Activity ID Activity Name Original

Duration
Start Finish Total
Float
TRIAL 1 TRIAL 1
248d 01-Jun-1108-Feb-120d
Sub Structure Sub Structure 141d 01-Jun-1122-Oct-11 0d
Foundation Foundation 47d 01-Jun-1118-Jul-11 0d
A1000 PCC 25d 01-Jun-1126-Jun-11 0d
A1010 WP 25d 06-Jun-1101-Jul-11 0d
A1020 Rff 30d 16-Jun-1116-Jul-11 0d
A1030 Shuttering 23d 23-Jun-1116-Jul-11 0d
A1040 Concreting 2d 16-Jul-11 18-Jul-11 0d
Verticals Verticals 26d 18-Jul-11 13-Aug-110d
A1050 Rff 15d 18-Jul-11 02-Aug-110d
A1060 Shuttering 20d 22-Jul-11 11-Aug-110d
A1070 Concreting 2d 11-Aug-1113-Aug-110d
Slab Slab 46d 19-Aug-1105-Oct-11 0d
A1080 Staging 20d 19-Aug-1108-Sep-110d
A1090 Shuttering 25d 29-Aug-1123-Sep-110d
A1100 Rff 25d 06-Sep-1101-Oct-11 0d
A1110 Concreting 3d 01-Oct-1105-Oct-11 0d
Verticals 2 Verticals 2 22d 29-Sep-1122-Oct-11 0d
A1120 Rff 15d 04-Oct-1119-Oct-11 0d
A1130 Shuttering 20d 29-Sep-1120-Oct-11 0d
A1140 Concreting 2d 20-Oct-1122-Oct-11 0d
Super Structure Super Structure 102d 27-Oct-1108-Feb-120d
Slab Slab 38d 27-Oct-1105-Dec-110d
A1150 Staging 20d 27-Oct-1117-Nov-110d
A1160 shuttering 25d 02-Nov-1127-Nov-110d
A1170 Rff 25d 07-Nov-1102-Dec-110d
A1180 Concreting 3d 02-Dec-1105-Dec-110d
Roof Roof 60d 09-Dec-1108-Feb-120d
A1190 MS Columns 30d 09-Dec-1108-Jan-120d
A1200 MS Skeleton 30d 24-Dec-1123-Jan-120d
A1210 Roofing 15d 23-Jan-1208-Feb-120d
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 29 Jun 05 Jun 12 Jun 19 Jun 26 Jul 03 Jul 10 Jul 17 Jul 24 Jul 31
1 2 3
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 29 Jun 05 Jun 12 Jun 19 Jun 26 Jul 03 Jul 10 Jul 17 Jul 24 Jul 31
1 2 3
0
83
167
250
333
417
208
417
625
833
1042
Budgeted Units
Actual Units
Remaining Early Units
Remaining Late Units
Limit
Allocation Limit
NOTE: ASSUMED ALL THE NECESSARY APPROVALS ARE OBTAINED.
TYPICAL FLOOR to FLOOR CYCLE CONSIDERED is
10 DAYS per FLOOR-OFFICE TOWER and 15 DAYS per FLOOR-RESIDENTIAL TOWER.

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Jul 31 Aug 07 Aug 14 Aug 21 Aug 28 Sep 04 Sep 11 Sep 18 Sep 25 Oct 02 Oct 09 Oct 16 Oct 23 Oct 30 Nov 06
3 4 5 6
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Jul 31 Aug 07 Aug 14 Aug 21 Aug 28 Sep 04 Sep 11 Sep 18 Sep 25 Oct 02 Oct 09 Oct 16 Oct 23 Oct 30 Nov 06
3 4 5 6
83
167
250
333
417
208
417
625
833
1042
NOTE: ASSUMED ALL THE NECESSARY APPROVALS ARE OBTAINED.
TYPICAL FLOOR to FLOOR CYCLE CONSIDERED is
10 DAYS per FLOOR-OFFICE TOWER and 15 DAYS per FLOOR-RESIDENTIAL TOWER.

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Nov 06 Nov 13 Nov 20 Nov 27 Dec 04 Dec 11 Dec 18 Dec 25 Jan 01 Jan 08 Jan 15 Jan 22 Jan 29 Feb 05
6 7 8 9
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Nov 06 Nov 13 Nov 20 Nov 27 Dec 04 Dec 11 Dec 18 Dec 25 Jan 01 Jan 08 Jan 15 Jan 22 Jan 29 Feb 05
6 7 8 9
83
167
250
333
417
208
417
625
833
1042
NOTE: ASSUMED ALL THE NECESSARY APPROVALS ARE OBTAINED.
TYPICAL FLOOR to FLOOR CYCLE CONSIDERED is
10 DAYS per FLOOR-OFFICE TOWER and 15 DAYS per FLOOR-RESIDENTIAL TOWER.