Académique Documents
Professionnel Documents
Culture Documents
Date of birth
17- APR-1983
: E-DISPUTE RESOLUTION MODEL ON
Title
CONTRACTUAL VARIATIONS
Academic Session
2010/2011
RESTRICTED
OPEN ACCESS
SIGNATURE
SIGNATURE OF SUPERVISOR
830417-08-6317
NAME OF SUPERVISOR
:
Date :
NOTES :
Date :
* If the thesis is CONFIDENTAL or RESTRICTED, please attach with the letter from
the organization with period and reasons for confidentiality or restriction
Signature
....................................................
Date
Disahkan oleh:
Tandatangan
Nama
Jawatan
(Cop rasmi)
Tarikh :
Nama
Tarikh :
DECEMBER 2010
ii
DECLARATION STATEMENT
Signature
....................................................
Name
Date
iii
iv
ACKNOWLEDGEMENT
The author would like to express his utmost gratitude to his supervisor,
Associate Professor Ir. Dr. Rosli Mohamad Zin for his guidance and assistance
throughout the study. The author would like to extend sincere appreciation to the
experts involved in this research for their contributions and helps in the research. The
completion of this dissertation would not have been possible without their
conscientious guidance and patience. Last but not least, deepest appreciation to
authors parents and friends for their continuous supports and encouragements
throughout the progress of this research.
ABSTRACT
vi
ABSTRAK
Kontrak pembinaan merupakan satu subjek yang rumit jika isu interpretasi
dan pentadbiran kontrak tidak ditangani dengan tepat. Dalam konteks ini, perubahan
dikenalpasti sebagai isu yang paling bermasalah dalam kontrak pembinaan.
Bantahan-bantahan boleh berlaku berpunca daripada komunikasi yang tidak
berkesan, pengabaian dan kurang pemahaman ke atas kewajipan-kewajipan dan
harapan-harapan yang tertera dalam kontrak. Penyelesaian bantahan melalui kaedah
penyelesaian pertikaian alternatif (ADR) telah menjadi pengganti utama kepada
perbicaraan mahkamah kerana ia tidak memerlukan proses perundangan yang
sepenuhnya. Meskipun ADR mempunyai banyak kelebihan, pengalaman sebenar
ADR adalah sangat rendah dalam industri pembinaan tempatan. Penyelidikan ini
bertujuan menangani keperluan untuk menilai semula pentadbiran kontrak yang
sedia ada serta pelaksanaan penyelesaian bantahan dan seterusnya mencadang dan
membangunkan model eDR ke atas isu-isu perubahan dalam kontrak sebagai satu
kaedah alternatif untuk menyelesaikan bantahan-bantahan dalam projek-projek
pembinaan. Dengan itu, objektif penyelidikan adalah untuk: (a) mengklasifikasi
sifat-sifat kaedah penyelesaian bantahan di sektor pembinaan Malaysia; (b)
mengenalpasti sifat dan perihal kaedah penyelesaian bantahan di sektor pembinaan
di Malaysia; (c) memantapkan pentadbiran kontrak yang sistematik melalui
pengenalpastian isu-isu kontrak dan pendekatan untuk kejelasan; (d) memeriksa dan
menilai kaedah-kaedah sedia ada dalam penyelesaian bantahan dan pentadbiran
kontrak; (e) membangunkan satu model eDR yang berpendekatan generik untuk
industri pembinaan; dan (f) membangunkan prototaip/system penggunaan eDR
aplikasi yang berdasarkan isu-isu perubahan dalam kontrak. Kajian literatur, soalselidik, temuduga semi-struktur dan kajian Delphi telah dilaksanakan untuk
mencapai objektif-objektif tersebut. Hasil kajian menunjukkan amalan penyelesaian
bantahan perlu diperbaiki dan eDR telah dicadangkan berdasarkan 75 garis panduan
untuk isu-isu perubahan yang telah disetujui dan dikenalpasti melalui kajian Delphi.
Seterusnya, satu prototaip eDR telah dibangunkan untuk garis panduan itu. Prototaip
tersebut telah menggunakan pendekatan isu-isu kontrak pemecahan dan Plain
English yang diperolehi melalui kaedah systematik pentadbiran kontrak. Penubuhan
eDR ini dapat membantu pengguna-pengguna mengambil keputusan yang lebih tepat
berbanding pendekatan tradisional yang merujuk kepada sekelompok dokumen dan
peruntukan kontrak yang kompleks.
vii
TABLE OF CONTENTS
CHAPTER
TITLE
PAGE
DECLARATION
ii
DEDICATION
iii
ACKNOWLEDGEMENTS
iv
ABSTRACT
ABSTRAK
vi
TABLE OF CONTENTS
vii
LIST OF TABLES
xv
LIST OF FIGURES
xvii
xix
LIST OF APPENDICES
xxii
INTRODUCTION
1.1
Introduction
1.2
Problem Statements
1.3
Research Questions
1.4
Aim
1.5
Research Objectives
1.6
Scope of Research
1.7
1.8
Research Methodology
1.9
12
1.10
Concluding Remarks
13
DISPUTE RESOLUTION
15
2.1
Introduction
15
2.2
16
viii
2.2.1
16
Disputes
2.3
17
2.4
19
2.4.1
20
2.4.2
21
2006
2.4.3
22
23
2.5
23
2.6
Prevention Stage
26
2.6.1
26
2.7
2.8
2.9
Negotiation
28
28
2.7.2
Advantages
29
2.7.3
Disadvantages
30
31
2.8.1
Mediation/Conciliation
31
2.8.2
32
2.8.3
Advantages
34
2.8.4
Disadvantages
35
36
2.9.1 Adjudication
36
37
2.9.1.2 Advantages
38
2.9.1.3 Disadvantages
39
2.9.2 Arbitration
39
40
2.9.2.2 Advantages
42
2.9.2.3 Disadvantages
43
2.9.3 Litigation
43
ix
45
2.9.3.2 Advantages
46
2.9.3.3 Disadvantages
46
2.10
47
2.11
Concluding Remarks
48
CONSTRUCTION CONTRACT
49
ADMINISTRATION
3.1
Introduction
49
3.2
50
3.2.1
DISCON, 1988
51
3.2.2
53
Interpretation, 1991
3.2.3
53
2000
3.2.4
Construction
Negotiation
Online
54
Construction
55
(CoNegO), 2004
3.2.5
Conflict
Resolution
in
57
58
Systems/Models
3.3
3.4
62
64
3.3.2
64
3.3.3
Post-Commencement Stage
66
67
3.4.1
68
69
and Obligations
3.5
70
3.5.1
73
Clarity Aspects
x
3.5.2 Measures on Enhancing Clarity
74
Concluding Remarks
76
CONTRACTUAL VARIATIONS
77
4.1
Introduction
77
4.2
Background of Variations
78
4.3
Myths on Variations
81
4.4
Issuance of Variations
84
4.4.1
84
3.6
4.5
85
4.4.3
Provisional Sum
85
4.4.4
86
Validity of Variation
88
4.5.1
Written Instruction
89
4.5.2
Definition/Principle of Variation
90
4.5.2.1 Addition
92
93
95
95
Contract
4.5.3
4.6
96
Valuation Rules
99
4.6.1
100
4.6.2
100
102
4.6.4
104
4.6.5
104
xi
4.6.6
4.7
104
108
Contract Sum
109
4.7.2
109
Subsequent Circumstances
4.8
Concluding Remarks
111
RESEARCH METHODOLOGY
112
5.1
Introduction
112
5.2
Literature Review
112
5.3
113
Critical Review
5.3.1
Content Analysis
114
5.4
Documentary Analysis
115
5.5
Questionnaire
115
5.5.1
Questionnaire Design
116
5.5.2
Questionnaire Sample
117
5.5.3
Questionnaire Analysis
118
119
120
5.6
121
5.6.1
Delphi Study
121
124
126
127
128
129
Normalization
5.6.2
5.6.3
130
132
5.7
Research Framework
133
5.8
Concluding Remarks
134
xii
6
136
MALAYSIA
6.1
Introduction
136
6.2
137
6.2.1
Background of Respondents
137
6.2.2
Position
138
6.2.3
Education Qualification
139
6.2.4
Working Experience
140
6.2.5
141
6.2.6
143
6.2.7
143
6.3
Factor Analysis
146
6.4
Discussion
151
6.5
Concluding Remarks
152
154
MODEL
7.1
Introduction
154
7.2
Model Development
155
7.3
DFD on eDR
156
7.4
157
7.5
158
7.6
162
162
165
166
169
171
172
173
173
Discussion
176
7.7
7.8
xiii
7.9
Concluding Remarks
177
178
Introduction
178
8.2
179
181
8.3
Background of Experts
184
8.4
186
186
189
191
194
197
200
8.5
Variations
8.5.4 Analysis on Additional Expenses and
204
Subsequent Circumstances
8.6
206
8.7
210
8.8
211
8.8.1 Database
212
214
215
216
220
8.9
221
8.10
222
8.11
Concluding Remarks
223
224
9.1
224
Introduction
xiv
9.2
225
Resolution Methods
9.3
227
227
on Clarity
9.5
229
229
9.7
230
9.8
231
REFERENCES
232
Appendices A F
247-267
xv
LIST OF TABLES
TABLE NO.
2.1
TITLE
PAGE
18
disputes
2.2
47
3.1
50
3.2
60
3.3
63
3.4
64
3.5
65
stage
3.6
66
3.7
73
3.8
74
3.9
75
4.1
79
forms in Malaysia
4.2
82
4.3
83
4.4
86
4.5
96
4.6
105
4.7
110
subsequent circumstances
5.1
121
5.2
131
6.1
143
annually
xvi
6.2
144
by mean score
6.3
147
6.4
149
Normalisation
6.5
151
7.1
164
7.2
167
8.1
179
8.2
180
8.3
185
8.4
187
8.5
188
8.6
189
8.7
190
8.8
192
8.9
194
8.10
194
8.11
195
8.12
198
8.13
201
8.14
205
subsequent circumstances
8.15
207
8.16
209
8.17
222
xvii
LIST OF FIGURES
FIGURE NO.
TITLE
PAGE
1.1
11
2.1
25
3.1
52
3.2
54
3.3
55
3.4
56
3.5
58
5.1
125
5.2
134
6.1
138
developers
6.2
Position of respondents
139
6.3
140
6.4
141
6.5
142
6.6
142
6.7
Scree plot
148
7.1
156
7.2
157
7.3
158
7.4
161
7.5
163
7.6
166
7.7
169
7.8
170
xviii
7.9
172
7.10
173
7.11
175
8.1
182
8.2
212
8.3
215
8.4
216
8.5
217
8.6
Content of issue
218
8.7
Forum interface
219
8.8
220
8.9
221
xix
SYMBOLS:
A(x)
Membership function
Triangular number
AL
AR
A(SR) ij
ai
Value of score
am
ain
ai1
ai2
a1
a2
Fi (SR)
MA
Geometric mean
xi
Respondent frequency
xx
ABBREVIATIONS
Adj
Adjudication
ADR
AI
Architects Instruction
Arb
Arbitration
BQ
Bill of Quantities
CDA
CIDB
CMA
CoNegO
CPC
DFD
DRT
DwF
eDR
e-Dispute Resolution
FCBR
FDM
IEM
IT
JCT
KMO
Kaiser-Meyer-Olkin
Lit
Litigation
Med
Mediation
MO
Modeling
Neg
Negotiation
PAM
PC
Prime Cost
PCA
PWD
Rank
RIBA
SD
Standard deviation
xxi
SMM
SO
Superintending Officer
SPSS
SR
Scale Rating
VO
Variations order
xxii
LIST OF APPENDICES
APPENDIX
TITLE
PAGE
247
250
255
259
264
265
CHAPTER 1
INTRODUCTION
1.1
Introduction
2
The results highlight an interesting dichotomy that the disputants are not
active in ADR even though they have great dissatisfaction on traditional dispute
resolution. Therefore, mitigation or prevention measure is necessary as it can be a
better approach to dispute resolution (Vallero and Vesilind, 2006). This research
addresses a proactive approach, namely e-Dispute Resolution (eDR) as a potential
area of improvement in contract administration and dispute resolution. Eventually,
the research renders an insight and assists in making inferences for a more clarified
and informative approach in the contract administration, and thereby contributes to
dispute prevention or mitigation.
1.2
Problem Statements
3
1997; Cutts, 2004; Styllis, 2005) and legalese or technical legal terms/jargon
(Candlin et al., 2002; Cutts, 2004), which results in disagreements between the
contracting parties on their rights and responsibilities. This statement has been
justified by a recent local research (Mohamad and Zulkifli, 2006), in that contractors
reported having problems in understanding the contract documents based on the
results from the survey. The research concluded that the contractors should be well
versed in the interpretation of clauses stated in contracts. Hence this local research
has inspired the investigation on the detailed study of the lack of understanding,
especially on the technical aspect of the language structure within a contract form,
which also highlighted by a number of overseas literatures (Martin 1993; Thomas et
al., 1994; Broome and Hayes; 1997, Hill, 2001; Feinman, 2003; Cutts, 2004;
Shumway et al., 2004; Rameezdeen and Rajapakse, 2007). The form should be
written and presented in such a way as to be useful for easy reference by non-legal
site and consultancy personnel (Robinson and Lavers, 1988).
4
factor is agreed and recognised as an important aspect in dispute resolution and
contract administration. Part and parcel of the human factor is considered in the
research, although it is not fall into the scope of the research.
1.3
Research Questions
1.
2.
5
3.
4.
5.
What is the alternative means for the research gap found from the
previous approaches and how it works in general?
6.
1.4
Aim
The research has highlighted the problem statements and research questions
on low practice of ADR and poor understanding of contract administration toward
the most litigious issue on contractual variations. Therefore, the aim of this research
is to addresses the need to review existing contract administration and dispute
resolution practices and subsequently propose and develop eDR model on
contractual variations as an alternative means for resolving disputes in construction
projects.
1.5
Research Objectives
6
1.
2.
3.
4.
5.
6.
1.6
Scope of Research
7
as a research subject for the application of eDR. The selection of this area is because
none of the contractual variations studies are related to the Delphi method either
locally or internationally based on the literature review, where the Delphi in
construction related research were in selection of procurement systems (Chan et al.
2001) and team selection in public private partnership (Kumaraswamy, and Anvuur,
2008).
Besides, the contract forms need to be sorted as many forms are available in
Malaysian construction industry. Pertubuhan Arkitek Malaysia (PAM) contract form
is the most popular and familiar form in private sector. The public sector contract
form Public Work Department (PWD) forms is not selected as the scope of research
because the latest version of PWD 203 (2007) standard form is very new and just
launched . Therefore, this research focuses on the PAM 2006 standard form, which a
revised version of PAM contract for the eDR research. The court cases and literature
materials are referred to support and enhance the content of the contract provisions
on the contractual variations.
1.7
8
principles dealing with causes of conflicts/disputes enables the contracting parties to
understand and appreciate the spirit of contract conditions. This fundamental
knowledge of contract provision needs to be addressed in order to have a more
professionalism and healthier working behaviour in construction industry since the
industry have been plagued by rising of conflicts/disputes and unprofessional
practices.
Another aspect of this research is to render a better insight into the clarity of
construction contract. This clarity approach is the solution for legalese and
complicated language in construction contracts. Plain English could modify the
language to be a more understandable and it is important to construction players who
are not from legal background, particularly the construction naive users and partially
experts in a project. When construction people clearly understand the clauses
provided under the contract, the parties will perceive the importance of their
contractual obligations and rights in the contract as required. Meanwhile, it also
prevents the manifestation of construction conflicts/disputes.
Besides that, the eDR model is unique. The model could serve as a template
for future research, even though there are differences in the legal system and diverse
local scenario, it can provide a generic approach to dispute mitigation/prevention. It
describes how a clarified, organized and reliable source of reference would be
produced. It would cultivate self-learning and examination by the end-users. The
reference is important as the poor understanding of contracts and lack of
prevention/mitigation means of dispute resolution in the construction industry. This
functional modelling is value added to existing body of knowledge, particularly for
contract administration and dispute resolution.
Last but not least, the eDR renders a proactive approach in dispute resolution,
particularly in the contractual variations. The system is designed to provide a more
understandable and informative approach for preliminary references and alertness to
end-users. It could help to make better decision-making. The system also serves as a
9
platform of lifelong learning and self-examination for the end-users to improve their
understanding and knowledge. Once the users understood the operating clauses
provided under the contract and its consequences, they would appreciate the
importance of their contractual liabilities, duties, obligations and rights under the
contract.
1.8
Research Methodology
10
information that is useful for the research. Basically, questionnaire
and Delphi study were the main source of primary data collection.
Subsequently, the model and system are developed based on the data
collected. The validation was carried out with the experts in the
Delphi study.
Stage D was the last stage of the research process. It mainly involved
writing up and recommendations for future research.
These four stages are described the overall of the research methodology that
would be adopted in this research. The details of each research method are explained
in Chapter 5.
11
Stage A:
Initial Study and
Confirmation of
Research Area
Research area
identification
Literature review
Critical review
Articles review
Stage B:
Research Proposal
Data collection
Primary data
Questionnaire
Delphi study
Secondary data
Articles and books
Document analysis
Conclusions &
recommendations
Stage D:
Write-up and Conclusions
12
1.9 Structure of the Thesis
This thesis consists of ten chapters. The chapters are arranged according to
the sequence of the objectives and rationale of the research. The ten chapters
comprises 1 chapter on research proposal, 3 chapters on literature review, 1 chapter
research methodology, 4 chapters on data analysis and discussion and 1 chapter on
conclusions and recommendations.
13
Chapter 5 explains all the procedures and processes involved in this research.
Basically, the research consists of six main research activities, such as literature
review, document analysis, critical review, interview, questionnaire survey and the
Delphi study. All these method are equally important to achieve the research
objectives.
Chapter 6 presents the questionnaire data analysis. Mean and factor analysis
are applied to analyse the data collected from the survey. This enables the
establishment of the behavior of dispute resolution techniques in the construction
industry. Subsequently, Chapter 7 is about the development of eDR modeling. It
explains the generic approach on the contents and features of the eDR model.
1.10
Concluding Remarks
14
process, rather it is aimed to provide preliminary references and alertness to the endusers.
CHAPTER 2
DISPUTE RESOLUTION
2.1
Introduction
16
2.2
To engage in a dispute.
2.2.1
Certainly, Conflict and dispute are two different notions although some
authors do not differentiate them (Fenn et al., 1997). The conflicts and disputes are in
inter-correlated relationship. In other words, the disputes would turn up if the
conflicts go into unresolved circumstance because the conflicts usually happen at the
early stage of disagreement or misunderstanding.
17
In addition, Fenn et al. (1997) stated that conflict is manageable and possibly
to the extent of preventing a dispute resulting from the conflict. Meanwhile, dispute
is required to be resolved through dispute resolution techniques such as mediation,
arbitration and so on. It normally associated with official intervention by a third party.
2.3
The purpose to review and identify the sources of conflicts and disputes for
the construction players is to avoid or forestall them or even to isolate and control the
root causes (Fenn et al., 1997; Kumarasamy, 1997). Kumarasamy (1997) also
reiterated that an appreciation of such causes or sources will be useful to revolve or
prevent any ongoing and unavoidable as well as avoidable disputes.
18
Table 2.1: Literature on sources of construction conflicts or disputes
Research
Williamson (1979)
Hellard (1987)
Conlin et al. (1996) (as Six areas: payment, performance, delay, negligence,
cited in Fenn et al., 1997)
Bristow (1998) (as cited in Five areas: unrealistic expectation, contract documents,
Pena-Mora et al., 2003)
19
nature for the same client, differing site condition, rules and regulations, market
conditions and project participants would change the development of the contract
(Pena-Mora et al., 2003). This is why the construction industry is so unique compare
to other industries and fields.
2.4
20
2.4.1
PWD 203A is a most popular standard form of contract for public sector. The
contract form has been revised in the year of 2007. Clause 65.0, Arbitration is the
only part of the contract for dispute resolution. There are eleven sub-clauses under
Clause 65.0.
All the disputes or differences in the contract can be referred to the officer
and the arbitrator for resolution except termination of contractors employment on
national interest as stated in Clause 65.1 and Clause 65.4. The officer (s) is
empowered to take action on behalf of the government.
21
2.4.2
PAM standard form of contract is the most common type of contract used in
private sector. In year 2006, the contract form has been updated and revised. There
are two clauses found in the contract form for dispute resolution and discussed on
mediation, adjudication and arbitration. Clause 35.0, Mediation is allocated in the
contract form. The mediation requires both the disputants written agreement before
referring to this dispute resolution. This mediation is carried out in a voluntary basis.
There is no condition precedent in this dispute resolution for its reference to other
dispute resolutions like adjudication and arbitration. Appointment of mediator is
done by President of Pertubuhan Arkitek Malaysia when the parties failed to agree
on the mediator. Upon appointment, the mediation is governed by PAM Mediation
Rules or any modification to such rules.
22
2.4.3
If the SO fails to give his decision by the expiry of 30 days or if either party
be dissatisfied with any decision by the SO (within 90 days after receiving the SOs
decision), then the disputant shall refer the dispute to mediation. The mediation must
obtain written consent by the disputants, if the parties fail to achieve any settlement
then upon the termination of the mediation pursuant to the CIDB Mediation Rules,
either party may refer the dispute to arbitration and it shall be a condition precedent
to commencement of arbitration proceedings.
23
2.4.4 Summary of Contract Forms
The local contract forms highlighted several dispute resolution methods such
as negotiation, mediation, adjudication, and arbitration. The negotiation is an indirect
of provisions in the contracts such as reference to the officer/SO regarding the
disputes. However, the mediation, adjudication and arbitration are the formal dispute
resolution techniques required in the contract. These formal and informal dispute
resolution methods together with litigation are the research subjects towards the
identification of the behaviour of dispute resolution in Malaysian construction
industry.
2.5
It would not be true to say that all disputes are resolved at court proceedings
or other formal settings of alternative dispute resolution methods. The stages of
dispute resolution should begin with a grievance. The grievance may be abandoned
where a person considers it to be trivial and not worth pursuing. The person may feel
unable to pursue the matter or may not realise that he/she may have legal recourse in
respect of it (Badman and Grimmett, 1996). This grievance is the least confrontation
and time consuming as the person would just follow or surrender due to his limited
knowledge or understanding about the dispute. In developing countries, the
grievance is very obvious and common although the parties may not realise it.
24
After that, the stage is negotiation, which is a very popular informal method
in dispute resolution. This stage is to communicate the grievance and negotiate for a
settlement. This negotiation technique is a preferred choice of the disputants, with
most disputes being resolved through this process (Cheung et al., 2000). It is the least
expensive, and it can preserve the working relationship of the parties involved. In
negotiation, the parties have absolute freedom with respect to the form, process and
type of agreement. In order to make it successful, the negotiation demands
cooperative effort from the disputants (Cheung, 1999; Edwin and Henry, 2005).
Therefore, the next stage is the methods that could render a legal binding
decision, i.e. adjudication, arbitration and litigation. The alternative to arbitration is
to the use of adjudication (Owens, 2008; Dancaster, 2008; Hill and Wall, 2008).
Adjudication deals with the payment problem between the contracting parties in
particular (Noushad Ali and Lim, 2008; Teo, 2008). Usually, it is under a contractual
provision in the contract and enforceable in law (Thomas, 2001).
Subsequently, the next stage is the use of arbitration. Here it is clear that the
disputants need an arbitrator, an independent expert to act as the decision maker. The
parties must agree to the appointment and are bound by the arbitrators decision.
Arbitration is conducted in private and confidentially (Teo and Aibinu, 2007). Yet,
over the years, with the increase in procedural complexity, arbitration is regarded as
25
a replicate of litigation (Cheung et al., 2000). Hence it is not considered one of the
ADR methods in this research.
Last but not least, litigation is the following stage of dispute resolution.
Litigation is costly, delaying and risky (Steen, 1994; Gebken and Gibson, 2006). It also
brings a number of variables and unable to satisfy the litigants (Harmon, 2004). On
the other hand, the court proceedings consist of several layers too, which is the
hierarchy of the courts. This is important and one kind of advantages for the
provision of an appeals structure (Badman and Grimmett, 1996).
Litigation
Arbitration
Adjudication
Mediation
Negotiation
Grievance
26
2.6
Prevention Stage
The prevention stage is the earliest stage before any formal or informal
dispute resolution methods. In UK, Construction Industry Institute, Dispute
Prevention and Resolution Task Force has proposed start right and stay right
approach for the contracting parties. Start right is about starting with suitable
contract language and with appropriate alternative dispute resolution while stay
right requires the parties solve emerging disputes quickly before they accelerated
into complex legal problems (Diekmann and Girard, 1995). Therefore, this approach
could help the contracting parties to identify the disputes at the outset of a project.
After that identification, the parties could avoid them or even to isolate and control
the root causes (Fenn et al., 1997; Kumarasamy, 1997). This is how the prevention
works, i.e. preventing conflict before it happens.
There are two scenarios for prevention means in construction industry. Firstly,
the prevention method applies before the construction is begun, which the decision
making solely falls on the owner/client/employer. Another scenario for prevention
27
method describes in the commencement of construction period, which includes the
contracting parties of the project.
For the first scenario, the prevention stage offers the greatest flexibility for
designing and creating ways to improve communication and job performance by
minimizing disagreement and helping the project team resolve those problems that
arise before they become disputes or claims. This approach applies to the
construction that has not begun yet. Therefore, the employer is the most crucial
participant in this stage. The techniques could be adopted are risk sharing, escrow bid
document, innovative project award and delivery systems, incentive programs,
constructability analysis and documentation, cost/schedule controls, and contract
implementation (Pena-Mora et al., 2003).
28
2.7
Negotiation
Cheong and Suen (2002) also pointed out that negotiation is the most
common form of dispute resolution. According to the research done by Jones (2006),
negotiation is best suited to preserving or enhancing existing job relationships and it
also effective in reducing costs and opening channels of communication.
Usually, the disputants expect there is give and take in the negotiation.
Therefore, cooperative effort from the disputants is required in order to have a
successful negotiation (Cheung, 1999; Edwin and Henry, 2005).
2.7.1
29
form, process and type of agreement towards a successful negotiation demand
cooperative effort from the disputants (Cheung, 1999).
During the negotiation process, the disputants will exchange the information
and make up a solution which meets the objectives of all parities. The parties will
present its proposals with supporting facts and argument for an agreement. The
negotiator will attempt to understand and adjust their position. The way of
negotiation conducted will cause an impact to their relationship. Normally the
disputants will not want to continue compromise if the proposals suggested by one
party are kept banned by another party unless a compromise is reached among the
disputant parties (Cheung and Suen, 2002).
The successful of the negotiation depends on the attitudes and expertise of the
representatives. Any settlements or resolutions are achieved only by the agreement
from both disputing parties (Essex, 1996). Thus, the disputing parties involve must
be willing to bind their respective parties to a settlement and never ask for a
representative to participate in the proceedings. In this negotiation, the quarrelling
parties will try to reach a suitable negotiated solution for the dispute without
involving any third-party. The parties will only consider other dispute solution
methods like neutral advice or mediation if the parties cannot solve the dispute
through negotiation the resolution is not reached within a predetermined length of
time (Koolwik, 2006).
2.7.2
Advantages
The discussion below focuses on the main advantages of the negotiation, such
as:
30
2.7.3
Disadvantages
There are two main disadvantages of negotiation in this discussion, i.e., both
the disputing parities will face a relatively high risk in settling their disputes if the
negotiation fail; and if the negotiation fails due to the communication failures, bad
negotiation skill will lead to the delay (Mohammad, 2005).
31
2.8
2.8.1
Mediation/Conciliation
The disputants require minimum cost for mediation. Generally, the costs of
the mediation are shared partially by each party and the mediator has no lien on the
view of his costs. The mediator plays an important role in assisting the parties to
32
agree on a settlement which can reflect the true intention of both parties (Singh,
1995). The cooperation of both parties is critical to determine the success of this
mediation.
Lastly, mediation helps the disputing parties to minimize the risk of losing
costly litigation fees and helps the parties in developing a creative solution. Although
the chances for the mediation to win is not so much but the risk of losing and the
view of pursuing costly litigation encourage the parties to choose mediation (Jones,
2006).
2.8.2
(a)
Parties are unable to narrow the gap and differences arise in the
dispute and cause the inflexibility of other parties.
33
(b)
Parties do not manage proceed the movement since too many matters
are unsolved.
(c)
The parties wish the mediator to discover and give a solution to them.
(d)
(e)
(f)
(g)
The process of mediation is to crate an environment where the parties can sit
down together to discuss and negotiate for a consensus agreement. The mediator also
helps both the parties to perceive a fair settlement and look for the alternative ways
to overcome obstacles through negotiation (Keith, 1997) or to simplify the issues
(Jones, 2006). Chan (1997) summarized the role of mediator as follow:
(a)
(b)
(c)
(d)
(e)
(f)
If the parties do not want to carry on further, the mediator will finish
off the mediation stage and regress to arbitration.
34
clarify each partys concept of the facts, priorities and positions. The mediator will
never advocate for either side, loosens rigid stances and he always helps the parties
find a fair resolution for the parties (Essex, 1996).
2.8.3
Advantages
35
maintain their business relationship if they are using mediation to
solve the settlement. According to Keith (1997), the successful of
using mediation to solve the dispute is more than 70% of the time in
the construction industry.
2.8.4
Disadvantages
If the mediation fails to present, the parties will have deserve for
losses in terms of time and money (Patterson, 1997).
36
2.9
2.9.1 Adjudication
Adjudication was first introduced into UK in the mid 1970s. The application
was restricted to disputes that occurred between main contractor and his
subcontractors. The process involved a third party as an adjudicator to help resolve a
dispute that had arisen (Ashworth, 2006). After some years, the standard forms of
contract have had provisions for adjudication. Formally, adjudication was introduced
to the construction industry in United Kingdom on 1st May 1998 when the Housing
Grants, Construction and Regeneration Act 1996 (HGCRA) came into force
providing mandatory requirements for construction contracts to include adjudication
as recommended by the Latham Report (Uff, 2002).
Ndekugri & Russell (2006) stated that under the HGCRA Act 1996, a party
has a right to refer a dispute to adjudication under construction contracts. Since the
fundamental objective of statutory adjudication is encourage dispute adjudication at
any time during the project, therefore the high percentage of adjudication
proceedings commenced after practical completion remains a genuine concern
(Cheung, 2006).
37
In Malaysian construction industry, only PAM 2006 contract form has a
provision for adjudication. One of possibility reasons may due to pending of
enactment of Malaysian Construction Industry Payment and Adjudication Act
(CIPAA). According to Noushad Ali and Lim (2008), the development of CIPAA is
going smoothly and many notable comments by the steering committee. It is
expected that the CIPAA would help to resolve payment issues in the industry once it
has been implemented.
On the other hand, adjudication is binding through the legislation, where all
the parties are given a statutory right without the consent of the other. In the United
Kingdoms HGCRA Act 1996, a party is automatic given a right to settle the disputes
overpayment by giving a notice at anytime for a 28 days adjudication. The
adjudicator would make a prompt decision within 28 days of the appointment by his
or her own specialist knowledge toward the subject matter of the dispute. The
adjudication decision is binding until the dispute is finally determined by the legal
proceedings or arbitration if they are not satisfied with the adjudicators decision
(Chau, 2007).
38
2.9.1.2 Advantages
39
2.9.1.3 Disadvantages
2.9.2
Arbitration
40
Arbitration arose when two parties to a contract were incapable to be in agreement
and wanted an impartial party to decide on the issue (Treacy, 1995).
41
construction field and the need for the expert witnesses may be limited and
testimonies are submitted in the form of swear affidavits (Harmon, 2003).
When the parties failed to agree on the procedure referred to (b), and
the arbitration consists of three arbitrators, each party shall appoint
one arbitrator and the two appointed arbitrators shall appoint the third
arbitrators as the presiding arbitrator.
When the two parties fail to agree on the third arbitrator within thirty
days of their appointment or such extended period as the parties agree,
either party may apply to the Director of the Kuala Lumpur Regional
Centre for Arbitration for such an appointment.
42
2.9.2.2 Advantages
43
2.9.2.3 Disadvantages
The parties are frustrated of going to court for the enforcement of the
arbitration award. This is due to additional cost had to be bear by the
parties (Riggs and Schenk, 1990).
Arbitration may act like litigation, which is started too late and takes a
long time to reach a settlement (Essex, 1996).
Arbitrator does not apply the strict rules of evidence as in the court.
However, it still subject to be reviewed if the matters related to law
points of view by the courts (Uff, 2002).
2.9.3
Litigation
44
method and provides an involuntary and binding solution. This method is a
compulsory form of dispute resolution because if the parties do not comply with the
specified procedures stated, they have an ultimate right of appeal to court (Jones,
2006). This appeal is referring to lawsuit, which consists of form of legal actions and
procedures in order to resolve the disputes.
On the other hand, the parties give their control over the process and
conclusion imposed by the third party (Cheung, 1999). Occasionally, litigation is a
preferable dispute resolution method if the dispute involves legal issues or view
points of law by the litigants and requires a settlement by a judge (Harmon, 2003).
Moreover, Cheeks (2003) stated that litigation is more preferable compare to binding
arbitration if the following issues are considered:
(a)
(b)
(c)
(d)
(e)
45
2.9.3.1 The Process of Litigation
The litigation process is extremely long and consists of many rules and
procedures. Uff (2002) stated that litigation procedure is a general term which covers
the various steps necessary to turn a legal right into a satisfied judgment of the court.
In Malaysia, Harbans Singh (2003c) stated that engineering and construction related
disputes are usually referred to civil procedure in civil court and comprised statutory
rules like:
The litigation procedure involves many steps to advance the litigants legal
right into an enforceable judgment. Overall, Harbans Singh (2003c) described that
the procedure consists of three main stages, namely:
The trial itself the trial starts with the plaintiff commences the
opening address and calls his witnesses subject to examinations, next
defendant opens his case/defence, calls his witnesses subject to the
same examinations and makes closing speech once all the defendants
witnesses have been called. Lastly the plaintiff makes his closing
speech.
46
2.9.3.2 Advantages
Although litigation is the last solution for the disputes, it has the following
advantages:
The disputing parties can appeal if they are not satisfied with the
decision imposed by the judge (Fisk, 2003).
Litigation is binding and the parties have to follow the decision make
by the judge (Fisk, 2003).
2.9.3.3 Disadvantages
In litigation, the time taken for the dispute to proceed is lengthy and
with each witness cross-examined several time (Gaitskell, 2005).
Thus, the time taken for litigation is unpredictable.
47
Litigation is expensive because it involved the cost for legal fee and
documentation for trial preparation (Mohammad, 2005).
Litigation is open to the public and media and it may affect the
reputation of the disputing parties (Mohammad, 2005).
The cost is high as to the attorneys fees and time (Gaitskell, 2005).
The disputing parties do not have the rights to select the individual to
solve the dispute but follow the assigned judge (Mohammad, 2005).
2.10
The summary distinguishes the characteristics and key features among the
dispute resolution methods, such as negotiation (Neg), mediation (Med), adjudication
(Adj), arbitration (Arb) and litigation (Lit) as shown in Table 2.2. The attributes have
been arranged according to the stages of dispute resolution, from negotiation until
litigation. This comparison is excluded grievance as mentioned in stages of dispute
resolution. It is because the grievance is not a method of dispute resolution.
Neg
Med
Adj
Economical
Preservation of relationship
Arb
Lit
48
Item
10
Neg
Med
Adj
Arb
Item
11
12
13
16
17
18
19
20
21`
22
23
24
25
26
27
2.11
Concluding Remarks
14
15
This chapter has presented a detailed literature study about the philosophy of
conflicts and disputes as well as dispute resolution in construction industry. The local
scenario has been discussed, although some of the references are derived from
overseas sources. The review on the local contract forms enhanced the knowledge on
the local practice of dispute resolution. The stages of dispute resolution were also
developed and more importantly the attributes of dispute resolution methods were
classified based on the literature review as to the first research objective. The
approach of grouping the attributes could render a wider perspective and
comprehensive view on the dispute resolution methods.
49
CHAPTER 3
3.1
Introduction
This chapter reviews alternative approaches from related previous studies and
highlights a systematic way of contract administration through identification of
contractual issues and approach on clarity. Contract administration is the process of
administering a business contract that governs contracting parties interests. In the
construction
industry,
it
revolves
around
the
pre-construction,
50
3.2
The critical review on previous studies is to understand the trend and research
gap for the proposal of alternative means in contract administration, i.e., eDR. One
hundred and twelve (112) journals have been reviewed and shown in Appendix B.
The journals are mainly derived from the list of refereed journals as appended below:
After reviewing, the previous studies could be classified out into five
categories, i.e., dispute resolution techniques (DRT), application of information
technology (IT), contract management and administration (CMA), conflict and
dispute analysis (CDA) and modeling (MO). The classification is based on the
research area focused by researcher(s) as shown in Table 3.1.
Negotiation (3)
Arbitration (5)
IT
Claim (3)
Decision
support
system risk
(5)
Decision
making
dispute
resolution (3)
Litigation
outcome (1)
CMA
Interpretation and
understanding (8)
Clarity (1)
CDA
Cost/time
overrun (2)
Delay
and
EOT (8)
MO
Conflict
behaviors (1)
Contract
bidding (2)
Claim
management (8)
Risk
management
(4)
Financing
conflict (1)
Resolution
outcome (2)
51
DRT
Mediation (6)
IT
CMA
Procedures
steps (2)
CDA
and Dispute
prediction (1)
DRB (2)
Relationship
contracting (2)
Contract
specification (1)
Litigation (2)
Dispute avoidance
and prevention (4)
Contract form (3)
Informal
means/tactics (2)
Adjudication (3)
MO
Decision
making
on
dispute
resolution
method (2)
Consequences
(1)
Conflict
management
(1)
The results of the review show the exiting alternative approaches are focused
on expert systems or modelling in current development. Therefore, six (6) closerelated studies to this research from year 1988 to 2009 were selected and analysed
concisely. It is to identify the research gaps for the current trend on the alternative
approaches to contract administration, in particular their strengths and lessons to be
learnt.
3.2.1
DISCON, 1988
52
be checked the system. At the end of an analysis, it will show the contractors chance
for recovery weighted by certainty factor that is estimated throughout the analysis.
The sources of knowledge in the system are mainly derived from two (2) lawyers
who dealing with construction claim regularly as well as a PhD holder, who as a
instructor from construction management and engineering. The system also referred
to contract clauses and justified the findings to court cases. Figure 3.1 shows the
structure of the DISCON.
DISCON.KB1
M1.EXE
First segment of
DISCONs
knowledge base.
DISCON.CFG
C program for
DISCONs external
calls
Configuration of
users interaction.
DISCON.EXP
Assistance and
instructions
Explanations
DISCON.CLR
DISCON.ASP
Assumptions
DISCON.IDP
Intermediate
conclusions
Clarifications
Second segment of
DISCONs
knowledge base
Intermediate
conclusions and
findings
Inference
engine.
C_DISCON.EXE
DISCON.GRL
DISCON.KB2
Cache
DISCON.KB3
Third segment of
DISCONs
knowledge base
DISCON.WFR
Explanations
DISCON.RNE
Reasons denying
the claim
DISCON.KB4
Forth segment of
DISCONs
knowledge base
DISCON.KB5
Fifth segment of
DISCONs
knowledge base
53
3.2.2
3.2.3
54
major parts: facts, dispute issues, and judgements. The there parts were used to
develop weights and correlations between the critical dispute characteristics, i.e.,
change, design/specification, contract condition, work, time/cost, and completion.
The statistical analysis process was to measure variables and build up the
correlations. The research targeted to the most severe disputes in the construction
projects. The proposed dispute prediction concept is as illustrated in Figure 3.2.
Completion of Project
Resolution
within
Project
Scope
Prevention
Resolved
Mediation
Dispute
Characteristics
Arbitration
Litigation
i.e
DRB
Process
Dispute
Prediction
Support
Dispute
Resolution
Process
Resolution
Support
Unresolved
Proposed Dispute
Prediction Concept:
Research Scope
Alternative Dispute
Resolution Process
Accumulated
Dispute
3.2.4
55
towards a dispute to figure out a consensus solution. This is a common practice in
negotiation. The concept of Even Swaps evaluates possible options available on
the basis of their relative importance. There will be few proposals were exchanged
between the negotiators before reaching consensus agreement. The online system
enables the negotiation take place at a distance, and utilizing computing facilities.
However, this system merely handles the figure or number based construction
dispute in order to allow the statistical analysis works in the application. Figure 3.3
presented the conceptual framework for the development of CoNegO.
1. Communication
Network(via
WWW)Email
2. Dataaccessibility
Exchangingsharedissues
Exchangingpreferences
Exchangingproposal
CoNegO
(Online Negotiation)
3. CommonSystem
KnowledgebasedExpert
CaseReasoning
TradeOffAnalysis
3.2.5
56
model doest not focus on the contractual terms for prevention of complex and high
cost disputes, rather more on the planning and problem solving ability of project
organization. Twenty four (24) construction disputes are analysed and referred in
order to develop the model. The model adopted the decision making/solution concept
in prisoners dilemma strategy to generate the possible states. It gives the general
guidelines to deal with the construction disputes from arising of problems to the
dispute resolution outcome. Figure 3.4 illustrates the Model of Dispute Development
and Resolution that described in the study. Confusion is likely to arise as some key
issues of construction dispute have not been clarified in detail in the model. The
dispute is hardly to be resolved when fails to address and locate the dispute sources
or problems.
Problem Solving
Effectiveness
- Behaviours, Relations
- Process
Who is
solution?
Uncertainty
- Complexity
- Performance
requirements
Problems
-Work
directives
- Environment
- Performance
Contractual
problems/Opp
ortunism
Problem
Situations
Four problems
types
Who is
responsible?
Dispute
Resolution
Effectiveness
- Integrative
- Distributive
Dispute
- Entitlement - Amount
Other factors
- Situational
- Costs of
conflict
- Culture
Dispute Resolution
Outcome
- Transaction costs
- Impact on relation
- Recurrence
57
3.2.6
The research Fuzzy Case-based reasoning (FCBR) is to develop a computeraided reasoning system that could be employed to help resolve construction
disputes.The objective are as follow:
Historical data were used as the main source for system development. It
derived from the Arbitration Association of the Republic of China, the Public
Construction Commission of Republic of China. There are 153 dispute cases. The
system incorporated with new similarity measurement, a new methodology to better
cope with construction disputes. Figure 3.5 illustrates how the system is operated.
58
Updating data
User
interface
Data base
Querying
Source
cases
FCBR
A target
case
Historical
data
Data of
similar cases
Information
3.2.7
The previous studies were dealt with both general construction disputes and
also a single problem basis. The studies highlighted that application of information
technology facilities enhances the usability and flexibility of an expert system in the
recent development. It is important to enabling the expert system publishing online in
order to meet the challenges and competitiveness in construction dispute research. It
is also very practical since the high internets accessibility and user-friendly of
computing at the current situation.
Apart from that, all the expert systems discussed above were encouraging the
win-win situation and harmony atmosphere of resolving dispute. The systems are
assisting users to analyze decision through self-examine approach. It will encourage
59
self-learning and clarification to the certain construction deputes, so that the users
able to avoid or prevent it subsequently.
Table 3.2 shows the summary of the 6 studies and explains the differences in
term of their research characteristics. The comparison between the studies has
rendered important information for their research strengths and limitations, for
example, use of IT advancement, contract form, historical/court cases and panel of
experts as well as decision making methods on the targeted issues. This comparison
would help to improve the value and significance of the future research.
As a result, the findings from critical review and comparison of the expert
systems/models form the basis of discussion for the next preliminary study in the
local scenario.
60
Year
Method of
Historical
Panel of
Reference of
decision
data/ court
expert
Standard
making/process
case
Targeted Issue
Use of IT
advancement
Form
DISCON
1988
Flow chart
Yes
Yes
Yes
Minimal
1991
Rule based
Yes
Yes
Yes
Contract Interpretation
Minimal
2000
Case-based reasoning
Yes
No
No
Minimal
Contract Interpretation
Prediction
of
Construction
Disputes
issues
CoNegO
2004
Even Swaps
Graph Model
2006
Prisoners
dilemma
No
No
No
Yes
No
No
No
General
Minimal
strategy
FCBR
2009
Fuzzy
reasoning
Disputes
Problem
case-based
Yes
No
No
General
construction
Yes
disputes
62
63
The review and earlier preliminary semi-structured interview with the local
experts revealed the need for a more comprehensive expert system for contract
administration. From the studies above, the depth discussion of all construction
disputes will not be feasible by referring it to DISCON (Kraiem, 1988). It is
impossible to resolve or generate accurate and reliable results for all the issues due to
the characteristics and facts of the particular issues. It is also affected by the time and
resources constraint as well as uncertainties of external factors. However, an expert
system presents the principle of contractual obligations and expectations as a
guideline in decision making could fine-tune the argument above. The expert system
deals with the interpretation issues are relevant and practical towards the construction
industry as demonstrated by Robinson et al. (1991) in Singapore. Nevertheless, the
system by Robinson et al. (1991) has three areas that could be improved, i.e., use of
IT advancement, referring to the leading court cases and involvement of experts. It is
because an online application in the expert system is able to handle the shortcomings
of updating, storing, and exchanging information (Cheung et al., 2004). Furthermore,
the leading court cases and involvement of the experts are very crucial in an online
system because of the reliability and quality of the content.
62
Therefore, the self-examination and proactive approach in contract
administration towards dispute resolution or prevention is feasible. It could be served
by demonstrating a clarified, organized and reliable source of reference towards the
contractual obligations and expectations. It will cultivate self-learning and
examination by the end-users. The reference is important as the poor understanding
of contracts and lack of prevention/mitigation means of dispute resolution in the
local industry. In conclusion, the eDR was proposed by considering the shortcomings
from the previous studies.
3.3
The Plans of Work Stages divide the design and construction process. These
plans are important to be referred for identifying the job activities and the contractual
problems as shown in Table 3.3.
63
Table 3.3: RIBA plans of work
RIBA Plan of Work 2007
Stage
Inception
Appraisal
Feasibility
Design Brief
Outline Proposals
Concept
Scheme Design
Design Development
Detail Design
Technical Design
Product Information
Production Information
Bills of Quantities
Tender Documentation
Tender Action
Tender Action
Project Planning
Mobilisation
Operations on Site
Construction to Practical
CONSTRUCTION
PRE-CONSTRUCT
DESIGN
PREPARATION
Stage
Completion
L
Completion
Feedback
USE
USE
CONSTRUCT
DESIGN
PREPARATION
Apart from that, many journals and books were studied and reviewed for
identification of contractual problems, in particular three books regarding
engineering and construction contract management in local construction industry,
which is absolutely suitable to be referred in this study (Harbans Singh, 2003a,
2003b and 2003c).
64
3.3.1
Pre-Construction Stage
Design information
Insurances
Site possession
Work pragramme
(Source: RIBA Plans of Work, Harbans Singh, 2003a, 2003b and 2003c)
3.3.2
65
Table 3.5: Contractual issues in commencement and construction stage
No
Accessing to site
Default on notice
Fluctuation of price
Interference/problem by professionals
Interim payment
10
Partial possession
11
12
13
Practical completion
14
Quality of workmanship
15
16
17
18
Statutory obligations
19
Supply difficulties
20
21
22
Variations
23
Weather
(Source: RIBA Plans of Work, Harbans Singh, 2003a, 2003b and 2003c)
66
3.3.3
Post-Commencement Stage
Defects
Determination
Dispute resolution
Liquated damages
Unresolved variations
(Source: RIBA Plans of Work, Harbans Singh, 2003a, 2003b and 2003c)
67
3.4
68
3.4.1
(i)
(ii)
These functions are perhaps not clearly distinguishable but the most
successful standard forms are those that, apart from serving their legal function, are
regarded as regulating day-to-day relationship on site. The form should be written
and presented in such a way as to be useful for easy reference by non-legal site and
consultancy personnel (Robinson and Lavers, 1988). It is because the contract forms
are still lack of clarity and having legalese problems (Chong et al., 2007 and Chong
and Rosli, 2008b).
Besides, Robinson et al. (1996) also summarized that the objectives and
content of the standard form should cover the issues as follow:
69
inadequately detailed or wrongly biased, to modify such terms and
conditions;
3.4.2
Shumway et al. (2004) highlighted that the biggest risks a contractor faces
today may not associate with timely or efficient performance, but with the terms and
clauses in the construction contracts. It is simply because the construction industry
has relied on construction contracts to define and enforce the obligations and rights
of contracting parties (Cheung et al., 2006).
70
of the contract documents are not fully appreciated or understood (Hartman et al.,
1997). Worst still, when the contract documents are complex as being too thick and
too many legal phrases (Mohamad and Zulkifli, 2006).
3.5
Clarity is the key factor when to appreciate the construction contracts (Chong
and Rosli, 2010). Oxford Advanced Learners Dictionary defined that clarity is the
quality of being expressed clearly or ability to understand something clearly. In other
perspective, clarity is a starting point for the understanding, afterwards only goes
for appreciation of the construction contracts. Without clarity, it will be very difficult
to value and appreciate the contracts.
71
identified as simply as a writing instrument. This is just one example of how
complex language can be made clearer (Corren, 2000).
When the first language is not English, then it needs to clarify the
contract clauses in standard form (Styllis, 2005). It is applicable to
Malaysians as the mother tongues are basically in Malay language,
Chinese language and Tamil language.
Styllis (2005) also identified that the style of language is the barrier
for clarity of contract such as passive voice, repetition, too long in a
sentence (more than 50 words), incorrect or too much using shall,
too many cross references and so forth. It is absolutely related to
PWD Form of contract as Lim (2004) explained that the PWD Forms
can be traced to the English 1931 RIBA standard form of contract.
Then, it is also stated by Broome and Hayes (1997) that origin of
contract, which UK and Commonwealth largely derived from very old
precedents, and archaic language.
72
into account as many foreseeable situations as he can. The Latin definition of contra
proferentem is against the one bringing forth or against the proffering person.
73
3.5.1
Clarity Aspects
Problems of Clarity
Sentence is too long (Candlin et al., 2002; Cutts, 2004; Henkin, 1988; Styllis,
2005).
10
11
74
However, legalese is something too abstruse and difficult or failed to
understand. Occasionally, the reader will misinterpret the actual meaning. Candlin et
al. (2002) described that legalese is a term used, often derogatorily, to refer to the
unique characteristics of legal English. Moreover, Law Dictionary defined it as slang
for the sometimes arcane, convoluted and specialized jargon by the lawyers and legal
scholars. Henkin (1988) also stated that the meaning of such expression (legalese)
often differs from the meaning assumed by non-lawyers. In general, the legalese is
the use of formal and technical language in legal documents upsets interpretation
(Feinman, 2003). Table 3.8 shows the legalese aspects could be found in construction
contracts.
Legalese Aspects
Too many legal terms or phrases (Cutts, 2004; Mohamad and Zulkifli, 2006)
75
in a way that gives a co-operative, motivated person a good chance of understanding
it at first reading, and in the same sense that the writer meant it to be understood.
Shorten the sentence for ease of reading to average 15-20 words (Cutts, 2004).
Use positive style rather than negative style (Candlin et al., 2002; Cutts, 2004).
Use everyday words and grammar and only include legal terms where it has to
(Styllis, 2005).
Use the active voice instead of passive voice (Candlin et al., 2002; Cutts,
2004).
Use language of obligation correctly: avoid using shall, but still using it to
express partys obligation (Styllis, 2005).
10
11
12
13
14
76
In summary, the approach on clarity is vital. It is because the contracting
parties understand and agree to the contract provisions, the parties would perceive
the importance of their contractual obligations and rights as required in the contract.
Thus, an appreciation of what the construction contracts actually meant to the
stakeholders would help to avoid or prevent a dispute from festering, although
sometimes total elimination may not be achievable.
3.6
Concluding Remarks
This chapter reviewed the previous studies and current trend of alternative
means in contract administration toward the proposal of eDR, which to achieve the
fourth objective. Besides, Thirty nine contractual issues have been identified through
the three work stages. Meanwhile, the clarity aspects were discussed, i.e., the
language structure problems and clarity measures. It would help the users to
understand and appreciate the contractual expectations and obligations laid in the
contracts. In summary, the review highlighted a systematic means in contract
administration through identification of the sources of contractual issues and contract
clarity for better understanding and appreciation as to the third research objective.
The systematic means would be considered in the development of eDR in the
research.
3577
CHAPTER 4
CONTRACTUAL VARIATIONS
4.1
Introduction
78
4.2
Background of Variations
Changes are inevitable, even though the project was carefully planned. It is
because the inherent characteristics of contraction contracts as the work progresses
along the period (Harban Singh and Kandan, 2004).
79
Table 4.1: Contract clauses of variation under different contract forms in Malaysia
Definition on Variation
PAM
PAM
2006
1998
CIDB
IEM
PWD
PWD
203A
DB/T
(83/07)
Alteration and
11.1
modification of quantity
11.1
1.1(a)
(i)
(addition or omission of -
23
24(b) /
(a)
24.2
27.1(a)
(i)
CIDB)
Change in quality
11.1
11.1
1.1(c)
(i)
23
24(b) /
(a)
24.2
27.1(a)
(iii)
forms)
Alteration or modification
11.1
of design
Exclude any changes for
11.1
11.1
24(b) /
(i)
24.2
11.1
1.1
27.1(a)
27.2
(vi)
breach of contract.
Addition or omission
11.1
11.1
(a)
(ii)
1.1(b)
23
24(b) /
27.1(a)
(a)
24.2(a)
(i)
(ii)
&
(v)
Substitution
11.1
11.1
24(b) /
27.1(a)
(a)
(ii)
24.2(a)
(i)
11.1
11.1
24(b) /
27.1(a)
(b)
(iii)
24.2(b)
(ii)
24(b) /
27.1(a)
24.2(c)
(iii)
or goods
Removal of any part of the 11.1
11.1
works, Equipment,
(iv)
(c)
1.1(e)
80
Definition on Variation
PAM
PAM
2006
1998
CIDB
IEM
PWD
PWD
203A
DB/T
(83/07)
Addition, alteration or
11.1
11.1
(d)
(v)
27.1(b)
obligations or restrictions
imposed by the Employer
on any limitation of
working hours, working
space, or access to or
utilisation of any specific
part of the site or the
execution and completion
of the work in any specific
order. (exclude obligations
or restrictions - PAM06)
Any change in the original
1.1
1.1(c)
and/or nature
- Change in levels,
1.1(d)
23
(a)
dimensions
(iv)
- Change in Contractor's
11.1
Temporary Works,
(vi)
1.1(f)
81
Definition on Variation
PAM
PAM
2006
1998
CIDB
IEM
PWD
PWD
203A
DB/T
(83/07)
- Postponement of any
1.1(g)
1.1(h)
11.1
(vi)
1.1
4.3
Myths on Variations
Occasionally, the changes in the contract would not the root problem in a
dispute. But, the consequent contractual obligations and expectations trigger the
dispute. Table 4.2 shows misapprehensions or myths by contractors pertaining to
variation claims:
82
Table 4.2: Misperceptions on variation claims by contractors
No
1
Prior to ordering extras, the employer must obtain the contractors agreement to
the rates for valuing the varied work.
In the situation where varied work has been undertaken, measured and valued
by the contract administrator but payment is not effected, the contractor is
automatically entitled to interest on the amount due.
The employer has no right to order and the contractor is not obliged to carry out
varied work in the defect liability period.
The contractor has a right to call for a review of measured and valued work
involving variations even after the final account has been prepared and the final
certificate issued.
The contractor has, in addition to the monetary claim for the varied work, a
parallel right to claim for extension of time and direct loss and expense.
(Source: Harbans Singh and Kandan, 2004)
On the other hand, the employer has a different view towards these variation
claims. Most probably, it is caused by ignorance or lack of proper understanding or
appreciation as shown in Table 4.3.
83
Table 4.3: Misperceptions on variation claims by employers
No
1
There are no variations in contracts based on firm Bills of Quantities and for
extras the use of the corresponding BQ rates is mandatory irrespective of the
quantum of the extras.
The employer can omit any work as he likes and award it to a third party of his
choice during the currency of the original contract.
For package deal types of contracts based on a firm price lump sum, there is
no entitlement to the contractor for variations.
Unless there is an express formula for valuing varied work, the final decision as
to the rates to be employed is the prerogative of the employer, the contractors
only recourse in the event of disagreement is to arbitrate the matter
10
Where the contractual provisions are not clear, the employer has an inherent
right to order varied work to be undertaken in the Defect Liability Period and
the contractor is obliged to effect the same.
11
Quantum meruit claims pertaining to varied work do not fall within the
contract administrators scope of responsibility and therefore the contractor
needs to pursue these either through arbitration or litigation
(Source: Harbans Singh and Kandan, 2004)
84
4.4
Issuance of Variations
4.4.1
First of all, the right person with the right authority shall be determined. In
PAM 2006, the right person is the Professional Architect approved by Board of
Architect under the Architect Act 1967 as named in Article 3. Clause 11.2 permits
the Architect to issue instructions requiring variations or sanction in writing for any
variations made by the Contractor. Under these two conditions, the variations will
not vitiate the original contract. The vitiations statement is to clarify the Architects
power/his discretion to order any variations which is deemed necessary. The
common law has restricted the Architects power as held in case Commissioner for
Main Roads v Reed and Stewart Pty. Ltd. & Another3, where the power to direct the
contractor to not perform certain works under the contract and then allow another
person to perform the work. Besides, the Architect may be liable to the employer if
he overruled, which the issued variation was outside the scope of contract without
special authority from the employer (Sundra, 1999). This statement can be referred to
Mitsui Construction Co v Attorney General of Hong Kong 4.
3
4
85
4.4.2
Period of Issuance
In addition to this, Clause 4.3 explains the Contractor must proceed with the
work to conform to the local authorities requirements, even though the Contractor
does not receive any response of Architect Instruction (AI) within 7 days. It is
provided that the Contractor already sent a written notice to the Architect regarding
the inconsistencies between the Contract documents and the local authorities
requirements. Any changes of this issue are regarded as a variation required by the
Architect in the Contract.
In other words, the valid period of variations is before the CPC. The Architect
cannot issue any AI on variations after this CPC. There is an exception to variations
if the project needs to comply with the local authorities requirements.
4.4.3
Provisional Sum
The provisional sum can be divided into two aspects as regards to variations,
i.e., provisional quantities and expenditure of provisional works. The first one does
not necessary require an AI for carrying out the work, example piling works stated in
the Bill of Quantities (BQ) (The Entrusty Group, 2007). It is inappropriate to get an
86
AI at the moment of driving the piles for its varied quantities. However, it is
advisable to obtain an AI before the work is carried out for acknowledgement.
Apart from that, AI is mandatory for the expenditure of Prime Cost (PC)
Sums and Provisional Sums as described in Clause 11.4 of PAM 2006. Usually,
these provisional works relate to the PC or provisional works, which are hard to
determine its actual quantity/quality based on the existing contract documents.
Furthermore, the instruction on the expenditure PC Sums work is regarded as
expenditure of Provisional Sums.
4.4.4
Issuance of Variations
Authorized Person and Power
A1
> The right Person is the Professional Architect or other form of practice
registered under Architect Act 1967 and named in the contract.
A2
> The right person also includes the Employer of the contract.
A3
A4
> Architects power is restricted, which he cant omit a work and give it to
another contractor.
87
Item
Issuance Variations
Period of Issuance
A5
> If Architect issues variations that outside the scope of Contract and without
expressed authority from the Employer, he may be liable to the Employer.
A6
A7
> Architect can issue variations at any time before issuance of the CPC.
A8
During DLP if the contractor fails to rectify the defects and with the
consent of Employer, Architect can issue omission for leaving the
defects from the set-off. The omission constitutes a valid issuance of
variation.
A9
> Contractor must conform to the local authorities and service providers
requirements and proceed the work if no AI in response for the
inconsistencies with statutory requirements within 7 Days of the given written
notice.
A10
A11
> There are two parts of provisional items for variations, i.e., Provisional
Quantity and expenditure of Provisional Sums.
A12
A13
Provisional Quantity describes as the tasks are with rates and prices
for the pre-estimate quantity and it subject to re-measurement for the
actual value.
A14
> Provisional Sums means Sums provided in the Contract and/or for
Nominated Sub-Contract for work, materials or goods in the BQ which
cannot be determined or detailed at the time.
A15
88
Item
Issuance Variations
Provisional Sums
A16
> Provisional Quantity does not necessary require an AI for carrying out the
work, like piling length in the BQ.
A17
(Source: PAM 2006, Commissioner for Main Roads v Reed and Stewart Pty. Ltd. &
Another, Mitsui Construction Co v Attorney General of Hong Kong and
researchers inputs)
Items A1, A3, A6, A7, A8, A9, A11, A12, A14 and A17 are derived from
Clause 11 of PAM 2006. Items A4 and A5 are from Commissioner for Main Roads v
Reed and Stewart Pty. Ltd. & Another3 and Mitsui Construction Co v Attorney
General of Hong Kong4, respectively. The remaining items A2, A10, A13, A15 and
A16 are the personal inputs from the researchers observations or elaborations. These
preliminary guidelines would be confirmed and verified by the experts in a
questionnaire form (Appendix D) during the subsequent Delphi study.
4.5
Validity of Variations
89
4.5.1
Written Instruction
1.
2.
3.
A well known case, Central Provident Fund Board v Ho Bock Kee 5 has
discussed in detailed about the validity of notice. The case highlighted the
determination issues from a building construction. Giving a notice with a particular
form, mode and manner is vital and required in most of contract forms. If notice was
delivered not according to the requirements in the contract, it would construe as an
invalid notice and bear no liability of legal effect to the concerned party as
highlighted in the case, where a registered post is required instead of hand delivery.
Lord Denning also took his view about this by pointing out a registered post would
show a clear proof of postage and of the time of posting.
90
Apart from that, there is a legal principle governed about waive of written
instruction, called habitual acceptance or by conduct of work completed. If this is
practiced by the concerned parties through oral agreement, it is able to waive the
requirement of written variation as subsequent actions or conducts could serve as
evidence for this circumstance. Hence the contractor recovers for extra work without
written instruction on variation. The court cases, Flooring System, Inc v Staat
Construction Co.
Developers, Inc v. Safeco Insurance Co. Inc7 could be referred as to a waiver of the
requirement of written instruction on variation. The Flooring System case further
emphasised without express and defined items on extras, it would not recoverable.
4.5.2
Principle of Variations
In general, any errors or inaccuracies in the bills of quantities are at the risk
of the employer in that it may constitute a variation. This statement is based on the
court case, Patman and Fortheingham Ltd v Pilditch8. However, this case should be
read along with the contract provisions under PAM 2006, which clarify the
concerned parties obligations regarding discrepancy or divergence between
documents (Clause 1.4) and correction of errors could be carried out by the Architect
or Consultant (Clause 12.2).
On the other hand, if the bills of quantities are not prepared in accordance
with the applicable Standard Method of Measurement (SMM), it may be a
contractual basis for a variation as referring to the Bryant and Sons Ltd v
Birmingham Hospital Saturday Fund9. Clause 12.1 supports this by stating that the
91
bill of quantities must be prepared in accordance with the principles of the SMM,
which sanctioned by the Institution of Surveyors Malaysia and currently in force.
works carried out by the contractor not required under the contract
and without any instruction is not considered extra work;
92
On top of that, all variation works must exclude any changes intended to
rectify any negligence, omission, default and/or breach of contract by the Contractor
and such changes executed by the Contractor entirely at his own cost. This statement
is found at last paragraph of Definition of Variation under Clause 11.1 of PAM 2006.
4.5.2.1 Addition
According to Clause 11.1 (a) of PAM 2006, the variation means the
alteration or modification of the design, quality or quantity of the Works including
the addition of the Work. Under this express provision, the clause briefly states about
addition work could be formed a variation in a contract. However, it does not discuss
in detail to which extend of the addition could be a variation. Few scenarios from the
court cases could reduce this gap.
10
93
Russel v Sa Da Bandeira11 also discusses the indispensably necessary works are not
considered as variations in a contract.
Apart from that, invalid additional work also could discuss in Cardinal
Changes. Harbans Singh (2003c) explains that if the variation ordered be
substantially different, either materially in excess of the agreed sum or
fundamentally changes the nature of the works, such a variation work would be
contractually invalid as referring to Sir Lindsay Parkinson and co Ltd v
Commissioners of His Majestys Works and Public Buildings 14 . For example,
increased of 60% in excavation, 40% in sewer length and 90% in concrete as
highlighted in Wegan Construction Pty Ltd v Wodonga Sewerage Authority15.
4.5.2.2 Omission and Removal of the Executed Works or Materials and Goods
Clause 11.1 (a) and Clause 11.1 (c) of PAM 2006 discuss about omission and
removal of works. Even though the clause numbers are different, they are sharing
some same principles for the variation works. The former deals with omission works,
while the latter is about removal from site any executed works, materials and goods
which are in accordance with the contract. The discussion focuses on the omission
11
94
works. It is because the omission of works requires more clarification and detailed
investigation, whereas the removal provision is clearly stated.
There are two different types of omission of work could be found in a project,
i.e., the work is omitted by a way of variation as certain part of work is no longer
needed in the project and secondly is about the omitted work has been given to
another contractor to carry out.
At the first scenario, the omission works are valid in the contract and quite
common in a construction project. It also includes reduction of the quantities of a
particular work in the contract. The omission works may cause by clients finance
problem and change of design requirements. Meanwhile, the second circumstance is
an invalid omission, where the omission of work has been given to a third party
(Harbans Singh, 2003c). It is an invalid exercise of the power given to the designated
person and could be construed as a breach of contract entitling the contractor to
rescission and/or damages as referring to Carr v JA Berriman Pty Ltd 16 and
Commissioner for Main Roads v Reed and Stewart Pty Ltd and Another17.
16
95
4.5.2.3 Substitution and Alteration of the Kind or Standard of Materials or
Goods
Clause 11.1 (a) states that the alteration or modification including substitution
of the design, quality or quantity of works. According to Oxford Dictionary,
substitution is defined as a person or thing acting or serving in place of another or
replacing another. In other words, the substitution is about replacing the work of
another for its design, quality or quantity.
There are two court cases that can be referred for above two scenarios, i.e.,
Thorn v Mayor and Commonalty of London12 and Blue Circle Industries v Holland
Dredging Co.13. The cases highlighted that if the varied work is so different from the
contract, it will be an invalid variation. It would constitute a separate contract.
i.
96
ii.
iii.
iv.
Theses changes are based on the contracts requirement and on a case basis. It
is subjected to the project characteristics and nature of the works to be carried out.
4.5.3
Table 4.5 shows the summary of validity of variation that discussed earlier. It
consists of eight main contractual areas and twenty-nine guidelines concerning
validity of variations.
Validity of Variations
Written Instruction
B1
B2
B3
97
Item
Validity of Variations
Written Instruction
B4
B5
> If the delivered notice was not according to the requirements in the contract,
it would construe as an invalid notice and bear no liability of legal effect.
Definition/Principle of Variation
B6
B7
B8
B9
> Contactor must execute variation entirely at his own cost if to rectify his
negligence, omission, default and/or breach of contract.
Addition
B10
B11
B12
B13
> An additional work has caused the cardinal changes of agreed sum or nature
of the Works, it construed as an invalid variation.
B14
Omission
B15
B16
> An omitted work is the part of the Work that no longer needed in the
project, it construed as a valid omission.
B17
> If the part of the Work is omitted and given it to other contractor, it
construed as an invalid omission.
98
Item
Validity of Variations
Omission
B18
> An omitted work changes the fundamental basis of the contract, it construed
as an invalid omission.
B19
Substitution
B20
> Variations define as changing the work of another for its design, quality or
quantity of the Work.
B21
> If the changed work has caused the cardinal changes of agreed sum or
nature of the Works, it construed as an invalid substitution.
Alteration of the Kind or Standard of Materials or Goods
B22
B23
> If the changed materials/goods are so different from the contract, it would
constitute an invalid variation.
B24
> Materials supplied by the Contractor are more superior than that specified
without any instruction is not considered as a variation.
> Variations define as removal from site any executed works, materials and
goods which are in accordance with the contract.
Changes to the provisions in the Contract
Variations also define as:
B26
B27
B28
> Access to or utilisation of any specific part of the Site e.g., difficulty to
access or use on the land or part of the site.
B29
> The execution and completion of the work in specific order e.g., changing
of method of statement, construction method, etc.
(Source: PAM 2006, Central Provident Fund Board v Ho Bock Kee, Flooring System,
Inc v Staat Construction Co, Missouri Department of Transportation, ex rel. PR
Developers, Inc v. Safeco Insurance Co. Inc, Patman and Fortheingham Ltd v
99
Pilditch, Bryant and Sons Ltd v Birmingham Hospital Saturday Fund, Wegan
Construction Pty Ltd v Wodonga Sewerage Authority, Carr v JA Berriman Pty Ltd,
Commissioner for Main Roads v Reed and Stewart Pty Ltd and Another,Blue Circle
Industries v Holland Dredging Co., Thorn v Mayor and Commonalty of London,
Chadmax Plastics v Hanson and Yuncken and researchers inputs)
Items B1, B2, B3, B4, B6, B8, B9, B10, B11, B13, B15, B20, B22, B25, B26,
B27, B28 and B29 are derived from Clause 1.4, 2.2, 4.3, 11 and 12 of PAM 2006.
Items B5, B7, B12, B13, B14, B17, B19, B21 and B23 are extracted from court cases.
The remaining items B16, B18 and B24 are the personal inputs from the researchers
observations or elaborations. These preliminary guidelines would be confirmed and
verified by the experts in a questionnaire form (Appendix D) during the subsequent
Delphi study.
4.6
Valuation Rules
Under PAM 2006, Quantity Surveyor shall measure and value the variation
works. The Contractor shall provide assistance to the Quantity Surveyor for any
recording of site information and/or site measurements are carried out at the site.
Then, the Quantity Surveyor is able to valuate the variations and provisional sums
works as described in Clause 11.5.
Six rules of valuation of variations are discussed in Clause 11.6 of PAM 2006.
It is for the variation works that executed by the Contractor. The works are the
provisional quantity that included in the bill of quantities and the expenditure of
provisional sums works.
100
4.6.1
The first rule uses the rates and prices laid in the contract documents to
determine the valuation under Clause 11.6 (a). This rule is only applicable to the
variation work is of a similar character and executed under similar conditions. It does
not significantly change the quantity of work as set out in the contract documents.
In other words, the clause could be explained that the variation causes a little
change in the quantity of the works. Most probably, the amount of changed quantity
is anticipated before the variation work is executed. Therefore, the original works
rate and price will be used for its valuation.
4.6.2
Clause 11.6 (b) states this valuation would take into consideration on a fair
adjustment into the rates and prices for determining the valuation. The rule is
targeted to the variation work of a similar character, and either is executed or not
executed under similar conditions but there is a significant change in the quantity of
work carried out.
101
Furthermore, these two contract provisions are quite similar in term of the fair
adjustment and fair market rates and prices. The term fair need to be clarified and
explained. Chappel et al. (2001) defined that what is fair will depend on the whole
of the contractors pricing strategy, either keenly priced or with a handsome profit
margin. Although a fair valuation is solely the responsibility of the quantity surveyor
under the contract provisions, he/she must still refer to the general tenor of pricing as
revealed in the contract documents.
Besides, these fair adjustment or rates are very common in litigation cases.
Many court cases discussed about the evaluation of price for the varied work, such as:
Laserbore Ltd v Morrison Biggs Wall Ltd19 The judge defined the
meaning of "fair and reasonable payments for all works executed". He
considered that the costs plus basis was wrong in principle even
though in some instances it may produce the right result. The
appropriate approach was to adopt general market rates.
Semco Salvage and Marine Pte Ltd v Lancer Navigation Co Ltd21 The fair rates and prices in this case explained that the equipment
and personnel used in the salvage operation means a fair rate of
expenditure and does not include any element of profit.
19
102
Weldon Plant Ltd v The Commissioner for The New Towns23 - The
contractors entitlement was to be paid a fair valuation. The judge
took the view that in evaluating a fair valuation, the calculation should
be based upon the reasonable costs of carrying out the works if
reasonably and properly incurred. The judge held that a fair valuation
should include elements for the cost of labour, the cost of plant, cost
of materials, the costs of overheads and profit.
With the aforesaid case law decisions, some of the cases are holding different
principles as to the fair valuation. However, it is relatively clear that the latest
development of the fair valuation should include the costs of labour, plant, material,
overheads and profit according to the Henry Boot Construction v Alstom Combined
Cycles Ltd22 and Weldon Plant Ltd v The Commissioner for The New Towns23.
4.6.3
Clause 11.6 (d) states that if the works cannot be properly measured and
valued under the Rule 1, Rule 2 or Rule 3, the Contractor shall be allowed to use
Rule 4, either:
23
103
without the daywork rates, at the actual cost to the Contractor of his
materials, additional construction plant and scaffolding, transport and
labour for the work concerned, plus fifteen (15) percent, which
percentage must include for the use of all tools, standing plant,
standing scaffolding, supervision, overheads and profit.
In either case, vouchers are required for the valuation and signed by the Site
Agent as well verified by the Site Staff, by specifying:
workers names
materials
scaffolding
transport
The vouchers must be delivered to the Architect and Quantity Surveyor at weekly
intervals with the final records delivered not later than 14 days after the work has
been completed.
Besides, a signed daywork sheet is only for evidence or record purposes and
does not signify an entitlement to additional payment as held in the Clusky v
Chamberlain24. The particulars of vouchers are vital for contractor to be entitled for
the payment.
24
[1995] BLM 6.
104
4.6.4
The valuation of omitted work is based on the rates and prices in the contract
documents. If the omissions substantially vary the conditions for the remaining
works are carried out, the prices of such remaining works must be valued under Rule
1, Rule 2 or Rule 3.
4.6.5
4.6.6
105
Table 4.6: Preliminary guidelines on valuation rules
Item
Valuation Rules
C1
> The Quantity Surveyor shall measure and value all variations.
C2
> The Contractor shall provide assistance to the Quantity Surveyor for any
recording of site information and/or site measurements are carried out at the
site.
C3
> The word similar used in valuation rules cannot be taken as identical, it
should consider the background information and facts of the variation.
C4
C5
> It uses the original rates and prices of BQ to determine the valuation.
C6
> This rule applies to the variation of a similar character and executed under
similar conditions. It does not significantly change the quantity of work as set
out in the BQ.
C7
C8
> It includes a fair adjustment into the original rates and prices of BQ to
determine the valuation.
C10
> This rule applies to the variation of a similar character and either is
executed or not executed under similar conditions but there is a significant
change in the quantity of work carried out.
C11
> The fair will depend on the whole of the contractors pricing strategy,
either properly priced or with a handsome profit margin.
C12
C13
> The calculation should be based upon the reasonable costs that properly
incurred from the works and included elements for the cost of labour, plant,
materials, overheads and profit.
C14
106
Item
Valuation Rules
Rule 2 of Fair Adjustment
C15
> It includes a fair market rates and prices for the variation of different
character.
C17
> A fair valuation must include an element of profit except for special
circumstances.
C18
>The calculation should be based upon the reasonable costs that properly
incurred from the works and included elements for the cost of labour, plant,
materials, overheads and profit.
C19
> This fair valuation is based on the variations character, instead of the
amount of changed quantities.
C20
> If the works cannot be properly measured and valued under the Rule 1,
Rule 2 or Rule 3, the contractor shall use Rule 4.
C22
> The valuation is either from Daywork Rates in the Contract documents; or
where there are no such Daywork Rates, at the actual cost to the Contractor of
his materials, additional construction plant and scaffolding, transport and
labour for the work concerned, plus fifteen (15) percent, which the percentage
must include the use of all tools, standing plant, standing scaffolding,
supervision, overheads & profit.
C23
> In either case, vouchers are required for the valuation, signed by the Site
Agent and verified by the Site Staff, by specifying:
time spent daily upon the work, workers names, materials, additional
construction plant, scaffolding and transport
The vouchers must deliver to the Architect and Quantity Surveyor at weekly
intervals and the final records must deliver within 14 Days after completing
the work.
107
Item
Valuation Rules
Rule 4 of Daywork Rates
C24
> Quantity Surveyor shall not change the figure or hours in the agreed and
signed Daywork rates or vouchers.
C25
> A signed Daywork sheet is only for evidence or record purposes and does
not signify an entitlement to the variation.
Rule 5 Omitted work
C26
> It uses the original rates and prices to determine the valuation of omitted
work. If the omissions substantially vary the conditions for the remaining
works are carried out, the prices of such remaining works must be valued
under Rule 1, Rule 2 or Rule 3.
Rule 6 Re-measurement on Actual Quantities (Provisional Quantity)
C27
C28
> The actual quantities must be based on the agreed as built drawings and/or
site records.
(Source: PAM 2006, Building Contract Dictionary, 2001, Weldon Plant Ltd v The
Commissioner for The New Towns, Henry Boot Construction v Alstom Combined
Cycles Ltd , Clusky v Chamberlain and researchers inputs)
Items C1, C2, C4, C5, C6, C9, C10, C16, C21, C22, C23, C26, and C27 are
derived from Clause 11 of PAM 2006. Items C11 is from Building Contract
Dictionary. Items C12, C13, C17, C18 and C25 are from the court cases. The
remaining items C3, C7, C8, C14, C15, C19, C20, C24 and C28 are the personal
inputs from the researchers observations or elaborations. These preliminary
guidelines would be confirmed and verified by the experts in a questionnaire form
(Appendix D) during the subsequent Delphi study.
108
4.7
Additional
Expense
and
Subsequent
Circumstances
Caused
by
Variations
Clause 11.7 explains that where a variation has caused or likely to cause the
Contractor to incur additional expenses for which he would not be paid under any
provisions in Clause 11.6. The Contractor may make a claim regarding this provided
that the Contractor shall give written notice to the Architect of his intention to the
claim together with an initial estimate duly supported with all necessary calculation
within 28 days from the date of the AI or Confirmation of Architects Instruction.
The notice is a condition precedent to the entitlement of the claim. Subsequently, the
Contractor shall send to the Architect and Quantity Surveyor complete particulars
and calculations within 28 days of completing such variation. If the Contractor fails
to submit the required particulars within the stated time or long period agreed by the
Architect in writing, then the Contractor has waived his rights to the claim.
However, it seems that Clause 11.7 under PAM 2006 would not allow for
loss of profit for the Contractor. It is because this is a new provision, which different
from clause 11.6 PAM 1998 direct loss and/or damage that possible to include the
gross profit. The direct loss and/or damage was held by the court that this wording
included loss of gross profit on the uncompleted work in Wraight Ltd v PH and T
Holdings25 (1968). Therefore, it is relatively clear that the contractor may claim his
expense only under the Clause 11.7.
Nevertheless, a claim for loss of profit will always be successful where the
varied work is by an invalid variation, for instance, omission of work. If the work is
omitted from the contract and given to others to execute it then the contracting
contractor/injured party will have an entitlement to loss of profit as referring to
McAlpine Humberoak Ltd v McDermott International Inc 26 and even for oral
agreement regarding invalid variation as held in the case of Kin Wah J F
25
26
109
Construction & Engineering Co Ltd v L&M Foundation Specialist Ltd27. Besides that,
the decision from Carr v JA Berriman Pty Ltd16 also clearly revealed that if a work is
omitted from the contract and given to others then the contractor will be entitled to
claim loss of profit.
4.7.1
Contract Sum
The amount caused by variations need to be added into the contract sum. As
soon as the Architect has ascertained the amount of variations as stated in Clause
11.9, the amount must be added to contract sum. In other words, the ascertained
amount must be included in the coming Interim Certificate. Basically, there is no
timeframe provided for the ascertainment.
4.7.2
110
Table 4.7: Preliminary guidelines on additional expenses and subsequent
circumstances
Item
D1
> If a variation has caused or likely to cause the Contractor to incur additional
expenses, where he would not be paid under the 6 Rules. He may claim it
provided that given a written notice of his intention to the Architect together
with an initial estimate duly supported with all necessary calculations within
28 Days from the date of the AI or CAI. The notice is a condition precedent
to the claim entitlement.
D2
> Subsequently, the contractor shall send to the Architect and QS complete
particulars, calculations and contemporaneous records within 28 Days of
completing such variation. If the contractor fails to submit the required
particulars within the stated time or longer period agreed by Architect in
writing, then the contractor has waived his rights to the claim of additional
expenses.
D3
> Loss of profit is not claimable in this provision as it was covered under the
Rule 2, 3 or 4.
D4
> However, a claim for loss of profit will always be successful for the invalid
omission.
D5
> The Architect and QS shall have access all contractors documents or
records in the possession, custody or control and with free of charge each to
them if requested until all variation claims resolved. Same for the subcontractors and/or suppliers documents in possession, custody or control by
the Contractor.
D6
> As soon as the Architect has ascertained the amount of variations and/or
additional expense, it will add into Contract Sum and include into the next
Interim Certificate.
D7
> The Architect could ascertain the amount anytime before Final Account as
no timeframe is provided.
(Source: PAM 2006, McAlpine Humberoak Ltd v McDermott International Inc, Kin
Wah J F Construction & Engineering Co Ltd v L&M Foundation Specialist Ltd, and
researchers inputs)
111
Items D1, D2, D5, D6 and D7 are derived from Clause 11 of PAM 2006. Item
D4 is extracted from McAlpine Humberoak Ltd v McDermott International Inc26 and
Kin Wah J F Construction & Engineering Co Ltd v L&M Foundation Specialist Ltd27.
The remaining D3 is the researchers observations or elaborations. These preliminary
guidelines would be confirmed and verified by the experts in a questionnaire form
(Appendix D) during the subsequent Delphi study.
4.8
Concluding Remarks
This chapter discusses the issuance and validity of variations. Architect is the
designated person to instruct a variation in written form, while validity is about the
principles or definitions of variations in the contract provisions. The concerned
parties should mutually agreed beforehand about the variation work as detail as
possible for its timing of execution, prices and rates, methodology, as well as
contractual provisions. Then, it would reduce or prevent any conflicts or disputes
occurred after the work was carried out. The preliminary guidelines were developed
through a detail investigation. It would be tested in the subsequent Delphi study
before the incorporation into the eDR.
112112
CHAPTER 5
RESEARCH METHODOLOGY
5.1
Introduction
5.2
Literature Review
113
review only the main works which more attention to the concepts, linkages and
measures (Tan, 2008). For the results of the first way of review, keywords and
important terminologies in the research were defined such as construction contract
administration, construction conflicts and disputes as well as dispute resolution.
These areas would be reviewed to understand and determine their backgrounds or
philosophies. The second way was a detailed literature study and included law case
studies. The findings of the review were presented in Chapter 1 to 5.
5.3
114
resolution and comments and recommendations. It was served as preliminary study
in this research. Content analysis was adopted to compare and analyse the data
recorded from the interview. The findings were merely used to justify and strengthen
the need of this eDR research as highlighted in problem statements.
Subsequently, the literature review was carried out concurrently. It kept open
and ensured its comprehensiveness towards the latest research findings. However, it
may lead to the review never being finished, so a critical review is carried out and
established a period (1990-2007), which the body of relevant literature from
previous research was reviewed critically (Fellows and Liu, 2003). As a result
of the critical review, a detailed literature study was conducted on the expert
systems/model as the latest development in the recent years. This subsequent review
is to identify the research gaps for the current trend on the application as shown in
Chapter 3. These two research methods were carried out at the early stage of research,
yet they have the significant findings towards the proposal of eDR.
5.3.1
Content Analysis
115
5.4
Documentary Analysis
5.5
Questionnaire
116
Likert scale selected for the questionnaire design, in which a set of items was
proposed with respect to a particular attitudinal object for the scaling respondents
method (Panneerselvam, 2006). Likert scale is a widely used instrument in
measuring opinions, beliefs and attitudes (Devellis, 1991). Therefore, the
questionnaire were incorporated the likert scale for the degree of agreement. Besides,
the self-administered questionnaire was selected and used in this research, particular
in achieving the second objective, i.e., to identify the behaviour and practice of
dispute resolution methods in Malaysian construction industry.
In this section, the details of the questionnaire design and administration are
explained. This method adopted to analyse the data collected from the survey
exercise is also described. Basically, there are two main sections for the
questionnaire such as:
117
Apart from that, since the questionnaire was determined to be selfadministered, it was realised that it should be self-explanatory without sharing any
clarifications regarding the questions. To ensure this, a covering letter and a separate
page of introduction describing the aim and objectives of the research were attached
to the questionnaire.
5.5.2
Questionnaire Sample
118
and ISO contractors because the are more competent contractors with systematic and
better management approaches in terms of ISO and their projects are exceeding RM
10 millions.
5.5.3
Questionnaire Analysis
Point 2: Disagree
Point 3: Neutral
Point 4: Agree
119
5.5.3.1 Mean Analysis
Average Index
a x
x
i
Subsequently, data obtained from the survey exercises were also tested in a
series of statistical tests. The following statistical methods have been used for data
analysis, with the aid of SPSS software, for instance:
The Kruskal-Wallis test indicated that the means of three groups are equal on
the problems of language structure because all the variables P-value larger than
critical value of significance 0.05 (Morgan et al., 2007). Meanwhile, Cronbachs
120
Alpha method was applied in this case to understand whether the data provide a good
support for internal consistency reliability. If the tested item has reliability
coefficient of more than 0.7 implies that it is statistically reliable and should not be
dropped for further analysis (Julie, 2005).
Factor Analysis was adopted to find the latent factors to be considered in this
research. The Factor Analysis is important as to further clarify the data analysis from
the mean score. Meanwhile, it helped to reduce and extract the essential factors
affecting the selection of dispute resolution methods. SPSS program was used to
perform the data analysis of the research. According to Petty (1995), factor analysis
is a technique to achieve parsimony through the identification of the smallest number
of descriptive terms to explain the maximum amount of common variance in a
component matrix
121
5.6
5.6.1
Delphi Study
The Delphi method is the main primary data collection method for the
development of the eDR. The Delphi method was developed by Norman Dalkey of
the RAND Corporation in the 1950s for a US-sponsored military project (Buckley,
1995; Meyrick, 2003; Skulmoski et al., 2007; Steinert, 2009). A commonly agreed
definition of the Delphi method was proposed by Linstone and Turoff (1975) as
follow: Delphi may be characterised as a method for structuring a group
communication process so that the process is effective in allowing a group of
individuals, as a whole, to deal with a complex problem. The Delphi method is a
popular method in research in the field of the social sciences especially at the masters
and doctoral levels (Skulmoski et al., 2007). This method has well accepted by the
academicians. A big number of publications regarding the Delphi can be found in the
well-known referred journals. However, many feedback reports and comments have
discussed about the implementation and effectiveness of the method. Thus, a detailed
investigation has been carried out on the Delphi method as shown in Table 5.1.
Recruitment term of expert may misuse in Delphi study (Mullen, 2003; Meyrick, 2003;
Hung et al., 2008).
Remarks: Choosing qualified experts is critical for success of Delphi
study. Hence the expert recruitment is based on the relevant knowledge,
experience of a particular topic and some soft issues like willingness and
effective communication skills (Mullen, 2003; Skulmoski et al., 2007).
122
Features
Number of
Issues: There is a wide range in the sample size, it can be from a few of
Participants
Number of
Issues: There is a possibility that outliers may withdraw from the study
Rounds
simply because the Delphi has no more rounds or they have been
excluded as they had failed to modify their opinion (Kuo and Chen,
2008).
Remarks: As the Delphi allows the respondents to give their feedback
and revise their earlier responses, two rounds of Delphi are a must
(Mullen, 2003). The number of rounds should depend on the research aim
and objectives and not be pre-determined at the outset of the research.
Anonymity
123
Features
Mode of
Interaction
Consensus
Issues: Delphi may become a tool for forcing consensus by having more
Results
124
render their view on a particular issue who cannot come together
physically.
The Delphi method is an effective and efficient method for PhD level
research due to its flexibility research technique to collect and distil
the anonymous judgment of experts.
Over the years, researchers has modified and improved the traditional Delphi
Method for their researches aim and need. It is because the traditional Delphi
method has always suffered from low convergence expert opinions, declined of
response rate, costly, time consuming and the possibility of filtering out particular
expert opinions by the researcher (Ishikawa et al., 1993; Kuo and Chen 2008).
Furthermore, in many real situations, experts judgments can not be properly
reflected in quantitative terms by having more rounds of Delphi. It will create
ambiguity due to the differences in the meanings and interpretations of the experts
opinions (Wang and Lin, 2008). Thus, Ishikawa et al. (1993) utilized fuzzy sets
theory in the Delphi method to eliminate these shortcomings by using the max-min
fuzzy type of Delphi method. Subsequently, this method has been adopted by many
researchers and described it as FDM.
125
x a1
for a 1 x a m , A L
a m a1
A A (x)
x a2
for a 2 x a m , A R
am a2
0
otherwise
AL and AR are the triangular number for left and right. The (a1, a2) is the supporting
interval and the point (aM, 1) is the peak as illustrated in Figure 5.1 below.
(am, 1)
1
AL
a1
AR
am
a2
126
this study because one round of Delphi cannot incorporate feedback and revision of
answers by the experts. It is vital to consider the defining features of traditional
Delphi because new data and/or view-refinement along the Delphi process would
contribute very important information toward this research. Therefore, a modified
Delphi method is proposed herein to overcome the methodological weaknesses of the
traditional Delphi method and FDM. The modified Delphi method was discussed in
Chapter 8 as Delphi with Fuzzy (DwF).
The eDR could not cater all the contractual issues in this research. Therefore,
the guidelines from the contractual variations in Chapter 4 was referred and set in to
the questionnaire. There are four main aspects on contractual variations such as:
1.
Issuance of variations
2.
Validity of variations
3.
4.
The experts were asked for their degree of agreement based on 11-points
likert scale (0-10). This likert scale is chosen as it could enhance and streamline the
levels of agreement. The score and definition for the agreements are referred and
modified from the studies of Liang et al. (2006) and Hsu et al. (2010) as follow:
127
Point 5 = Neutral
The score from zero to ten was applied for the experts during the interview
with the experts. It is purely for the ease of rating and understanding by the experts.
Subsequently, the score was modified from the point 0-10 to the point 1-11 in
analysis part as to the geometric mean analysis. The conversion is important to avoid
calculation error that would be occurred when calculating zero score.
128
One of the key features of this Delphi study is the application of the
geometric mean to calculate the value of the guidelines in the questionnaire. The
maximum and minimum values of the expert opinions are calculated based on
triangular fuzzy numbers. The geometric mean is taken as the membership degree of
triangular fuzzy numbers to derive the statistically unbiased effect and avoid the
impact of extreme values (Kuo and Chen, 2008). In this Delphi calculation, the
geometric mean is the point of peak (aM) where supported interval points a1 and a2 as
illustrated Figure 5.1.
129
MA
a i 1a i 2 ...a i n
Usually, the value of geometric mean is lower or equal than the arithmetic
mean (average index/mean). In this research, the geometric mean was used to denote
the consensus of the expert group. Microsoft Excel is applied to calculate the
geometric mean.
Besides, the Kruskal Wallis test on the discrepancy between the experts in
term of mean ranks. For the variables were under the discrepancy, the Mann-Whiney
U test was applied to examine which group was different in their overall response by
Since the geometric mean was applied in the analysis, the defuzzification and
normalization procedures were also modified. The threshold value was used to
perform the function as described by Kuo and Chen (2008). However, the threshold
value set by the authors is not appropriate in this 11-scale Likert study. Therefore, for
the threshold value or selection of the guidelines, the common 5-point Likert scale is
referred. It modifies from the 5-point Likert scale (1-5) and its three categories of
agreement (Chong and Zin, 2010).
130
I 2X Y
Where,
I = Total sum up of the interval within the Likert scale;
X = Interval/range value for the category of disagreement and agreement; and
Y = Interval/range value for the category of neutral.
As a result, the classification of the three categories for the 11-point Likert
scale is as follow:
5.6.2
131
from the experts to end-users. Besides, the DFD is like the plot of a story where
reading the diagram is very much like reading a story (Rinzler, 2009). It could
deliver a complicated process or model in a simplified and organised hierarchy
structure. By combining diagrams hierarchically, the DFD combines the best of the
flowchart and the function diagram, which able to demonstrate followings strength as
described by Oppel (2004). The strengths of the DFD are:
DFD Element
Entity
DFD Notations
DISPUTES
Process
0
Mitigate/ prevent
the issue
systematically
and proactively
Explanation
Entity is a data source or data sink about
construction conflicts and disputes. The
data flow (contractual issue) will start and
end at the entities.
Process is an activity of mitigating or
preventing the contractual issue that
involved in the model. It shows in bubble
shape. The process is stated the numbering
to show the sequence and level for the
transformation of data. It shall start with
verbs in the process.
132
No
3
DFD Element
DFD Notations
Data Flow
Contractual issues
Data Store
D1
Explanation
Project database
5.6.3
Prototype/Template of eDR
133
practicality, functionality, coverage and overview of it. Subsequently, an open
question for comment and feedback is designed.
5.7
Research Framework
The research stages have described a clear methodology for this research. As
such, a research framework should be provided to highlight the proper steps to be
established in order to achieve the research aim and objectives. The research
activities and outputs are the main components in the research framework as
illustrated in Figure 5.2.
134
Literature review
Critical review
Interview
Questionnaires
Model developmentDFD
Delphi study
5.8
Concluding Remarks
135
detail of literature review (including documentary analysis and critical review),
questionnaire surveys, Delphi study, modelling and eDR template development have
been described. The outcomes of the analysis and results of the data collected are
presented in Chapter 6 until Chapter 8.
CHAPTER 6
6.1
Introduction
The conflict would turn into the dispute when the contracting parties failed to
manage the conflict. At this moment, dispute resolution would be applied either
through binding or nonbinding approach. Selection of an appropriate dispute
resolution method is vital as every project is bound to have disagreement. ADR
techniques do not require a full legal process and become the mainstream option to
traditional dispute resolution, i.e., arbitration and litigation. Besides, the low
frequency of practicing ADR in the local construction industry needs to be addressed.
Therefore, to explore this topic, the questionnaires were distributed to gather the
information required. The questionnaires were specially designed to obtain the
objectives of this research. Dispute resolution methods are grouped and discussed
together, based on the similarity of their characteristics (refer to Table 2.1), and used
for the questionnaire survey.
This research approach is different from the previous studies, which mostly
focused on a single dispute resolution method, for instance, negotiation (Cheung, et
al., 2004; Cheung, et al., 2006), mediation (Yiu, et al., 2006; Cheung and Yiu, 2007),
137
adjudication (Dancaster, 2008; Owens, 2008; Teo, 2008), and arbitration (Armstrong
and Hurley, 2002; Harmon, 2004). Some studies have discussed ADR, but it is still
limited to the method individually (Treacy, 1995; Keith, 1997; Rubin and Quintas,
2003) or the ADR itself (Cheung, 1999). This approach of grouping could render a
wider perspective and comprehensive view on the dispute resolution methods. It
would be very beneficial for future research and development on bridging the gap
between the academia and industry.
6.2
6.2.1
Background of Respondents
138
16, 27%
Developer
Contractor
44, 73%
6.2.2
Position
The Figure 6.2 illustrated the position of the respondents involved in the
construction industry. The survey was responded by 60 respondents, which was
consisted of 24 contract executives, 6 project managers, 5 contract managers, 5
directors, and another 20 construction professionals. They were in the right position
to answer the questionnaire and provide useful information regarding the dispute
resolution practice within their organisations.
139
6, 10%
20, 33%
Project Manager
Contract Executive
Director
24, 41%
Contract Manager
Others
5, 8%
5, 8%
6.2.3
Education Qualification
140
2, 3%
2, 3%
10, 17%
SPM/STPM or
equivalent
Diploma
Degree
Master or PhD
46, 77%
6.2.4
Working Experience
Working Experience
141
21
5-10 years
16
Over 10 years
23
10
15
20
25
Number of respondents
6.2.5
Figure 6.5 illustrated types of the project mostly completed by the contractors
and developers. Residential projects were the most common project undertaken by
the contractors and developers. It consisted of 61% or 37 from the total 60
respondents. Besides, the rest were commercial projects (15%), transportation
projects (7%), industrial projects (6%) and others (2%). A question on the project
involvement was needed to know the background of the projects toward the dispute
resolution practice. It justified that the most respondents were working with
organizations that normally involved in building projects.
142
6, 10%
1, 2%
7, 12%
Residential Project
Commercial Project
Industrial Project
Transportation Project
9, 15%
37, 61%
Others
5, 8%
15, 25%
Private sector
Government
Joint venture
40, 67%
143
6.2.6
Conflict and dispute were studied in the survey to understand the frequency
of the cases involved in the industry as shown in Table 6.1. A majority of the
respondents (63%) expressed an average of 1-5 cases of conflict in a project, while
only 5 respondents (8%) indicated zero such cases. Besides, about 53% of the 60
respondents did not involve in any dispute cases. However, there are 35% of the
respondents indicated an average of 1-5 cases of dispute involved in the organization
annually. The result indicated that conflicts are very common in a project, while
disputes are infrequent. This can be justified that the disputes only occurred when the
conflicts failed to be managed based on literature.
Table 6.1: Conflict cases in a project and dispute cases involved annually
Number of Cases
Frequency
Percentage
Conflict
Dispute
Conflict
Dispute
Nil
32
8.33%
53.33%
1-5
6-10
> 10
TOTAL
38
8
9
60
21
6
1
60
63.33%
13.33%
15.00%
100%
35.00%
10.00%
1.66%
100%
6.2.7
In this section, the central limit theorem was applied to model the sample
mean (Mann, 2005). According to this theorem, the mean of the sample size is equal
to the mean of the population, where x . The samples approach to normal
distribution. Table 6.2 examined the extent to which factors to be considered by the
respondents in selecting the dispute resolution methods, sorted according to the mean
rank (R). Standard deviation (SD) of the data set shows the results are close to mean.
144
The highest rank was the factor related to negotiation and mediation, i.e., fair
treatment of both parties during the negotiation process prior to any official hearing
and ruling. The second highest mean was 3.88, which was contributed by expert
judgment in construction of those involved in the process (Adj & Arb) and the
parties are free to look for other dispute resolution methods (without legal liability) if
they are not satisfied with the result (Neg & Med). However, the lowest rank (3.30)
was improvement of cash flow, as referring to adjudication. This is probably due to
the pending implementation of adjudication in the industry.
Table 6.2: Factors of selecting dispute resolution methods ranked by mean score
Item
4
21
5
12
7
15
25
3
23
9
8
20
24
17
10
1
13
SD
Pvalue
3.98
0.70
0.16
3.88
0.61
0.48
Mean
R
1
2
3
3.88
0.69
0.08
3.83
3.83
0.76
0.78
0.10
0.19
3.82
0.79
0.21
3.77
0.81
0.25
3.75
0.73
0.35
3.70
3.68
3.68
0.81
0.77
0.85
0.09
0.22
0.35
3.68
0.87
0.74
3.67
3.67
0.75
0.91
0.33
0.59
3.67
0.75
0.45
3.63
1.04
0.18
3.60
0.76
0.18
4
5
6
7
8
9
10
11
12
13
14
15
16
17
145
Item
11
19
2
26
27
6
14
18
22
16
SD
Pvalue
3.58
0.77
0.53
3.57
0.83
0.23
3.57
1.01
0.24
3.53
3.53
3.53
0.77
0.79
0.81
0.54
0.99
0.27
3.48
0.77
0.26
3.47
3.45
3.30
0.93
0.79
0.98
0.62
0.11
0.55
Mean
R
18
19
20
21
22
23
24
25
26
27
146
6.3
Factor Analysis
The mean score and Factor Analysis were adopted to identify the factors. The
mean rank was to understand the arithmetic average of the distribution while the
Factor Analysis was to find the latent factors to be considered in this research. The
Factor Analysis is important as to further clarify the data analysis from the mean
score. Meanwhile, it helped to reduce and extract the essential factors affecting the
selection of dispute resolution methods. SPSS program was used to perform the data
analysis of the research.
PCA was chosen as a method of data reduction towards the 27 factors using
the SPSS program. All the means, which were more than 3.00 and close to each other,
were skewed toward agree category; therefore, the extracted factors are significant
in this study. It can be used to represent the latent factors within the various variables
based on their similar characteristics (Hsia et al., 2009). Two statistical tests are
required to perform prior to this PCA such as Kaiser-Meyer-Olkin (KMO) and
Bartletts test of sphericity. The KMO test is to indicate whether the sample size used
for analysis is sufficient, while the Barletts test is to assess whether factor analysis
could be performed.
The KMO value was 0.620, substantially exceeding the recommended value
of 0.6 (Kaiser, 1974 as cited in Bradbury et al., 2009), while the Bartletts test was
657.030 with significance 0.000, which is less than 0.05. Hence, the data set is valid
and supported the suitability of PCA.
In this study, finding the latent factors or the number of factors to be retained
is a critical issue. Yet, there is no 100% foolproof statistical test or unique way to
determine the number of factors to be retained (Cudeck and MacCallum, 2007).
Therefore, a few sources of reference are considered such as Kaiser Criterion, ScreePlot and theoretical consideration of the PCA. The Kaiser Criterion was used to drop
147
all the factors with eigenvalues below 1. Therefore, there are 10 Components found
in the Factor Analysis as shown in Table 6.3.
Total
5.639
3.226
2.106
1.733
1.518
1.372
1.319
1.186
1.118
1.023
.875
.762
.738
.584
.567
.486
.419
.413
.331
.310
.267
.238
.206
.173
.162
.141
.087
% of Variance
20.886
11.949
7.801
6.417
5.623
5.080
4.885
4.392
4.142
3.789
3.243
2.824
2.733
2.163
2.100
1.800
1.553
1.528
1.225
1.148
.988
.882
.761
.641
.600
.522
.324
Cumulative %
20.886
32.834
40.636
47.053
52.676
57.756
62.642
67.033
71.176
74.965
78.207
81.031
83.764
85.927
88.027
89.827
91.381
92.908
94.133
95.281
96.269
97.151
97.912
98.554
99.154
99.676
100.000
Next, the Scree-Plot test was done along with theoretical consideration of
factors with eigenvalues more than 1 and with at least 1 pair variables. Subsequently,
the Scree-Plot made a cut-off point after Component 7 using the rule of thumb that
plotted the eigenvalues in the decreasing order to obtain the scree as illustrated in
Figure 6.7.
148
Eigenvalue
Omitting Point
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Component Number
149
Table 6.4: Rotated component matrix - VARIMAX with Kaiser Normalisation
Item
4
11
20
7
10
18
16
9
3
13
6
27
19
17
24
25
23
14
15
21
26
1
0.75
0.71
0.58
0.54
0.54
0.03
0.11
0.09
0.31
0.09
0.11
-0.08
-0.02
0.32
0.00
0.07
0.00
0.04
0.41
0.06
0.15
2
-0.06
0.23
0.15
0.22
-0.02
0.87
0.86
0.55
0.06
0.10
0.17
-0.08
0.11
0.12
-0.02
0.03
-0.16
-0.01
0.07
0.07
-0.10
3
0.20
0.20
-0.02
0.43
0.00
0.07
0.04
0.45
0.77
0.70
0.68
0.19
-0.08
-0.23
0.00
0.00
0.24
0.16
0.09
0.15
0.02
Factor
4
0.00
-0.19
0.45
-0.03
0.04
0.01
0.03
-0.04
0.04
0.03
0.08
0.85
0.71
0.52
0.01
0.18
0.49
0.01
0.21
0.15
0.13
5
0.10
-0.12
0.20
-0.02
0.06
-0.07
0.04
0.07
-0.01
0.32
-0.16
0.07
0.11
0.09
0.82
0.77
0.52
0.19
-0.05
0.07
0.03
6
0.22
-0.21
0.19
0.17
0.17
-0.02
0.12
-0.26
0.00
0.16
0.29
0.15
0.01
-0.25
0.16
-0.08
0.21
0.79
0.68
0.05
0.31
7
-0.01
0.15
-0.01
0.07
0.29
0.12
-0.01
-0.14
0.21
0.38
-0.24
0.01
0.38
0.01
0.16
-0.01
-0.14
0.20
0.02
0.86
0.61
The extracted factors accounted for 77.8% of the variance. The seven Factors
can be classified based on their similar characteristics as below:
After the classification, the Factors were ranked by using the factor Scale
Rating (SR) (Cheung, 1999). It is to understand the viewpoint of the respondents
150
based on mean scale rating and the formula is as follow:
Fi (SR)
A(SR)
j1
ij
Where,
Fi (SR) is the factor score based on scale rating and A (SR) ij is the mean scale rating
of the j-th. For instance,
Factor 1 = (Mean of the items) / number of items
= (3.98+3.58+3.68+3.83+3.67) / 5
= 3.748
The Factor Scale Rating of the seven Factors is listed at Table 6.5. The factor
ranking scores indicated that the users were greatly concerned about the process of
proceedings, which graded at the first ranking. The process covered all the dispute
resolution methods except litigation. These proceedings, without interference by the
legal profession, highlight the attributes for meeting out fair treatment, meeting the
budget and schedule, and privacy. The second highest Factor was the effect of
proceedings. It related to binding, enforceability as well as the ability to appeal
against the proceedings. The factors lying in the middle range of importance were
reliable decision, expert ruling, and informal method of proceedings. The last two
Factors perceived as of lesser importance were the traditional approach of
proceedings and outcome of ADR. The Factor Analysis showed another perspective
of the results compare to mean score after the rotation. The rotation does not change
the raw data, but makes the interpretation of the analysis easier. It can be concluded
that the seven Factors are the aspects to be considered in selecting the methods.
151
Table 6.5: Ranking of Factor Scale Rating
Factor
1
2
3
4
5
6
7
6.4
Description
Factor
Scale
Rating
Process of proceedings 3.748
Outcome of ADR
3.483
Informal method of
3.627
proceedings
Traditional approach
3.590
of proceedings
Effect of proceedings
3.713
Expert ruling
3.650
Reliable decision
3.705
Ranking
1
7
5
6
2
4
3
Discussion
The respondents evinced keen interest in the ADR methods based on the
mean score analysis. Four of the top 5 factors were associated with negotiation and
mediation. The factors discussed were fair treatment, voluntary, flexibility and speed
of the proceedings. The respondents ranked it as top priority in the selection of a
dispute resolution method. On the contrary, Factor Analysis has further clarified that
the ADR methods are regarded as important in the process of proceedings (Factor 1),
rather than the outcome of ADR (Factor 2). This is an obvious contradiction result
generated by the Factor Analysis on the ADR methods, which the Factor 1 is mostly
consisted of the ADR methods. It could be explained by looking at the factors that
derived from the outcome of ADR. The factors are towards the attributes of
adjudication, which the method is yet launched officially in the local industry. It
would cause the low appreciation on the true benefits of ADR and probably
contribute to the lack practice of the ADR in local industry. Most likely, this scenario
is caused by the uncertainties result and bindingness of the ADR in nature.
152
This apart, the factors associated with arbitration and litigation were ranked
lower than the ADR. However, the methods were accepted by the respondents one
way or another; for instance, the lowest mean score among them was 3.45, which
was still classified in the agree category according to the likert scale. In all
likelihood, the respondents had understood and appreciated the features of these
methods. Factor Analysis also supports this likely situation, as most of the factors
related to the characteristics of arbitration and litigation are ranked higher after the
Factor Scale Rating, for instance, the Factors 5, 6 and 7. Further, the lowest mean
score for the improvement of cash flow as well as the Factor 7: outcome of ADR
were most probably caused by the pending implementation of adjudication in the
construction industry.
As noted, the features of dispute resolution methods are shared among each
other in a factor. It might have several dispute resolution methods in a single factor in
selection of dispute resolution method. Hence it is vital to have a clarification of the
results as well for the future reference concerned. It could be clarified by taking into
consideration of the two main aspects of the research such as, stages of dispute
resolution and Factor Analysis. The Factor Analysis has extracted the latent factors
and loaded into 7 Factors, which able to render a better interpretation and more
understandable results. While, the stages of dispute resolution could assist decision
makers to select the least confrontation method in term of time, cost, controversy and
adversary.
6.5
Concluding Remarks
All dispute resolution methods have pros and cons. The features of dispute
resolution methods grouped and discussed together into a factor have achieved the
second objective. The results have addressed the behaviour of the dispute resolution
methods, where the negotiation and mediation are the preferred option by the
153
respondents. Adjudication is rated unpopular by the respondents compared to other
ADR methods. While, the arbitration and litigation are somewhat accepted by the
respondents as the methods are well established and familiar in the industry. The
findings of the Factor Analysis also revealed that the process of proceedings is the
first criteria in selection of dispute resolution methods, while the outcome of ADR is
not a major concern of the selection. It indicated that the appreciation of the true
benefits of the ADR is very low. Hence the selection of ADR or non-ADR itself is
not the major issue; rather, the increased efficiency and appreciation of the methods
in the construction industry are more demanding. Ultimately, the second research
objective was achieved and highlighted the need to have an alternative means of
contract administration, namely eDR to facilitate the conflicts or disputes since the
low appreciation toward the true outcomes of the dispute resolution.
154
CHAPTER 7
7.1
Introduction
155
7.2
Model Development
A good system supplies useful information and data for users to make
decisions or references. The model on eDR consists of two sub-models to deliver the
contents and features. Figure 7.1 illustrates the eDR model development.
On the other hand, the second model describes the features required in the
eDR. The online portal is the final and complete system that would be achieved in
this eDR model. The online portal consists of three main features such as keywords
searching, dispute sub-categories (breakdown of issue), and forum for comments or
discussion. It is designed in a simple way to ease searching and feedback by users.
Eventually, the system is aimed to render a self-examination and proactive approach
in contract administration towards dispute resolution or prevention, whereby the
clarified references/guidelines are referred and retrieved by end-users.
156
eDR Model
Development
- Project characteristics
- Breakdown of
contractual issues
- Contract provisions
- Leading court cases
- Involvement of local
experts
- Project characteristics
- Keywords searching
- Breakdown of subcategories
- Updating or storing (if
any)
- Exchange of information
(forum for comments)
7.3
DFD on eDR
The context diagram is the highest level of diagram in the set of DFD which
reveals an external picture and overall function of an information system (Tam et al.,
2001). The next level is Level-0 DFD, which it is made up of a number of processes
from the main activity in the Context Diagram. The following is Level-1 DFD, which
decomposes from a parent process in the Level-0 DFD. The splitting of DFD
diagrams presents better visualisation of the model as illustrated Figure 7.2.
157
Context Diagram
0
Level-0 DFD
1.0
2.0
3.0
Level-1 DFD
3.1
3.2
3.3
7.4
The Context Diagram of the eDR model is illustrated in Figure 7.3. This level
is an overall picture of the process flow model and briefly illustrates how the
clarified references/guidelines are produced. The activity numbering 0 is the only
process involved in the Context Diagram, i.e., mitigating/preventing the contractual
issue systematically and proactively.
158
DISPUTES
Contractual issue
Mitigate/
prevent the
issue
systematically
and
proactively
Clarified
references/guidelines
END-USERS
7.5
The Level-0 DFD is a child diagram from the Context Diagram. It is the most
comprehensive data that presented in this model. This Level-0 DFD of the model
indicates detailed information on how the processes involved as illustrated in Figure
7.4.
The first activity is to classify the project characteristics and contractual issue.
There are two information flows into the project database. The first stores the new or
additional data from a new case, while the second is a database that contains previous
project particulars. This project database is vital as different project characteristics
would have different effects and implications on the contractual issue. The project
particulars could be classified as project type, contract procurement system,
procurement method, project scale and standard form of contract.
Meanwhile, the contractual issues can be categorized into three main stages.
They are pre-contract award stage (seven areas), construction or commencement of
work stage (twenty three areas), and post-commencement stage (nine areas). These
159
work stages are organized in such a way to make clear the contractual activities that
involved by the principal contracting parties.
The second activity is to identify the relevant contract clauses related to the
targeted issue. The relevant contract provisions will be identified from the contract
form (D2). The targeted issue is classified according to the project particulars under
the first activity of selecting the contract form. The issue will be referred to the main
clause and its sub-clauses. In the meantime, other related clauses will be studied to
have a wider view of the expressed contractual obligations and expectations. All the
related clauses will be combined and cross-referred. The principle of read and
interpret as a whole is applied to produce contract provisions regarding the targeted
issue.
160
The activity numbering 5.0 is the last process of the conceptual model of eDR.
It is the most important process because it is the centre of the quality system which
provides useful information and references to end-users. Therefore, the Delphi
approach has been incorporated under this process to denote a consensus result from
a mixture of experts. Construction industry is unique and adversarial in nature and
this consensus is vital especially when dealing with conflicts or disputes. After the
verification and commentary, the clarified references/guidelines will serve as a
preliminary reference or to alert the end-users. The verification process by the
experts is not only confined to language structure but also to the meaning and certain
legal intents of the contents.
161
DISPUTES
Contractual issue
New cases (if any)
1.0
D1
Project database
Previous cases
Classify the
project
characteristics
and
contractual
issue
Targeted issue
2.0
D2
Standard Form
Contract clauses
Identify the
relevant
contract
clauses
Contract provisions
3.0
D3
Investigate
and organise
the provisions
in detail
Comprehensive details
4.0
D4
Clarity references
Clarity aspects
Clarify the
content for
the ease of
understanding
Drafted references/guidelines
5.0
Verify and
comment the
references by
mixture of
experts for
the consensus
Clarified references/guidelines
END-USERS
162
7.6
The Level-1 DFD is a child diagram from a process in the Level-0 DFD. It
has further discussed on the development of eDR.
7.6.1
Activity 1.0
Figure7.5 illustrates how the process activity 1.0 has been split up to be
functioned in the model. It is about classifying the project characteristics and
contractual issue. Firstly, the contractual issue will be classified and organised.
Project database (D1) is referred to locate any similar cases or issues for the same
type of project. New case will be stored into the database if no previous case is
located. After that, the project characteristics will be categorised and organised as:
163
Contractual issue
New cases (if any)
1.1
D1
Project database
Previous cases
Classify and
organise the
issue based
on project
characteristics
Project particulars
1.3
Check for the
pre-contract
award stage
1.4
Check the
construction/
commenceme
nt of work
stage
1.5
Check the
postcommenceme
nt stage
Related issues
1.6
Identify the
main
contractual
issue from the
related issues
Targeted issue
Subsequently, the next activities numbering 1.3, 1.4 and 1.5 are in a parallel
process. The classified project principles will be checked by these three activities to
identify all related issues for this dispute. The project particulars would help in
sorting out the issues, especially the standard form of contract and procurement
method in the project. Cross reference is needed between the three work stages in
order to search all the related issues, i.e., pre-contract stage, construction or
commencement of work stage and post commencement stage. All the possible
contractual issues are allocated in these three work stages as shown in Table 7.1.
164
Table 7.1: Contractual issues in the three work stages
Pre-contract
award stage
SEVEN areas:
1. Estimating and
pricing
2. Design
information
3. Insurances
4. Performance
bond
submission
5. Site possession
6. Tender
documentation
and
requirements
7. Work
pragramme
Construction or commencement of
work stage
TWENTY THREE areas:
1. Accessing to site
2. Compensation/loss and expenses
3. Default on notice
4. Delay and extension of time
5. Discrepancy and inconsistency of
information
6. Fluctuation of price
7. Interference/problem by
subcontractors and suppliers
8. Interference/problem by professionals
9. Interim payment
10. Partial possession
11. Period of honouring certificates
12. Postponement or suspension of work
13. Practical completion
14. Quality of workmanship
15. Set off by employer
16. Site and nature of work
17. Standard and quality of material
18. Statutory obligations
19. Supply difficulties
20. Testing and inspection
21. Valuation and measurement (work
done)
22. Contractual Variations
23. Weather
Post-commencement
stage
NINE areas:
1. Defect liability
period
2. Defects
3. Determination
4. Dispute
resolution
5. Final
account
and certificate
6. Liquidated
damages
7. Outstanding
claim and set off
8. Retention monies
or fund
9. Unresolved
variations
The last sub-activity 1.0 is to identify the main contractual issues from all the
related issues. A detailed examination is required to prioritise the weightage of the
related issues. As a result, a targeted issue will be identified for the subsequent
activity 2.0.
165
7.6.2
Activity 2.0
After selecting the contract form, the issue will be referred to the main clause
and its sub-clauses. In the meantime, other related clauses will be studied to have a
wider view on the expressed contractual obligations and expectations. Subsequently,
all the related clauses will be combined and cross referred. The principle of read and
interpret as whole is applied to produce the contract provisions regarding the targeted
issue.
166
Targeted issue
2.1
D2
Standard Form
Select the
contract form
that used in
the project
Contract clauses
Contract form
2.2
2.3
Refer the
main clause
and subclauses for
the issue
Refer other
related
clauses that
related to the
issue
Related clauses
2.4
Combine and
cross
reference for
the contract
provisions
Contract provisions
7.6.3
Activity 3.0
Three activities are discussed in the activity 3.0 as illustrated in Figure 7.7.
The first activity is to investigate the contract provisions with literature materials.
Background information will be sought to understand the characteristics of the issue.
For example, one of the contractual issues mentioned in activity 1.4, i.e., variations
and changes under PAM 2006 (with quantities) contract form. After a detailed
literature study from database D3 (journals, articles and books), the issue can
167
breakdown into few categories and sub-categories. The breakdown of the
characteristics of the issue is as shown in Table 7.2. The four main issues are
issuance of variations, validity of variations, valuation of variations and additional
expenses
and
subsequent
circumstances
caused
by
variations.
List
of
Characteristics
1
Issuance of variations
2 Validity of variations
2.1 Written instruction
2.2 Definition/principle of variations
2.3 Addition
2.4 Omission
2.5 Substitution
2.6 Alteration of kind or standard of materials or goods
2.7 Removal of executed works, materials and goods
2.8 Changes to the provisions in the contract
168
Activity 3.2 is a complicated process. It is because this activity alone could be
a main source of reference especially for law related research. Therefore, the scope
of study is limited in this applied social science research, which is constrained to the
found contract provisions in the earlier process. The court cases or statutes merely
support or enhance the content of the contract provisions. The investigation of the
court cases could be derived from database D3 either from local cases (Malayan law
journal) or international cases from United Kingdom, Singapore, Australia, etc.
Meanwhile, the applicable statues or other laws consist of Contract Act 1950,
Arbitration Act 2005, Law of Tort, Land Law and other relevant law. The common
law and legal principles will be produced from the court cases and statues.
169
Contract provisions
3.1
D3
Investigate
the provisions
with literature
materials
Construction law
7.6.4
Activity 4.0
170
The next activity is to improve and clarify the language structure problems
using Plain English. Database D4 (refer to Table 3.9) is referred, which a list of
clarity aspects. It is to determine which type of measure would be applied on it. More
importantly, the clarifying process must
obligations/legal
intent
laid
in
the
contract.
Eventually,
Comprehensive references
4.1
Check the
problems of
clarity and
legalese
Clarity references
Clarity aspects
Improve and
clarify the
language
structure
using Plain
English
Drafted references/guidelines
the
drafted
171
7.6.5
Activity 5.0
Figure 7.9 illustrates the last procedure in developing the content of eDR. The
procedure links with the Delphi method, which is to elicit experts knowledge for a
consensus result. In activity 5.1, the drafted references/guidelines will be verified by
the experts for two aspects. The first aspect is to verify the clarified sentences for its
intended meanings, while the second is to make sure the legal intents or obligations
still exist in the references. After the process, the experts will comment and respond
to the verified contents. Feedbacks or refinements may be raised by the experts and it
will be reverted back to the earlier process. Nevertheless, there will be at least two
rounds of interaction with the experts to allow the experts to modify or revise their
opinions after the verification and feedback.
172
Drafted references/guidelines
5.1
Verify the
meanings and
legal intents
by mixture of
experts
Verified contents
5.2
Comment and
respond to the
verified
contents by
the experts
Results
5.3
Determine the
consensus
using an
appropriate
research
approach
Clarified references/guidelines
END-USERS
7.7
The clarified references or guidelines are the sources for the online portal of
the eDR. It discusses how the online system associated with the outcome of the eDR.
The online portal consists of three main features such as keywords searching, dispute
sub-categories (breakdown of issue), and forum for comments or discussion.
173
7.7.1
Context Diagram
0
DISPUTES
Contractual issue
Search and
refer to the
clarified and
organised
references/
guidelines
Sorted
references/guidelines
END-USERS
Comments/discussion
7.7.2
Level-0 DFD
174
The next process is to target a main issue from contractual issues database
(D2). All the contractual issues are store in the three work stages of the database. The
issue can be retrieved via searching the keywords or by selecting the concerned issue
from issues breakdown. A targeted issue will be obtained.
The
last
process
is
to
select
the
dispute
root
cause
for
the
175
DISPUTES
Contractual issue
1.0
D1
Project database
Choices of project particulars
Select the
project
particulars
Specified particulars
2.0
D2
Contractual issues
Three work stages - issues
Search the
contractual
issue via
keywords or
issues
breakdown
Targeted issue
3.0
Sort and
examine for
the subtopics/root
cause from
the issue
Breakdown of the issue
4.0
D3
eDR database
Consensus data by the experts
Select the
dispute cause
for reference/
guidelines
Clarified references/guidelines
Comments/discussion
END-USERS
176
7.8
Discussion
Two models were successfully developed using DFD. The first model
describes how to build up the contents of the eDR, while the second explains how the
clarified references/guidelines to be referred by end-users through the online portal.
These model are discussed separately instead of having a single one because to
provide a better understanding on the eDR. The models need to be referred together
when setting up a complete eDR system.
Certain limitations need to be considered in the eDR models. The models are
designed based on Malaysian scenario for the culture, working environment and
legal system. For overseas practice, it needs to be considered the cultural differences
and legal system of their countries. Nevertheless, the eDR models can be used as a
point of reference by other countries as it provides a generic approach on how to
mitigate/prevent contractual issues.
177
7.9
Concluding Remarks
CHAPTER 8
8.1
Introduction
179
8.2
The traditional Delphi method and the FDM have different features of
implementation as highlighted from Chapter 5. The difference mainly caused by the
one round of investigation using the geometric mean. This issue needs to be
addressed, as two of the defining features are absent in the Delphi process, i.e.,
feedback and answer revision by the experts. Although the FDM highlights its
features to overcome some of the weaknesses in the traditional Delphi, it is vital to
reconsider the defining features of the traditional Delphi so that the true values of the
Delphi would not go in vain. It is because the new information and / or view
refinement along the Delphi process would probably be ignored in the FDM.
Traditional Delphi
FDM
DwF
General
Consensus results
anonymity are
triangle approach
rounds of Delphi or
refinement of
results
geometric mean
geometric mean.
180
Elements
Traditional Delphi
FDM
DwF
Strengths
New information
Possibility of new
may be added by
shortcomings of
information raised by
experts
vagueness and
experts is considered in
ambiguousness of
to differences of experts
interpretations by
by referring to FDM.
es
and cost
be ignored as single
consuming, may
round of Delphi.
decline the
research.
Besides, Table 8.2 shows their different characteristics or features under the
Delphi principles.
Traditional
FDM
DwF
Delphi
Number of Rounds
Usually more
1 round
than 2 rounds
Maximum of 2
rounds
Could be semi-
Must be
Could be semi-
question
structured
structured
structured
questionnaire
questionnaire
questionnaire
181
Different Characteristics
Traditional
FDM
DwF
Delphi
Opportunity for feedback and
Yes
No
Yes
High
Not at all
Slight
answer modification
Time and cost consuming
possibilities
Declined of response rate
High
possibilities
Not at all
possibilities
Low convergence expert
High
opinions
possibilities
Achievable of Consensus
Easy
Slight
possibilities
Not at all
Slight
possibilities
Easiest
Easier
Results
8.2.1
The DwF method was selected in the research after discussion on the pros
and cons of the traditional Delphi method and FDM. The following sections discuss
how the DwF being incorporated into the research to achieve the last objective of this
research, i.e., to develop an application of eDR prototype/system based on
contractual variations.
The content of eDR is representing the core of the research. The research
approach towards its content must be well defined and justified in order to have the
quality system. The DwF framework was developed towards the eDR. It is based on
the mutual benefits from traditional Delphi and FDM as illustrated in Figure 8.1.
182
START
No
Yes
Is anonymity response
from the experts?
No
Yes
Any open-ended
questions (semistructured)?
No
Yes
Yes
Any feedbacks or
additional information
provided?
No
Yes
No
END
183
The flowchart diagram above represents a sequence of operations. The DwF
framework would consider the original values of the traditional Delphi and also
address the problems raised from the FDM such as the possibility of new information
and answer modification by the experts. Therefore, the DwF framework is
accommodated with a semi-structured type of question in the Delphi study, which
allows for additional information to be contributed by the experts. It may bring an
extra round in the Delphi process due to the additional information. At the end of the
process, the experts are also given a chance to verify and revise the data.
Meanwhile, the DwF would not tolerate the issues caused by the traditional
Delphi, wherein the time and cost consuming in the process had resulted in a low
convergence of expert opinions. Hence, the fuzzy triangular number with the
geometric mean is applied into the data analysis. It could also make sure that there
are only a maximum of two rounds of investigations in the Delphi study. Using the
geometric mean reduces the ambiguity caused by the differences between experts
opinions and helps to encompass all their opinions in one investigation.
In summary, the content of the eDR is elicited and analysed from experts
knowledge. It could be the best practice or idea generated towards the contractual
issues.
184
8.3
Background of Experts
In this DwF research, all the experts are freely express their view without any
pressures. It is because they are responded in the anonymous mode.
185
Legal
L1
L2
L3
Architect
A1
A2
A3
Engineer
E1
E2
E3
Quantity
Surveyor
Q1
Q2
Q3
Expertise
Registered
arbitrator or legal
profesional
Registered and
professional
architect
Registered and
professional
engineer
Registered and
professional QS
Project
management and
contract
administration
Construction
contract drafting
185
186
8.4
The DwF consists of two rounds. A total of eighty-one guidelines were asked
in the form of a questionnaire during the first round of interview. The questionnaire
includes the open-ended questions that allow feedback and comments from the
experts. Any changes or modifications of the guidelines during the interview would
be confirmed by the experts in the second round.
The first-round analysis discusses the experts feedback. There are two parts
of the feedback, namely, improvement and corrections to the guidelines; and new
information or guidelines provided by the experts. The statistical results of the
questionnaire are presented in the second round of the Delphi after the results
confirmation of the results by the experts.
8.4.1
Table 8.4 shows the improvements and corrections made to Part A (Issuance
of Variations). The changes are based on the need of legal intent and meaning of the
contract for example, person should be written as Person, local authorities
should be described along with service providers, and a clearer meaning provided for
sub-contract works. These terms and language structure were edited to present the
intended meaning of the contract.
187
Table 8.4: Improvements and corrections on Part A
No
1
Original version
The right person is the Professional
Improved version
The right Person is the Professional
Employer.
3
But, after CPC period, the variations But, after CPC period, the variations
must be necessitated by obligations
the Work.
the Work.
188
No
6
Original version
Improved version
Original version
Improved version
AI must be in writing
189
Apart from that, the experts agreed with all the guidelines provided in Part C
(Valuation Rules of Variations) and Part D (Additional Expenses and Subsequent
Circumstances Caused by Variations) in terms of their language structure and
meanings.
8.4.2
Additional Information
There are two additional guidelines have been suggested by the experts. The
guidelines are aimed at enhancing the value and coverage of the contractual
variations. The first guideline explains the principle and definition of omission. The
BX is a new guideline to be referred by end-users for omission. Table 8.6 shows the
location of item BX after the 16th guideline of Part B. It would be rated for
agreement by experts in the second round of DwF.
Validity of Variations
Omission
B15
B16
> An omitted work is the part of the Work that no longer needed in the
project, it construed as a valid omission.
BX
B17
> If the part of the Work is omitted because to give it to other contractor,
it construed as an invalid omission.
B18
B19
190
Besides, the subsequent additional guideline is located in Part D. It discusses
the claim of work done on the completed variation in the contract. This is a different
procedure as highlighted in Clause 11.7, which is discussed in the claim of additional
expenses. Table 8.7 shows the location of the new info of the claim (DX) under Part
D.
D1
D2
D3
> Loss of profit is not claimable in this provision as it was covered under
the Rule 2, 3 or 4.
D4
> However, a claim for loss of profit will always be successful for the
invalid omission.
D5
> The Architect and QS shall have access all contractors documents or
records in the possession, custody or control and with free of charge each
to them if requested until all variation claims resolved. Same for the subcontractors and/or suppliers documents in possession, custody or control
by the Contractor.
191
Item
D6
> As soon as the Architect has ascertained the amount of variations and/or
additional expense, it will add into Contract Sum and include into the next
Interim Certificate.
D7
> The Architect could ascertain the amount anytime before Final Account
as no timeframe is provided.
DX
> However, if the contractor has applied for the properly executed
variations into Interim Claim, together with complete details and
particulars, the Architect shall issue an Interim Certificate within 21 Days
from the date of receipt of the payment application.
8.5
The second round of DwF comprises two main activities. The first activity is
to confirm the given results of the previous round by comparing the experts score
with the average score. Next, the experts are required to rate their degree of
agreement with reference to the additional guidelines (BX and DX) regarding
contractual variations.
Table 8.8 shows the results of the geometric mean for all the variables. The
variables are the guidelines or references on the contractual variations. This statistical
analysis is carried out after the score confirmation of the scores and the experts
response on the new information.
192
Table 8.8: Results on the geometric mean
Part A
MA
Part B
MA
Part C
MA
Part D
MA
A1
10.02
B1
9.87
C1
8.93
D1
8.88
A2
3.31
B2
9.53
C2
10.03
D2
7.89
A3
8.58
B3
9.69
C3
10.03
D3
8.73
A4
8.57
B4
8.55
C4
9.68
D4
5.57
A5
9.48
B5
5.86
C5
10.19
D5
9.34
A6
10.29
B6
6.43
C6
10.12
D6
9.90
A7
9.37
B7
8.18
C7
9.39
D7
9.23
A8
5.19
B8
8.52
C8
9.77
DX
9.21
A9
9.58
B9
9.71
C9
9.77
A10
9.94
B10
9.40
C10
8.51
A11
8.26
B11
9.65
C11
8.22
A12
8.66
B12
9.31
C12
9.27
A13
9.91
B13
8.93
C13
9.44
A14
7.87
B14
7.22
C14
8.94
A15
9.83
B15
9.73
C15
8.52
A16
9.58
B16
8.06
C16
8.75
A17
10.43
BX
8.68
C17
9.68
B17
10.37
C18
9.52
B18
9.69
C19
9.57
B19
6.10
C20
9.02
B20
9.48
C21
9.77
B21
9.34
C22
9.68
B22
9.48
C23
10.10
B23
4.36
C24
8.70
B24
9.30
C25
8.14
B25
8.70
C26
9.68
B26
9.25
C27
9.46
B27
9.25
C28
9.20
B28
9.24
B29
8.30
193
The geometric mean is applied in the analysis to calculate the consensus
value. Most of the variables were agreed with by the experts. Eight out of eightythree variables have been rejected as the guidelines for users because they are out of
the range of the agree category, i.e., 7.25 geometric mean 11.00. It is an
approximately 9.64% rejection rate for the variables.
The right person also includes the Employer of the contract (A2).
During DLP if the contractor fails to rectify the defects and with the
consent of Employer, Architect can issue omission for leaving the
defects from the set-off. The omission constitutes a valid issuance of
variation (A8).
However, a claim for loss of profit will always be successful for the
invalid omission (D4).
194
of 0.976 from the correlation among the eighty-three variables as shown in Table 8.9.
This value is larger than 0.70, and it is interpreted as a great support for the
consistency of the results (Morgan et al., 2007).
Subsequently, the agreed variables were tested again for the internal
consistency reliability after the rejection. The test showed a very positive result in
terms of the correlation among the agreed variables. The Cronbachs Alpha value
now increased from 0.976 to 0.982 as shown in Table 8.10. In other words, the
rejected variables using the geometric mean are appropriate, where the variables are
weak correlated in the data. As a result, the agreed variables are valid in term of the
consistency reliability.
8.5.1
This section discusses the details of the variables associated with issuance of
variations. Two variables were rejected in Part A as described earlier. The item A2
(MA, = 3.31) was rejected because the experts opined that the Employer should not
195
intervene in the issuance of variations by the Architect, even though, most often the
variations are instructed by the employer. In this case, the Employer should listen and
seek the Architects advice regarding the issuance of variations. Furthermore, there
are no such contract provisions or legal cases regarding the authorised person also
should be included the Employer of the contract. This idea of the guideline was
derived indirectly from the literature review.
Besides, the experts were neutral or undecided regarding item A8 (MA, 5.19)
because the defects were not counted as variations in the contract, although the
leaving the defects from the set-off seemed like an omission work. Therefore, some
of the experts expressed some reservations on their view regarding the defects as
omission works.
Table 8.11 shows the agreed guidelines serve in the eDR prototype.
Issuance of Variations
Authorized Person and Power
A1
> The right Person is the Professional Architect or other form of practice
registered under Architect Act 1967 and named in the contract.29
A3
A4
> Architects power is restricted, which he cant omit a work and give it to
another contractor. 31
A5
> If Architect issues variations that outside the scope of Contract and without
expressed authority from the Employer, he may be liable to the Employer.32
29
196
Item
Issuance of Variations
Period of Issuance
A6
> Architect can issue variations at any time before issuance of the Certificate
of Practical Completion (CPC).
A7
A9
> Contractor shall conform to the local authorities and service providers
requirements and proceed the work if no AI in response for the
inconsistencies with statutory requirements within 7 Days of the given written
notice.34
A10
A11
> There are two parts of provisional items for variations, i.e., Provisional
Quantity and expenditure of Provisional Sums.35
A12
A13
Provisional Quantity describes as the tasks are with rates and prices
for the pre-estimate quantity and it subject to re-measurement for the
actual value.
A14
> Provisional Sums means Sums provided in the Contract and/or for
Nominated Sub-Contract for work, materials or goods in the BQ which
cannot be determined or detailed at the time.37
A15
A16
> Provisional Quantity does not necessary require an AI for carrying out the
work, like piling length in the Bill of Quantities (BQ).
A17
33
Clause 11.3
Clause 4.3
35
Clause 11.6
36
Article 7 (at)
37
Article 7 (au)
38
Clause 11.4
34
197
8.5.2
Most of the variables rejected were from this part. Four out of thirty variables
fall into the category of neutral or undecided, whereas another variable was placed in
the category of disagree. These five variables were referred from the court cases.
The experts opined that the court cases concerning the five variables were
based on case-by-case basic. The facts of the cases need to be looked into; for
example, the item B5 was referred to the notice of determination instead of the
validity of variations. This constraint is also applicable to the items B14 and B19,
where the basis should be the facts of the case rather an arbitrary figure to determine
the validity of variations. Moreover, the experts had doubts concerning the item B6
because sometimes there are conditions or terms in the preamble of the contract that
prevent the issuance of variations due to the non-compliance of the SMM principles.
In addition, the item B23 was disapproved by the experts because changed
materials or goods are very common in a construction project. It would not have the
effect like cardinal change as highlighted in the case of Carr v JA Berriman Pty Ltd
39
and Commissioner for Main Roads v Reed and Stewart Pty Ltd and another40.
Table 8.12 shows the agreed guidelines on the validity of variations for the
eDR prototype. Besides, the additional guideline (BX) was well accepted by the
experts.
39
40
198
Table 8.12: Agreed guidelines on validity of variations
Item
Validity of Variations
Written Instruction
B1
B2
B3
B4
B7
B8
B9
> The Contactor must execute variation entirely at his own cost if to rectify
his negligence, omission, default and/or breach of contract.45
Addition
B10
B11
B12
B13
> An additional work has caused the cardinal changes of agreed sum or nature
of the Works, it construed as an invalid variation.49
41
Clause 2.2
Clause 36.1, Clause 36.2 and Clause 36.3
43
Patman and Fortheingham Ltd v Pilditch (1904)
44
Clause 1.4
45
Clause 11.1(last sentence)
46
Clause 11.1(a)
47
Clause 4.3
48
Blue Circle Industries v Holland Dredging Co (1987)
49
Lindsay Parkinson and co Ltd v Commissioners of His Majestys Works and Public Buildings
(1949)
42
199
Item
Validity of Variations
Omission
B15
B16
> An omitted work is the part of the Work that no longer needed in the
project, it construed as a valid omission.
BX
B17
> If the part of the Work is omitted and given it to another contractor, it
construed as an invalid omission.51
B18
> An omitted work changes the fundamental basis of the contract, it construed
as an invalid omission.
Substitution
B20
> Variations define as changing the work of another for its design, quality or
quantity of the Work.52
B21
> If the changed work has caused the cardinal changes of agreed sum or
nature of the Works, it construed as an invalid substitution.53
Alteration of the Kind or Standard of Materials or Goods
B22
B24
> Materials supplied by the Contractor are more superior than that specified
without any instruction is not considered as a variation.
Removal of the Executed Works, Materials and Goods
B25
> Variations define as removal from site any executed works, materials and
goods which are in accordance with the contract.55
50
Clause 11.1(a)
Carr v JA Berriman Pty Ltd (1953) and Commissioner for Main Roads v Reed and Stewart Pty Ltd
and another (1974)
52
Clause 11.1(a)
53
Thorn v Mayor and Commonalty of London (1876) and Blue Circle Industries v Holland Dredging
Co (1987)
54
Clause 11.1(b)
55
Clause 11.1 (c)
51
200
Item
Validity of Variations
Changes to the provisions in the Contract
Variations also define as:
B26
B27
B28
> Access to or utilisation of any specific part of the Site e.g., difficulty to
access or use on the land or part of the site.58
B29
> The execution and completion of the work in specific order e.g., changing
of method of statement, construction method, etc. 59
8.5.3
All the variables in this part were fall into the agree category, i.e., 7.25
geometric mean 11.00. This also includes the examples given of different types of
the valuation rules such as C8, C15 and C20, where the examples were derived
indirectly from the literature review. This acceptance is probably because most of the
variables are derived from the contract provisions.
There are six valuation rules on the contractual variations such as:
56
Clause 11.1(d)(i)
Clause 11.1(d)(ii)
58
Clause 11.1(d)(iii)
59
Clause 11.1(d)(iv)
57
201
Table 8.13 shows the guidelines on the valuation rules of variations for the
eDR prototype.
C1
> The Quantity Surveyor (QS) shall measure and value all variations.60
C2
> The Contractor shall provide assistance to the QS for any recording of site
information and/or site measurements are carried out at the site.60
C3
> The word similar used in valuation rules cannot be taken as identical, it
should consider the background information and facts of the variation.
C4
C5
> It uses the original rates and prices of BQ to determine the valuation.62
C6
> This rule applies to the variation of a similar character and executed under
similar conditions. It does not significantly change the quantity of work as set
out in the BQ.62
C7
C8
60
Clause 11.5
Clause 11.6
62
Clause 11.6(a)
61
202
Item
C9
> It includes a fair adjustment into the original rates and prices of BQ to
determine the valuation.63
C10
> This rule applies to the variation of a similar character and either is
executed or not executed under similar conditions but there is a significant
change in the quantity of work carried out.63
C11
> The fair will depend on the whole of the contractors pricing strategy,
either properly priced or with a handsome profit margin.64
C12
C13
>The calculation should be based upon the reasonable costs that properly
incurred from the works and included elements for the cost of labour, plant,
materials, overheads and profit.66
C14
C15
> It includes a fair market rates and prices for the variation of different
character.67
C17
> A fair valuation must include an element of profit except for special
circumstances.65
C18
>The calculation should be based upon the reasonable costs that properly
incurred from the works and included elements for the cost of labour, plant,
materials, overheads and profit.66
C19
> This fair valuation is based on the variations character, instead of the
amount of changed quantities.
C20
63
Clause 11.6(b)
Building Contract Dictionary by Chappel et al.(2001)
65
Henry Boot Construction v Alstom Combined Cycles Ltd (2000)
66
Weldon Plant Ltd v The Commissioner for The New Towns (2000)
67
Clause 11.6(c)
64
203
Item
C21
> If the works cannot be properly measured and valued under the Rule 1,
Rule 2 or Rule 3, the contractor shall use Rule 4.68
C22
> The valuation is either from Daywork Rates in the Contract documents;69 or
where there are no such Daywork Rates, at the actual cost to the contractor of
his materials, additional construction plant and scaffolding, transport and
labour for the work concerned, plus fifteen (15) percent, which the percentage
must include the use of all tools, standing plant, standing scaffolding,
supervision, overheads & profit.70
C23
> In either case, vouchers are required for the valuation, signed by the Site
Agent and verified by the Site Staff, by specifying:
time spent daily upon the work, workers names, materials, additional
construction plant, scaffolding and transport
The vouchers must deliver to the Architect and QS at weekly intervals and the
final records must deliver within 14 Days after completing the work.68
C24
> QS shall not change the figure or hours in the agreed and signed Daywork
rates or vouchers.
C25
> A signed Daywork sheet is only for evidence or record purposes and does
not signify an entitlement to the variation.71
Rule 5 Omitted work
C26
> It uses the original rates and prices to determine the valuation of omitted
work. If the omissions substantially vary the conditions for the remaining
works are carried out, the prices of such remaining works must be valued
under Rule 1, Rule 2 or Rule 3.72
68
Clause 11.6(d)
Clause 11.6(d)(i)
70
Clause 11.6(d)(ii)
71
Clusky v Chamberlain (1995)
72
Clause 11.6(e)
69
204
Item
C27
> The QS shall re-measure the original BQ provisional quantities based on the
actual quantities executed. The original rates and prices determine the
valuation.73
C28
> The actual quantities must be based on the agreed as built drawings and/or
site records.
8.5.4
One variable was rejected in Part D, which the item D4 fell in the category of
neutral or undecided. This guideline is about the invalid omission that will have an
entitlement to loss of profit as referring to the cases McAlpine Humberoak Ltd v
McDermott International Inc74 and Kin Wah J F Construction & Engineering Co Ltd
v L&M Foundation Specialist Ltd75. The experts expressed reservations regarding
this guideline because it could not provide a generic approach regarding contractual
variations to the end-users. It is subject to case-by-case consideration.
73
Clause 11.6(f)
[1992] 58 BLR 1
75
[2004] HCA 226.
74
205
Table 8.14: Agreed guidelines on additional expenses and subsequent circumstances
Item
D1
D2
> Subsequently, the Contractor shall send to the Architect and QS complete
particulars, calculations and contemporaneous records within 28 Days of
completing such variation. If the contractor fails to submit the required
particulars within the stated time or longer period agreed by Architect in
writing, then the contractor has waived his rights to the claim of additional
expenses.77
D3
> Loss of profit is not claimable in this provision as it was covered under the
Rule 2, 3 or 4.
D5
> The Architect and QS shall have access all contractors documents or
records in the possession, custody or control and with free of charge each to
them if requested until all variation claims resolved. Same for the subcontractors and/or suppliers documents in possession, custody or control by
the Contractor. 78
D6
> As soon as the Architect has ascertained the amount of variations and/or
additional expense, it will add into Contract Sum and include into the next
Interim Certificate.79
D7
> The Architect could ascertain the amount anytime before Final Account as
no timeframe is provided.79
DX
> However, if the Contractor has applied for the properly executed variations
into Interim Claim, together with complete details and particulars, the
Architect shall issue an Interim Certificate within 21 Days from the date of
receipt of the payment application.80
76
206
8.6
The test was compared the mean ranks to find out any statistically significant
differences among the four groups of experts as shown in Table 8.15. P-value of
Kruskal-Wallis was included in the analysis to test the null hypothesis that the means
of the four groups are equal versus the alternative hypothesis that their means are not
equal.
207
Table 8.15: Kruskal Wallis test on the agreed guidelines
Part A
P-Value
Part B
P-Value
Part C
P-Value
Part D
P-Value
A1
0.153
B1
0.150
C1
0.558
D1
0.038
A3
0.323
B2
0.036
C2
0.955
D2
0.068
A4
0.254
B3
0.153
C3
0.344
D3
0.105
A5
0.300
B4
0.124
C4
0.277
D5
0.337
A6
0.300
B7
0.621
C5
0.300
D6
0.324
A7
0.378
B8
0.436
C6
0.709
D7
0.621
A9
0.324
B9
0.415
C7
0.378
DX
0.525
A10
0.048
B10
0.480
C8
0.324
A11
0.868
B11
0.243
C9
0.324
A12
0.364
B12
0.293
C10
0.276
A13
0.153
B13
0.925
C11
0.043
A14
0.041
B15
0.138
C12
0.246
A15
0.427
B16
0.912
C13
0.077
A16
0.469
BX
0.181
C14
0.258
A17
0.196
B17
0.046
C15
0.026
B18
0.713
C16
0.248
B20
0.277
C17
0.277
B21
0.133
C18
0.078
B22
0.277
C19
0.263
B24
0.781
C20
0.105
B25
0.364
C21
0.324
B26
0.499
C22
0.277
B27
0.499
C23
0.364
B28
0.254
C24
0.750
B29
0.728
C25
0.263
C26
0.277
C27
0.277
C28
0.364
208
The seven guidelines of different view indicated in the Kruskal Wallis test are
as follow:
Table 8.16 shows the results of the Mann Whitney U test for the seven
guidelines. It is notable that the engineers, the main group of experts, gave different
views on the items compared to the legal professionals, architects and quantity
surveyors. Fourteen out of twenty-one variables had statistically different values
compared to the other groups, where the engineers P-value of asymptotic
209
significance (2-tailed) was less than the critical value of significance 0.05.
Meanwhile, the architects were placed at the second, with nine variables different
from the other groups. The legal professionals and quantity surveyors had the least
discrepancy among the groups, with eight variables different from the other groups.
Furthermore, the architects and engineers were the most different pair in terms of
their agreement. However, the legal professionals and quantity surveyors shared
more in terms of their views based on the statistical analysis. Overall, the tests on the
agreed guidelines indicated that the experts were generally had the same degree of
agreement for the variables, with more than 90% consensus based on the Kruskal
Wallis test.
A10
A14
B2
B17
C11
C15
D1
Legal
professional
and Architect
0.034
0.121
0.121
0.037
0.121
0.121
0.121
0.487
0.046
0.178
0.376
0.037
0.037
0.037
0.034
1.000
0.121
0.037
0.827
0.487
0.487
0.121
0.034
0.034
0.121
0.025
0.025
0.025
1.000
0.121
1.000
1.000
0.037
0.034
0.317
0.121
0.046
0.034
0.121
0.121
0.034
0.034
Legal
professional
and Engineer
Legal
professional
and Quantity
Surveyor
Architect and
Engineer
Architect and
Quantity
Surveyor
Engineer and
Quantity
Surveyor
210
8.7 Discussion of Statistical Analysis
Most of the clarified guidelines were agreed to by the experts for thier content
and language structure in the DwF study. The guidelines provide a generic approach
to contractual variations, although some of the guidelines are referred from court
cases and literature review. This is a value added to the guidelines because it could
enhance the content and detail of the contract provisions from the PAM 2006.
Furthermore, all the guidelines were incorporated with clarity aspects for
better understanding, which included the contract provisions from the contract form.
The guidelines with referring to the contract provisions were all agreed to by the
experts. It shows that the clarified contract provisions are valid with reference to the
meaning and intention of the contract. The clarifying of the language structure is both
practical and important to the construction practitioners because most of them do not
have a well-trained legal background.
Moreover, the Kruskal Wallis and Mann Whitney U tests were applied to the
arithmetic means to compare whether any discrepancy existed between the four
groups of experts. Although the arithmetic means were applied to the test for the
examination, the procedure did not have any conflicts with the earlier geometric
means because the tests were focused on examining the discrepancy in terms of the
mean ranks from the four groups.
211
The DwF research approach achieved the desired objectives from the
contributions of the experts. Totally, seventy-five out of eighty-three guidelines were
accepted after the classification of the threshold value. The viability of Plain English
adopted in the research has proven useful and important for clarifying the language
structure as all the clarified contract provisions were accepted by the experts.
Moreover, the guidelines have been incorporated with additional information apart
from the clarified contract provisions from PAM 2006. These information have
enhanced the coverage and contents of the contract provisions for better explanations
and references. Eventually, all the accepted guidelines are used as the raw data in the
eDR database.
8.8
212
8.8.1
Database
PreIssues list all the contractual issues related to pre-contract work stage
as discussed in Chapter 3 (Table 3.3).
213
MainVariations list the four main aspects for contractual variations such
as issuance of variations, validity of variations, valuation rules of
variations and additional expense and subsequent circumstances caused
by variations.
SubVariations list the sub-issues from the four main aspects for
contractual variations such as authorised persons and power, period of
issuance, provisional sums, written instruction, definition/principle of
variation, addition, omission, substitution, alteration of the kind or
standard of materials or goods, removal of executed works, materials and
goods, changes to the provisions in the contract, valuation rules of
variations, Rule 1 of contracts rates and prices, Rule 2 of fair adjustment,
Rule 3 of fair market rates and prices, Rule 4 of daywork rates, Rule 5 of
omitted work, Rule 6 of re-measurement on actual quantities (provisional
quantity) and additional expense & subsequent circumstances caused by
variations.
Subsequently, the database queries and forms were developed from the tables.
The forms are the important features in the eDR database. The eDR interface was
developed from the forms. The final eDR database file was converted to exe file as a
template setting using the Access Developer Extensions and Runtime. Therefore, it
serves as a read-only analytical database that is used as the foundation for decisionmaking. The portion of the forum for comments or feedbacks is excluded from this,
which is purposely set in an unlocked mode.
214
8.8.2
Front Page
The front page of the eDR explains a brief introduction of the template. Basically,
it discusses the following two main elements before entering into the eDR:
These two elements are important as the database has its limitations and
scopes. The eDR is focused on the contractual variations and contract provisions
from PAM 2006 contract form. Since the database involves many legal principles and
obligations with regard to variations, the exclusion of liability is also explained in the
front page to avoid any conflicts or disputes that might arise.
Figure 8.3 illustrates the front page of the eDR, which was designed using the
Access 2007 Developer Extensions and Runtime software.
215
8.8.3
Main Menu
The next interface of the eDR template is the main menu. It provides two
choices of selection. The first choice is issue breakdown, while the second is
keyword searching. The issue breakdown describes how breakdown of the sub-issues
is derived. The keyword searching uses a search tool to locate the references required
by users. Figure 8.4 illustrates the main menu interface of the eDR.
216
8.8.4
Issues Breakdown
217
After clicking the Click here for DETAILS, there will be a pop-up screen
from the database. It shows all the guidelines as to the sub-issue. For example, the
guidelines on the sub-issue of Authorised Person and Power are as follow:
81
218
the Employer.84
Figure 8.6 illustrate the interface for the content of issue on Authorised
Person and Power.
Subsequently, the users are able to comment or give their feedback after
referring to the guidelines. It can be done by clicking the button GO to
Forum/Comments. This forum has been set unlocked on purpose and with the
command of Auto Number so that users can comment or discuss in the forum; all
the comments will be stored automatically. Figure 8.7 illustrates the blank column of
comments to be filled up by the users.
84
219
As a result, if there are any comments given into the forum, it will be stored
and displayed at the issue breakdown as well by clicking the page of
FORUM/COMMENTS as illustrated in Figure 8.8.
220
8.8.5
Keyword Searching
221
8.9
222
of the guidelines on contractual variations. . This was evident from the comments
from respondents, such as, the respondents would like to have more discussions and
elaborations on the contractual variations. Moreover, a checklist regarding the
contractual variations was suggested by the respondents as well. In summary, the
evaluation process received good responses and revealed that this prototype has
managed to achieve its objectives to deliver a more user-friendly, reliable and
organised means in contract administration. It helps to make better decision-making.
Testing variables
Mean (%)
Interpretation
75.6
Satisfying
74.4
Satisfying
70
Satisfying
66.9
Slightly satisfying
74.1
Satisfying
Overall
8.10
223
organised and clarified contents. However, certain limitations need to be considered.
The template need to be further developed because the construction industry is not
only plagued by the disputes on variations, but also affected and contributed by many
others contractual issues, such as delay and extension of time, interim payment, etc.
Hence a complete data warehouse is a must before it publish online and supported by
the relevant professional bodies. The internet is considered as a macro level in the
future research as to absorb and manage huge amounts of data from the industry.
Once the web data put into the system is able to be integrated that very useful
information will be created and beneficial to all the construction users.
8.11
Concluding Remarks
The last or sixth objective was achieved in this chapter. The application of
eDR revealed two important findings from the research. Firstly, the results from the
DwF indicated that the existing contract provisions on contractual variations could be
improved in terms of clarity of the language structure and its contents. The total
seventy-five agreed guidelines render the comprehensive references on the
contractual variations, where it could enhance the existing contract provisions on
variations. Secondly, the use of information technology has improved the practice of
contract administration in the construction industry, where the electronic approach
has highlighted a more user-friendly and organised means in the contract
administration.
CHAPTER 9
9.1
Introduction
Chapter 9 is the last chapter of the thesis. It describes how the six research
objectives have been achieved based on the results and analysis from the previous
chapters. The research has addressed the low practice of ADR and the problems of
understanding in contract administration in construction industry by identifying the
behaviour of dispute resolution and establishing the systematic approach of contract
administration as well as developing the clarified and informative approach on
contractual variations in the application of eDR prototype/system to achieve the
research aim. An innovative research method, DwF method was applied to the eDR
development. The outcome of the eDR is novel in terms of the easily understandable
and better coverage of the existing contract provisions on variations as well as the
more user-friendly and organised way of retrieving the information from the database.
225
9.2
Preservation
of
relationship
(e.g.
Negotiation,
Adjudication)
Mediation,
226
Third party helps to negotiate and narrow down the issues (e.g.
Mediation, Adjudication)
Both parties are fairly treated during negotiation process before any
official hearing and ruling (e.g. Mediation)
The parties are free to look for other dispute resolution methods
(without legal liability) if they are not satisfied with the result (e.g.
Negotiation, Mediation)
227
9.3
Besides, the findings of Factor Analysis also analysed that the respondents
evinced keen interest in the ADR methods. However, Factor Analysis has further
clarified that the ADR methods are regarded as important in the process of
proceedings, instead of the outcome of ADR based on the seven latent factors. In
other words, the outcome of ADR is not a major concern of the selection. It then
indicated that the appreciation of the benefits of the ADR is very low. Hence the
selection of ADR or non-ADR itself is not the major issue; rather, the increased
efficiency and appreciation of the methods in the construction industry are more
demanding. The continuing search for and the use of the ADR should be emphasized
and more widely employed in the construction industry in order to improve the actual
practice and obtain the desired benefits at the end of the proceedings.
9.4
228
literature review is applied to achieve the objective by identifying all the contractual
issues associated with contract administration and applying the clarified contract
provisions to prevent or control the issues. Total thirty nine contractual issues were
identified in three work stages such as:
Subsequently, the literature review on the contract provisions found out that
the language structure is the main problem of understanding in the construction
contracts. Clarity approach is promoted using the Plain English as an antidote to the
language. Fifteen problems of clarity and legalese aspects were identified and
fourteen measures were proposed from the literature to improve the language
structure. The approach on clarity in contract administration is vital as to understand
and appreciate the contractual obligations and expectations in order to prevent and
control the construction conflicts and disputes.
229
9.5
9.6
230
build up the content of the eDR, while the second explains how the clarified
references/guidelines to be referred by end-users through the online portal. The eDR
model also highlights an applied social science research accommodates the Delphi
and law in construction. This model renders a generic approach on the contractual
issues and could be served as a template or reference for other related construction
law research.
9.7
Two main findings have achieved in this objective. Firstly, the court cases and
ideas from literature review were accepted as valid clarified guidelines in the
contractual variations notwithstanding the allocated contract provisions. The
guidelines could enhance the contents of the exiting contract provisions and render a
practical reference to end-users. Besides, it is also proved that the practicability of
the DwF method in the construction law related research. Subsequently, the second
important finding is the eDR template. The template is incorporated with the
information technology. This electronic method could improve the existing approach
on contract administration in term of retrieving and updating the information.
Moreover, the template is more user-friendly and organised according to the positive
response from the evaluation. It helps to promote life long learning and a more
proactive self-examination on the contractual issue.
231
In summary, the eDR is more focused and simpler compared to the
conventional approach of contract administration, particularly for the easy accessing
of data through the organised issues breakdown and keyword searching. Moreover, it
also provides a more clarified and reliable sources of information when the data of
the contract provisions have been clarified and enhanced by court cases and
literatures.
9.8
1.
2.
The eDR model could serve as a template for future research, even
though there are differences in the legal system and diverse local
scenario. It is because the model provides a generic approach to
dispute mitigation/prevention.
3.
232
REFERENCES
Badman, J. and Grimmett, L. (1996). Legal Framework for the Built Environment.
London: E & FN Spon.
Bojadziev, G. and Bojadziev, M. (2007). Fuzzy Logic for Business, Finance, and
Management. 2nd edition. Singapore: World Scientific Publishing Company.
233
Candlin, C. N., Bhatia, V. K. and Jensen, C. H. (2002). Developing Legal Writing
Materials for English Second Language Learners: Problems and Perspectives.
Journal of English for Specific Purposes. 21: 299-320.
Chan, A. P. C., Yung, E. H. K., Lam, P. T. I., Tam, C. M. and Cheung, S. O. (2001).
Application of Delphi Method in Selection of Procurement Systems for
Construction Projects. Construction Management and Economics, 19, 699
718.
234
Cheung, S. O. (1999). Critical Factors Affecting the Use of Alternative Dispute
Resolution Processes in Construction. International Journal of Project
Management. 17(3): 189-194.
Cheung, S. O., Tam, C. M., Ndekugri, I. and Harris, F. C. (2000). Factors Affecting
Clients Project Dispute Resolution Satisfaction in Hong Kong. Journal of
Construction Management and Economics. 18(3): 281-294.
235
Chong, H. Y. and Rosli, M. Z. (2008a). Contract Administration A Modest
Proposal on E-Dispute Resolution. Proceedings of the International
Conference on Project Management. 18-20 November. Kuala Lumpur: UM
and IEM, 611-618.
Chong, H. Y. and Zin, R M. (2010). A Case Study into the Language Structure of
Construction Standard Form in Malaysia. International Journal of Project
Management. 28(6): 601-608.
Corren, B. (2000). New Jury Instructions Aim to Simplify Legalese. Retrieved March
3, 2009, from http://www.courtinfo.ca.gov/courtnews/julaug00-1.pdf.
236
Duhaime, L. (2007). Part 7: Interpretation of Contracts. Retrieved March 3, 2009,
from
http://www.duhaime.org/LegalResources/Contracts/tabid/339/articleType/Art
icleView/articleId/92/Part-7-Interpretation-of-Contracts.aspx.
Feinman, J. M. (2003). 1001 Legal Words You Need to Know. New York: Oxford
University Press.
Fenn, P., Davies, E. and OShea, M. (1998). Dispute Resolution and Conflict
Management in Construction: an International Review. New York: E & FN
SPON.
Fenn, P., Lowe, D., and Speck, C. (1997). Conflict and Dispute in Construction.
Journal of Construction Management and Economics. 15(6): 513-518.
Fisk, E. R. (2003). Construction Project Administration. 7th edition. New Jersey:
Prentice Hall.
237
Gebken, R. J and Gibson, G. E. (2006). Quantification of Costs for Dispute
Resolution Procedures in the Construction Industry. Journal of Professional
Issues in Engineering Education and Practice. 132(3): 264-271.
Harbans Singh, K.S. and Kandan, K. S. (2004). Variation Claims- Pitfalls and
Pratfalls. Engineering and Law (Bulletin Ingenieur): 36-42.
238
Hill, C. A. (2001). Why Contracts are Written in Legalese. Chicago: Kent College
of
Law.
Retrived
19
May
2008,
from
http://lawreview.kentlaw.edu/articles/77-1/HillLegaleseFinal.pdf.
Hill, T. and Wall, C. (2008). Adjudication: Temporary Binding and Tiered Dispute
Resolution in Construction and Engineering: Hong Kong Experience. Journal
of Professional Issues in Engineering Education and Practice. 134(3): 306308.
Hsia, T. C., Hsu, Y. L. and Jen, H. L. (2009). A Factor Analysis Based Selection
Process for Predicting Successful University Color Guard Club Members.
Expert Systems with Applications. 36: 27192726.
Hsu, Y. L., Lee, C. H. and Kreng, V. B. (2010). The Application of Fuzzy Delphi
Method and Fuzzy AHP in Lubricant Regenerative Technology Selection.
Expert Systems with Applications. 37(1): 419-425.
Ishikawa, A., Amagasa, M., Shiga, T., Tomizawa, G., Tatsuta, R. and Mieno, H.
(1993). The Max-min Delphi Method and Fuzzy Delphi Method via Fuzzy
Integration. Fuzzy Sets and Systems. 55(3): 241-253.
Jonker, J. and Pennink, B. (2010). The Essence of Research Methodology. New York:
Springer
239
Julie P. (2005). SPSS Survival Manual. New York: McGraw-Hill.
240
Landeta, J. (2006). Current Validity of the Delphi Method in Social Sciences.
Technological Forecasting & Social Change. 73: 467-482.
Meyrick, J. D. (2003). The Delphi Method and Health Research. Health Education.
103(1): 7-16.
241
Mitropoulos, P. and Howell, G. (2001). Model for Understanding, Preventing, and
Resolving Project Disputes. Journal of Construction Engineering and
Management. 127(3): 223-233.
Norusis, M. J. (1998). SPSS 8.0 Guide to Data Analysis. New Jersey: Prentice Hall.
242
Noushad Ali, N. A. A. and Lim, C. F. (2008). A Report on the Proposal for A
Malaysian Construction Industry Payment and Adjudication Act. CIOB
CONNECTION 2: 3-10.
PWD Eyes Full Power to Monitor Projects. (2007, May 3). New Straits Time. p.6.
243
Rinzler, B. (2009). Telling Stories: A Short Path to Writing Better Software
Requirements. Indiana: Willey Publications.
Robinson, N., Betts, M., and Santhanam, J. (1991). Expert Systems for Construction
Contract Interpretation. Proceedings of Mini-Conference on Expert System
Applications in Construction Contract Law. June 24-26. Bangkok: AIT, 5067.
Shumway, R., Richard, A. and Ritti, J. (2004). New Trends and Bad Results in
Construction Contracts. Leadership and Management in Engineering. 4(3):
93-104.
244
Singh, R. (1995). Dispute Resolution in Britain: Contemporary Trends. International
Journal of Manpower. 16(9): 42-52.
Skulmoski, G. J., Hartman, F. T. and Krahn, J. (2007). The Delphi Method for
Graduate Research. Information Technology Education. 6: 1-20.
14
February
2008
from
http://www.contractjournal.com/Articles/2005/12/02/48461/constructingconstruction-contracts-the-need-for-clarity.html.
Sundra, R. (1999). The Malaysian Standard Form of Building Contract (The PAM
1998 Form). Kuala Lumpur: Malayan Law Journal Sdn Bhd.
245
Tan, W. (2008). Practical Research Method. Singaopre: Prentice Hall.
The Entrusty Group (2007). Can A Contractor Claim for Compensation for Extra
Work When There is No S.O. Instruction. Master Builders. 2nd Quarter: 9294.
The Entrusty Group (2008). What Constitute Variations and How to Evaluate Them.
Master Builders. 4th Quarter: 82-92.
246
Vallero, D. A. and Vesilind, P. A. (2006). Preventing Disputes with Empathy.
Journal of Professional Issues in Engineering Education and Practice.
132(3): 272-278.
APPENDIX A
Awards and publications as to the research
247
Award
2009
Research Grants
2010 -2011
International Publications
1.
2.
3.
4.
Chong, H-Y, and Rosli MZ, (2010) A Case Study into the Language Structure
of Construction Standard Form in Malaysia, International Journal Project
Management, 28(6), 601-608 (Elsevier, Thomson ISI).
5.
Chong, H-Y, and Rosli MZ. (2010) Application of the Delphi into
Construction Law Research. International Journal of Interdisciplinary Social
Sciences, 5(1), 1-8 (Common Ground Publisher, Cabells Directory).
APPENDIX A
Awards and publications as to the research
248
Conference/Seminar Papers
1.
2.
3.
4.
5.
Chong, HY and Rosli MZ, Contract Administration - a Modest Proposal on EDispute Resolution, International Conference on Project Management Achieving Excellence Through Project Management, ICoPM 2008, Hilton
Hotel, Petaling Jaya, Malaysia, 18th 20th Nov 2008, pp. 611-618.
6.
Chong, HY, Rosli MZ and Lim CC, Expert System on Alternative Dispute
Resolution (ADR): A Proactive Approach of Decision Making in Contract
Administration, 4th Post-Graduate Seminar - Theoretical and Preliminary
Findings, M Suite Hotel, Johor, Malaysia, 19th March 2008, pp. 1-11.
7.
Norazam O, Rosli MZ, Lee, CY and Chong, HY, Clarity Issues in Drafting
Construction Contracts: Guidelines to Future Contract Drafters, The Quantity
Surveying
International
Convention-Construction
Contract
and
Cost
Management: The Next Generation, QSIC 2008, Hotel Istana, Kuala Lumpur,
21st 22nd Oct 2008, pp.1-9.
8.
APPENDIX A
Awards and publications as to the research
249
Appointments
Invited Reviewer:
Keynote/Main Speaker:
APPENDIX B
List of journals in the critical review
250
1990
1992
1993
1994
1996
1997
ADR in Government
APPENDIX B
List of journals in the critical review
251
1998
1999
2000
2001
2002
APPENDIX B
List of journals in the critical review
252
2003
2004
2005
APPENDIX B
List of journals in the critical review
253
2006
APPENDIX B
List of journals in the critical review
254
2007
litigation vs ADR
APPENDIX C
Questionnaire survey: dispute resolution
255
[ ] Contract manager
[ ] Director
[ ] Industrial projects
[ ] Commercial projects
[ ] Highway
[ ] Private sector
[ ] Joint venture
4) Gender: [ ] Male
[ ] Female
5) Age
[ ] 31-40 years
: [ ] 21-30 years
[ ] 41- 50 years
6) Education Qualification:
[ ] PMR or equivalent
[ ] Degree or equivalent
[ ] Master or PhD
[ ] Diploma
[ ] 16 - 20 years
[ ] 5 - 10 years
[ ] Over 20 years
[ ] 11 - 15 years
[ ] > 51 years
APPENDIX C
Questionnaire survey: dispute resolution
SECTION B: DISPUTE RESOLUTI0N METHODS
There are TWO parts for Section B. Part 1 is about philosophy of conflicts and
disputes and Part B is selection factors for dispute resolution methods.
PART 1:
1. Average, how many cases of conflict happen in a construction project?
Rate it accordingly:
] Nil
]1-5
] 6 - 10
] more than 10
] Nil
]1-5
] 6 - 10
] more than 10
256
APPENDIX C
Questionnaire survey: dispute resolution
257
PART 2
What are the factors will you consider while choosing the Dispute Resolution methods, i.e. Negotiation, Mediation, Adjudication
(refer oversea practice - UK, Australia, New Zealand and Singapore), Arbitration and Litigation?
Agree
Neutral
Strongly
agree
257
Disagree
Strongly
Disagree
Strongly
agree
Agree
Neutral
258
Disagree
Strongly
agree
APPENDIX C
Questionnaire survey: dispute resolution
Providing a qualified, neutral experts to hear complex matter (e.g. Mediation, Adjudication,
Arbitration)
258
APPENDIX D
Complete Delphi questions on contractual variations
259
Please rate the score (0-10) for the four aspects of variations under PAM 2006 (with quantities) as: 0=Absolutely disagree,
1=Strongly disagree, 2= Highly disagree, 3=Quite disagree, 4=Slightly disagree 5=Neutral, 6=Slightly agree, 7=Quite agree,
8=Highly agree, 9=Strongly agree, & 10=Absolutely agree.
No
A
Score
(0-10)
(
AQ2
> The right person also includes the Employer of the contract.
AQ3
> Architect issues variations or sanctions contractors variations provided that the variation will not vitiate
the original contract.2
AQ4
> Architects power is restricted, which he cant omit a work because to give it to other contractor. 3
AQ5
> If Architect issues variations that outside the scope of Contract and without expressed authority from the
Employer, he may be liable to the Employer.4
Period of Issuance
> Architect can issue variations at any time before issuance of the Certificate of Practical Completion
(CPC).5
But, after CPC period, the variations must be necessitated by obligations or compliance with the
local authorities and service providers requirements towards the Work,6 or
> Provisional Quantity means the estimated quantities of work, materials or goods in the BQ which cannot
be determined or detailed at the time.10
Provisional Quantity describes as the tasks are with rates and prices for the pre-estimate quantity
and it subject to re-measurement for the actual value.
> Provisional Sums means Sums provided in the Contract and/or for Nominated Sub-Contract for work,
materials or goods in the BQ which cannot be determined or detailed at the time.11
Expenditure of Provisional Sums describes as the tasks but without detailed information for its
quantity, and rates.
> Provisional Quantity does not necessary require an AI for carrying out the work, like piling length in the
Bill of Quantities (BQ).
> AI is mandatory for expenditure of Prime Cost Sums or Provisional Sums.12
AQ1
AQ6
AQ7
AQ8
AQ9
AQ10
AQ11
AQ12
AQ13
AQ14
AQ15
AQ16
AQ17
During DLP if the contractor fails to rectify the defects and with the consent of Employer,
Architect can issue omission for leaving the defects from the set-off. The omission constitutes a
valid issuance of variation7.
> Contractor must conform to the local authorities and service providers requirements and proceed the work
if no AI in response for the inconsistencies with statutory requirements within 7 days of the given written
notice.8
> AI to rectify Contractors default is not considered as a variation either before or after the CPC.
Provisional Sums
> There are two parts of provisional items for variations, i.e., Provisional Quantity and expenditure of
Provisional Sums.9
APPENDIX D
Complete Delphi questions on contractual variations
B
BQ1
BQ2
BQ3
BQ4
BQ5
VALIDITY OF VARIATIONS
Written Instruction
> Written notice in AI is mandatory.13
> The written notice must be in a valid mode, duly served and proved as:14
1.
by hand, at the time of delivery and a signed of acknowledgement of receipt;
2.
by ordinary mail or registered post, after 3 days of posting and a receipt of posting from Post
Office; or
3.
by facsimile transmission, at time of transmission and a transmission report generated by the
transmitting equipment.
> If the delivered notice was not according to the requirements in the contract, it would construe as an
invalid notice and bear no liability of legal effect.15
260
(
(
)
)
BQ6
Definition/Principle of Variation
> Generally, if BQ is not prepared in accordance with applicable Standard Method of Measurement, it could
be a contractual basis for a variation.16
BQ7
> Any errors or inaccuracies in the BQ are at the risk of employer as it constitutes a variation. 17
BQ8
> However, if Contractor finds any discrepancy or divergence between documents; he must send a written
notice to Architect before commencement of the work.18
BQ9
> Contactor must execute variation entirely at his own cost if to rectify his negligence, omission, default
and/or breach of contract.19
BQ10
Addition
> Variations define as addition of design, quality or quantity of the Works.20
BQ11
> An additional work is under statutory requirement but not provided in the contract, it construed as a valid
variation.21
BQ12
> If an additional work is so peculiar, so unexpected and different from the contract, then it would constitute
a separate contract or an invalid variation.22
BQ13
> An additional work has caused the cardinal changes of agreed sum or nature of the Works, it construed as
an invalid variation.23
BQ14
E.g., increased of 60% in excavation, 40% in sewer length and 90% in concrete, it construed as an
invalid variation.24
13
Clause 2.2
Clause 36.1, 36.2 and 36.3
Central Provident Fund Board v Ho Bock Kee (1981)
16
Clause 12.1, Bryant and Sons Ltd v Birmingham Hospital Saturday Fund (1938)
17
Patman and Fortheingham Ltd v Pilditch (1904)
18
Clause 1.4
19
Clause 11.1(last sentence)
20
Clause 11.1(a)
21
Clause 4.3
22
Blue Circle Industries v Holland Dredging Co (1987)
23
Lindsay Parkinson and co Ltd v Commissioners of His Majestys Works and Public Buildings (!950)
24
Wegan Construction Pty Ltd v Wodonga Sewerage Authority (1978)
14
15
APPENDIX D
Complete Delphi questions on contractual variations
BQ15
Omission
> Variations define as omission of design, quality or quantity of the Works.25
261
BQ16
> An omitted work is the part of the Work that no longer needed in the project, it construed as a valid
omission.
BQX
> An omitted work is also referred to a reduction of the quantities of the Works.
BQ17
> If the part of the Work is omitted because to give it to other contractor, it construed as an invalid
omission.26
BQ18
BQ19
> An omitted work changes the fundamental basis of the contract, it construed as an invalid omission.
(
(
)
)
> If the changed work has caused the cardinal changes of agreed sum or nature of the Works, it construed as
an invalid substitution.29
Alteration of the Kind or Standard of Materials or Goods
> Variations define as alteration or changing and modification of the kind or standard of materials or goods
to be used in the Work.30
BQ20
BQ21
BQ22
BQ23
> If the changed materials/goods are so different from the contract, it would constitute an invalid variation.24
BQ24
> Materials supplied by the Contractor are more superior than that specified without any instruction is not
considered as a variation.
BQ25
BQ26
BQ27
> Working space e.g., changing of original space to a smaller or restricted one, either inside the building or
external area of the project.33
BQ28
> Access to or utilisation of any specific part of the Site e.g., difficulty to access or use on the land or part
of the site.34
BQ29
> The execution and completion of the work in specific order e.g., changing of method of statement,
construction method, etc. 35
25
Clause 11.1(a)
Carr v JA Berriman Pty Ltd (1953) and Commissioner for Main Roads v Reed and Stewart Pty Ltd and another (1974)
27
Chadmax Plastics v Hanson and Yuncken (1984)
28
Clause 11.1(a)
29
Thorn v Mayor and Commonalty of London (1876) and Blue Circle Industries v Holland Dredging Co (1987)
30
Clause 11.1(b)
31
Clause 11.1 (c)
32
Clause 11.1(d)(i)
33
Clause 11.1(d)(ii)
34
Clause 11.1(d)(iii)
35
Clause 11.1(d)(iv)
26
APPENDIX D
Complete Delphi questions on contractual variations
C
CQ1
CQ2
262
> The contractor shall provide assistance to the QS for any recording of site information and/or site
measurements are carried out at the site.33
CQ3
> The word similar used in valuation rules cannot be taken as identical, it should consider the
background information and facts of the variation.
CQ4
> The Rules apply to expenditure of Provisional Sums and Provisional Quantity.37
Rule 1 of Contracts Rates and Prices
> It uses the original rate and prices of BQ to determine the valuation.38
CQ5
CQ6
> This rule applies to the variation of a similar character and executed under similar conditions. It does not
significantly change the quantity of work as set out in the BQ.34
CQ7
E.g., a variation caused a little change in quantity for a concrete structure, but conditions (grade,
dimension or method) of the concrete structure remains.
Rule 2 of Fair Adjustment
> It includes a fair adjustment into the original rates and prices of BQ to determine the valuation.39
> This rule applies to the variation of a similar character and either is executed or not executed under similar
conditions but there is a significant change in the quantity of work carried out.39
> The fair will depend on the whole of the contractors pricing strategy, either properly priced or with a
handsome profit margin.40
> If properly priced, a fair valuation must include an element of profit except for special circumstances.41
>The calculation should be based upon the reasonable costs that properly incurred from the works and
included elements for the cost of labour, plant, materials, overheads and profit.42
CQ8
CQ9
CQ10
CQ11
CQ12
CQ13
CQ14
CQ16
E.g., a variation caused a significant change in quantity for a concrete structure, whether under
similar or different conditions (grade, dimension or method), but the concrete structure remains.
Rule 3 of Fair Market Rates and Prices
> It includes a fair market rates and prices for the variation of different character.43
CQ17
> A fair valuation must include an element of profit except for special circumstances.41
CQ18
>The calculation should be based upon the reasonable costs that properly incurred from the works and
included elements for the cost of labour, plant, materials, overheads and profit.42
> This fair valuation is based on the variations character, instead of the amount of changed quantities.
CQ15
CQ19
CQ20
36
Clause 11.5
Clause 11.6
Clause 11.6(a)
39
Clause 11.6(b)
40
Building Contract Dictionary (2001)
41
Henry Boot Construction v Alstom Combined Cycles Ltd (2000)
42
Weldon Plant Ltd v The Commissioner for The New Towns (2000)
43
Clause 11.6(c)
37
38
APPENDIX D
Complete Delphi questions on contractual variations
CQ21
263
CQ22
> The valuation is either from Daywork Rates in the Contract documents;45 or where there are no such
Daywork Rates, at the actual cost to the contractor of his materials, additional construction plant and
scaffolding, transport and labour for the work concerned, plus fifteen (15) percent, which the percentage
must include the use of all tools, standing plant, standing scaffolding, supervision, overheads & profit.46
CQ23
> In either case, vouchers are required for the valuation, signed by the Site Agent and verified by the Site
Staff, by specifying:
time spent daily upon the work, workers names, materials, additional construction plant,
scaffolding and transport
The vouchers must deliver to the Architect and QS at weekly intervals and the final records must deliver
within 14 days after completing the work.39
CQ24
CQ25
> QS shall not change the figure or hours in the agreed and signed Daywork rates or vouchers.
> A signed Daywork sheet is only for evidence or record purposes and does not signify an entitlement to the
variation.47
Rule 5 Omitted work
> It uses the original rates and prices determine the valuation of omitted work. If the omissions substantially
vary the conditions for the remaining works are carried out, the prices of such remaining works must be
valued under Rule 1, Rule 2 or Rule 3.48
Rule 6 Re-measurement on Actual Quantities (Provisional Quantity)
> The QS shall re-measure the original BQ provisional quantities based on the actual quantities executed.
The original rates and prices determine the valuation.49
(
(
)
)
CQ26
CQ27
CQ28
D
DQ1
> The actual quantities must be based on the agreed as built drawings and/or site records.
ADDITIONAL EXPENSE & SUBSEQUENT CIRCUMSTANCES CAUSED BY VARIATIONS
> If a variation has caused or likely to cause the contractor to incur additional expenses, where he would not
be paid under the 6 Rules. He may claim it provided that given a written notice of his intention to the
Architect together with an initial estimate duly supported with all necessary calculations within 28 days from
the date of the AI or CAI. The notice is a condition precedent to the claim entitlement.50
DQ2
> Subsequently, the contractor shall send to the Architect and QS complete particulars, calculations and
contemporaneous records within 28 days of completing such variation. If the contractor fails to submit the
required particulars within the stated time or long period agreed by Architect in writing, then the contractor
has waived his rights to the claim of additional expenses.51
DQ3
> Loss of profit is not claimable in this provision as it was covered under the Rule 2, 3 or 4.
DQ4
> However, a claim for loss of profit will always be successful for the invalid omission.52
DQ5
> The Architect and QS shall access all contractors documents or records in the possession, custody or
control and with free of charge each to them if requested until all variation claims resolved. Same for the
sub-contractors and/or suppliers documents in possession, custody or control by the Contractor. 48
DQ6
> As soon as the Architect ascertained the amount of variation and/or additional expense, it will add into
Contract Sum and include into the next Interim Certificate.53
DQ7
>The Architect could ascertain the amount anytime before Final Account as no timeframe is provided.53
DQX
> However, if the contractor has applied for the properly executed variations into Interim Claim, together
with complete details and particulars, the Architect shall issue an Interim Certificate within 21 days from the
date of receipt of the payment application.54
44
Clause 11.6(d)
Clause 11.6(d)(i)
46
Clause 11.6(d)(ii)
47
Clusky v Chamberlain (1994)
48
Clause 11.8
49
Clause 11.6(f)
50
Clause 11.7 and 11.7(a)
51
Clause 11.7(b) and 11.8
52
McAlpine Humberoak Ltd v McDermott International Inc (1990) and Kin Wah JF Construction & Eng. v L&M Foundation Specialist Ltd
(2004)
53
Clause 11.9
54
Clause 30.1 and 30.2
45
APPENDIX E
Prototype demonstration and evaluation form
264
Please rate your satisfaction score (0-100%, i.e., 0 = extremely dissatisfied, 30% =
dissatisfied, 50% = neither satisfied nor dissatisfied, 70% = satisfied, 100% =
extremely satisfied) on the questions below.
APPENDIX F
List of respondents from questionnaire survey
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
1.
2.
3.
4.
5.
6.
7.
8.
265
APPENDIX F
List of respondents from questionnaire survey
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
266
APPENDIX F
List of respondents from questionnaire survey
43.
44.
267