the building D-BID-134H-001 PLANT GATE HOUSE PLAN, ELEVATION AND SECTION 0 4,195 134 Plant Gate House: Additional Space for Card Reader Card Reader &Turnstile were located outdoor. Remove the card reader / turnstile into the gate house D-BID-134H-001 PLANT GATE HOUSE PLAN, ELEVATION AND SECTION 0 10,502 COMMENTS FROMMEETINGS OF 9~11 DEC. 2009 Cancelled as per M-GT-J Y/SHY-0045 &0045 Rev.1 135 Plant Gate House: Change of Gate Type and Additional Door for Pedestrian No Door for Pedestrian Provide a motorized slide gate and a door for pedestrian crossing D-BID-134H-001 PLANT GATE HOUSE PLAN, ELEVATION AND SECTION 0 41,360 136 Plant Gate House: Additional Windows No Window - provide small window400x400 for toilet D-BID-134H-001 PLANT GATE HOUSE PLAN, ELEVATION AND SECTION 1 107 137 Plant Gate House: Additional Pave No Pave - add paved area D-BID-134H-001 PLANT GATE HOUSE PLAN, ELEVATION AND SECTION 1 4,069 138 Plant Gate House: Additional Panic Bar for Door No Panic Bar Provide SD/1, SD/2 with panic anti-bar system D-BID-134H-003 PLANT GATEHOUSE DOOR AND WINDOW SCHEDULE 0 1,656 139 DSP Base: Additional Air Lock No Airlock Provide: - airlock for canteen room D-BID-1340-011 DSP BASE CONCEPTUAL LAYOUT 0 4,295 140 DSP Base Additional Toilet for Each Cabin One Central Toilet - provide showers and toilets for every cabin D-BID-1340-011 DSP BASE CONCEPTUAL LAYOUT 0 172,839 141 DSP Base: Additional Pave No Paving -provide paved area D-BID-1340-011 DSP BASE CONCEPTUAL LAYOUT 0 7,076 142 DSP Base Additional Weapon Store Not specified - Details for weapons store and dike refer to our comment in C-GT-SHY/J Y-0137. D-BID-1340-011 DSP BASE CONCEPTUAL LAYOUT 1 389,305 143 DSP Base: Additional Tuff Paving (800m2+512m2) Refer to contract drawing Due to SH comments on DSP Base D-CPF-1317-904 CONCEPTUAL LAYOUT OF PAVING 13,781 144 Chemical Storage: Raise of Floor Elevation (GL+200mm) GL+50mm - Reviewthe elevation at least (300 mm) D-BID-134N-101 CHEMICAL STORAGE PLAN, ELEVATION AND SECTION 0 10,923 145 Power Supply Scheme: FAP to be Powered by UPS Not specified F.A.P must be U.P.S powered. S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 62,436 146 Power Supply Scheme: Additional Essential Power for Metering HVAC Normal Power 2.5 METERING HOUSE: add HVAC equipment to essential lowvoltage S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 10,406 147 Power Supply Scheme: Additional Essential Power for Maintenance BLDG HVAC Normal Power 2.9 MAINTENANCE BLDG: add HVAC equipment 50% to essential lowvoltage S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 20,812 148 Power Supply Scheme: Additional Emergency Lighting for Flammable Liquid Storage Normal Lighting 2.3 FLAMMABLE LIQUID STORAGE: add emergency lighting to essential lowvoltage S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 2,081 149 Power Supply Scheme: Additional Emergency Lighting for Chemical Storage Normal Lighting 2.14 CHEMICAL STORAGE: add emergency lighting to essential lowvoltage S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 2,081 150 Power Supply Scheme: Additional Essential Power for DSP Lighting Normal Lighting 2.16 DSP BASE: add lighting to essential lowvoltage S-CPF-1340-081 POWER SUPPLY SCHEME FOR BUILDINGS 0 2,081 151 General Specification: Additional Ablution in Main Control Building No Ablution &Prayer Room - ablution roomin Main Control - Hand washbasin in toilets S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 0 12,242 as per clarification on 08 J AN 2010 152 General Specification: Additional Hot Water Supply for Toilet and Ablution Cold Water Only Complete by hot water provided for - Hand washbasin in toilets - ablution room S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 0 36,727 as per clarification on 08 J AN 2010 153 General Specification: Dedicated CO2 Systemfor Main Substation One Systemfor HV &LV Area - Dedicated CO2 Systemwith 100% spare for HV area and LV area to be provided. S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 0 189,022 As per M-GT-J Y/SHY-0026 Rev.1 154 General Specification: Dedicated Fir AlarmPanel for Main Substation One Systemfor HV &LV Area - Dedicated fire alarmpanel for HV area and LV area to be provided. S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 0 10,406 As per M-GT-J Y/SHY-0026 Rev.1 155 General Specification: Change fromFM200 to NOVEC 1230 FM200 - "FM200" to be "FM200 or equivalent" S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 0 564,816 As per M-GT-J Y/SHY-0045 156 General Specification: Additional Horizontal Blind No Blind - 4.3.5.californians stores (curtains) shall be provided for external windows of offices S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 1 44,071 157 General Specification: Change minimumThickness of Heavy Duty Slab minimum150mm - 5.5.and 200mmfor heavy loads S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 1 52,978 158 General Specification: Additional Hot Water Supply for Mess Room Cold Water Only - 7.5.1. Mess Room S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 1 48,969 159 General Specification: Additional Requirement of Noncombustible Material for MCB &LAB Not specified - Materials used for internal finishing in MCB &LAB to be noncombustible materials S-CPF-1340-002 GENERAL SPECIFICATION FOR BUILDING 1 39,937 Ishizu e-mail on 18 J une 2010 160 Schematic Diagramfor BLDG F&G System: Additional Sprinkler for Warehouse Indoor Hose Station only - 4.7 Extinguish systemby water to be provided for Warehouse S-CPF-1340-071 SCHEMATIC DIAGRAM FOR BUILDING F&G SYSTEM 1 96,492 L-GT-J Y/SHY-459 161 Car Parks: Reduce of car parking from40 to 30 for ADM 40cars Car Parking for Administration Building to be reduced from40 to 30 D-CPF-1340-003 STANDARD DRAWING FOR COVERED CAR PARKS AND TRUCK SHED 0 -167,710 as per M-GT-J Y/SHY-0045 162 Car Parks: Additional Sunshade for 18 Car parkings No sunshade for car park Parking for 18 cars with sunshade and 2 buses without sunshade to be provided. D-CPF-1340-003 STANDARD DRAWING FOR COVERED CAR PARKS AND TRUCK SHED 0 473,200 as per M-GT-J Y/SHY-0045 163 MAR: Change of Floor Finishing fromCarpet Flooring to Ceramic Tile Carpet Flooring - Carpet Flooring for ADM MGR RM, Reservoir MGR RM, Secretary (RM), Maint. MGR RM, Secretary (MM), HSE MGR RM &Secretary (HSSM) to be changed to ceramic- tile-A. MAR No. 040 Carpet Flooring 0 38,134 Ishizu e-mail on 01 J uly 2010 164 Office Furniture: Change of Type and Quantity Refer to contract document - Additional Furniture to be provided S-CPF-1340-004 Office Furniture List 0 Later C-GT-SHY/J Y-1470 L-GT-J Y/SHY-0458 5,122,741 -168,730 Exchange Rate 1USD=72.9394 DA TOTAL 4,954,010 1EUR=103.5010 DA 100J PY=75,4754DA 1EUR=1.4190 USD 100J PY=1.0348 USD 4 / 4