Installation to be carried out as per manufacturers instruction. All the PEX pipes and fittings to comply to DIN80! & DIN8080 then test and commission to the satisfaction of the Engineers. 'Hec+ pipe or+ chasing is including red and blue conduits to be installed as indicated on appro#ed construction dra ings.
Installation to be carried out as per manufacturers instruction. All the PEX pipes and fittings to comply to DIN80! & DIN8080 then test and commission to the satisfaction of the Engineers. 'Hec+ pipe or+ chasing is including red and blue conduits to be installed as indicated on appro#ed construction dra ings.
Installation to be carried out as per manufacturers instruction. All the PEX pipes and fittings to comply to DIN80! & DIN8080 then test and commission to the satisfaction of the Engineers. 'Hec+ pipe or+ chasing is including red and blue conduits to be installed as indicated on appro#ed construction dra ings.
METHOD STATEMENT FOR INSTALLATION OF PEX PIPES & FITTINGS
FOR HOT & COLD WATER SUPPLY SYSTEM
1. SCOPE OF WORK Installation to be carried out as per manufacturers instruction. All the PEX pipes & fittings to comply to DIN80! & DIN8080 then test and commission to the satisfaction of the Engineers. 2. RESPONSIBILITY "uper#ision$ Inspection and implementation of the "tandard installation of PEX Pipes & %ittings for &ot & 'old (ater system. )efore commencement of installation$ the follo*ing *or+s are re,uired to be completed by the -ain 'ontractor. /.0 -ar+ the bloc+ *all$ the location of PEX piping for chasing. /./ (here re,uired$ to be pro#ided on the bloc+ *or+ in positions as mar+ed. /.1 'hec+ pipe *or+ chasing is including red & blue conduits to be installed as indicated on appro#ed construction dra*ings. /.1 'hec+ materials to be used ha#e an appro#ed material submittal. /.2 'hec+ *or+ area clean and safe. 3. DESCRIPTION OF WORK Inst! ! t" #n #$ PEX P" %&s & F" tt" n's " n(! )*" n' +&* & ,! )& (#n*)" ts " n t-& ,! #(./! ! . Inst! ! t" #n #$ 0&+t" (! %" %& s)%%#+t . 1.0 All #ertical concealed hot & cold *ater supply pipes to indi#idual fi3tures units dropped from ceiling are PEX pipes. 1./ After *all chasing by the main contractor install the female elbo* at the height suitable for each fi3ture and concrete around it to secure in the *all at that location.
1. LABOUR2 PLANT & MATERIAL RE3UIREMENTS 2.0 4abour *ill be as per the program and as re,uired for the abo#e said acti#ity to finish the 5ob on time. 4. SUPER0ISION ARRANGEMENTS 6.0 7ualified super#isors$ foremen & charge hands *ill conduct super#ision8 to achie#e a good ,uality of *or+ as per the appro#ed standard and appro#al to the satisfaction of the Engineers. 5. TEMPORARY WORKS TO BE DESIGNATED AND INSTALLED N9A 6. HEALTH AND SAFETY RE3UIREMENTS .0 Ensure *or+ area is clean and tidy. ./ "afety e,uipment :e3ample &ard &ats$ "afety "hoes$ safety harness$ ;lo#es$ ;oggles *hen necessary etc.< *ill be *orn at all times. .1 ))AE & -ain 'ontractor "afety =fficers *ill conduct a *ee+ly "afety a*areness orientation to "uper#isors$ %oremen and 'harge hands. 7. EN0IRONMENTAL RE3UIREMENT 8.0 Ensure *or+ place is clean and tidy 8./ Ensure *or+ place is ha>ard free. 8. SECURITY ARRANGEMENTS N9A 19. SPECIFIC CONTRACTUAL OBLIGATIONS N9A 11. REFERENCE DOCUMENTS 00.0 ?ele#ant dra*ing issued for 'onstruction 00./ @echnical "pecification ?ef. 06200 00.1 @est "heet 12. RECORDS TO BE PRODUCED 0/.0 Appro#al by the Engineers for the installation for the abo#e said acti#ity. 0/./ (ater lea+ testing appro#al by Engineers. P+&%+&* ,:; K. L"n'nn R&<"&/&* ,:; Cn&+ T#n. A%%+#<&* ,:; Cn&+ T#n. S"'nt)+&; S"'nt)+&; S"'nt)+&;