10 PREAMBLE:
GPT-Rahee JV has been awarded the work of fabrication of 17×123m + 2×64m Span
Steel Girders for Rail-cum-Road Bridge over River Ganga at Patna (South Blank) by M/s
IRCON International Limited for East Central Railway. The total quantum of fabrication
work involved is approximately 36,000 MT.
Given the volume of work and limited time frame, we intend to deploy at least 4 agencies
to enable us to complete the work on time. Each agency shall be required to deploy
adequate workers and other resources to achieve an average capacity of approximately
300 MT of steel components per month. The work allocated to you shall have to be
completed within 32 months from the date of start. It is intended that the work will be
started by February 2009.
20 SCOPE OF WORK:
Please note that the above scope of work includes the related gussets along with
the components, which shall be detailed separately in case required. All gussets
are to be of High Tensile Steel.
You shall quote your separate rates for the 5 packages, and we shall award each
agency one package as found economical / suitable by us. Package 5 shall be
awarded to one of the 4 agencies.
You shall be required to manufacture the jigs / master plates / templates for your
own scope of work, and cost of the same shall be demand to be included in your
rates.
Please note that the above scope of work is tentative and subject to change
depending on actual progress achieved by you / other agencies.
2.2 You shall deploy adequate qualified and experienced engineers / supervisors at
site for planning, supervision and monitoring progress of the work.
2.3 The engineers shall also provide necessary assistance in setting up of site
facilities and installation of machineries, etc. so as achieve desired capacity of
production at the earliest.
2.4 You shall provide labour for unloading of row materials and consumables, as
required with the help of cranes and handling materials to be provided by us,
including handling, stacking, re-stacking, as required. Separate payment for
unloading of only raw steel shall be made. No separate payment shall be made
for shifting of steel of fabricated components from one place to another within the
fabrication yard.
2.6 Fabrication of the girder members, gussets, stringers, bracings, etc. by properly
marking, cutting and drilling of steel sections including straightening and end
milling if required.
2.7 Shifting of fabricated components to the sandblasting and metalizing yard shall
be included in your scope of work, and no extra payment shall be made for this
work. Handling equipments and trailers, etc. required for the purpose shall be
provided by us.
2.11 The work in the fabrication shop shall at all times be available for inspection by
us, Railways or their agencies. All facilities as required for carrying out the
inspection shall be provided to the Inspecting Authority. The fabricated materials
shall be dispatched after Inspection Certificates are issued. Defects, if any
noticed during inspection in the execution of the work, shall be rectified/ replaced
as per the decision of the client. No extra claim whatsoever shall be entertained
on this account.
2.12 You shall maintain proper records for the steel supplied by us, and provide us
with periodic reconciliation of steel supplied and consumed. We shall provide you
an enclosed area for storage of scrap / off-cuts generated by you. However it
shall be your responsibility to ensure safety of the same till the same is returned
to us.
2.13 Raw steel supplied shall be cut strictly in accordance with the approved cutting
plan provided by us. In case of any deviation in the same due to change in size
of raw steel, you shall take advance clearance from our authorized
representative for such deviation.
3.1 All raw materials will be supplied by GPT-Rahee (JV) free of cost.
1.1.1 Rivets and bushes etc. will be supplied by us. The limit of wastage for
rivets shall be maximum 3%. For wastage beyond 3% the cost of rivets
will be recovered from you. However, if any defective rivet is supplied, the
same will be replaced if pointed out before use. Blots, nuts, drifts required
for fabrication shall be supplied by us chargeable basis at fixed issue rate,
as below.
1.1.2 All machineries required for the works shall be provided by us at site.
However, you shall be responsible for routine maintenance and minor
repairs (i.e. repairs costing less than Rs. 2500)/-) in the machinery
provided by us.
1.1.3 Power and fuel for all equipments shall be provided by us free-of-cost.
However, you shall ensure that no wastage of fuel or power occurs on
account of non-productive operation of equipments.
1.1.4 Consumables:
Consumable as required for the works shall be issued to you free-of-cost.
However, you shall quote your rate for the labour portion only on per MT
basis, and also indicate your upper ceiling for cost of consumables per
MT, based on the issue rates of various consumables indicated in
Annexure-A. In case the cost consumables exceeds the upper ceiling as
noted in your order, the cost of the same shall be recovered from you.
However, no extra payment / bonus shall be paid in case consumption is
less than the upper ceiling.
It is clearly understood by you that your rates for the work are based
on the above issue rates for consumables, and that you shall not
purchase any consumables for the work directly, even if they are
available at a lower price in the market.
1.2.1 Power supply and compressors with fuel (if required for shop rivets) and
operators will be supplied by us for all fabrication works.
1.2.4 Suitable covered space for fabrication and mobile crane for handling of
materials will be provided.
1.2.5 Site accommodation for your supervisors & engineers, and labour
hutments as required will be provided near the site.
1.2.6 We shall provide raw steel for fabrication of jigs, fixtures, stallages,
templates, etc. However, fabrication labour and consumables required for
the same shall made. Your rate shall be deemed to be inclusive of the
cost of fabrication and consumables for such items. The fixtures and
stallages fabricated are to be returned to us after completion of the work.
4.1 You shall arrange workmen’s compensation insurance coverage and fulfill
all statutory obligations for all your labour engaged at the site. You shall
be responsible for all kinds of medical/ accident treatment of any of your
workers.
4.2 You shall be responsible for payment of wages to all your workers as per
provision of minimum wages act of Bihar. Weekly / fortnightly master roll
of the payment made shall have to be furnished regularly, and you shall
indemnify us from any liabilities arising out of non-payment of wages to
your workers by you.
4.3 You shall register yourself with PF department, and furnish us with your
registration number so what we do not recover any sum towards PF your
workers, and you shall indemnify us from PF liabilities, if any in the future.
4.4 You shall be required to place a written indent for consumables and raw
materials with our Project Manager, well in advance of their requirement,
so that work is not held up / hindered on this account.
4.5 No claim for compensation on account of idle labour for any reason
whatsoever shall be entertained.
4.6 Since there shall be other agencies working in the same fabrication yard,
you shall be required to co-operate with other agencies in the interest of
the work, including sharing of workshop space, machineries, jigs,
templates, etc. as required.
4.7 Before start of work, you shall submit us a list of manpower and
supervisory staff to be deployed by you. After mobilization of workers, you
shall submit us a list of workers, for issuance of ID cards. No personnel
shall be allowed entry into our fabrication workshop area, without proper
authorization.
4.8 You shall not retain the services of any workers or contractors working for
other agencies without the express written consent of the agency.
4.10 Your workers shall observe safety procedures and use safety equipments
at all times. In this connection, you shall provide all necessary safety
equipments to your workers, including helmets, safety belts, safety shoes,
jackets, goggles, etc. Any safety equipments, if issued by us will be
debited to your account. In case of any violation of safety norms laid
down by any of your workers, you shall be fined Rs. 100/- (Rupees One
Hundred Only) per worker per instance. Repeat offenders shall also be
subject to disciplinary action, including expulsion from site.
30 COMPLETION PERIOD
The total time of completion for the work shall be 32 months from the date of start. It is
intended that the work will be started by February 2009.
4.1 Your quoted rates for the work shall be filled out by you separately under
Annexure-B, duly indicating your offer for the labour portion only, as also your
upper ceiling for consumption of consumables.
4.2 The above rates are inclusive of all taxes and duties, as may be applicable on
you. Service tax, if applicable shall be paid in addition to the above rates.
However, at present, no service tax is applicable, as the work is for a new railway
bridge. In case service tax is applicable in the future, we shall be at liberty to split
the contact to account for the labour portion separately.
4.3 The quantities in the schedule are indicative. These may vary during the course
of work, according to progress made.
50 TERMS OF PAYMENT
5.1 You shall raise monthly progress bills by the 10th of every month for the work
done the previous month. We shall release interim payment amounting to 60% of
your invoice value within 10 days and balance amount shall be released within
45 days subject to final certification by our engineers.
5.2 Measurement as received by us from our principal client for your portion of the
work shall be passed on to you.
5.3 Mobilization Advance of Rs. 2.50 Lakhs (Rupees two Lakh Fifty Thousand Only)
will be paid after full mobilization of work force at site. This amount will be
recoverable in 6 equal installments from the progress bills.
5.4.1 45% (Forty five Percent) shall be paid upon completion of marking,
cutting, drilling & tag welding of steel sections of the relevant component
(s), in accordance with the following terms and conditions:
Basis of weight
Sl. Component Payable After calculation
i) Loose items like Marking, Cutting, Weight of relevant item
gussets, etc. Straightening (if
required), Drilling.
ii) Bott. Chord, Marking, cutting, Total weight of relevant
Diagonals, Verticals, Straightening (if component subject to
Horizontals, cross required) and diaphragm, battens,
Girder, Stringers I/Channel/box etc. having been
formation with tack marked and cut
welding
iii) Top chord, End Raker, Marking, cutting, Total wt. of relevant
End Verticals. straightening (if component, subject to
required) along with
tack welding of
I/Channel/Box section
Basis of weight
Sl. Component Payable After calculation
iv) Other components May be left to the site
engineer to decide on
the same general
principles
5.4.2 50% (Fifty Percent) shall be paid after assembly and final welding of the
components, and approval of the same by inspecting agency.
6.1 This being a long duration contract, price variation on labour shall be paid as per
the following norms:
8.1. Price variation shall be effected once a year, and revised prices
ascertained in January of the year shall remain valid for the entire year.
The first price variation shall be calculated in January 2010.
8.1.2 Since consumables are being issued free-of-cost, no price variation shall
be applicable on consumables. 70% of your accepted rate for labour
portion shall be subject to price variation as per following formula:
Where,
Qr = Revised rate valid for the entire year staring from January of the year