Question1
Marks: 4/4
See some processes below:
(1) Material Planning
(2) Procure to Pay process
(3) Order to Cash process
(4) Manufacturing Execution Process

Which one is/are included in Production Planning?
Choose one answer.

a. only (1) and (4)

b. only (1), (2) and (3)

c. only (1), (2) and (4)

d. only (2) and (4)
Submit

Correct
Marks for this submission: 4/4.
Question2
Marks: 4/4
Routings enable the company to plan the production of materials (products) since it can give the information about
the series of sequential steps or operations.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question3
Marks: 4/4
In product grouping for hierarchical grouping
Choose one answer.

a. no correct answer

b. The lowest level always consist of materials

c. The lowest level always not consist of materials

d. The lowest level may consist of materials
Submit

Correct
Marks for this submission: 4/4.
Question4
Marks: 4/4
Production Scheduler works for strategic planning activities.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question5
Marks: 4/4
Below is the internal procurement type, except
Choose one answer.

a. Production order

b. Schedule line

c. Planned order

d. Process order
Submit

Correct
Marks for this submission: 4/4.
Question6
Marks: 4/4
In Production Plan Process.........is the process of predicting future demand for a companys products.
Choose one answer.

a. Master Production Scheduling

b. Material Requirement Planning

c. Sales Forecasting

d. Sales and Operations Planning
Submit

Correct
Marks for this submission: 4/4.
Question7
Marks: 4/4
In SAP, we can create the sales and operation plan which is based on historical consumption.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question8
Marks: 4/4
If "<--" stands for "consist of" and A <-- B, C, D, E. The dependent demand includes the requirement for B, C, D,
and E materials
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question9
Marks: 4/4
In Work Center, costing data may include cost center and does not contain the information about the activity types.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question10
Marks: 4/4

Which one is/are correct statement(s) regarding to the Bill of Material (BOM)
1. A BOM is a hierarchical depiction of the materials needed to produce a finished good or semifinished good.
2. BOM is defined for a material at the storage location level.
3. BOMs range from very simple to very complex, depending on the material.
4. A BOM can contain different types of items, which are distinguished by the item category

Choose one answer.

a. all statements are correct

b. only (1), (3), (4)

c. only (1) is correct

d. only (1) and (4)
Submit

Correct
Marks for this submission: 4/4.
Question11
Marks: 4/4
As a result of MRP process, planned order can be converted either into internal procurement or external
procurement.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question12
Marks: 4/4
Plant is an organizational unit in Production Planning, allowing differentiation between the various stocks of a
material in a plant.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question13
Marks: 4/4
Demand management links between Strategic Planning (SOP) & Detailed Planning (MPS/MRP)
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question14
Marks: 4/4
Master production scheduling (MPS) focuses exclusively on the requirements for the top-level items in the BOM.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question15
Marks: 4/4
The backward multi-level scheduling in procurement, starts from requirements date.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question16
Marks: 4/4
Planned order, production order, and purchase orders are the orders which are occurred in planning level.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question17
Marks: 4/4
We need the data from sales information system exactly before we perform the sales and operations planning.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question18
Marks: 4/4
Assume the "<--" stands for "consists of" and consider the case study below.
A <-- B, C, D, E.
Choose one answer.

a. This is neither a single level BOM, nor a multi level BOM

b. This is a multi level BOM

c. non of all choices are correct

d. This is a single level BOM
Submit

Correct
Marks for this submission: 4/4.
Question19
Marks: 4/4
In static lot-sizing procedures, the procurement quantity is calculated exclusively by means of the quantity
specifications entered in the material master.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question20
Marks: 4/4
The........process determines the amount and timing of raw material orders.
Choose one answer.

a. Demand Management

b. Detailed Scheduling

c. Materials Requirements Planning (MRP)

d. Forecasting
Submit

Correct
Marks for this submission: 4/4.
Question21
Marks: 4/4
Trend forecasting: long-term forecasting, which includes the process of analysis and evaluation that can be identified
by scanning a variety of sources for information.
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question22
Marks: 4/4
The data in work center can be user for the following activities, except
Choose one answer.

a. Costing

b. Capacity planning

c. Scheduling

d. Sales forecasting
Submit

Correct
Marks for this submission: 4/4.
Question23
Marks: 4/4
The material requirement process (MRP) includes the following logical steps, except
Choose one answer.

a. Gross requirement calculation

b. BOM explosion

c. Lot size calculation

d. Scheduling
Submit

Correct
Marks for this submission: 4/4.
Question24
Marks: 4/4
Demand program is commonly represented as the output of the process which is requiring information from
forecasting and sales activities
Answer:
True False
Submit

Correct
Marks for this submission: 4/4.
Question25
Marks: 4/4
............is the quantity of material that is specified in the procurement proposals generated by the material planning
process
Choose one answer.

a. Lot size

b. no correct answer

c. Inventory plan

d. Safety stock
Submit

Correct
Marks for this submission: 4/4.