Please review this document for corrections or clarifications for it will be considered as official after 48 hours. Thank you.
MINUTES OF THE MEETING

Agenda X10 Server Set-up And Migration Strategy Minutes ID 060514_MID031v1
Hosted by JC De Jesus Date 06/05/2014
Attendees Levi Umali
JP Dimaano
Bea Maligaya
Bea Dedicatoria
Joyce Mendoza
Randall Lozano
Rowell Canlapan
Jaymark Macaranas
Ronie Ang
Cloudette Coronel
Arthur Ekanda
Shirley San Jose
Tiffany Elemento
JC De Jesus
Gus Ascalon
Teng Alarcon
Joel Olarte
Joey Onda
Time Started
Time Ended
10:00 am
11:00 am
Apologies Venue SMART TOWER,
BASEMENT
Issues Discussed Remarks Actors Action
1. Recap from
discussion yesterday
Yesterdays discussions were about server set-
up, high level Migration strategy, some nodes,
and possible risks we may encounter.

2. Server Set-up There are 3 x10 servers connecting to
EXADATA EA and 1 of the x10 server in EA is
connecting to DR location while on the DR
location we are doing the commission per
server and as of yesterday 1 of the server is
already completed, 1 is on going for set-up,
while the remaining 2 is still pending.
JC Provide update on the 3
remaining servers for their
status later today.
3. High Level Migration
Strategy
They were currently coordinating with the
developers to determine the set-up of the
management for the actual test the NARS,


8th Floor Jafer Place Bldg., 19 Eisenhower St.,
Greenhills, San Juan, San Juan 1504 (02) 744 9013

2
Please review this document for corrections or clarifications for it will be considered as official after 48 hours. Thank you.
YELLOW, SEA, GSM, USSD..
4. Pre- Migration set-up The servers to prove the commission are 4 in
the apps and 4 in the IDC. There new boxes
given but all of them are in the East Avenue,

5. Transition Phase 3 version 7 instances will be use for the GSM
port servers and re-pointed for upgrading.

6.
Cut-over Phase
The port server will be reconfigured and will
re-point to the new 11g.

7.
Post X10 Migration
All existing servers will be upgraded to 11g, 15
servers for the installation then out of the 15
servers 3 servers will be upgraded from
version 7 to version 11 those are the GSM SRI,
with minor update the upgrading will now 6
version 7 to version 11 prior to migration.

8.
Notes
Port servers, no upgrades but still for checking
to Oracle client for compatibility.

9.
Next Steps
X10 instances in EA 1 instance is completed, 1
is ongoing and 2 are still pending,
identification and commissioning of the 7 new
servers target day will be on Monday (June 9
2014).



Prepared by Acknowledged by



Jason De Jesus
Document Analyst


Project Manager and Attendees