REF: EIPL/MURATA FACTORY/January 2014

7th July 2014


Murata Electronics Thailand Ltd.
Northern Region Industrial Estate 63 Moo 4, Tambol
Ban Klang Amphur Muang, Lamphun 51000, Thailand
Attn: Mr. Pongpat Sonpan

Dear Sirs,
1BU

Re: Proposed Lease of Energy Management System to MURATA Factory

A: PROPOSAL OVERVIEW
The proposed Energy Management System uses utility class energy meters for the
measurement and recording of electrical consumption.
These meters store the energy consumption data in half-hourly load intervals.
The data are then retrieved automatically and stored at the Remote Server for report generation
and energy management using our web-based software - CLARITI.
The interactive web-based energy usage information service that is included in our proposed
solution is a critical tool to help energy users to manage their energy usages.
User-friendly interfaces, coupled with a range of useful reports provide energy users the
information required to achieve their energy management goals.
All reports can be exported to PDF/MS EXCEL/CSV files format.
Schedules can also be created for the generation and automatic delivery of reports via email.
Additionally, email based notifications (alerts) could also be received when energy usage at a
site (meter) meets a predefined set of threshold criteria.
This proposal is based on a wireless system design using a General Packet Radio
Service(GPRS) communications technology.
This means that the energy data from the meters are communicated to the Remote Server by the
GPRS communications.
As such, no costly communications hard-wiring and networking equipment are required.
Capital outlay for the server and peripherals will not be necessary as well since the Remote Server
is hosted in the secured Server Room.
Interactive Web-based Energy Usage Information Service - CLARITI

This service application provides energy users insight into their energy usages.
http://www.energyclariti.com/

EDMI (Thailand) Limited

Private & Confidential

Page 1 of 5

REF: EIPL/MURATA FACTORY/January 2014

B: EIPLS SCOPE OF WORK


1. Supply & Install Electronic Tariff Class Energy Meters
i. EDMI Three-Phase Four-Wire, Class 0.5 Meter
ii. EDMI Three-Phase Three-Wire, Class 0.5 Meter
2. Supply & Setup the infrastructure for GPRS network communication to support the
Energy Management System
i. GPRS Network Devices
3. Web-Portal Service
i.
CLARITI

EDMI (Thailand) Limited

Private & Confidential

Page 2 of 5

REF: EIPL/MURATA FACTORY/January 2014

CLARITI Sample Display:

SAMPLE ONLY

NLY
1. Language
i. English and Japanese
C: CUSTOMERS SCOPE OF WORK
1. Customer shall be responsible for the disposal/return of the existing meters.

D: AMR LEASE PLAN


1. Lease Price Per Meter
Description
Three-Phase Four-Wire Meter
Three-Phase Three-Wire Meter

Monthly Lease Price Per Meter


THB
THB

Price above does not includes meter installation.

2. Duration of Lease Period


i. Lease Period is 5 Years

EDMI (Thailand) Limited

Private & Confidential

Page 3 of 5

REF: EIPL/MURATA FACTORY/January 2014

3. End of 5 Years Lease Period


At the end of the 5years lease period, MURATA will own the meters. However, the
networking devices; namely the concentrator and SIM cards will still belong to the Leaser
(EIPL).
i. At the end of the 5years lease period, customer can contract EDMI to continue to
provide the Energy Management System Services.
In this case, EIPL will
continue to provide the customer. EDMI will charge the customer THB per
month per meter for this service. This rate applies to both three-phase four-wire
meters and three-phase three-wire meters.
OR
ii. Customer can use the meters for manual meter reading. In this case, the
concentrator and the SIM cards will be collected back by EDMI.

4. Early Termination Fee


Time of Termination
At the end of 1st Year
At the end of 2nd Year
At the end of 3nd Year
At the end of 4th Year

Termination Fee
Monthly Lease Price of Meter(THB) X Total Number of Meters(Units) X 48(Mths)
Monthly Lease Price of Meter(THB) X Total Number of Meters(Units) X 36(Mths)
Monthly Lease Price of Meter(THB) X Total Number of Meters(Units) X 24(Mths)
Monthly Lease Price of Meter(THB) X Total Number of Meters(Units) X 12(Mths)

5. Additional mater Charges


i. If MURATA is add to meter (Measurement point), EDMI quotes the additional
mater charges.

6. Site Services Charges


i. No charges if the source of the problem is due to the performance or reliability of
the system.
ii. If otherwise, THB

per trip applies

E: PAYMENT TERMS

EDMI (Thailand) Limited

Private & Confidential

Page 4 of 5

REF: EIPL/MURATA FACTORY/January 2014

1. 30 days credit
2. Monthly invoice amount will be based on the number of meters installed

If you have any queries concerning our above proposal, please feel free to contact me at
Mob: +668 1173 2843 for discussion.
Look forward to hear from you soon.