Académique Documents
Professionnel Documents
Culture Documents
data loggers,
which are programmed to read and store all information obtained
from the instruments. The data loggers and power supplies are
housed in steel enclosures. For some of the installed instruments,
steel terminal boxes are used to house intermediate connections
of the instruments to the data loggers.
Normally, the data loggers are set to six hour or 12 hour scan
rates. The data loggers are set to take readings at five minute
intervals a minimum of 30 minutes before stope firings. This five
minute scan rate is maintained for the length of the re-entry
period that is imposed to the level (generally 24 hour exclusion).
At the end of this exclusion period, all data is interpreted before
entry to the level is granted. The instrument results are compared
to the Omori analysis results from the seismic data for the same
period to ensure all key trends are not exceeding the required
limits. Any time-dependent changes (ie slow stress redistribution,
ongoing load increase, displacement from rock mass creep, etc)
can be assessed before any persons enter these areas.
Once preliminary assessments are completed and entry to the
level is granted, loggers are reset to 12 hour scan rates. This scan
rate can be changed to six hour scan rates if the stope area is
within known high seismic hazard areas. Loggers will remain in
six hour scan rates until the seismicity returns to acceptable or
background levels.
The data loggers acquire all the data in millivolts and only
display the last recorded values, therefore it is not possible to
determine whether any changes have been recorded by the
instruments at the data logger itself. All recorded data must be
converted into the appropriate units to allow analysis to be
undertaken. Conversion factors from the millivolt record to the
appropriate units for the various instruments installed in the
clusters are shown in Table 1.
OBSERVED AND MEASURED BEHAVIOUR
(DATA ANALYSIS)
The 930 West instrument cluster in the 940 West Stope Block has
been selected for discussion in this section, and its behaviour is
tracked through firing of the first 11 stoping panels since its
installation in December 2007. All other instrument clusters in
the 940 West Stope Block exhibit similar responses and trends to
the 930 West instrument cluster, and are not discussed further.
The first ten stopes were fired in the 940 West Stope Block.
Narrow Vein Mining Conference Ballarat, Vic, 14 - 15 October 2008 167
THE USE OF GEOTECHNICAL INSTRUMENTATION TO OPTIMISE AN ENGINEERED MINE DESIGN AT BEACONSFIELD GOLD MINE
FIG 2 - Layout of instruments in 930 West illustrating pre- and post-stoping damage profile.
Stope 3A was in the 940 East Stope Block was fired almost
concurrently with Stope 3. Stope 11 was the first stope fired in
the 980 West Stope Block in April 2008 and was accompanied
by a M
L
1.9 seismic event. The location of all instrument clusters
in the 940 and 980 West Stoping Blocks and of the 11 stopes
fired during the analysis period discussed is illustrated in
Figure 3.
As was the practice throughout the 11 stope firings, each stope
was extracted in a single firing using electronic detonators. Little
change was observed on any of the instruments during the
extraction of stope panels one to four. This was primarily due to
the stope panels being 15 m west of the 930 instrumentation
cluster. Stope 5 was the closest stope firing to the 930 West
instrument cluster, located in the immediate hanging wall of the
instrument cluster, and the first significant change recorded by
the instruments was observed in response to that firing.
Following the extraction of Stope 5, minor stress changes
continue to occur throughout the extraction of the remainder of
the block but no large step changes were recorded.
The most significant change measured was that of the local
stress field as measured by the HI Cell. The use of the HI Cells in
this application does not allow determination of principle stress
directions. Orthogonal stress components
max
int
min
refer to
the maximum, intermediate and minimum changes in
compressive stress over the measurement period. In the case of
the 930W HI Cell, this amounted to a drop in
int
and
min
by
3 MPa and 10 MPa respectively, and a rotation of the stress field
of approximately 50 with associated changes in dip (Figures 4a,
4b and 4c). These changes were in line with analysis of
numerical modelling results undertaken for the design of the
drive using Map3D. This is the key outcome and requirement of
the analysis. With further iterative analysis, these observed stress
changes could be resolved into changes to the principal virgin
stress components, but this has not been done.
It was also with the firing of Stope 5 that the first real changes
were observed on the MPBX and SMART
cable (Figures 5
and 6). Displacements were recorded between nodes at 3 m to
4 m and 4 m to 5 m on the MPBX with the greatest displacement
168 Ballarat, Vic, 14 - 15 October 2008 Narrow Vein Mining Conference
A R PENNEY, P B HILLS and R J WALTON
Conversion factor Units Notes
CSIRO HI cell (4 mV) / V
input
GF) M (micro strain)
V
input
= 1.99 for system used
GF = 2.097 for cell and cable type used
Resistance wire
extensometer
(RWE
1n
- RWE
Datum
)0.8 mm (displacement)
RWE
Datum
is the first record in mV
RWE
1n
is any subsequent record in mV
SMART MPBX (N
1n
- N
1Datum
) - (N
2n
- N
2Datum
) 0.0415 mm (displacement)
N
1Datum
is the first record at node 1 in mV
N
1n
is any subsequent record at node 1 in mV
N
2Datum
is the first record at node 2 in mV
N
2n
is any subsequent record at node 2 in mV
SMART cable (N1n - N
1Datum
) - (N
2n
- N
2Datum
) 2.55 (0.212/D) Tonne (load)
N
1Datum
is the first record at node 1 in mV
N
1n
is any subsequent record at node 1 in mV
N
2Datum
is the first record at node 2 in mV
N
2n
is any subsequent record at node 2 in mV
D is the length of cable between node 1 and 2
Vibrating wire (R
1n
- R
Datum
) G 0.00689 MPa (pressure)
G = 1 for E of rock
R
Datum
is the first record
R
1n
is any subsequent record
TABLE 1
Data conversion factors from mV (recorded) to engineering units for instruments in use at Beaconsfield Gold Mine.
FIG 3 - Longitudinal projection of the 940 and 980 West Stoping Blocks illustrating the location of instrument clusters and the
stoping extraction sequence.
Narrow Vein Mining Conference Ballarat, Vic, 14 - 15 October 2008 169
THE USE OF GEOTECHNICAL INSTRUMENTATION TO OPTIMISE AN ENGINEERED MINE DESIGN AT BEACONSFIELD GOLD MINE
S
t
o
p
e
1
S
t
o
p
e
2
S
t
o
p
e
3
S
t
o
p
e
3
a
S
t
o
p
e
4
S
t
o
p
e
5
S
t
o
p
e
6
S
t
o
p
e
7
S
t
o
p
e
8
S
t
o
p
e
9
S
t
o
p
e
1
0
S
t
o
p
e
1
1
-16.00
-12.00
-8.00
-4.00
0.00
4.00
04/12/07 24/12/07 13/01/08 02/02/08 22/02/08 13/03/08 02/04/08
Date
S
t
r
e
s
s
c
h
a
n
g
e
(
M
P
a
)
max
int
min
Stope Firing
Decrease in compressive stress
Increase in compressive stress
A
S
t
o
p
e
1
1
S
t
o
p
e
1
0
S
t
o
p
e
9
S
t
o
p
e
8
S
t
o
p
e
7
S
t
o
p
e
6
S
t
o
p
e
5
S
t
o
p
e
4
S
t
o
p
e
3
a
S
t
o
p
e
3
S
t
o
p
e
2
S
t
o
p
e
1
0
45
90
135
180
225
270
315
360
4/12/07 24/12/07 13/01/08 2/02/08 22/02/08 13/03/08 2/04/08
Date
B
e
a
r
i
n
g
o
f
s
t
r
e
s
s
c
h
a
n
g
e
(
d
e
g
r
e
e
)
max
int
min
Stope Firing
B
S
t
o
p
e
1
1
S
t
o
p
e
1
0
S
t
o
p
e
9
S
t
o
p
e
8
S
t
o
p
e
7
S
t
o
p
e
6
S
t
o
p
e
5
S
t
o
p
e
4
S
t
o
p
e
3
a
S
t
o
p
e
3
S
t
o
p
e
2
S
t
o
p
e
1
0
10
20
30
40
50
60
70
80
90
4/12/07 24/12/07 13/01/08 2/02/08 22/02/08 13/03/08 2/04/08
Date
D
i
p
o
f
s
t
r
e
s
s
c
h
a
n
g
e
(
d
e
g
r
e
e
)
max
int
min
Stope Firing
C
FIG 4 - Stress component magnitude change (A), bearing change (B) and dip change (C) measured by the 930 West HI Cell during
the extraction of Stopes 1 to 11.
occurring between the 4 m and 5 m node points. Load on the
SMART
cable following
Stope 5 extraction were:
~400 kg/firing on cable for length between 2.0 m to 4.5 m, and
~100 kg/firing on cable for length between 4.5 m to 6.0 m.
The displacement and load changes occurred in the section of
ground coinciding with the debonded section of the SMART
cable. This was expected as the bungee bolts do not form active
reinforcement in this zone. Rather, they provide more passive
reinforcement, designed to act as energy absorption anchors
when the rock mass is subjected to high ground motions. The
debonded section of cable is from 1.0 m to 5.5 m into the rock
mass and is in the region where the load and displacement
occurred. While the use of alternative reinforcing elements such
as Garford bulbed cables may help to reduce displacements, the
resulting stiffer ground control would tend to fail when subjected
to high ground motions imposed from a large seismic event due
to its low energy absorption capacity. The design implications of
the bungee cable are discussed further by Scott, Penney and
Fuller (2008).
A key consideration in the results from the MPBX and SMART