Compaction equipment
Bitumen plants
Bulk cement carriers
Planning is very important for selecting the right type of equipment. The planner has to see
what type of work he is doing & then he should know various types of equipments that can
be used for the work. He should study the capacity & cost of equipment. He also has to see
what types of equipments he is having. He also has to look into the probable life of
equipment & its depreciation. He should go in for equipment, which has minimal
maintenance. Experience is one of the most important aspects for equipment planner.
Nature of Work:Construction of New International Airport 30 km. away from a mega city.
Scope of Work:
Cutting and dozing of 100000 cum. of earth having average height 0.75 m.
Transportation of 5000 cum. earth, 3 km. away from site (Spreading & leveling)
Bringing in 2000 cum. of sand from 20 km. (spreading & leveling)
Requirement of 5000 liters of bitumen per day for 30 days and apron work from
60th day of starting of work. Bitumen to be obtained from refinery at Bongaigaon in
Assam.
Lead time on site is 45 days. Storage facility available on site is 50000 liters.
Earthwork:
Excavation:Total Earthwork
Total days estimated
(Considering 5days allowance
for equipment breakdown &
maintenance)
= 100000 cum.
= 70 days
Page 3
= Rs. 7000.
= 100000/70
= 1430 cum. (approx.)
= 1430 / 500
= 2.86 ~ 3 machines per day.
= 3 x 7000
= Rs. 21000.
= 50 cum.
= 5 cum.
= 50/5
= 10 trips per hour
= 10 / 4
= 2.5 nos.
Page 4
= 2.5 x 3
= 7.5 nos.
= Rs. 1200
= 50 x 3
= 150 cum. per hour
Capacity of bulldozer
(Blade size of bulldozer is
3.5m. x 1.5m. category is 3D )
= 2 nos.
Transportation of sand
Total quantity of sand required
to be transported from quarry
to site
= 2000 cum.
= 70 days
= 30 / 5
=6
= 2000 / 70
= 28.57 ~ 30 cum.
Page 5
= 10 / 2.5 = 4
=6/4
= 1.5
= 70 days
= 2000 / 70
= 28.57 cum. per day
Capacity of bulldozers
= 28.57 / 750
= 0.038 nos. per day
Recommendations / Conclusions:
Summary of machineries required for earthwork and sand filling:
Poclain
Dumpers
Bulldozers
Costing of equipments:
Poclain
Dumpers
Bulldozers
= Rs. 56256 x 70
= Rs. 39, 37,920.
Starting date of bituminous work is on 60th day after commencement date of project
Lead time for transportation if bitumen is 45 days from source to site
Bitumen storage capacity is 50000 liters
Sr. No.
1
2
3
4
5
6
7
8
9
10
Material
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Bitumen
Quantity
(Liters)
5000
5000
5000
5000
5000
5000
5000
5000
5000
5000
Page 7
Day of order
After
commencement
date of project
5th day
6th day
7th day
8th day
9th day
11th day
12th day
13th day
14th day
15th day
Day on which
material to be
received (45 days
lead time)
After
commencement
date of project
50th day
51st day
52nd day
53rd day
54th day
55th day
56th day
57th day
58th day
59th day
Recommendations/Conclusions
Thus, we shall receive 50000 liters bitumen on 59th day after commencement date
of project. So, we can start the work on 60th day with daily consumption of 5000 liters of
bitumen.
Now same as 1st 50000 liters of lot, we would continue the order of remaining 100000 liters
of bitumen. So that we shall receive total 150000 liters of bitumen on 79th day after
commencement dates of project. That means, we have to continue our day of order from 5th
day after commencement of project up to 34th day to finish total order of bitumen.
Page 8
BIBLIOGRAPHY / READING:
Page 9