JOB Code : 0-5353-20

PJ Name : Gassi Touil Project


Log List for SH Comments
(Building Works)
Rev.2 As of 27 Dec 2010
Positive Negative
1
Main Substation:
Additional Access fromSwitchgear Roomto
Cable Space
Access fromoutdoor only
Complete by providing
- an access fromswitchgear roomto cable room
D-6E0-134A-001
MAIN SUBSTATION FLOOR
PLAN
0 2,772
2
Main Substation:
Additional Double Swing Door
Single Door only - double swing door on north switchgear room D-6E0-134A-001
MAIN SUBSTATION FLOOR
PLAN
0 68,857
3
Main Substation:
Additional Fire Wall between HV Area and LV
Area
One Roomfor HV &LV Switchgear
- Additional fire wall between HV area and LV area
without door to be provided.
D-6E0-134A-001
MAIN SUBSTATION FLOOR
PLAN
0 44,956 As per M-GT-J Y/SHY-0026 Rev.1
4
Main Substation:
Dedicated CO2 Cylinder Shed
One CO2 Cylinder Shed for HV &LV Switchgear Room - Dedicated CO2 Cylinder Shed to be provided. D-6E0-134A-001
MAIN SUBSTATION FLOOR
PLAN
0 43,451 As per M-GT-J Y/SHY-0026 Rev.1
5
Main Substation:
Additional Desk space
No Space for a Desk
Provide one desk , one desktop computer and two
printers for Essential Room
Space to be verified
D-6E0-134A-001
MAIN SUBSTATION FLOOR
PLAN
1 8,819 Hadji-san requested it on 24 MAR 2010.
6
Main Substation:
Additional Wall for Cable Space
Wire Mesh Fence
Cable space area should be closed against sand storm.
Wire mesh for cable space area is inacceptable
D-6E0-134A-002
MAIN SUBSTATION ELEVATION
AND SECTION
0 88,120
7
Main Substation:
Additional Rain Water Downspout
No Rain Water Downspout - provide on the water the rainwater discharge system D-6E0-134A-002
MAIN SUBSTATION ELEVATION
AND SECTION
0 9,575
8
Main Substation:
Additional Ceramic Tile Walkway in Cable Space
Backfilling only
provide for cable space floor sand and ceramic tile for
walkway
D-6E0-134A-003
MAIN SUBSTATION FINISHING
SCHEDULE (INTERIOR AND
EXTERIOR)
0 48,360
9
Main Substation:
Additional Panic Bar for Doors
External Single Door only SD1, SD3, SD4 - equipped with bar panic system D-6E0-134A-004
MAIN SUBSTATION DOOR AND
WINDOW SCHEDULE
0 1,656
10
Main Substation:
Change of Door Width (900mm)
850mmW
- SD-2, SD-3, SD-5, SD-6 change width (W) of doors 900
instead 850.
D-6E0-134A-004
MAIN SUBSTATION DOOR AND
WINDOW SCHEDULE
1 933 Clarified with Hadji-san on 03 MAR 2010
11
Main Substation:
Additional Split AC for Essential Room
Central HVAC only
- Split AC with essential power for Essential Roomto be
provided
D-6E0-134A-004
MAIN SUBSTATION DOOR AND
WINDOW SCHEDULE
1 19,557 Requested by Hadji-san on 02 MAR 2010
12
Laboratory:
Additional Concrete Apron
No Apron
Complete by providing:
- concrete paving around the building
D-5L0-134L-001 LABORATORY FLOOR PLAN 0 5,320 Also requested by M-GT-J Y/SHY-0017
13
Laboratory:
RC Wall for Cylinder Sheds
Concrete Block provide wall of cylinder shed in Reinforced concrete. D-5L0-134L-001 LABORATORY FLOOR PLAN 0 791
14
Laboratory:
Additional Canopy
No Canopy - Provide RC canopy D-5L0-134L-001 LABORATORY FLOOR PLAN 1 3,254 Hadji-san requested it on 03 MAR 2010.
15
Laboratory:
Additional False Ceiling for Chemical and Product
Storage Room
No False Ceiling
- complete by providing ceiling for chemical and product
storage room.
D-5L0-134L-002
LABORATORY ELEVATION AND
SECTION
0 3,836
16
Laboratory:
Raise of Floor Elevation (GL+450mm)
GL+300mm
- Reviewthe elevation of building (at least 2 steps/ground
level)
D-5L0-134L-002
LABORATORY ELEVATION AND
SECTION
0 64,229 Revised by SH E-mail on 17 DEC 2001
17
Laboratory:
Additional Rain Water Downspout
No Rain Water Downspout - define on the drawing the rainwater discharge system D-5L0-134L-002
LABORATORY ELEVATION AND
SECTION
0 4,276
18
Laboratory:
Additional Panic Bar for doors
No Panic Bar - Complete by providing panic bars to BD/1 and BD/2 D-5L0-134L-004
LABORATORY DOOR AND
WINDOW SCHEDULE
0 2,208
19
Laboratory:
Change of Door Width (900mmW)
850mmW - Change the width of door 900 instead of 850mm. D-5L0-134L-004
LABORATORY DOOR AND
WINDOW SCHEDULE
1 386 Clarified with Hadji-san on 03 MAR 2010
20
Laboratory:
Additional Failure Alarmfor RoomPressurization
No alarm
- Addition of signal failure of the BLDG pressurization
systemshall signal a visual &audible alarmin LAB
(locally)
D-5L-134L-051
LABORATORY BASIC HVAC
FLOW SCHEME
1 3,673 C-GT-SHY/J Y-0977
21
Laboratory:
Additional Visual and Audible Alarm
Not specified - alarmshall be visual and audible D-5L-134L-051
LABORATORY BASIC HVAC
FLOW SCHEME
2 1,842
22
Main Control Building:
Additional RC Apron
No Apron - provide concrete paving around the building D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
0 4,788 Also requested by M-GT-J Y/SHY-0017
23
Main Control Building:
Change Type of Interior Wall (Steel Partition)
Dry Wall Partition
- change the dry wall partition in steel partition with phonic
insulation
D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
0 76,123
24
Main Control Building:
Additional LowPartition Wall for Urinals
No Partition
- Lowpartition walls between urinals to be provided.
(Common Comments for all toilets)
D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
0 1,582
25
Main Control Building:
Additional Canopy for Main Entrance
No Canopy
- Canopy to be provided for main entrance. (Common
comment for Administration BLDG)
D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
0 4,880
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009 And Hadji-san requested RC canopy on 03
MAR 2010.
26
Main Control Building:
Additional Automatic Fire Extinguishing System
for UPS Room&TelecomRoom
Indoor Hose Station only
- Automatic Fire Extinguishing Systemto be applied to
UPS Room&TelecomRoomin unmanned buildings"
(MCB &ADM)
D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
0 57,949 As per M-GT-J Y/SHY-0045
27
Main Control Building:
Additional Hot Water Supply to Sink for Mess
Room
No Hot Water
- Provide one sink with cold &hot water service for Mess
Room
D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
1 2,312
Hadji-san requested it on 17 MAR 2010.
Only Hot water service is additional as Kitchen Sink
+Cold water service are part of original concept.
28
Main Control Building:
Additional Emergency Corridor &Exit Door
No Dedicated Emergency Corridor &Exit Door - Provide corridor &emergency exit door D-5C0-134B-001
MAIN CONTROL BUILDING
FLOOR PLAN
2 23,949 C-GT-SHY/J Y-0943
29
Main Control Building:
Additional False Ceiling for Rack Room
No False Ceiling
Complete by providing:
- Ceiling for rack room
D-5C0-134B-002
MAIN CONTROL BUILDING
ELEVATION AND SECTION
0 47,495
30
Main Control Building:
Additional Panic Bar for doors
No Panic Bar Provide BD/1 panic bar system D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
0 1,104
31
Main Control Building:
Change of Door Size (1800mmW x 2200mmH)
1700mmW x 2100mmH - BD-2 change in 1800 x 2500 D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
1 874
32
Main Control Building:
Change of Door Width (900mW)
850mmW - SD-2 change in 900 x 2100 instead 850 x 2100 D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
1 196
33
Main Control Building:
Change of Door Width (900mmW)
850mmW - WD-1 change 900 x 2100 instead 850 x 2100 D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
1 202
34
Main Control Building:
Change of Door Width (900mmW)
850mmW - WD-3 change in 900 instead 850mm D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
1 202
35
Main Control Building:
Change of Door Width (900mmW)
800mmW - WD-6 change in 900 instead 800 D-5C0-134B-005
MAIN CONTROL BUILDING
DOOR AND WINDOW
SCHEDULE
1 101
36
Administration RC Building:
Additional Apron
No Apron - concrete paving around the building D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 7,595 Also requested by M-GT-J Y/SHY-0017
37
Administration Building:
Change of RoomLayout
(2 Offices with 2 Secretary Offices)
2 Offices
change the (02) open offices in (02) offices with (02)
secretary office.
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 35,183
38
Administration Building:
Change of RoomLayout
(2 Offices with 2 Secretary Offices)
3 Offices
- change the three offices in First floor in (01) office with
(01) secretary office
(01) office with (01) secretary office
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 17,133
39
Administration Building:
Additional Windows
No Window - External Windows to be added for Classroom-1 &2. D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 9,017
40
Administration Building:
Additional Windows
No Window
- External windows to be added for the newoffices
instead of Open Office-1 &2.
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 158,729
41
Administration Building:
Change of RoomLayout
(2 Offices)
One Open Office
- Open Office-1 to be change to 2 Offices for 2 persons
each.
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 17,591
42
Administration Building:
Change of RoomLayout
(1 MGR Office with 1 Secretary Room)
One Open Office
- Open Office-2 to be changed to HSE Safety Manager
Roomand one Secretary Room.
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 17,591
43
Administration Building:
Additional LowPartition Wall for Urinals
No LowPartition Wall
- Lowpartition walls between urinals to be provided.
(Common Comments for all toilets)
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 336
Remarks
Hadji-san agreed that double leaf doors to be
1700mmand not 1800mmon 03 MAR 2010.
Serial
No.
Description Original Contractual Requirements SH Comments Reference Document
Proposed Change Amount
(USD)
1 / 4
JOB Code : 0-5353-20
PJ Name : Gassi Touil Project
Log List for SH Comments
(Building Works)
Positive Negative
Remarks
Serial
No.
Description Original Contractual Requirements SH Comments Reference Document
Proposed Change Amount
(USD)
44
Administration Building:
Additional Automatic Fire Extinguishing System
for UPS Room&TelecomRoom
Indoor Hose Station only
- Automatic Fire Extinguishing Systemto be applied to
UPS Room&TelecomRoomin unmanned buildings"
(MCB &ADM)
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
0 140,481 As per M-GT-J Y/SHY-0045
45
Administration Building:
Additional Desk Space
No Space for a Desk - Provide desk for TelecomSupervisors (Two persons) D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
1 2,487
46
Administration Building:
Additional Ablution &Prayer Room
No Ablution &Prayer Room
- Toilet area (G FL) , provide toilet, ablution and prayer
room.
D-BID-134P-001
ADMINISTRATION BUILDING
FLOOR PLAN
2 8,714 C-GT-SHY/J Y-1006
47
Administration Building:
Raise of Floor Elevation (GL+500mm)
GL+300mm
Reviewthe floor level (FL) at least four (04) steps from
the ground level
D-BID-134P-002
ADMINISTRATION BUILDING
ELEVATION AND SECTION
0 7,554
48
Administration Building:
Additional Faade
No Faade - Make more proposal for faade and provide Faade D-BID-134P-002
ADMINISTRATION BUILDING
ELEVATION AND SECTION
1 15,338
49
Administration Building:
Additional Glass Curtain Wall around Main
Entrance
Concrete Block
Curtain Wall around Main Entrance ( including HVAC
capacity up )
D-BID-134P-002
ADMINISTRATION BUILDING
ELEVATION AND SECTION
1 58,565 based on M-GT-J Y/SHY-0144
50
Administration Building:
Additional Skylight
Flat Roof without Skylight Skylight ( including HVAC capacity up ) D-BID-134P-002
ADMINISTRATION BUILDING
ELEVATION AND SECTION
1 55,776 based on M-GT-J Y/SHY-0144
51
Administration Building:
Additional Windows and HVAC Thermal Load
Windows for MGT Roomonly
WindowArea Increase fromFEED Design ( including
HVAC Capacity up )
D-BID-134P-002
ADMINISTRATION BUILDING
ELEVATION AND SECTION
1 78,087 based on M-GT-J Y/SHY-0144
52
Administration Building:
Additional Panic Bar for Doors
No Panic Bar SD/1, SD/2, SD/3 with panic bar system D-BID-134P-005
ADMINISTRATION BUILDING
DOOR AND WINDOW
SCHEDULE
0 1,656
53
Administration Building:
Change of Main Entrance Door Height
(2500mmH)
2100mmH - The main door height AD-1 shall be 2,500mm D-BID-134P-005
ADMINISTRATION BUILDING
DOOR AND WINDOW
SCHEDULE
1 1,495
54
Unit IB Substation:
Additional Access fromSwitchgear Roomto
Cable Space
Access fromoutdoor only
Provide access fromthe switchgear roomto the cable
space
D-BID-134A-001
UNIT IB SUBSTATION FLOOR
PLAN
0 630
55
Unit IB Substation:
Additional Airlock
One Airlock provide airlock for the entrance deck D-BID-134A-001
UNIT IB SUBSTATION FLOOR
PLAN
0 3,135
56
Unit IB Substation:
Change of HVAC Equipment Location (on
ground)
On roof
change location of HVAC outdoor units (on floor instead
of roof).
D-BID-134A-001
UNIT IB SUBSTATION FLOOR
PLAN
0 23,205
57
Unit IB Substation:
Additional Rain Water Downspout
No Rain Water Downspout complete by providing the rainwater discharge system D-BID-134A-002
UNIT IB SUBSTATION
ELEVATION AND SECTION
0 4,676
58
Unit IB Substation:
Additional Ceramic Tile Walkway in Cable Space
Backfilling only
Provide walkway in cable space with sand and ceramic
tile
D-BID-134A-003
UNIT(IB) SUBSTATION
FINISHING SCHEDULE
(INTERIOR AND EXTERIOR)
0 9,979
59
Unit IB Substation:
Additional panic Bar for Doors
External Single Door only
SD/1, SD/2, SD/3, SD/4 should be equipped with panic
bar system
D-BID-134A-004
UNIT(IB) SUBSTATION DOOR
AND WINDOW SCHEDULE
0 2,760
60
Unit IB Substation:
Change of Door Width (900mmW)
850mmW
- SD-2, SD-3, SD-5, SD-6 change the width of doors 900
instead 850mm.
D-BID-134A-004
UNIT(IB) SUBSTATION DOOR
AND WINDOW SCHEDULE
1 586
Hadji-san agreed that SD-6 was not applicable on 03
MAR 2010.
61
Safety Building:
Change of RoomLayout
Refer to contract drawing
Reviewcompletely the drawing and submit a floor plan on
ground-floor
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 2,706
62
Safety Building:
Change of HVAC Equipment Location (on
ground)
On roof
Provide on HVAC systemwith outdoor units on ground
(instead of roof)
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 23,205
63
Safety Building:
Change of Shutter Type to Sectional Shutter
Rolling Shutter Provide sectional doors instead Roller Shutter D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 5,635
64
Safety Building:
Change of Door Type (Steel Door)
Wooden Door Provide steel doors instead wood doors D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 11,302
65
Safety Building:
Change of Door Type to Steel Door
AluminumDoor Change AD-1 in SD-1 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 732
66
Safety Building:
Change of Door Type to Steel Door
AluminumDoor Change AD-2 in SD-2 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 518
67
Safety Building:
Additional Windows
No Window
Windows should be provided for nurse's and doctor's
room(reviewthe position)
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 8,003
68
Safety Building:
Additional Access to Roof Fans
No Permanent Access Provide access to roof fan by inside D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 1,205 Clarification on 08 J AN 2010
69
Safety Building:
Additional LowPartition Wall for Urinals
No LowPartition Wall
- Lowpartition walls between urinals to be provided.
(Common Comments for all toilets)
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 336
70
Safety Building:
Additional RC Apron
No Apron Concrete paving on the area around the building D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 14,385 As per M-GT-J Y-SHY-0017
71
Safety Building:
Increase of Fire Car Garage (359m2)
15.5mx 19.0m=295m2
Trailer mounted lighting equipment and trailer mounted
pump to be added.
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 0 252,787
As per M-GT-J Y/SHY-0045 Rev.1
72
Safety Building:
Change of WindowSize
(1600mmWx1200mmH(2nos)&1200mmWx1200
mmH(1nos))
900mmW x 1200mmH (3nos) - Command Room: the windowshall be 1600 x 1200 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 3,112
73
Safety Building:
Change of WindowSize
(900mmW x 1200mmH)
No Window - Office-6 : windowshall be 1600 x 1200 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 1,556
74
Safety Building:
Additional Sofa Space
No Salon - provide furniture for Salon (Sofa) D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 13,018
75
Safety Building:
Additional Door
Single Door for Corridor - provide double leaf door similar to SD-6 D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 3,965
76
Safety Building:
Additional Ceramic Tile and Rain Water Sewer for
Court
No Pave
- the court shall be provided with ceramic tile and
rainwater sewer
D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 5,203
77
Safety Building:
Additional Canopy
No Canopy - Provide sunshade canopy D-BID-134F-001 SAFETY BUILDING FLOOR PLAN 1 7,066
Hadji-san agreed not to provide canopy for
Substations on 03 MAR 2010.
78
Safety Building:
Additional Rain Water Downspout
No Rain Water Downspout Showon the drawing the rainwater discharge D-BID-134F-002
SAFETY BUILDING ELEVATION
AND SECTION
0 4,075
79
Safety Building:
Additional Windows
Translucent Panel Provide fixed windows instead translucent panel D-BID-134F-002
SAFETY BUILDING ELEVATION
AND SECTION
0 5,135
80
Safety Building:
Additional Panic Bar
No Panic Bar SD-4 should be equipped with anti-panic door D-BID-134F-005
SAFETY BUILDING DOOR AND
WINDOW SCHEDULE
0 552
81
Safety Building:
Change WindowSize
900mmW x 1200mmH - office-5 : windows shall be 1600 x 1200 D-BID-134F-005
SAFETY BUILDING DOOR AND
WINDOW SCHEDULE
1 1,556
82
Safety Building:
Additional Emergency Split AC for First Aid Room
Central HVAC only - Provide emergency HVAC type SAC for First Aid Room D-BID-134F-051
SAFETY BUILDING BASIC HVAC
FLOW SCHEME
1 50,321
83
Warehouse:
Additional Windows
Translucent Panel - fixed windows instead translucent panels D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 34,237
84
Warehouse:
Additional Rolling Shutter
No Shutter
- Additional one rolling shutter for 10 ton truck to be
provided on the east wall between grid-B and grid-C. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 2,413
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
85
Warehouse:
Additional Windows
One Wooden Door and No Window
- One WD-1 to be deleted and one windowto be added
for Office.
D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 7,132
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
86
Warehouse:
Additional Interior Wall, False Ceiling and
Mechanical Ventilation for Drawer/Cupboard/Bin
R k
Interior Fence Wall, No False Ceiling and Natural Ventilatio
- Fence for Drawer/Cupboard/B.W Rack to be changed to
solid wall and false ceiling &mechanical ventilation to be
added for Drawer/Cupboard/Bin Rack.
D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 23,537
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
Mechanical Ventilation to be added.
2 / 4
JOB Code : 0-5353-20
PJ Name : Gassi Touil Project
Log List for SH Comments
(Building Works)
Positive Negative
Remarks
Serial
No.
Description Original Contractual Requirements SH Comments Reference Document
Proposed Change Amount
(USD)
87
Warehouse:
Additional Office
One Office only - One office to be added for a material controller. D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 34,833
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
88
Warehouse:
Additional RC Apron
No Apron Concrete paving on the area around the building D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 7,140 As per M-GT-J Y-SHY-0017
89
Warehouse:
Additional Canopy
No Canopy - Provide sunshade canopy D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 2,874
Hadji-san agreed not to provide canopy for
Substations on 03 MAR 2010.
90
Warehouse:
Additional Lay down Area
No Lay down Area outdoor - Provide lay down area outside D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 40,887 Hadji-san requested on 17 MAR 2010
91
Warehouse:
Additional Space for Big Truck
No Indoor Space for Track - Consider access of big truck (13mL) inside of BLDG D-BID-134N-001 WAREHOUSE FLOOR PLAN 0 12,829 Hadji-san requested on 17 MAR 2010
92
Warehouse:
Additional Access for Roof Fan
No Permanent Access for Roof Fan - provide access to fan roof D-BID-134N-002
WAREHOUSE ELEVATION AND
SECTION
0 3,099
93
Warehouse:
Change of Roof Type (Flat Roof) Steel Sheet Slope Roof
- roof for warehouse shall be considered as a technical
roof (access for fans)
D-BID-134N-002
WAREHOUSE ELEVATION AND
SECTION
1 1,504 C-GT-SHY/J Y-1015
94
Warehouse:
Additional Panic Bar for Doors
No Panic Bar - provide panic bar systemfor SD/2 D-BID-134N-004
WAREHOUSE DOOR AND
WINDOW SCHEDULE
0 1,104
95
Warehouse:
Change of WindowWidth (1200mmW)
900mmW - AW-1 to be 1200x1200 instead of 900x1200 D-BID-134N-004
WAREHOUSE DOOR AND
WINDOW SCHEDULE
1 724 C-GT-SHY/J Y-1019
96
EP Maintenance Building:
Deletion of Corridor
Corridor
Reviewthe access to offices 6,7,8 by warehouse .
Remove corridor (office 1 to 5) to offices (6 to 8)
D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 -1,021
97
EP Maintenance Building:
Additional Access for Roof Fans
No Permanent Access for Roof Fan Provide access to roof and roof fan D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 2,135
98
EP Maintenance Building:
Additional LowPartition Wall for Urinals
No LowPartition Wall for Urinals
- Lowpartition walls between urinals to be provided.
(Common Comments for all toilets)
D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 1,582
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
99
EP Maintenance Building:
Additional RC Apron
No Apron Concrete paving on the area around the building D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 10,336 As per M-GT-J Y-SHY-0017
100
EP Maintenance Building:
Additional Locker Roomwith Shower
No Locker Roomwith Shower - Locker Roomwith shower to be added D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 39,642 Requested by Hadji-san on 04 MAR
101
EP Maintenance Building:
Additional Canopy
No Canopy - Provide sunshade canopy D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
0 3,593
Hadji-san agreed not to provide canopy for
Substations on 03 MAR 2010.
102
EP Maintenance Building:
Relocation of Toilet/Locker Shower/Prayer Room
(Exterior Zone)
Interior Zone - Reviewlocation of toilet / Locker Shower / Prayer Room D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
1 57,957 Tanabe-san e-mail on 16 Apr 2010
103
EP Maintenance Building:
Additional Windowfor Locker and Prayer Room
No Window
- Small windows shall be provided for locker and prayer
room
D=BID-134M-101
EP MAINTENANCE SHOP
FLOOR PLAN
1 2,292
104
EP Maintenance Building:
Additional Windows
Translucent Panel
Provide fixed windows instead translucent panel on north
and south elevation
D-BID-134M-102
EP MAINTENANCE SHOP
ELEVATION AND SECTION
0 40,499
105
EP Maintenance Building:
Raise of Floor Elevation (GL+180mm)
GL+150mm Reviewthe elevation : at least three steps / ground floor D-BID-134M-102
EP MAINTENANCE SHOP
ELEVATION AND SECTION
0 141,361
106
Metering House:
Change of HVAC Equipment Location
(on ground)
On roof
Provide outdoor HVAC on ground instead of roof, with
shelter
D-360-134Z-001
METERING HOUSE PLAN,
ELEVATION AND SECTION
0 9,931
107
Metering House:
Change of Door Size (1200mmHx2400mmH)
1200mmW x 2100mmH
Reviewthe width and height of SD-1 (1200 x 2100)
insufficient to allowaccess of material and equipment
D-360-134Z-001
METERING HOUSE PLAN,
ELEVATION AND SECTION
0 1,450
108
Metering House:
Additional Rain Water Downspout
No Rain Water Downspout
Showon the drawing the rainwater evacuation (drainage)
(rainwater discharge)
D-360-134Z-001
METERING HOUSE PLAN,
ELEVATION AND SECTION
0 2,049
109
Metering House:
Additional RC Apron
No Apron Concrete paving on the area around the building D-360-134Z-001
METERING HOUSE PLAN,
ELEVATION AND SECTION
0 1,918 As per M-GT-J Y-SHY-0017
110
Metering House:
Additional Panic Bar for Doors
No Panic Bar Provide anti-panic bar for outdoors SD-1 and SD-2 D-360-134Z-003
METERING HOUSE DOOR AND
WINDOW SCHEDULE
0 1,656
111
Metering House:
Additional Ceramic Tiles for Air Lock
Floor Hardener - provide ceramic tile in the air lock D-360-134Z-003
METERING HOUSE DOOR AND
WINDOW SCHEDULE
1 487
112
Maintenance Building:
Additional RC Apron
No Apron Complete by concrete paving around the building D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 13,273 Also requested by M-GT-J Y/SHY-0017
113
Maintenance Building:
Change of Corridor Width (1850mmW)
1200mmW
Reviewthe width of corridor (1200mm) at least >
1500mm
D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 1,246
114
Maintenance Building:
Additional Access for Roof Fans
No Permanent Access for Roof Fan Provide access to roof and roof fan D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 3,443
115
Maintenance Building:
Additional Windows
Translucent Panel
Provide fixed windows for:
- garage
- open general machinery
- open area workshop
- assembly welding area
D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 21,827
116
Maintenance Building:
Additional Electrical &Instrumentation Mechanic
Roomin Garage
Garage
Divide the garage in electrical and instrumentation area,
add an other roomsimilar to mechanic room
D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 60,249
117
Maintenance Building:
Additional LowPartition Wall for Urinals
No LowPartition Wall for Urinals
- Lowpartition walls between urinals to be provided.
(Common Comments for all toilets)
D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 1,582
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
118
Maintenance Building:
Additional Interior Wall
Showers in Toilet - provide wall separation between toilet and showers. D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 336 As per M-GT-J Y/SHY-0097 dated 22 FEB 2010
119
Maintenance Building:
Additional Canopy
No Canopy - Provide sunshade canopy D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
0 4,491
Hadji-san agreed not to provide canopy for
Substations on 03 MAR 2010.
120
Maintenance Building:
Additional LowPartition Wall for Urinals
No LowPartition Wall for Urinals - wall separation for urinals shall be provided D-BID-134M-001
MAINTENANCE BUILDING
FLOOR PLAN
1 1,582 C-GT-SHY/J Y-1012
121
Maintenance Building
Additional Windows
Translucent Panel Provide fixed windows instead translucent panel D-BID-134M-002
MAINTENANCE BUILDING
ELEVATION AND SECTION
0 28,246
122
Maintenance Building
Raise of Floor Elevation (GL+180mm)
GL+150mm
- Reviewelevation of building / ground floor (at least three
steps)
D-BID-134M-002
MAINTENANCE BUILDING
ELEVATION AND SECTION
0 76,651
123
Maintenance Building:
Additional False Ceiling
No False Ceiling
Complete by providing ceiling to:
- mechanic room
- electrical workshop
- instrument workshop
- test room
D-BID-134M-003
MAINTENANCE BUILDING
FINISHING
SCHEDULE(INTERIOR)
0 21,037
124
Maintenance Building:
Additional Panic Bar for Doors
No Panic Bar
- Provide panic bar systemfor all doors to outside: SD/2,
SD/3, SD/1, SD/10
D-BID-134M-005
MAINTENANCEBUILDING DOOR
AND WINDOW SCHEDULE
0 2,208
125
Maintenance Building:
Additional Split AC for Spare Room
No Air-conditioning - AC to be provided for Spare Room D-BID-134M-051
MAINTENANCE BUILDING
BASIC HVAC FLOW SCHEME
0 15,423 Requested by Hadji-san on 04 MAR 2010
126
Main Gate House:
Additional RC Apron
No Apron Provide concrete paving around the building D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
0 4,195
127
Main Gate House:
Change Gate Type (Motorized Slide Gate)
Swing Gate Provide motorized sliding gate D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
0 41,360
128
Main Gate House:
Additional Space for Card Reader, Scanner and
Frame Detector
Card Reader was located outdoor and Scanner &Frame
Detector was not considered.
Remove the card reader into the gate house and provide
a scanner inside the gate house
D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
0 210,553
3 / 4
JOB Code : 0-5353-20
PJ Name : Gassi Touil Project
Log List for SH Comments
(Building Works)
Positive Negative
Remarks
Serial
No.
Description Original Contractual Requirements SH Comments Reference Document
Proposed Change Amount
(USD)
129
Main Gate House:
Installation of Additional Frame Detector and
Scanner
Frame detector &scanner were not considered.
- One frame detector and one scanner to be supplied by
SH.
D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
0 4,826
As per M-GT-JY/SHY-0045
Installation Only
130
Main Gate House:
Additional Window
No Window - add window400x400 for toilet D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
1 107
131
Main Gate House:
Additional Paving
No Paving - add paved area D-BID-134G-001
MAIN GATE HOUSE PLAN,
ELEVATION AND SECTION
1 8,950
132
Main Gate House:
Additional Panic Bar for Doors
No Panic Bar Provide SD/1, SD/2 with panic bar D-BID-134G-003
MAIN GATEHOUSE DOOR AND
WINDOW SCHEDULE
0 1,656
133
Plant Gate House:
Additional RC Apron
No Apron Provide concrete paving around the building D-BID-134H-001
PLANT GATE HOUSE PLAN,
ELEVATION AND SECTION
0 4,195
134
Plant Gate House:
Additional Space for Card Reader
Card Reader &Turnstile were located outdoor. Remove the card reader / turnstile into the gate house D-BID-134H-001
PLANT GATE HOUSE PLAN,
ELEVATION AND SECTION
0 10,502
COMMENTS FROMMEETINGS OF 9~11 DEC.
2009
Cancelled as per M-GT-J Y/SHY-0045 &0045 Rev.1
135
Plant Gate House:
Change of Gate Type and Additional Door for
Pedestrian
No Door for Pedestrian
Provide a motorized slide gate and a door for pedestrian
crossing
D-BID-134H-001
PLANT GATE HOUSE PLAN,
ELEVATION AND SECTION
0 41,360
136
Plant Gate House:
Additional Windows
No Window - provide small window400x400 for toilet D-BID-134H-001
PLANT GATE HOUSE PLAN,
ELEVATION AND SECTION
1 107
137
Plant Gate House:
Additional Pave
No Pave - add paved area D-BID-134H-001
PLANT GATE HOUSE PLAN,
ELEVATION AND SECTION
1 4,069
138
Plant Gate House:
Additional Panic Bar for Door
No Panic Bar Provide SD/1, SD/2 with panic anti-bar system D-BID-134H-003
PLANT GATEHOUSE DOOR
AND WINDOW SCHEDULE
0 1,656
139
DSP Base:
Additional Air Lock
No Airlock
Provide:
- airlock for canteen room D-BID-1340-011
DSP BASE CONCEPTUAL
LAYOUT
0 4,295
140
DSP Base
Additional Toilet for Each Cabin
One Central Toilet - provide showers and toilets for every cabin D-BID-1340-011
DSP BASE CONCEPTUAL
LAYOUT
0 172,839
141
DSP Base:
Additional Pave
No Paving -provide paved area D-BID-1340-011
DSP BASE CONCEPTUAL
LAYOUT
0 7,076
142
DSP Base
Additional Weapon Store
Not specified
- Details for weapons store and dike refer to our comment
in C-GT-SHY/J Y-0137.
D-BID-1340-011
DSP BASE CONCEPTUAL
LAYOUT
1 389,305
143
DSP Base:
Additional Tuff Paving (800m2+512m2)
Refer to contract drawing Due to SH comments on DSP Base D-CPF-1317-904
CONCEPTUAL LAYOUT OF
PAVING
13,781
144
Chemical Storage:
Raise of Floor Elevation (GL+200mm)
GL+50mm - Reviewthe elevation at least (300 mm) D-BID-134N-101
CHEMICAL STORAGE PLAN,
ELEVATION AND SECTION
0 10,923
145
Power Supply Scheme:
FAP to be Powered by UPS
Not specified F.A.P must be U.P.S powered. S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 62,436
146
Power Supply Scheme:
Additional Essential Power for Metering HVAC
Normal Power
2.5 METERING HOUSE: add HVAC equipment to
essential lowvoltage
S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 10,406
147
Power Supply Scheme:
Additional Essential Power for Maintenance
BLDG HVAC
Normal Power
2.9 MAINTENANCE BLDG: add HVAC equipment 50% to
essential lowvoltage
S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 20,812
148
Power Supply Scheme:
Additional Emergency Lighting for Flammable
Liquid Storage
Normal Lighting
2.3 FLAMMABLE LIQUID STORAGE: add emergency
lighting to essential lowvoltage
S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 2,081
149
Power Supply Scheme:
Additional Emergency Lighting for Chemical
Storage
Normal Lighting
2.14 CHEMICAL STORAGE: add emergency lighting to
essential lowvoltage
S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 2,081
150
Power Supply Scheme:
Additional Essential Power for DSP Lighting
Normal Lighting 2.16 DSP BASE: add lighting to essential lowvoltage S-CPF-1340-081
POWER SUPPLY SCHEME FOR
BUILDINGS
0 2,081
151
General Specification:
Additional Ablution in Main Control Building
No Ablution &Prayer Room
- ablution roomin Main Control
- Hand washbasin in toilets
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
0 12,242 as per clarification on 08 J AN 2010
152
General Specification:
Additional Hot Water Supply for Toilet and
Ablution
Cold Water Only
Complete by hot water provided for
- Hand washbasin in toilets
- ablution room
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
0 36,727 as per clarification on 08 J AN 2010
153
General Specification:
Dedicated CO2 Systemfor Main Substation
One Systemfor HV &LV Area
- Dedicated CO2 Systemwith 100% spare for HV area
and LV area to be provided.
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
0 189,022 As per M-GT-J Y/SHY-0026 Rev.1
154
General Specification:
Dedicated Fir AlarmPanel for Main Substation
One Systemfor HV &LV Area
- Dedicated fire alarmpanel for HV area and LV area to
be provided.
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
0 10,406 As per M-GT-J Y/SHY-0026 Rev.1
155
General Specification:
Change fromFM200 to NOVEC 1230
FM200 - "FM200" to be "FM200 or equivalent" S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
0 564,816 As per M-GT-J Y/SHY-0045
156
General Specification:
Additional Horizontal Blind
No Blind
- 4.3.5.californians stores (curtains) shall be provided for
external windows of offices
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
1 44,071
157
General Specification:
Change minimumThickness of Heavy Duty Slab
minimum150mm - 5.5.and 200mmfor heavy loads S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
1 52,978
158
General Specification:
Additional Hot Water Supply for Mess Room
Cold Water Only - 7.5.1. Mess Room S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
1 48,969
159
General Specification:
Additional Requirement of Noncombustible
Material for MCB &LAB
Not specified
- Materials used for internal finishing in MCB &LAB to be
noncombustible materials
S-CPF-1340-002
GENERAL SPECIFICATION FOR
BUILDING
1 39,937 Ishizu e-mail on 18 J une 2010
160
Schematic Diagramfor BLDG F&G System:
Additional Sprinkler for Warehouse
Indoor Hose Station only
- 4.7 Extinguish systemby water to be provided for
Warehouse
S-CPF-1340-071
SCHEMATIC DIAGRAM FOR
BUILDING F&G SYSTEM
1 96,492 L-GT-J Y/SHY-459
161
Car Parks:
Reduce of car parking from40 to 30 for ADM
40cars
Car Parking for Administration Building to be reduced
from40 to 30
D-CPF-1340-003
STANDARD DRAWING FOR
COVERED CAR PARKS AND
TRUCK SHED
0 -167,710 as per M-GT-J Y/SHY-0045
162
Car Parks:
Additional Sunshade for 18 Car parkings
No sunshade for car park
Parking for 18 cars with sunshade and 2 buses without
sunshade to be provided.
D-CPF-1340-003
STANDARD DRAWING FOR
COVERED CAR PARKS AND
TRUCK SHED
0 473,200 as per M-GT-J Y/SHY-0045
163
MAR:
Change of Floor Finishing fromCarpet Flooring to
Ceramic Tile
Carpet Flooring
- Carpet Flooring for ADM MGR RM, Reservoir MGR RM,
Secretary (RM), Maint. MGR RM, Secretary (MM), HSE
MGR RM &Secretary (HSSM) to be changed to ceramic-
tile-A.
MAR No. 040 Carpet Flooring 0 38,134 Ishizu e-mail on 01 J uly 2010
164
Office Furniture:
Change of Type and Quantity
Refer to contract document - Additional Furniture to be provided S-CPF-1340-004 Office Furniture List 0 Later
C-GT-SHY/J Y-1470
L-GT-J Y/SHY-0458
5,122,741 -168,730
Exchange Rate
1USD=72.9394 DA TOTAL 4,954,010
1EUR=103.5010 DA
100J PY=75,4754DA
1EUR=1.4190 USD
100J PY=1.0348 USD
4 / 4