ID Task Name Duration Start Finish Predecessors Resource Names

1 110 KV switchyard and associated works in M/s. HLL BIOTECH LIMITED 256.38 days Sat 5/31/14 Tue 5/26/15
2 Purchase order stage 20 days Sat 5/31/14 Mon 6/30/14
3 Release of LOA 1 day Sat 5/31/14 Sat 5/31/14 HBL
4 Submission of Bank guarantee 18 days Mon 6/2/14 Wed 6/25/14 3 SVEPL
5 Release of PO 7 days Wed 6/25/14 Mon 6/30/14 4 HBL
6 Payment of advance 5 days Wed 6/25/14 Sun 6/29/14 4 HBL
7 Preparatory work 1 day Mon 10/6/14 Mon 10/6/14
8 Pooja work 1 day Mon 10/6/14 Mon 10/6/14 5,22 SVEPL
9 CEA drawing approval 28.75 days Mon 6/30/14 Thu 8/7/14
10 Preparation of drawings 15 days Mon 6/30/14 Fri 7/18/14 5 SVEPL
11 Getting drawing approval 30 days Fri 7/18/14 Thu 8/7/14 10 CEA/SVEPL
12 Ordering work 30 days Mon 6/30/14 Fri 8/8/14
13 Vendor finalisation 20 days Mon 6/30/14 Fri 7/25/14 6 SVEPL
14 Release of PO for suppliers 10 days Mon 7/28/14 Fri 8/8/14 13 SVEPL
15 Drawing stage for equipments 27 days Mon 8/11/14 Tue 9/16/14
16 Receipt of drawings from vendors 25 days Mon 8/11/14 Fri 9/12/14 14 SVEPL
17 Approval of drawings by consultant 7 days Fri 9/12/14 Tue 9/16/14 16 HBL/NNE
18 Civil works 174 days Wed 9/17/14 Mon 5/18/15
19 Drawing stage 13 days Wed 9/17/14 Sun 10/5/14 17
20 Preparation of drawings 9 days Wed 9/17/14 Mon 9/29/14 17 SVEPL
21 Submission of drawings for getting approval for construction 1 day Tue 9/30/14 Tue 9/30/14 20 SVEPL
22 Approval of drawings by consultant 7 days Tue 9/30/14 Sun 10/5/14 21 NNE
23 Foundation works for All equipment except Transformer 113 days Mon 10/6/14 Wed 3/11/15 22
24 Setting out -Survey 7 days Mon 10/6/14 Tue 10/14/14 22 SVEPL
25 Marking of foundations 7 days Wed 10/15/14 Thu 10/23/14 24 SVEPL
26 Excavation 12 days Fri 10/24/14 Mon 11/10/14 25 SVEPL
27 Sand filling &PCC 5 days Tue 11/11/14 Mon 11/17/14 26 SVEPL
28 Shuttering 7 days Tue 11/18/14 Wed 11/26/14 27 SVEPL
29 Reinforcement 7 days Thu 11/27/14 Fri 12/5/14 28 SVEPL
30 First lift concreting 12 days Mon 12/8/14 Tue 12/23/14 29 SVEPL
31 Shuttering 12 days Wed 12/24/14 Thu 1/8/15 30 SVEPL
32 Reinforcement 12 days Fri 1/9/15 Mon 1/26/15 31 SVEPL
33 Second lift concreting with fixing foundation bo 10 days Tue 1/27/15 Mon 2/9/15 32 SVEPL
34 Curing 6 days Tue 2/10/15 Tue 2/17/15 33 SVEPL
35 Back filling, levelling and compaction 12 days Wed 2/18/15 Thu 3/5/15 34 SVEPL
36 Whitewashing 4 days Fri 3/6/15 Wed 3/11/15 35 SVEPL
37 Foundation works for Transformer 65 days Mon 10/6/14 Fri 1/2/15
38 Setting out -Survey 7 days Mon 10/6/14 Tue 10/14/14 22 SVEPL
39 Marking of foundations 3 days Wed 10/15/14 Fri 10/17/14 38 SVEPL
40 Excavation 3 days Mon 10/20/14 Wed 10/22/14 39 SVEPL
41 Sand filling &PCC 5 days Thu 10/23/14 Wed 10/29/14 40 SVEPL
42 Reinforcement 3 days Thu 10/30/14 Mon 11/3/14 41 SVEPL
43 Shuttering 2 days Tue 11/4/14 Wed 11/5/14 42 SVEPL
44 Raft 1 day Thu 11/6/14 Thu 11/6/14 43 SVEPL
45 First lift concreting 3 days Fri 11/7/14 Tue 11/11/14 44 SVEPL
46 Shuttering 2 days Wed 11/12/14 Thu 11/13/14 45 SVEPL
47 Second lift concreting with base plates 5 days Fri 11/14/14 Thu 11/20/14 46 SVEPL
48 Curing 7 days Fri 11/21/14 Mon 12/1/14 47 SVEPL
49 Excavation for retainer wall 1 day Tue 12/16/14 Tue 12/16/14 48FS+10 days SVEPL
50 Sand filling 2 days Wed 12/17/14 Thu 12/18/14 49 SVEPL
51 PCC & flooring n construction of drain chamber 2 days Fri 12/19/14 Mon 12/22/14 50 SVEPL
52 Construction of retainer wall 3 days Tue 12/23/14 Thu 12/25/14 51 SVEPL
53 Back filling, levelling and compaction 3 days Fri 12/26/14 Tue 12/30/14 52 SVEPL
54 Plastering 2 days Wed 12/31/14 Thu 1/1/15 53 SVEPL
55 White washing 1 day Fri 1/2/15 Fri 1/2/15 54 SVEPL
56 Cable trench works 34 days Fri 1/2/15 Wed 2/18/15 8
57 Excavation 5 days Fri 1/2/15 Thu 1/8/15 54 SVEPL
58 Sand filling 2 days Fri 1/9/15 Mon 1/12/15 57 SVEPL
59 PCC 3 days Tue 1/13/15 Thu 1/15/15 58 SVEPL
60 Shuttering 5 days Fri 1/16/15 Thu 1/22/15 59 SVEPL
61 Reinforcement 4 days Fri 1/23/15 Wed 1/28/15 60 SVEPL
62 Raft concreting 2 days Thu 1/29/15 Fri 1/30/15 61 SVEPL
63 Shuttering 5 days Mon 2/2/15 Fri 2/6/15 62 SVEPL
HBL
SVEPL
HBL
HBL
SVEPL
SVEPL
CEA/SVEPL
SVEPL
SVEPL
SVEPL
HBL/NNE
SVEPL
SVEPL
NNE
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
rter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Timing plan for 110 KV project for M/s. HBL
M/s. Shri Vaari Electricals
ID Task Name Duration Start Finish Predecessors Resource Names
64 Side wall concreting 3 days Mon 2/9/15 Wed 2/11/15 63 SVEPL
65 Curing 5 days Thu 2/12/15 Wed 2/18/15 64 SVEPL
66 Fire barrier wall 69 days Tue 12/2/14 Fri 3/6/15 8
67 Excavation for columns 3 days Tue 12/2/14 Thu 12/4/14 48 SVEPL
68 Sand filling 2 days Fri 12/5/14 Mon 12/8/14 67 SVEPL
69 PCC 2 days Tue 12/9/14 Wed 12/10/14 68 SVEPL
70 Shuttering 5 days Thu 12/11/14 Wed 12/17/14 69 SVEPL
71 Reinforcement 5 days Thu 12/18/14 Wed 12/24/14 70 SVEPL
72 Mat concreting 2 days Thu 12/25/14 Fri 12/26/14 71 SVEPL
73 Shuttering 2 days Mon 12/29/14 Tue 12/30/14 72 SVEPL
74 Raising of columns upto plinth beam level 3 days Wed 12/31/14 Fri 1/2/15 73 SVEPL
75 Reinforcement for plinth beam 2 days Mon 1/5/15 Tue 1/6/15 74 SVEPL
76 Shuttering 2 days Wed 1/7/15 Thu 1/8/15 75 SVEPL
77 Concreting 2 days Fri 1/9/15 Mon 1/12/15 76 SVEPL
78 Curing 3 days Tue 1/13/15 Thu 1/15/15 77 SVEPL
79 Raising of columns up to intermediate level 5 days Fri 1/16/15 Thu 1/22/15 78 SVEPL
80 Reinforcement 2 days Fri 1/23/15 Mon 1/26/15 79 SVEPL
81 Shuttering 2 days Tue 1/27/15 Wed 1/28/15 80 SVEPL
82 Lapping of reinforcement 1 day Thu 1/29/15 Thu 1/29/15 81 SVEPL
83 Concreting up tie beam level 3 days Fri 1/30/15 Tue 2/3/15 82 SVEPL
84 Curing 3 days Wed 2/4/15 Fri 2/6/15 83 SVEPL
85 Brick work construction 6 days Mon 2/9/15 Mon 2/16/15 84 SVEPL
86 Plastering 5 days Tue 2/17/15 Mon 2/23/15 85 SVEPL
87 Curing 7 days Tue 2/24/15 Wed 3/4/15 86 SVEPL
88 Whitewashing 2 days Thu 3/5/15 Fri 3/6/15 87 SVEPL
89 Burnt oil pit 35 days Fri 1/2/15 Thu 2/19/15 8
90 Excavation 2 days Fri 1/2/15 Mon 1/5/15 54 SVEPL
91 Sand filling 2 days Tue 1/6/15 Wed 1/7/15 90 SVEPL
92 PCC 2 days Thu 1/8/15 Fri 1/9/15 91 SVEPL
93 Reinforcement for raft and wall 2 days Mon 1/12/15 Tue 1/13/15 92 SVEPL
94 Shuttering for raft 1 day Wed 1/14/15 Wed 1/14/15 93 SVEPL
95 Concreting of raft 1 day Thu 1/15/15 Thu 1/15/15 94 SVEPL
96 Curing 5 days Fri 1/16/15 Thu 1/22/15 95 SVEPL
97 Shuttering for wall 2 days Fri 1/23/15 Mon 1/26/15 96 SVEPL
98 Concreting of walls 1 day Tue 1/27/15 Tue 1/27/15 97 SVEPL
99 Curing 5 days Wed 1/28/15 Tue 2/3/15 98 SVEPL
100 Shuttering for roof slab 3 days Wed 2/4/15 Fri 2/6/15 99 SVEPL
101 Reinforcement for roof slab 2 days Mon 2/9/15 Tue 2/10/15 100 SVEPL
102 Concreting for roof slab 2 days Wed 2/11/15 Thu 2/12/15 101 SVEPL
103 Curing 5 days Fri 2/13/15 Thu 2/19/15 102 SVEPL
104 Yard levelling works 13 days Thu 4/2/15 Mon 4/20/15
105 Filling of selected earth 3 days Thu 4/2/15 Mon 4/6/15 160 SVEPL
106 Consolidation 4 days Tue 4/7/15 Fri 4/10/15 105 SVEPL
107 Ramming 6 days Mon 4/13/15 Mon 4/20/15 106 SVEPL
108 Storm water drain 18 days Thu 4/23/15 Mon 5/18/15
109 Excavation 3 days Thu 4/23/15 Mon 4/27/15 117 SVEPL
110 PCC 2 days Tue 4/28/15 Wed 4/29/15 109 SVEPL
111 Brick work construction 3 days Thu 4/30/15 Mon 5/4/15 110 SVEPL
112 Plastering 3 days Tue 5/5/15 Thu 5/7/15 111 SVEPL
113 Flooring 3 days Fri 5/8/15 Tue 5/12/15 112 SVEPL
114 Fixing of MS grating 3 days Wed 5/13/15 Fri 5/15/15 113 SVEPL
115 White washing 1 day Mon 5/18/15 Mon 5/18/15 114 SVEPL
116 Fencing retainer wall 20 days Tue 4/21/15 Mon 5/18/15
117 Excavation 2 days Tue 4/21/15 Wed 4/22/15 156,160,107 SVEPL
118 PCC 3 days Thu 4/23/15 Mon 4/27/15 117 SVEPL
119 Brick work construction 4 days Tue 4/28/15 Fri 5/1/15 118 SVEPL
120 Fixing of fencing posts 2 days Mon 5/4/15 Tue 5/5/15 119 SVEPL
121 Plastering 3 days Wed 5/6/15 Fri 5/8/15 120 SVEPL
122 Fixing of panels 2 days Mon 5/11/15 Tue 5/12/15 121 SVEPL
123 Plastering 2 days Wed 5/13/15 Thu 5/14/15 122 SVEPL
124 Whitewashing 1 day Fri 5/15/15 Fri 5/15/15 123 SVEPL
125 Filling of blue metal 2 days Fri 5/15/15 Mon 5/18/15 123 SVEPL
126 Foundation for yard flood light 17 days Fri 1/2/15 Mon 1/26/15
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
rter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Timing plan for 110 KV project for M/s. HBL
M/s. Shri Vaari Electricals
ID Task Name Duration Start Finish Predecessors Resource Names
127 Excavation 3 days Fri 1/2/15 Tue 1/6/15 54 SVEPL
128 PCC 2 days Wed 1/7/15 Thu 1/8/15 127 SVEPL
129 Reinforcement 2 days Fri 1/9/15 Mon 1/12/15 128 SVEPL
130 Shuttering 2 days Tue 1/13/15 Wed 1/14/15 129 SVEPL
131 Concreting with foundation bolts 2 days Thu 1/15/15 Fri 1/16/15 130 SVEPL
132 Curing 5 days Mon 1/19/15 Fri 1/23/15 131 SVEPL
133 Whitewashing 1 day Mon 1/26/15 Mon 1/26/15 132 SVEPL
134 Delivery of equipment 90 days Wed 9/17/14 Tue 1/20/15
135 Lattice type structurals 45 days Wed 9/17/14 Tue 11/18/14 17 SVEPL
136 CT and PT 70 days Wed 9/17/14 Tue 12/23/14 17 SVEPL
137 SF6 breaker 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
138 Lightning arrestor 60 days Wed 9/17/14 Tue 12/9/14 17 SVEPL
139 Power transformer 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
140 Distribution transformer 80 days Wed 9/17/14 Tue 1/6/15 17 SVEPL
141 Isolator 80 days Wed 9/17/14 Tue 1/6/15 17 SVEPL
142 Psot Insulators 70 days Wed 9/17/14 Tue 12/23/14 17 SVEPL
143 11 KV panels 70 days Wed 9/17/14 Tue 12/23/14 17 SVEPL
144 LT panels 70 days Wed 9/17/14 Tue 12/23/14 17 SVEPL
145 C&R panels 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
146 Control cables & accessories 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
147 Cable tray and accessories 50 days Wed 9/17/14 Tue 11/25/14 17 SVEPL
148 Earth flats and accessories 30 days Wed 9/17/14 Tue 10/28/14 17 SVEPL
149 N2 system 80 days Wed 9/17/14 Tue 1/6/15 17 SVEPL
150 NGR 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
151 Battery and Battery chargers 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
152 Safety items 70 days Wed 9/17/14 Tue 12/23/14 17 SVEPL
153 Other sundry items 90 days Wed 9/17/14 Tue 1/20/15 17 SVEPL
154 Erection 19 days Fri 3/6/15 Wed 4/1/15
155 Structurals erection 12 days Fri 3/6/15 Mon 3/23/15 135,35 SVEPL
156 Equipment erection 7 days Tue 3/24/15 Wed 4/1/15 155,137,136,138,139,140,141,142,143,149 SVEPL
157 Earthing works 19 days Fri 3/6/15 Wed 4/1/15
158 Excavation for earth mat 5 days Fri 3/6/15 Thu 3/12/15 35,148 SVEPL
159 Earth flat laying 8 days Fri 3/13/15 Tue 3/24/15 158 SVEPL
160 Earth mat termination 6 days Wed 3/25/15 Wed 4/1/15 159 SVEPL
161 Cabling 14 days Wed 3/11/15 Mon 3/30/15
162 Cable laying 7 days Wed 3/11/15 Thu 3/19/15 166,65 SVEPL
163 Termination 7 days Fri 3/20/15 Mon 3/30/15 162 SVEPL
164 Tray works 14 days Thu 2/19/15 Tue 3/10/15
165 Tray support fabrication 7 days Thu 2/19/15 Fri 2/27/15 65,147 SVEPL
166 Tray erection 7 days Mon 3/2/15 Tue 3/10/15 165 SVEPL
167 Power Transformer works 8 days Wed 1/21/15 Fri 1/30/15
168 Transformer erection 8 days Wed 1/21/15 Fri 1/30/15 139 SVEPL
169 Distribution Transformer works 10 days Wed 1/7/15 Tue 1/20/15
170 Transformer erection 10 days Wed 1/7/15 Tue 1/20/15 140 SVEPL
171 11 KV panel at Individual substation side 10 days Wed 12/24/14 Tue 1/6/15
172 HT panel erection 10 days Wed 12/24/14 Tue 1/6/15 143 SVEPL
173 N2 system 10 days Wed 1/7/15 Tue 1/20/15
174 erection 10 days Wed 1/7/15 Tue 1/20/15 149 SVEPL
175 Sundry items erection 25 days Wed 1/21/15 Tue 2/24/15
176 erection 25 days Wed 1/21/15 Tue 2/24/15 150,151,152,153,145,144 SVEPL
177 CEA 5.38 days Tue 5/19/15 Tue 5/26/15
178 Arranging for inspection 4 days Tue 5/19/15 Fri 5/22/15 172,170,160,132,114,87,176,36,55,88,115,124,133,103,11,163,168,173,174,125 SVEPL
179 Receipt of safety certificate 6 days Fri 5/22/15 Tue 5/26/15 178 CEA
180 Precomissioning and testing 2 days Tue 5/26/15 Thu 5/28/15 179 SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
CEA
5/28
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
rter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Timing plan for 110 KV project for M/s. HBL
M/s. Shri Vaari Electricals