Académique Documents
Professionnel Documents
Culture Documents
Ramagundam
BB Tripathy
AGM (O&M)
WORKING PRINCIPLE:
FAHP water lines are charged to wetting unit & air washer units
Air intake valve is opened to create air flow in the above header.
Wet ash system: In wetting unit water is injected & ash slurry in
collected in the collector tank from where it flows to ash slurry
sump.
Dry ash system: in the bag filter ash is separated from air &
collected in buffer hopper & transported to ash SILO by means of
transport air compressor
The NUVA FEEDER operation shall be of cyclic order having the following
sequence:
VENTING: vent valve opens for venting of air from Nuva Feeder, and
equalizes the vacuum between the buffer hopper and the Nuva Feeder.
FILLING: top gate opens and remains open for 40 seconds.
Top gate closes followed by closing of vent valve.
EQUALISING: equalizing valve opens thereafter for pressure equalization
between the Nuva Feeder and the pressure conveying stream.
UNLOADING: bottom gate opens and remains open for one minute to allow
discharge of ash from Nuva Feeder into conveying stream.
Bottom gate closes followed by closing of equalizing valve.
The above sequential events together make one complete operating cycle of
Nuva Feeder. The duration of each cycle is two minutes. The operating
sequence of the Nuva Feeder on a stream is staggered equally spread over
the total cycle period in order to provide an even flow of ash through the ash
conveyor.
To start the with pressure conveying system, the pulsejet cycle of silo vent
filter is to be started. Once the TAC is loaded the selected Nuva Feeder
sequence starts. Under dry mode selection the pulse jet in the bag filter
starts.
From dry ash silo dry ash is unloaded through rotary unloader to tankers and
wet ash is unloaded through rotary Feeder to open trucks
IMPORTANAT SETTINGS
Set points:
1)
Vacuum BKR-A
110
100
Vacuum BKR-B
110
100
Vacuum BKR-C
110
100
Vacuum BKR-D
Stop Deashing.
Start Deashing.
10
Stop Deashing.
Start Deashing.
11
Hopper fluidizing lines Jam. hopper valves keep open for a long
time -- ash fails to drop down from Hopper.
Material like spring, clinkers are stuck-up in Ash in take valves-hopper valves keep open for a long time -- ash fails to drop down
from Hopper.
Other VS value passing. Header Vacuum high > 250MM
Vacuum leak though common header couplings. sufficient vacuum
not available - - 100MM at test conditions
Pulse jet not OK. ESP Hopper valves fail to open if supply to
pulse jet fails.
Bag fillers choking. vacuum high continuously > 250MM
Vacuum pump Transmitters problem Transmitter choking
Air washer nozzles chokage. Ash quantity high in Vacuum pump
discharge.
Branch Header value passing. Header frequent jamming.
Poor pulse jet instrument air pressure > 5.0Ksc
Vacuum at test conditions to be set Dry Healthy 120 MM
Dry OK - 140MM
12
2).
Check bottom gate passing and operation. High Vacuum as bag filter
tend to choke because of vent valve passing & ash enters back with
pressure from transportation lines.
i) Ash returns back to Branch lines Branch lines will come under
pressure.
13
Check Top gate and bottom gates --fluidizing air lines choke.
Silo Bag Filters choke silo relief valve opens ( > 0.9 Ksc).
Silo Level High - manual checking.
Nuva Feeder Bottom gate Fluidising pads fixing Anabond fails
Ash comes in air line to Pads.
14
Start HP and LP seal water pumps (other than running HP, LP seal
Water Pumps).
Open series suction value.
Open HP, LP Series seal water values.
Start Series.
Open plug value.
15
Activity
Schedule
Remarks
To ensure that
Hopper is empty
Feedback
for
hopper empty
Fluidising return
line to discharge
air
16
Wetting unit
nozzles cleaning
S.No
Activity
Schedule
Once in a month
In service pumps
Greasing and
gland adjustment
Suction
header
flushing cleaning ,
Foundation bolts ,
belts
,glands
replacement ,
Spare
Nuva
inspection
Fluidizing pads ,
vent valves &
equilising valves
discs , Bottom and
top gates
10
11
Remarks
Every morning
shift
for
30
minutes
17
filter cleaning
14
S.No
Schedule
Remarks
15
Silica Gel
Once in 2 years
16
Every 6 months
17
18
19
20
21
Solenoid
valves 5 nos per day _ Replace
and
inspection in total flyash air lines and
inspect internals
system
22
23
Once in a month
Once in a month
3 Greasing
18
Spare
Quantity
Bag Filters
Fluidising pads
50 Nos
Solenoid valves
50 Nos
20 Nos
02 Nos
19