Price list for biogas plant on natural manure




Technical performances of biogas plants on natural manure(85% wet)


Characteristics

Parameters

Values
1 Raw material capacity (inlet) tons/day 60 120 180 240
2 Biogas production m
3
/day 3229 6458 9688 12917
3 Electricity consumption kW 18 36 54 72
4 Heat power consumption kW 148 267 385 504
5 Number of main digesters pcs. 1 2 3 4
6 Maintenance personnel operator 1 1 1 1
7 Area required hectares 0,4 0,8 1,2 1,6
8 Liquid bio-fertilizer output m
3
/day 39 78 117 156
9 Solid bio-fertilizer output tons/day 17 34 51 68




Price list for biogas plant on natural manure

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
60 45000 21000 470000 340000
120 51000 22000 780000 490000
180 57000 23000 1090000 640000
240 63000 24000 1400000 790000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
www.zorg-biogas.com
**** - VAT is not included.
ATTENTION: Equipment includes steel elamel coated tanks.



Price list for biogas plant on liquid manure




Technical performances of biogas plants for cattle farms (diluted manure ,
94% of wet)


Characteristics

Parameters

Values
1 Raw material capacity (inlet) tons/day 150 300 450 600
2 Biogas production m
3
/day 3229 6458 9688 12917
3 Electrical power consumption kW 18 36 54 72
4 Heat power consumption kW 353 677 1000 1324
5 Number of main digesters pcs. 1 2 3 4
6 Maintenance personnel operator 1 1 1 1
7 Area required hectares 0,4 0,8 1,2 1,6
8 Solid bio-fertilizer output tons/day 17 34 51 68
9 Liquid bio-fertilizer output m
3
/day 129 258 387 516




Price list for biogas plant on liquid manure

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
150 45000 21000 470000 340000
300 51000 22000 780000 490000
450 57000 23000 1090000 640000
600 63000 24000 1400000 790000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG's documentation and consultancy
www.zorg-biogas.com
ATTENTION: Equipment includes steel elamel coated tanks.



Price list for biogas plant on egg poultry dung




Technical performances of biogas plants on egg poultry dung (75% wet)


Characteristics

Parameters

Values
1 Raw material capacity (inlet) tons/day 20 40 80 120 240
2 Biogas production m
3
/day* 2063 4125 8250 12375 24750
3 Electrical power consumption kW 11 23 46 69 136
4 Heat power consumption kW 88 147 265 383 737
5 Maintenance personnel operator 1 1 1 1 1
6 Number of main digesters pcs. 1 2 3 4 7
7 Area required hectares 0,4 0,7 1,3 2 3
8 Solid bio-fertilizer output tons/day 8 17 34 51 101
9 Liquid bio-fertilizer output m
3
/day 9 18 36 55 109

* - biogas production from fresh egg poultry dung.




Price list for biogas plant on egg poultry dung

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
20 54000 25000 564000 408000
40 61200 26400 936000 588000
80 68400 27600 1308000 768000
120 75600 28800 1680000 948000
240 97200 32400 2796000 1488000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.
www.zorg-biogas.com
ATTENTION: Equipment includes steel elamel coated tanks.



Price list for biogas plant on chicken dung with
bedding

Technical performances of biogas plants on chicken dung with bedding
(60% wet)


Characteristics

Parameters

Values
1 Raw material capacity (inlet) tons/day 20 40 80 120 240
2 Biogas production m
3
/day* 2700 5400 10800 16200 32400
3 Electriccal power consumption kW 15 30 60 90 180
4 Heat power consumption kW 101 172 315 459 888
5 Maintenance personnel operator 1 1 1 1 1
6 Number of main digesters pcs. 1 2 3 5 9
7 Area required hectares 0,4 0,7 1,3 2 4
8 Solid bio-fertilizer output tons/day 16 32 63 95 190
9 Liquid bio-fertilizer output m
3
/day 1 2 4 5 11

* - biogas production from fresh chicken dung.




Price list for biogas plant on chicken dung with bedding

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
20 54000 25000 564000 408000
40 61200 26400 936000 588000
80 68400 27600 1308000 768000
120 82800 30000 2052000 1128000
240 111600 34800 3540000 1848000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.
www.zorg-biogas.com




Price list for biogas plant on distillery waste




Technical performances of biogas plants on distillery waste (94% wet)

Characteristics Parameters Values
1 Raw material capacity (inlet) tons/day 25 50 100 150 200 250 300
2 Biogas production m
3
/day* 3,1 6,3 12,7 19 25,3 31,7 38
3 Electrical power consumption kW 18 35 70 106 141 176 211
4 Heat power consumption kW 38 47 65 83 100 118 136
5 Maintenance personnel operator 1 1 1 1 1 1 2
6 Number of main digesters pcs. 1 2 4 6 8 9 11
7 Area required hectares 0,4 0,8 1,6 2,4 3,2 3,6 3,2
8 Solid bio-fertilizer output tons/day 6,5 13 26 39 52 65 78
9 Liquid bio-fertilizer output m
3
/day 14,7 29 59 88 118 147 176

* - biogas production from fresh distillery slop.




Pricelist for biogas plant on distillery waste

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
25 54000 25200 564000 408000
50 61200 26400 936000 588000
100 75000 28000 1680000 948000
150 90000 31200 2424000 1308000
200 104400 33600 3168000 1668000
250 111600 34800 3540000 1848000
300 126000 37200 4284000 2208000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.




ATTENTION: Equipment includes steel elamel coated tanks.
www.zorg-biogas.com
ATTENTION: Equipment includes steel elamel coated tanks.





Pricelist for biogas plants on spent brewers
grains

Technical performances of biogas plants on spent brewers' grains
(77% wet)

Characteristics Parameters Values
1 Raw material capacity (inlet) tons/day 25 50 100 150 200 250 300
2 Biogas production m
3
/day* 3,1 6,3 12,7 19 25,3 31,7 38
3 Electrical power consumption kW 18 35 70 106 141 176 211
4 Heat power consumption kW 38 47 65 83 100 118 136
5 Maintenance personnel operator 1 1 1 1 1 1 2
6 Number of main digesters pcs. 1 2 4 6 8 9 11
7 Area required hectares 0,4 0,8 1,6 2,4 3,2 3,6 3,2
8 Solid bio-fertilizer output tons/day 6,5 13 26 39 52 65 78
9 Liquid bio-fertilizer output m
3
/day 14,7 29 59 88 118 147 176

* - biogas production from fresh brewer's grains (humidity 80%).




Pricelist for biogas plants on spent brewers' grains

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
25 54000 25200 564000 408000
50 61200 26400 936000 588000
100 75000 28000 1680000 948000
150 90000 31200 2424000 1308000
200 104400 33600 3168000 1668000
250 111600 34800 3540000 1848000
300 126000 37200 4284000 2208000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.
www.zorg-biogas.com
ATTENTION: Equipment includes steel elamel coated tanks.



Price list for MSW biogas plant




Technical performances of biogas plants on municipal solid waste


Characteristics

Parameters Values

1
Raw material capacity
(inlet)

tons/day

10

20

40

60

80

160
2 Biogas production m
3
/day* 3036 6072 12144 18216 24288 48576

3
Electrical
power consumption

kW

17

34

67

101

135

270
4 Heat power consumption kW 98 167 305 443 581 1134
5 Maintenance personnel operator 1 1 1 1 1 2
6 Number of main digesters pcs. 1 2 4 6 7 14
7 Area required hectares 0,6 0,8 1,8 2 3 6
8 Solid bio-fertilizer output tons/day 4,5 9 18 27 36 72
9 Liquid bio-fertilizer output m
3
/day 2 4 7 11 15 29

* - biogas production from sorted municipal solid waste.




Price list for MSW biogas plant

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
10 45000 21000 470000 340000
20 51000 22000 780000 490000
40 63000 24000 1400000 7900000
60 75000 26000 2020000 1090000
80 81000 27000 2330000 1240000
160 123000 34000 4500000 2290000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.
www.zorg-biogas.com
ATTENTION: Equipment includes steel elamel coated tanks.



Price list for biogas plant on corn silage




Technical Performances of biogas plants on corn silage (70% wet)


Characteristics

Parameters Values

1
Raw material capacity
(inlet)

tons/day

20

40

60

80

100

120
2 Biogas production m
3
/day 3398 6797 10195 13594 16992 20390

3
Plant electricity
consumption

kW

19

38

57

76

94

113

4
Plant heat power
consumption

kW

119

210

300

391

481

572
5 Maintenance personnel operator 1 1 1 1 1 1
6 Area required hectares 0,4 0,8 1,2 2 2,0 2,4
7 Number of main digesters pcs. 1 2 3 4 5 6
8 Solid bio-fertilizer output tons/day 6 13 19 26 32 38
9 Liquid bio-fertilizer output m
3
/day 10 19 29 38 48 57




Price list for biogas plant on corn silage

Raw material
capacity
(inlet),
tons/day
Price EUR

Project
documentation

Engineering*

Equipment**

Construction***
20 45000 21000 470000 340000
40 51000 22000 780000 490000
60 57000 23000 1090000 640000
80 63000 24000 1400000 790000
100 69000 25000 1710000 940000
120 75000 26000 2020000 1090000

* - includes on-site consultancy, trouble-shooting, training
** - includes delivery CPT Your destination
*** - construction part can be executed by Customer under ZORG documentation consultancy
**** - VAT is not included.

Vous aimerez peut-être aussi