STAIRCASE

BIL OPERATION METHOD DIAGRAM



PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

1















2








Excavate trench
for ramp beam
and step













Pour the hardcore


Excavate trench for ramp
beam not exceeding 1.50m
deep.

Excavate trench for toe
beam at steps not
exceeding 1.50m deep.









150mm thick for ramp







150mm thick under steps

-excavater















-Lorry


- Site
supervisor
- 1 skill
worker












- Site
supervisor
- 2 skill
worker


1 m



2 m











25 m







25 m























25/8 hrs
=3.125
3.125/3
=1.042




25/8 hrs
=3.125
3.125/3
=1.042

1 days















1 days







1 days


BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

3












4

Pour the lean
concrete











Mass concrete


Grade 25as specified:

50mm Thick under steps










Grade 25 as specified:

200mm x 75mm Thick
capping


-mobile crane
-concrete
mixer
-Lorry








-concrete
mixer


- Site
supervisor
- 2 skill
worker









- Site
supervisor
- 2 skill
worker


25 m












14 m

25/8 hrs
=3.125
3.125/3
=1.042









14/8 hrs
=1.75
1.75/3
=0.58

1 days












1 days




BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

5

















Install vibrated
reinforced
concrete















Grade 25 as specified;

Staircase




150mm Thick landing slab




Landing beam




100mm thick ramp slab




Ramp beam








-mobile crane
-vibrator
concrete
-concrete
mixer
-Lorry


- Site
supervisor
- 3 skill
worker




34 m




83 m




4 m




25 m




4 m








34/8 hrs
=4.25
4.25/4
=1.06

83/8 hrs
=10.375
10.375/4
=2.59

4/8 hrs
=0.5
0.5/4
=0.125

25/8 hrs
=3.125
3.125/3
=1.04

4/8 hrs
=0.5
0.5/4
=0.125



1 days




3 days




1 days




1 days




1 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION













6






















Reinforcement
bar for landing
beam


Steps











Mild steel bar reinforcement
of landing beam for 10mm
diameter as stirrups




























-bar cutter
-bender
machine
- pliers
-measuring
tape














-Site
supervisor
-bar bender
- 4 skill
workers


6 m











228 kg

6/8 hrs
=0.75
0.75/4
=0.19








228/80
=28.5
28.5/6
=4.75

1 days











5 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

7

Reinforcement
bar for staircase,
landing slab,
landing beam and
steps


High tensile bar
reinforcement as specified:

Staircase

10mm diameter bar





12mm diameter bar







16mm diameter bar





-bar cutter
-bender
machine
- pliers
-measuring
tape





-Site
supervisor
-bar bender
- 4 skill
workers








360 kg





1165 kg







3721 kg








360/8 hrs
=45
45/6
=7.5


50kg/day
1165/ 50
=23.3
23.3/6
=3.88



50kg/day3
721/50
=74.42
74.42/6
=12.40







7 days





4 days







12 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

Landing slab

10mm diameter bar





16mm diameter bar




Landing beam

16mm diameter bar







25mm diameter bar





262 kg





830 kg






191 kg






467 kg






262/8 hrs
=32.75
32.75/6
=5.46


50kg/day8
30/50
=16.6
16.6/6
=2.77


191/8 hrs
=23.88
23.88/6
=3.98



50kg/day4
67/50
=9.34
9.34/6
=1.56



5 days





3 days






4 days






2 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

Steps

10mm diameter bar






12mm diameter bar






16mm diameter bar



157 kg






424 kg






79 kg



157/8 hrs
=19.63
58.38/6
=3.27



424/8 hrs
=53
53/6
=8.83



79/8 hrs
=9.88
9.88/6
=1.65



3 days






9 days






2 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

8










9

Install mild steel
fabric
reinforcement








Install formwork

Layer of mild steel fabric
reinforcement well lapped at
joints and embedded in slab

Ref . No. BRC A6
embedded in ramp slab




Sawn formwork as
specified:
Sloping soffit of staircase





Soffit of landing slab





Side of toe beam









-bar cutter
-bender
machine
- pliers
-measuring
tape







- saw
-nails
-2 hammers
-measuring
tape


-Site
supervisor
- 3 skill
workers









- site
supervisor
- 2 skill
worker







38 m







150 m





112 m





8 m










38/8 hrs
=4.75
4.75/4
=1.19




150/8 hrs
=18.75
18.75/3
=6.25


112/8 hrs
=14
14/3
=4.67


8/8 hrs
=1
1/3
=0.33






1 days







6 days





5 days





1 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

To undercut riser for steps,
175mm high





Edges of concrete,
exceeding 100mm and not
exceeding 200mm high



To undercut riser for steps,
150mm high




To raking open string,
300mm( extreme wide)
including cutting to profile of
treads and risers

468 m






32 m






76 m





472 m

30m/day4
68/30
=15.6
15.6/3
=5.2


32/8 hrs
=4
4/3
=1.33



76/8 hrs
=9.5
9.5/3
=3.17


30m/day4
68/30
=15.6
15.6/3
=5.2


5 days






1 days






3 days





5 days



BIL OPERATION METHOD DIAGRAM PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

10












11

Brickwork












Finisher

Brickwork in common bricks
in cement and sand(1:6)
mortar with an approved
plasticizer reinforced with
and including approved
expanded metal reinforced
at every fourth courses for
112mm Thick brickwall



Cement and sand (1:6)
plastering with an approved
plasticizer as specified

20mm thick to sloping soffit
of staircase




20mm thick to soffit of land
slab
















Concrete
mixer, bucket,
scope, water
level.


- site
supervisor
- 2 skill
worker










- site
supervisor
- 3 skill
worker


21 m

















116 m





83 m




21/1.5 hrs
=14















116/8 hrs
=14.5
14.5/4
=3.63


83/8 hrs
=10.38
10.38/4
=2.60


14 days

















4 days





3 days


BIL OPERATION METHOD DIAGRAM PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

20mm thick to sides and
soffit of landing beam






20mm thick to open string of
staircase, 360mm
wide(extreme)



20mm thick to open string of
staircase, 400mm
wide(extreme)




20mm thick to edges of
concrete, exceeding 10mm
and but not exceeding
200mm high


49 m







140 m





70 m






32 m


49/8 hrs
=6.13
6.13/4
=1.53




140/8 hrs
=17.5
17.5/4
=4.38


70/8 hrs
=8.75
8.75/4
=2.19



32/8 hrs
=4
4/4
=1


2 days







4 days





2 days






1 days


BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

12

Finisher

Cement and sand (1:3)
screed trwollwed hard and
smooth as specified:

18mm thick to landing slabs



25mm thick to landing slab
at ramp



18mm thick to treads,
275mm wide




18mm thick to risers,
175mm high




Extra for 100mm x 200mm x
3mm thick homogenous
nosing tiles



Concrete
mixer, bucket,
scope, water
level.


- site
supervisor
- 3 skill
worker





83 m




7 m




363 m





396 m





363 m




83/8 hrs
=10.38
10.38/4
=2.59

7/8 hrs
=0.88
0.88/4
=0.22

30m/day3
63/30
=12.1
12.1/4
=3.03

30m/day3
93/30
=13.1
13.1/4
=3.28

30m/day3
63/30
=12.1
12.1/4
=3.03





3 days




1 days




3 days





4 days





3 days


BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION





































20mm thick to ramp
complete with pattern
groove


20mm thick to parapet wall
and concrete capping



20mm thick to undercut riser
for steps, 150mm high




20mm thick to tread at
steps, 250mm wide





15 m




42 m





76 m





76 m










15/8 hrs
=1.88
1.88/4
=0.47

42/8 hrs
=5.25
5.25/4
=1.31


76/8 hrs
=9.5
9.5/4
=2.38


76/8 hrs
=9.5
9.5/4
=2.38


1 days




2 days





2 days





2 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

13



















14











Finisher



















Finisher











100mm x 200mm
homogeneous tiles as
specified bedded and
jointed in cement and sand
(1:3) mortar pointed in
matching colured cement:

To steps





EXTRA OVER anti slip
homogenous nosing tiles to
steps



Prepared and apply one
coat of alkali resisting
primer sealer and two coats
of emulsion paint on the
following

Plastered sloping soffit of
staircase




Concrete
mixer, bucket,
scope, water
level.


- site
supervisor
- 3 skill
worker
















- site
supervisor
- 3 skill
worker










21 m





76 m











134 m













21/8 hrs
=2.63
2.63/4
=0.66


76/8 hrs
=9.5
9.5/4
=2.38








134/8 hrs
=16.75
16.75/4
=4.19










1 days





2 days











4 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

Plastered soffit of landing
slab




Plastered sides and soffit of
landing beam




To parapet wall and
concrete capping



















112 m





34 m





42 m

112/8 hrs
=14
14/4
=3.5


34/8 hrs
=4.25
4.25/4
=1.06


42/8 hrs
=5.25
5.25/4
=1.31

4 days





1 days





1 days


BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION

15

Install hand
railing

150mm wide x 150 mm
thick concrete in-situ as
specified handrail twice
rebated and including all
necessary formwork as per
Architects drawings


150mm wide x 150 mm
thick concrete in-situ as
specified bottom rail once
rebated and including all
necessary formwork as per
Architects drawings


700mm High precast
concrete balustrading
comprising of 2 Nos. 75mm
x 75mm baluster twice
rebated at both, 50mmx
70mm guide rail in cross
pattern and 2 Nos.
intermediate rail, well
connected to handrail and
bottom rail as per Architects
drawings

-concrete
mixer
- drill set


- Site
supervisor
- 2 skill
worker

70 m







70 m








120

70/8 hrs
=8.75
8.75/3
=2.92




70/8 hrs
=8.75
8.75/3
=2.92





120/8 hrs
=15
15/3
=5

3 days







3 days








5 days



BIL OPERATION METHOD DIAGRAM

PLANT/
MACHINERY
MANPOWER QUANTITY OUTPUT DURATION














16














Install stainless
steel to the
handrail

200mm x 200mm x 150mm
high concrete in-situ as
specified post complete with
300mm x 300mm x 25mm
thick concrete capping at
top and including all
necessary formwork as per
Architects drawings




800mm high handrail
consisting of 75mm
diameter stainless steel
hollow section welded to
25mm x 25mm stainless
steel hollow section
embedded to parapet wall















-concrete
mixer
- drill set















- Site
supervisor
- 2 skill
worker

28












22 m

28/8 hrs
=3.5
3.5/3
=1.17









22/8 hrs
=2.75
2.75/3
=0.92

1 days












1 days