Vous êtes sur la page 1sur 10

USER MANUAL SUPRIT DAS

CREATIONS OF ROUTING SAP PP CONSULTANT


1
CREATIONS OF ROUTNG
INITIAL SCREEN

PRESS ENTER


PRESS ENTER
I
Enter TCODE:CA01
Enter the Material Code
for which you want to
create a routing
Enter the Plant Name

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
2
FILL THE REQUIRED PARAMETERS IN THE ROUTING HEADER
DATAILS



STATUS:You use the status key to indicate the processing status of a task list. For
example, you can indicate whether the task list is still in the creation phase or has
already been released.
Enter Usage Value: 1
Enter Staus: 4(Released)
You can see the Validity
period,Created by,created on of the
Routing auto generated

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
3
CLICK ON THE OPERATIONS TAB TO ENTER THE DETAILED OPERATIONS




Enter the
Workcenter
Code No
Enter the
Control
Key
Enter the Desired
operations
Enter the Activity durations &
unit

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
4
CLICK ON THE COMPONENTS ALLOCATIONS TAB ON THE
OPERATIONS OVERVIEW SCREEN

You can have a look at the particular BOM components




USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
5
ASSIGNMENT OF BOM COMPONENT TO PARTICULAR
OPERATIONS
Click on the Components on which you want to allocate the Operations and select the
NEW ASSIGNMENT tab (upper).
Assign the activity no and press the button

Other wise all the BOM Components will be allocated to the First Operations In
the Routing by Default.
2
nd
Click on the
tab
Ist select the the
component for
Operations
allocations
3
rd

Enter the Activity
on which you want
to allocate the
component &
press enter

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
6
For eg: BOM has been assigned to the particular operations
You can also REASSIGN the particular Components to any other operations by
simply pressing the REASSIGN TAB
PRESS THE SAVE BUTTON
Blue color
highlighting the
Allocated
component for
the operations 10

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
7
CHECKING OF WORKCENTER DESCRIPTIONS ON THE SAME SCREEN
1) Select the Workcenter you want to see it in detail or double click on the desired
Workcenter.

2)Here you can only see /view the Workcenter(Display mode).You cant make any
change here.


USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
8
ADDITIONS OF PRODUCTIONS RESOURCES TOOLS(PRT)
1)Select the Operations on which you want to assign particular PRT.
2)Click on the PRT tabs



Select the
Operations
Click on the
PRT tabs

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
9

3)Put the desired PRT you want to assigned in that particular Operations
4)Then Click on the Button.

NOTE: Before assigning PRT ,at first you have to maintain the Material Master of the
desired PRT in SAP.

Enter the PRT
Material Code.
Click this button

USER MANUAL SUPRIT DAS
CREATIONS OF ROUTING SAP PP CONSULTANT
10

Vous aimerez peut-être aussi