DAILY WORK SCHEDULE REPORT

Project : Expansion of KINDASA Tanker-Filling Station #1 Weather : Sunny Date 01/04/2009

Work Done Today WEDNESDAY 01/04/2009

installation of power cables for MCC panels for pumps


Installation of roof coloums for tank-3
Excavation in progress for 800 mm grp line inside the seaport area
completed Installation of power fedder panals for CPS system for external /internal
Installation of roof coloums for tank-3
Daily Equipment / Tools Status
Description Prv. Ttl Today Total Description of Equipment Total
Project Manager 277 1 278 bobcat 1
M. Engineer 197 1 198 forklift 0
Site.Engineer 210 1 211 dyna 1
Surveyor 78 1 79 mini roller 0
Site Supervisor 51 1 52 air compressor 1
Labourers 3768 19 3787 plate Compactor medium 2
Operators 779 1 780 Welding machines 11
crane Operator 166 1 167 butt welder 2
generator 2
Total Station 0
Levelling Instrument 1
Fire Extinguisher 1
Crane 1

Total No. of days 4776 19 4795 Total 23

Material Received Today S.No Description Prv. Ttl Today Total


1 Average No. of workers 7833 19 7852
2 No. of Lost time Accidents 0 0 0
3 No.of Restricted work Cases 0 0 0
4 No. of Medical Treatement Cases 0 0 0
5 No. of First Aid Cases 0 0 0
6 No. of occupational illness Cases 0 0 0
7 Any Accident on site Cases 0 0 0
8 Any Incident on site Cases 0 0 0

Site Manager Salco Received ACEC/ACE

Eng'r Nasser Omar Eng'r Saeed Omar/ Eng'r Abdul Aziz