Académique Documents
Professionnel Documents
Culture Documents
PT.TAIYO SINAR
PT.TAIYO SINAR
Doc No : TSRT-PR-021
Page | 1
MECHANICAL PRECOMMISSIONING
Doc No : TSRT-PR-021
PT.TAIYO SINAR
Document No.
TSRT PR 021
Project Code
2014.08.007
PO No.
Project Name :
IFF. PHASE 1 PROJECT
OWNER :
PT.ESSENCE INDONESIA ( IFF )
Rev
Status
05/11/14
Date
PT.TAIYO SINAR
Description
IRWAN
Issued
by
SUSILO
Checked
by
TEBODIN
Approved
by
IFF
Com
pany
Appr
oval
Page | 2
MECHANICAL PRECOMMISSIONING
Doc No : TSRT-PR-021
PT.TAIYO SINAR
TABLE OF CONTENTS
1.0
INTRODUCTION
2.0
PRE-COMMISSIONING CHECK
3.0
PRECOMMISSIONING TEST
PT.TAIYO SINAR
Page | 3
MECHANICAL PRECOMMISSIONING
PT.TAIYO SINAR
1.0
Doc No : TSRT-PR-021
INTRODUCTION
Under the generic terminology of Mechanical Pre-commissioning are covered
in the present procedure. All pre-commissioning checks and test related to the
followings:
- Mechanical equipment
- Piping and general equipment
- Safety Equipment
- Structure and Building
It is also cover the simplified pre-commissioning scope of works applicable to
these package with have been subject to an acceptance test at the
manufacturers and are listed as such in contract.
The pre-commissioning of mechanical equipment, piping, safety equipment,
structure and building shall be carried out in accordance with the rule given in
Procedure No: COM-SNCL-001.
2.0
PRE-COMMISSIONING CHECK
2.1
Check Line index
The List shall be indexed as table below: (See Commissioning sequence)
2.2
Procedure
The Contractor shall carry out equipment check and fill in relevant check list
as per the rules given in the Procedure.
2.3
Check List Master Forms
Refer to attached following Forms
3.0
PRECOMMISSIONING TEST
3.1
Test Sheet Index
The following Test Sheets available:
- General Purpose
- Vessel and Tank
- Heat Exchanger
- Pipe Work Pressure test
- Pipe Work Flushing
- Valve Pressure test
- NDT Clearance
- Machinery Alignment
- Piping Pressure Test Index
PT.TAIYO SINAR
Page | 4
MECHANICAL PRECOMMISSIONING
PT.TAIYO SINAR
3.2
Doc No : TSRT-PR-021
Test Procedure
3.2.1 Re-testing of Vendors Equipment
Vendor supplied Vessel (Equipment) will normally been
pressure tested at Vendors Works as part of Acceptance Test
requirements and shall only require to be re-tested on site if
they have been damaged in transit or on site.
The decision to be carried out the Pressure testing will be made
by the Company Engineer.
3.2.2
3.2.3
PT.TAIYO SINAR
Page | 5
MECHANICAL PRECOMMISSIONING
PT.TAIYO SINAR
Doc No : TSRT-PR-021
3.2.5
3.2.6
PT.TAIYO SINAR
Page | 6
MECHANICAL PRECOMMISSIONING
Doc No : TSRT-PR-021
PT.TAIYO SINAR
PT.TAIYO SINAR
Page | 7
MECHANICAL PRECOMMISSIONING
Doc No : TSRT-PR-021
PT.TAIYO SINAR
PT.TAIYO SINAR
Page | 8