Académique Documents
Professionnel Documents
Culture Documents
DESIGN EXAMPLES
A.1 INTRODUCTION
The following examples are for unguyed tangent transmission and
distribution (T/D) poles. They have been included to illustrate some of
the concepts presented in this manual. The examples use force coefcients
(drag coefcients, shape factors) that are based on the minimum recom-
mendations of the 1991 edition of American Society of Civil Engineers
(ASCE) Manual 74 (ASCE 1991). For wind on poles, the force coefcient
values were selected using ASCE Manual 74, Table 2-3 (ASCE draft). For
wire loads, force coefcients of 1.0 are used for all wires, with or without
ice. In the calculation of wind forces on both wires and poles, the selection
of appropriate force coefcients is very important. Supplemental infor-
mation on force coefcients can be found in Appendix H of ASCE Manual
74 (ASCE draft) as well as in other specications such as in Appendix B
of ASCE 7-02 (ASCE 2002) and International Electrotechnical Commission
(IEC) Standard IEC 60826 (IEC 2002). Information in ASCE Manual 74
(ASCE draft), Appendix H, for example, suggests that force coefcients
greater than 1.0 may be appropriate for small-diameter (
-in.) wire,
and IEC 60826 recommends force coefcients between 1.0 and 1.4 for
ice-covered wires.
The design parameters used for these examples do not represent all
possible load conditions, structure types, or components but do provide
insight into how to properly apply the reliability-based design (RBD)
methodology discussed herein. These examples demonstrate how the
loading requirements prescribed in the working draft of ASCE Manual 74
can be used to determine the size of various pole types for different grades
of construction. Examples are given for wood, steel, concrete, and ber-
reinforced polymer (FRP) poles based on pole bending (strength being
the only design criterion). These examples do not consider other design
criteria such as electrical clearances or seismic effects. In each example the
pole size is initially established based on a calculated groundline moment
(GLM), and then the pole strength is veried at other locations along the
53
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
54 RELIABILITY-BASED DESIGN OF UTILITY POLE STRUCTURES
pole. As implemented, this GLM accounts for the deected shape (P-)
effect.
The poles in each of the examples are sized for National Electrical Safety
Code (NESC) (IEEE 2002) Grades B and C construction using the load fac-
tors given in Table 2-3 in Chapter 2 of this manual. As illustrated in the
examples, weather-related loads on poles are independent of material
type. Wind loading on the pole structure depends on the geometry of the
pole (including the projected wind area of the pole above groundline), the
height of the vertical centroid of the applied wind pressure, and the pole
force coefcient (round, polygonal).
A.2 EXAMPLE LOAD REQUIREMENTS
In the following examples, two different pole congurations will be
considered, each assumed to be governed by different loading condi-
tions. A transmission pole will be designed for an extreme wind loading
and a distribution pole will be designed for a combined ice and wind
loading, both in accordance with the criteria set forth in the working
draft of ASCE Manual 74 (ASCE draft). (In practical applications, the
controlling condition will often correspond to that of extreme wind
loading, for both transmission and distribution poles.) For all exam-
ples, both pole congurations assume weight spans that are equal to
the wind spans, although this is not often the case in actual practice.
Note that the wind force formula used in the working draft of ASCE
Manual 74 (ASCE draft), Eq. 2.1-1, is the same as formula specied in
the National Electric Safety Code (IEEE 2002) for extreme wind loading.
This design process is an iterative one. Most methods require that an
assumption be made regarding pole size. This pole size is then ana-
lyzed for the forces it must support. Based on this analysis, if a different
pole size is required the analysis should be repeated to verify the ade-
quacy of the pole.
Transmission Pole Design (Las Vegas, Nevada)
Consider a 75-ft-long pole (65.5-ft height above ground), of the congu-
ration indicated, and subject to the following conditions and parameters
(Fig. A-1):
ASCE Extreme Wind: 90 mph, Exposure C
Design for two grades of construction: NESC (IEEE 2002) Grade B
and Grade C
Wire Parameters:
Conductor: 795 aluminum conductor steel-reinforced (ACSR) (26/7)
Dia. 1.108 in., Wt 1.091 lb/ft
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
Shield Wire: 3/8-in. high-speed steel (HSS)
Dia. 0.36 in., Wt 0.273 lb/ft
Communication Wire:
Dia. 2.0 in., Wt 2.25 lb/ft
Span Parameters:
Wind and Weight Spans 500 ft
(3) Phase Conductors:
(1) 3/8 OHGW
795 (26/7) ACSR
56 from Pole CL
Groundline
(1) Communication Wire:
2 Diameter
P
o
l
e
L
e
n
g
t
h
=
7
5
f
t
3
5
.
5
1
4
9
.
5
dl
1.1, and for Grade C the corresponding load factors are
wind
0.5
for poles that do not extend more than 60 ft above ground; for those that
do,
wind
1.0 and
dl
= 1.1. The GLM for each pole design is calculated by
multiplying each of these forces by their respective load factors and their
corresponding distances from the groundline. In addition, the eccentricity
of the conductor arrangement is accounted for by multiplying the weight
of one conductor (616 lb) times its offset from the centerline of the pole
(~5.5 ft). The calculations for the wire-related GLMs follow. Since for all
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
TABLE A-1. Loads for Transmission Pole Design Example
Line Component
Wind Pressure
(psf)
Wind Area
(ft
2
)
Wind Force
(lb)
Wind on Conductors
(ea)
17.16 46.17 792
Wind on Shield Wire 17.64 15.00 265
Wind on
Communication
Wire
16.01 83.33 1,334
Wind on Pole 19.97 C
f
Varies with pole geometry
transmission pole examples the pole extends 65.5 ft above ground and
extreme wind is the applied load case, the load factors (
wind
1.0 and
dl
1.1) and the wire-related loading are the same for both Grade B and
Grade C construction. The moment due to wind on the pole is specic to
pole geometry and will be calculated for each specic design example. The
net result is that for each transmission example, the same-sized poles are
required for Grade B and Grade C construction to meet the extreme wind
load case (Table A-2).
Distribution Pole Design (Portland, Oregon)
Consider a 45-ft long pole (38.5 ft height above ground), of the con-
guration indicated (Fig. A-2) and subject to the following conditions and
parameters:
ASCE Combined Ice and Wind: 50-mph wind plus 1-in. ice
Design for two grades of construction: Grade B and Grade C
Wire Parameters:
Conductor: 336.4 ACSR (26/7)
Dia. 0.72 in., Wt 0.462 lb/ft
Neutral Wire: 3/0 all-aluminum conductor (AAC)
Dia. 0.464 in., Wt 0.156 lb/ft
Communication Cable (+ Messenger):
Dia. 1.5 in., Wt 1.12 lb/ft
Span Parameters:
Wind and Weight Spans 275 ft.
In accordance with Eq. 2.1-1 of the working draft of ASCE Manual 74
(ASCE draft), the wind force, F, in pounds is calculated:
Appendix A: Design Examples 57
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
58 RELIABILITY-BASED DESIGN OF UTILITY POLE STRUCTURES
F Q K
z
(V)
2
G C
f
A
where
Q air density factor = 0.00256
K
z
velocity pressure exposure coefcient, given by 2.01 (H/900)
(2/9.5)
,
where H effective height (ft), which yields the following values
for K
z
1.029 for conductors,
1.005 for neutral wire,
0.975 for communication wire, and
0.951 for pole.
V 3-s gust wind velocity 50 mph
G gust response factor, given by (1 2.7 E B
0.5
) / k
v
2
, as
described in the working draft of ASCE Manual 74 (ASCE draft)
or the National Electric Safety Code (IEEE 2002) for wires and
structures, where
E exposure factor,
TABLE A-2. Groundline Moment (GLM)
Grade B Grade C
Line
Component
Force
(lb)
Distance
(ft)
GLM
(ft-lb)
GLM
(ft-lb)
Wind on Top
Conductor
792 59.5 1.0 47,124 1.0 47,124
Wind on Middle
Conductor
792 54.5 1.0 43,164 1.0 43,164
Wind on Bottom
Conductor
792 49.5 1.0 39,204 1.0 39,204
Wind on Shield
Wire
265 64.5 1.0 17,093 1.0 17,093
Wind on
Communication
Wire
1334 35.5 1.0 47,357 1.0 47,357
Conductor
Eccentricity
546 5.5 1.1 3,300 1.1 3,300
Subtotal
(without
pole wind force)
197,242 197,242
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
P
o
l
e
L
e
n
g
t
h
=
4
5
f
t
2
9
4
.
5
6
.
5
buckling load, as calculated below.
P
cr
= P
cr
'*P
*
,
where,
MOE I
2* * 144
[ ]
=
2
2
* *
'
top
P
cr
L
and
=
2.7
bottom
top
D
P
*
D
.
Note: The 2.7 exponent in the above equation is applicable only for
solid, round cross sections.
FIGURE A-3. Calculation of P- Effect.
= Diameter at Top
a
= Diameter at Groundline
D
top
P
cr
D
bottom
L
=
B
u
c
k
l
i
n
g
L
e
n
g
t
h
Appendix A: Design Examples 73
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.
74 RELIABILITY-BASED DESIGN OF UTILITY POLE STRUCTURES
As an example, in the Wood Transmission Pole (Grade B construction)
example in Section A.3, the amplication factor of 1.112 was calculated as:
VL factored weight of pole (above ground) cross-arms wires
(3,551 0 3,111) 1.10
7,328 lb
L distance from groundline to centroid of horizontal loads
43.80 ft
D
top
12.67 in.
D
bottom
18.33 in.
MOE mean modulus of elasticity for kiln-dried Douglas r pole
2,376 ksi
I
top
moment of inertia for D
top
of 12.64 in.
D
top
4
/ 64
1,265 in.
4
Thus,
P
cr
26,845 lb
P* 2.71
P
cr
72,750 lb, which yields an amplication factor = 1.112.
Note: This example uses the conservative approach of applying the full
weight of the pole above ground (3,551 lb) in the calculation of the con-
centrated load that is applied to the top of the pole, VL. Since a large por-
tion of this load is in the lower portion of the pole and thus has a lesser
inuence on P-, a less-conservative approach would be to use only a por-
tion of the pole weight to calculate the value, VL. In this case, using only
one-third of the poles weight would result in an amplication factor of
1.069 rather than 1.112, effecting a total GLM that is approximately the
same as that obtained using nonlinear analysis techniques. Should such a
reduction factor be used, it must be carefully selected to avoid producing
nonconservative results.
Reliability-Based Design of Utility Pole Structures
D
o
w
n
l
o
a
d
e
d
f
r
o
m
a
s
c
e
l
i
b
r
a
r
y
.
o
r
g
b
y
e
r
i
c
c
a
s
t
i
l
l
o
o
n
1
2
/
0
9
/
1
3
.
C
o
p
y
r
i
g
h
t
A
S
C
E
.
F
o
r
p
e
r
s
o
n
a
l
u
s
e
o
n
l
y
;
a
l
l
r
i
g
h
t
s
r
e
s
e
r
v
e
d
.