Académique Documents
Professionnel Documents
Culture Documents
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
2
,
P
a
c
k
e
t
P
a
g
e
2
0
MRWPCA Test Well Outfall Agreement & Approval
Contracts
Awarded
JUNE JULY AUG SEPT OCT NOV DEC
CEMEX Test Well Schedule
Updated October 2, 2014
Finalize
Report
6/18-
6/27
7/10
Marina
Planning
Commission
CCC
Prepare & Distribute
Staff Report
Nov. 12-14
CCC Mtg
for Appeal &
Original
Application
Test Well RFP
Preparation
RFP
released
RFP received, evaluated, negotiated
CEQA
NEPA
Finalize Report
6/18-6/20
Public Review
6/23-7/26
Prepare
Draft
FONSI
7/26-8/10
Construction
MBNMS
Review of
FONSI 8/10-
8/30
Final
FONSI
9/1
9/15
FONSI
Approval
9/15
10/1
Agreements & Land
Construction
(mid Nov to March 1)
CEMEX Easement / Access Rights
9/3
Submittal
approvals and
pre-con activity
Order Long Lead Items (pump, stainless steel screens, pump column)
CCC
Appeal
Filed
9/24
Council
Special
Mtg
Post
Appr.
Compl.
Items
2014
2014
Cemex Slant Test Well Anticipated Schedule
Note: The schedule is based on the information and assumptions available at time of update.
Court Proceedings
10/8: CalAm briefs & proposed order
10/15: CEMEX file opposition
10/22: CalAm file replies
10/31: Hearing & Decision
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
3
,
P
a
c
k
e
t
P
a
g
e
2
1
CEMEX Test Well Schedule
Note: The schedule is based on the information and assumptions available at time of update is accurate to +/-3 months.
Submit
Project to
Lead
Agency
Finalize
IS/MND
CEQA CA STATE PARKS LEAD AGENCY
NEPA
Draft EA
Prepare, Revise, Review
30-day
Public
Public
Review
Prepare
Draft
FONSI
MBNMS
Review of
FONSI
Final
FONSI
FONSI
Approval
30-day
Public
Review
OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT
2014 2015
Potrero Slant Test Well Anticipated Schedule
Draft IS/MND
Prepare, Responsible Agency Comments
Revise, Review
Submit
Project to
Lead
Agency
Lead Agency
IS/MND
Approval
Review
Final
IS/MND
Coastal Commission
10-day
Appeal
CCC
Prepare &
Distribute
Staff Report
CCC Mtg
Sept. 9-11
Construction
(mid-Oct to March 1)
2015 2015
Updated October 2, 2014
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
4
,
P
a
c
k
e
t
P
a
g
e
2
2
FULL SCALE EIR & CCC/LCP SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 8:34:55 PM MST
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
5
,
P
a
c
k
e
t
P
a
g
e
2
3
CEMEX TEST WELL SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:06:15 PM MST
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
6
,
P
a
c
k
e
t
P
a
g
e
2
4
Exported on July 6, 2014 9:06:15 PM MST
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
7
,
P
a
c
k
e
t
P
a
g
e
2
5
FULL SCALE PLANT & PIPELINES SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:12:23 PM MST
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
8
,
P
a
c
k
e
t
P
a
g
e
2
6
POTRERO CONTINGENCY PERMITTING SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:10:38 PM MST
M
P
R
W
A
T
A
C
M
e
e
t
i
n
g
,
1
0
/
9
/
2
0
1
4
,
t
e
m
N
o
.
8
.
,
t
e
m
P
a
g
e
9
,
P
a
c
k
e
t
P
a
g
e
2
7
Monterey Peninsula Regional Water Authority
Agenda Report
Date: October 09, 2014
Item No: 9.
FROM: Executive Director Cullem
SUBJECT: Receive Report And Discuss A "Decision Tree" For Slant Well Alternatives
And Options Including A Potential Move To The Protrero Rd Site.
RECOMMENDATION:
Staff recommends that the TAC receive report from Cal Am on a "decision tree" for
alternatives to the CEMEX slant well site including the Protrero Road Option. This was
requested by the TAC at its meeting of September 8, 2014.
DISCUSSION:
CEMEX has recently denied Cal Am access to the test well site, raising a serious
question as to the long term availability of the site for the slant wells
Cal Am has been requested to discuss the decision process(Exhibit A) to be followed to
insure a timely move to alternative locations such as Protrero Road.
EXHIBITS:
A-MPWSP Test Well Timeline
MPRWA TAC Meeting, 10/9/2014 , tem No. 9., tem Page 1, Packet Page 29
Appeal Period 21 Calendar Days (MMC
17.41.090.D.4) (7/23 8/13)
Issue CDP
(8/14)
DRILLING WINDOW
~11/1/14 3/1/15
CCC Considers
CDP
Application De
Novo,
Potentially
Causing CAW
to Miss 2014-
15 Drilling
Window
Consider
Legal
Challenge
and/or or
Pursue
Different
Project
Location
CCC Consideration of CDP Applications / Hearing:
9/10-12 (North Coast Area);
NOTE: CCC Decision Moots CEQA Challenges to City CDP
SHPO
Review and
Consultation
re. Cultural
Resources
Assessment
(5/1 5/30)
Additional Technical Studies, Including:
Primary/Secondary Habitat Assessment; Cultural
Resources Assessment; Geotechnical Report;
Coastal Hazard/Wave Run-up Study; Project
Description
(Present 4/30)
Draft Admin Proposed MND/EA
(Present 4/25)
Review Draft Proposed MND/EA (4/25
4/30)
Public Review / Comment re.
Proposed MND 30
Calendar Days (14 CCR
15073(a)) (5/2 6/1)
Response to
Comments, Final
MND, Notice of
Proposed Action on
CDP Application
(6/1 6/20)
Final
Cultural
Resources
Assessment
(6/1 6/6)
Notice Period 10 Calendar Days (MMC
17.41.090.D.1) (6/21 7/1)
Planning Commission Meeting MND and
CDP Application (7/2)
Appeal Period 7 Business Days (MMC
17.41.090.D.2) (7/3 7/9)
City Council Meeting to Hear Any Timely
Filed Appeal (7/22)
Notice of Intent to Adopt MND (14 CCR 15072) (5/1)
Notice Period 10 Calendar Days (MMC
17.41.090.D.2) (7/10 7/21)
CCC Hearing re. Appeal w/in 49 days
(Before 10/1) Does Appeal Raise
Substantial Issue?
Y N
Complete Pre-
Drilling
Conditions in
Permit (60
Days); Drill
Test Well (90
days) Target
Completion
2/9/15
CDPs
Approved by
CCC?
Y N
CCC Potentially
Combines Appeal
Hearing with CDP
Application
Hearing
Appeal to City
Council Filed?
Y
N
MND /CDP
Approved by
PC?
Y
N
Appeal to CCC
Filed?
Approved by
City Council?
Y
N
N
MBNMS
Review
EA (4/28
5/16)
Draft EA
5/19
5/30)
Public Review /
Comment re. EA
30 Calendar
Days
(6/1 7/1)
Admin
Draft
FONSI
(6/23
7/25)
MBNMS
Review
FONSI
(7/28
8/22)
Final
FONSI
(8/25
9/5)
MBNMS
Authoriz
ation /
FONSI
(9/8
9/19)
State & Federal Agency
Project Referral
(Present -2/28)
Y
CCC Staff
Review of
CDP
Application
(Ongoing /
In Process)
Submit Any
Additional
Studies or
Information
Requested
by CCC
(Ongoing /
In Process)
CDP
Application
Deemed
Complete
MPWSP TEST WELL TIMELINE - DRAFT FOR DISCUSSION PURPOSES - 3/3/14
MPRWA TAC Meeting, 10/9/2014 , tem No. 9., tem Page 2, Packet Page 30
Monterey Peninsula Regional Water Authority
Agenda Report
Date: October 09, 2014
Item No: 10.
FROM: Executive Director Cullem
SUBJECT: Discuss The Issue Of "Stranded Costs" And Make A Recommendation To
The Water Authority.
RECOMMENDATION:
Staff recommends that the TAC receive report from the Water Management District and
from Cal Am as to the potential for stranded costs associated with the MPWSP.
DISCUSSION:
The issue of stranded costs has been raised by members of the public at a number of
past TAC and Water Authority meetings. At its last meeting, the TAC requested a
presentation on potential stranded costs.
Dave Stoldt and Ian Crooks have been asked to give us their best analysis of the
problem at the meeting.
MPRWA TAC Meeting, 10/9/2014 , tem No. 10., tem Page 1, Packet Page 31