Vous êtes sur la page 1sur 5

2

0 20 40 60 80 100 120 140 160


P
O
N
M
L
K
J
I
H
G
F
E
D
C
B
A
Time
Gantt Chart
Critical Activity Noncritical Activity Slack
3
Activity
Time Pred 1 Pred 2 Pred 3 Pred 4 Pred 5
Need survey A 20
Set product specs B 15 A
Shelf life report C 10 B
Nutrition report D 5 B
Select fruit suppliers E 20 C D
Equyipment rehab F 30 B
Production Trials G 15 E F
Quality trials H 20 G
Quality Metrics I 5 H
Quality training J 15 I
Market testing K 30 C D
Package design L 15 K
Select Distributors M 25 C D
Complete FDA
Certification N 15 E K
Regiuster trademark O 5 E K
Prepare product Launch P 15 J L M N O



ID Task Name Start Finish Late Start Late Finish
Free
Slack
Total
Slack

POM+Project Tuesday, 03 January, 2012 Thursday, 12 July, 2012 Tuesday, 03 January, 2012 Thursday, 12 July, 2012 0 0

R&D Product development Tuesday, 03 January, 2012 Tuesday, 06 March, 2012 Tuesday, 03 January, 2012 Tuesday, 06 March, 2012 0 0
A Need survey Tuesday, 03 January, 2012 Saturday, 21 January, 2012 Tuesday, 03 January, 2012 Saturday, 21 January, 2012 20 0
B Set product specs Wednesday, 01 February, 2012 Tuesday, 21 February, 2012 Wednesday, 01 February, 2012 Tuesday, 21 February, 2012 35 0
C Shelf life report Wednesday, 22 February, 2012 Tuesday, 06 March, 2012 Wednesday, 22 February, 2012 Tuesday, 06 March, 2012 45 0
D Nutrition report Wednesday, 22 February, 2012 Tuesday, 28 February, 2012 Wednesday, 22 February, 2012 Tuesday, 28 February, 2012 45 5
E Select fruit suppliers Wednesday, 07 March, 2012 Tuesday, 03 April, 2012 Wednesday, 07 March, 2012 Tuesday, 03 April, 2012 65 0

Initial Production Wednesday, 22 February, 2012 Wednesday, 20 June, 2012 Wednesday, 22 February, 2012 Wednesday, 20 June, 2012 0 0
F Equyipment rehab Wednesday, 22 February, 2012 Tuesday, 03 April, 2012 Wednesday, 22 February, 2012 Tuesday, 03 April, 2012 65 0
G Production Trials Wednesday, 04 April, 2012 Tuesday, 24 April, 2012 Wednesday, 04 April, 2012 Tuesday, 24 April, 2012 80 0
H Quality trials Wednesday, 25 April, 2012 Tuesday, 22 May, 2012 Wednesday, 25 April, 2012 Tuesday, 22 May, 2012 100 0
I Quality Metrics Wednesday, 23 May, 2012 Wednesday, 30 May, 2012 Wednesday, 23 May, 2012 Wednesday, 30 May, 2012 105 0
J Quality training Thursday, 31 May, 2012 Wednesday, 20 June, 2012 Thursday, 31 May, 2012 Wednesday, 20 June, 2012 120 0

Distribution Wednesday, 07 March, 2012 Tuesday, 08 May, 2012 Wednesday, 07 March, 2012 Tuesday, 08 May, 2012 5 5
K Market testing Wednesday, 07 March, 2012 Tuesday, 17 April, 2012 Wednesday, 07 March, 2012 Tuesday, 17 April, 2012 105 30
L Package design Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 120 30
M Select Distributors Wednesday, 07 March, 2012 Tuesday, 10 April, 2012 Wednesday, 07 March, 2012 Tuesday, 10 April, 2012 120 50

Legal Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 5 5
N Complete FDA Certification Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 Wednesday, 18 April, 2012 Tuesday, 08 May, 2012 120 30
O Regiuster trademark Wednesday, 18 April, 2012 Tuesday, 24 April, 2012 Wednesday, 18 April, 2012 Tuesday, 24 April, 2012 120 40
P Prepare product Launch Thursday, 21 June, 2012 Thursday, 12 July, 2012 Thursday, 21 June, 2012 Thursday, 12 July, 2012 135 0







Memo
To:
From:
cc:
Date: February 5, 2014
Re: The POM+ Project

This memo is to inform you that the POM+ Project is estimated to be complete on July 26, 2012. It will
take 135 working days based on eight-hour days, with allowance for federal holidays. The critical path
is: Needs Survey, Set Product Specs, Shelf Life Report, Secure Fruit Suppliers, Equipment Rehab,
Production Trials, Quality Trials, Quality Metrics, Quality Training, and Prepare Product Launch.
Selecting distributors had the most total slack. The network is very sensitive, the majority of the task
are dependent on the task before it. The project start date, production trials, and project end are
milestones. These project starts are associated with a group of tasks necessary to achieve the
significant event. The project team can easily recognize the number of tasks that need to be
completed to achieve the milestone. They are event markers.
AS

Vous aimerez peut-être aussi