REHABILITATION AND UPGRADING OF EXISTING PASSENGER TERMINAL BUILDING , ROAD CAR PARK AND PARKING APRON AT DAMASCUS INTERNATIONAL

AIRPORT
SYRIAN ARAB REPUBLIC
Dated: 09/12/09
M&E Testing & Commissioning

Item Sub Con Description of Testing & Commissioning Schedule Actual

1 Electrical Boards (MSBs, SSBs, DBs) 10/26/2009 11/8/2009

KEMJ 10/28/2009
2 Public Address 10/27/2009
11/14/2009

3 Generator Set 11/2/2009 11/7/2009

4 Uninteruptable Power Supply, UPS 11/5/2009 11/8/2009

5 Telephone System 11/25/2009 TBA

Palmac
6 Plumbing Services 10/28/2009 11/3/2009
Construction
11/3/2009

11/17/2009

11/19/2009

11/21/2009
Meridian
7 Fire Protection Services 11/3/2009 11/23/2009
Engineering
Meridian
7 Fire Protection Services 11/3/2009
Engineering

8 Baggage Handling System, BHS 11/4/2009 TBA


9 Airconditioning & Mechanical Ventilation System 11/9/2009 TBA

11/10/2009
10 Networking System 11/9/2009
KLIA INFORMATIK

06 - 07/01/10

11/11/2009
11 Flight Information Display System, FIDS 11/12/2009
11/16/2009

12 Close Circuit Television, CCTV 10 - 14/01/10 TBA


13 Network Training 10 – 11/01/10 TBA
14 FIDS Training 13 – 14/01/10 TBA
15 CCTV Training 17 – 18/01/10 TBA
M&E Outstanding Work
Daily work progress
Item Sub Con Services Description of Outstanding Works
Previous Current
1
Local Electrical Cabling work for mobile genset 0% 0%
supplier
2 Electrical Termination of essential supply to EMSB. 0% 0%

3 Electrical Electrical Panel MSB, SSB, DB type tested. 0% 0%


KEMJ
4 Electrical Alternator issue 0% 0%

5 Electrical Fitting installation for Keluar Sign fitting 65% 0%


Leakage of hot water tank at New Arrival Public toilet & VIP
6 Plumbing 0% 0%
toilet (4 nos leaked as-off todate).
Fire
Beam detector. 0% 0%
Protection

7 CUPS CUPS software 0% 0%

KLIA Info
8 CCTV Image focusing and joystick at control room mulfunction. 0% 0%
9 CCTV Additional 3 nos CCTV camera / DVR / Monitor 0% 0%
Rectification work for all existing AHU as requested by
10
SCAA :
11 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
12 ACMV b) Duct insulation for existing ductworks 0% 0%
G3-1
13 c) Motor changed/fan inspected 90% 10%
a) Hot & Chilled Water Pipes Insulation for existing
14 0% 0%
pipes
AHU
15 ACMV b) Duct insulation for existing ductworks 0% 0%
G3-2
16 c) Motor changed/fan inspected 90% 10%
17 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
18 ACMV b) Duct insulation for existing ductworks 100% 0%
GT-1
19 c) Motor changed/fan inspected 90% 10%
20 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
21 ACMV b) Duct insulation for existing ductworks 100% 0%
GT-2
22 c) Motor changed/fan inspected 90% 10%
23 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
24 ACMV b) Duct insulation for existing ductworks 100% 0%
C1W
25 c) Motor changed/fan inspected 90% 10%
26 a) Hot Water Pipes Insulation for existing pipes 0% 10%
AHU
27 ACMV b) Duct insulation for existing ductworks 100% 0%
C4E
28 c) Motor changed/fan inspected 100% 0%
29 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
30 ACMV b) Duct insulation for existing ductworks 100% 0%
K6W
31 Pathfinder c) Motor changed/fan inspected 100% 0%
32 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
33 ACMV b) Duct insulation for existing ductworks 0% 20%
I6E
34 c) Motor changed/fan inspected 90% 10%
35 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
36 ACMV b) Duct insulation for existing ductworks 100% 0%
K7W
37 c) Motor changed/fan inspected 90% 10%
38 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
39 ACMV b) Duct insulation for existing ductworks 100% 0%
I6W
40 c) Motor changed/fan inspected 90% 10%
41 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
42 ACMV b) Duct insulation for existing ductworks 100% 0%
I5E
43 c) Motor changed/fan inspected 90% 10%
44 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
45 ACMV b) Duct insulation for existing ductworks 100% 0%
K6E
46 c) Motor changed/fan inspected 90% 10%
47 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
48 ACMV b) Duct insulation for existing ductworks 0% 0%
E4E1
49 c) Motor changed/fan inspected 90% 10%
50 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
51 ACMV b) Duct insulation for existing ductworks 0% 0%
D7E
52 c) Motor changed/fan inspected 90% 10%
53 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
54 ACMV b) Duct insulation for existing ductworks 0% 0%
C5W
55 c) Motor changed/fan inspected 0% 90%
56
Pathfinder a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
57 ACMV b) Duct insulation for existing ductworks 0% 0%
E7E-1
58 c) Motor changed/fan inspected 0% 90%
59 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
60 ACMV b) Duct insulation for existing ductworks 0% 0%
E7E-2
61 c) Motor changed/fan inspected 50% 40%
62 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
63 ACMV b) Duct insulation for existing ductworks 0% 0%
E6E
64 c) Motor changed/fan inspected 90% 10%
65 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
66 ACMV b) Duct insulation for existing ductworks 0% 0%
E2E
67 c) Motor changed/fan inspected 90% 10%
68 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
69 ACMV b) Duct insulation for existing ductworks 0% 0%
G4W-1
70 c) Motor changed/fan inspected 0% 0%
71 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
72 ACMV b) Duct insulation for existing ductworks 0% 0%
G4W-2
73 c) Motor changed/fan inspected 90% 10%
74 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
75 ACMV b) Duct insulation for existing ductworks 0% 0%
ZE-1
76 c) Motor changed/fan inspected 10% 90%
77
Pathfinder a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
78 ACMV b) Duct insulation for existing ductworks 0% 0%
ZE-2
79 c) Motor changed/fan inspected 10% 90%
80 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
81 ACMV b) Duct insulation for existing ductworks 0% 0%
G4-1
82 c) Motor changed/fan inspected 90% 10%
83 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
84 ACMV b) Duct insulation for existing ductworks 0% 0%
G4-2
85 c) Motor changed/fan inspected 90% 10%
86 Existing FCU unit at 1st floor transit area (4 nos):
87 ACMV b)Rectify all duct work due to poor air distribution. 0% 0%
88 c)To install grille/diffuser/flexible duct at Departure Gates 0% 0%
89 ACMV To add splitter/damper at sick bay duct branch out. 0% 0%

Pathfinder To extend condensing pipes to the nearest gutter/floor trap for


90 ACMV 100% 0%
PC 1, PC 2, PC 3 and PC 6.

91 ACMV Pressure test for chilled water and hot water system. 50% 0%

Softener test result to achieved correct water hardness. To add


92 ACMV 0% 0%
softener tank.
Installation of replacement body skirting accessories for
93 Carousal Carousel OB-1 at Departure area.(Previously damaged by 0% 0%
SCAA)
To check and rectify the damaged of conveyor belt at departure
94 Carousal 0% 0%
INTERROLLER area.
95 Carousal Review of departure carousal congestion problem at T-junction. 0% 0%

96 Carousal To clarify thermal load protection breaker rating too high. 0% 0%

To submit construction drawing for M&E and architectural. To


Presidential
97 fabricate electrical board IP44 from Malaysia. Site to clarify 0% 0%
Pavillion
design drawing.
Terminal building existing VIP roof leaking repair work. To
98 Civil work 0% 0%
provide proposal to GCEC-Halcrow for approval.

99 Civil work Apron concreting area B, C, D, E and F. 36% 1%

100 Civil work Apply silicon for area B,C,D,E and F 0% 0%

101 Civil work High mast, edge light and airfield signage installation. 0% 0%

102 Civil work GSC road construction for area B, C, and D. 0% 0%


By Others
103 Civil work Folding door modification / replacement. 0% 0%

104 Civil work Car park road cutting. 100% 0%

105 Civil work Car park road painting (repainting). 94% 1%

106 Civil work Car park water ponding rectification work. 100% 0%

107 Civil work To review drainage system comment by Halcrow. 0% 0%

108 Civil work Proposal to extent conveyor and guardrail 0% 0%

109 Civil work To rectify wearing course at departure area. 100% 0%

110 Civil work To provide clading surrounding external VIP facial. 0% 0%

111 Civil work Manhole at arrival carousal to be air tight type. 100% 0%

112 Civil work Painting at arrival rentaining wall and external void. 87% 0%

113 Civil work Painting at external departure area. 100% 0%

114 Civil work Replacement of "Terminal 1" signage. 0% 0%

Completed work.
Work in progress (WIP)

Notes:
1. Zink sheet for hot & chilled water pipe delivered to site not enough.
PARK AND PARKING APRON AT DAMASCUS INTERNATIONAL AIRPORT

Actual Remark Action

GCEC emphasize on the “type tested” panel requirement


(including DB and SSB)
GCEC advise not to terminate the new essential supply
new EMSB until the “type tested” issue resolve to avoid
inconvenient to airport operation

Meb had notified GCEC that MSB shall be VO to the Mobilazation of kitlite
contract. Meb is awaiting acknowledgement from GCEC expected on 23/12/09 in
T&C completed with comment on echo phenomenon in anticipation that balance
1st Inspection concourse area. GCEC advised Meb to treat the echo material like conduit
2nd Inspection problem. (including additional light
T&C completed but final approval subject to documents to arrive / clear by
22/12/09)
submission conforming to the specification.
T&C completed but final approval subject to the
documents submission conforming to the specification.
MEB had written to Airport Director request for fix line
for testing. MEB to coordinate with airport maintenance
team for this line. Letter sent
T&C completed with comment on damages and defective
fittings due to public rough handling.
HR & Pyrogen
T&C of Hose reel & Pyrogen system completed. T&C of
FA 1st T&C Fire Alarm System in progress

FA 2nd T&C GCEC require original catalogue submission for all fire
protection devices installed at site especially for FA
FA 3rd T&C panel. Catalogue under compilation & target to submit
12/12/09. HQ to assist getting JVK to justify:
FA 4th T&C
1) PC based graphic central control system

2) Fault isolator

3) Panel for 4 loops used against 10 loops in final


installation (whether to change the panel to 10 loops or
not).
GCEC agreed to proceed the training as per Meb/Petris
submission. Require SCAA to confirm training date.
SCAA has run boiler for heating system. Temperature 24

1st T&C First inspection at server room has been carried out.
Second inspection at access point in the ground area
pending due to inspector do not have workpass. Target to
2nd T&C carry out on 6 January 2010.
T&C completed with general comment on cleanliness of
1st T&C the monitors and replacement of some burn mark
2nd T&C monitors.
Target physical inspection on Mid Dec 2009 and official
inspection around Mid Jan 2009.
As-Off: 12/8/2009
Daily work progress
Remarks
Completed
0% No confirmation from SCAA. Please advice.
GCEC advised no to connect main electrical system to
0% the new essential supply until the "type tested" issue
KEMJ workers demob on
resolved.
2/12. HQ is arranging for
0% Please advise. Kitlite to mob tentative on
23/12/09 subject to the full
T&C completed but final approval subject to documents
0% delivery of conduit and light
submission conforming to the specification.
fittings / accessories.
65% Awaiting material from supplier Wassem.
0% HQ to order 4 nos hot water tanks.
Beam detector arrived on 8/12/09. Worker went back TKH to assist getting next
0%
without permission on 6/12/09. from Meridian.

Awaiting confirmation from SCAA to proceed with the


0% IATA compliancy audit to our system. SCAA to give
official confirmation and commitment.
0% KLIA Infomatic informed material ETA by end of Dec 09.

0% KLIA Infomatic informed material ETA by end of Dec 09.

0%
0%
100%
0%
0%
100%
0%
100%
100%
0%
100%
100%
0% Fabrication of hot water jacket completed.
100%
100%
10% Sourcing zink sheet from
local in progress. Current
100% stock 600 out of 2000 meter
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
20% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run in progress.
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run of airflow in progress.
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run in progress.
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Fabrication of hot water jacket completed. Sourcing zink sheet from
local in progress. Current
0% Dismantle of existing insulation completed.
stock 600 out of 2000 meter
0% Motor on site.
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0%
0%
100% Test run in progress.
0%
0%
100% Test run in progress.
0%
0%
100%
0%
0%
100%

0%
0%
0%

100%

Pressure test on hot water pipe completed. Pressure test


50%
for chilled water system in progress.
HQ to assist finalize the order of softener with
0%
Pathfinder.
0% Material on site.

0%

0%

Interoller claimed has sent the letter regarding this issue


0%
to MEB HQ. Ahmad please advise. TQ

0% 8/25/2009

SCAA's contractor already commence repair work on


0% 8/25/2009
26/11/09.

37% Apron F- 2 panels casted TBA TBA

0% TBA TBA

0% TBA TBA

0% TBA TBA

0% TBA TBA

100% completed

95% 12/15/2009

100% completed

0% TBA TBA

0% TBA TBA

100% TBA completed

0% Material under importation. TBA TBA

100% TBA completed

Internal completed. External texture paint approved


87% 12/15/2009
26/11/09. Appoinment of subcontractor in progress.

100% completed

Quotation received on 6-12-09, submited to GCEC on


0% 22-11-09 for approval. Appoinment of subcontractor in TBA TBA
progress.