19-30th Oct 2009

OVERALL SUMMARY
• Report on Bokor Phase III submitted on 14th October 2009 currently awaiting response from
Bokor PMT.
• Chiguetti Methanol Leak determined to be subsea ; Preparation is being made for
intervention to repair.
• 4 out of 11 PETRONAS Subsea Technical Manuals Rev. A1 have been submitted by OPR for
review

1.1 KEY ACTIVITIES


1.2 CAPABILITY DEVELOPMENT

1.2.1 SUBSEA SYSTEM ( Pak Farid/Pak Awal/Farah/Suhaira)

• Support Kanowit Subsea of Kumang Cluster development project.

 Continue with flow assurance study for pre-detail engineering of


Kanowit Subsea Development i.e frequency of pigging result.
Currently 75% completed.
 Review the Optimization system engineering study proposed by Aker
 Review of Kanowit process safe guarding system (i.e. SIL-1 OPPS
installed at Xmas tree)
 Review the piping system design proposed by contractor (i.e. API 5000
system vs. ANSI 2500 system)
 Review Drawings (i.e. P&ID) and subsea hardware design basis (i.e.
12” jumpers)

• Support the flow assurance analysis for Mauritania Banda Gas Development in
terms of reservoir fluid analysis and Subsea Compressor Study
• Continue with preparation of “Guideline of Feasibility Study for Subsea
Development”. Issuance for interdisciplinary review is planned end September.
Current stage is 8% progress.
• Review of “In-Progress” Subsea Field Development Benchmark of Technology
Project
• Support M4-Reactivation Project in terms of existing subsea wells activation
cost verification.
• Support JV – Block 16/19 Mozambique Field Development Study. Review the
field development options proposed by partner (Sasol Petroleum International)
1.1.1 SUBSEA HARDWARE(Zahid/Azri/Radzlan/ Fahmi)

• Support Kanowit subsea of Kumang Cluster development project

• Review Kanowit Optimization Cases & Cost Benefits.

• Review of Structure Design Basis


• Review of Foundation Design
• Review of Kanowit Coating Specifications Technical Queries.
• Review of Tie-In Design Basis & Jumper Design Basis.
• Review of Fishermen vs Overtrawlable Structure comparison.

• Participate in Kumang Kanowit Subsea Development Project P&ID


Presentation by Aker Solutions.
• Review of Rev A1 PSTM No. 1a – Subsea Production System – Subsea Xmas
Tree for TP1 still ongoing
• Review of Rev A1 PSTM No. 1b – Subsea Production System Hardware for TP1
still ongoing.
• Participate in Coabis, Integrity, Inspection and Corrosion Management
Software by Aker Offshore on 20th October 2009.
• Prepare and consolidate Technical Evaluation Questionnaire for TMU Due
Diligence study of Shell’s Cold Flow Technology. The due-diligence will be
conducted in Huston & Wyoming on 9th-14 November 2009.
• Conducted a discussion with FMC Technology & Cameron on Mudline Xmas
Tree design on 29th October 2009.

1.1.1 SUBSEA CONTROL (Mahadzir/Steven/Fikri H)

• SKG 14.2 TI&R and descriptor presentation is with SKG 14 advisor for approval
from VP R&T.
• Review PSTM No. 10 – Subsea Distribution System for TP1
• Support Kanowit System Engineering and optimization study.

1.1.1 SUBSEA UMBILICAL / INTERVENTION (Yunus/Amizal/Colin/Hafiz


H/Faizal/K.Anwar)
• Support in identifying the offshore installation requirement for the subsea
equipment on topside KAKG-A (Kanowit Project).
• Ongoing Umbilical Study/Handbook preparation on Introduction to Dynamic
Analysis Umbilical Study and Subsea Umbilical Manufacturing Process of Steel
Tube. 50% progress.
• Ongoing Intervention database preparation. 10% progress
• Ongoing Intervention handbook preparation on “Well and Equipment
Intervention”. 10% progress.
• Chinguetti Methanol Leak determined to be subsea; Preparation is being made
for intervention to repair.

1.1.1 OTHERS
• Ongoing discussion on Subsea Engineering Interface Matrix
• Conducted a subsea in-house training classroom on topic:
 Introduction to Subsea Field Architecture by Awaluddin Berwanto on
9th October 2009
• Completed 38% of overall subsea in-house training class
• Sequoia Development Project has been completed where the 1st gas has flown
from D1 (08/08/09) and the last from D4 (27/08/09). The PMT has now being
roll over to WDDM Phase VIIIa

1.1 DATABASE SET-UP(Fahmi/Zack)

• Re-analyze document structure for database improvement.


• Updated database web page and user interface
• Promote user to use online discussion board
• Uploaded 3 document to database:
 Saderi subsea production control system

 Project document from Mr.Ajmel

 Subsea Flow Assurance by vendor ( Roxar)

1.1 SKILL RATIONALIZATION(Pak Awal)

• Continue perform in-house coaching for subsea engineers.


• Continue monitor the progress of subsea engineers who are identified to be
involved in Skill Rationalization Project.
• Awaiting direction from PETRONAS Skill Rationalization Project Team

1.1 SUBSEA TECHNOLOGY PROJECT

1.1.1 SUBSEA TECHNOLOGY PROJECT 1(Pak Farid/M Azri)

• 9 out of 11 PETRONAS Subsea Technical Manuals Rev. A1 have been


submitted by OPR for review.
• OPR continue with writing, improving and incorporating PCSB comments in the
manual.
• Meeting with OPR Lead Consultant for PSTM 7-Installation & Vessel
Requirement on 26 October 2009.
th
1.1.1 SUBSEA NEW TECHNOLOGY QUALIFICATION(M Zahid)

• PCSB’s management approval was received on 18th September


2009.Agreement with JIP’s coordinator currently being vetted through.
• Change code has been received on 12th October 2009 from TMU.

20 SUBSEA PROJECT DEVELOPMENT


KANOWIT SUBSEA DEVELOPMENT PROJECT (KUMANG CLUSTER)
(Amizal/Radzlan/Azlan/Farah/Sue/Faizal/Fikri H)

2.1.1 PROGRESS STATUS/ PROJECT HIGHLIGHTS


• Ongoing Flow Assurance study on frequency of pigging requirement during
operation. 78% completed.
• Ongoing study on availability of service provision for new technology
qualification, received proposal on Qualification Basis & Technology
Assessment from DNV. Due to Aker Solution’s preference on API 17N, thus
Kanowit will not be using DNV for the Qualification Basis & Technology
Assessment.
• Evaluation of WGFM in progress, pending contract to be awarded by Aker.
• Attended Petronas Project Management System (PPMS) Training by DPR on
2nd October 2009 at Citibank Tower.
• A follow up meeting to be arranged with ASM based on feedback from PCSB
CTE to conclude the issue of scope of work.
• Follow up the feedback of the scope of work discussion with Aker is in
progress.

2.1 CHINGUETTI DEVELOPMENT PROJECT


2.1.1 ACTIVITIES HIGHLIGHTS(Razali)

• PCM1 Workover Subsea Equipments are currently stored (temporarily) in the


SBS yard at Edzell, Aberdeen. Preparation of ITB Document is on-going.
Currently at the final stage of review. Plan to issue ITB in two weeks time
• Supported upcoming Chinguetti Intervention activities, to take place in middle
October involving Sliding sleeve open, SCM Change out jobs, MeOH leak
investigation, hydraulic jumper change out and General Visual Inspection.
• Ongoing activities on Chinguetti Phase 3 feasibility study with prospect of 2
in-fill wells

2.1 BANDA GAS DEVELOPMENT PROJECT

2.2 ACTIVITIES HIGHLIGHTS(Noor Hafiz)


• Reviewed the draft report of Process System Design Report for Banda Subsea
Wet Gas Compressor System Study
• Basic crude / condensate assay analysis is 80% completed, water analysis is
100% completed, wax analysis is 60% completed and PVT analysis is 100%
completed.
• Reviewed the table of contents for laboratory Report for Banda Mauritania
Fluid Characterization and PVT Analysis.
• All fluid characterization study and PVT analysis are expected to be completed
by end of October 2009

20 POTENTIAL SUBSEA PROJECT DEVELOPMENT

2.1 ADP KUMANG PHASE II(Amizal/Azlan)

• The Area Development Plan (Plan) Report is ongoing.

2.1 BOKOR PHASE III(Farid/Zahid)

• Report submitted on 14th October 2009 currently awaiting response from Bokor
PMT.

40 AREAS OF CONCERN / CHALLENGES

• No major highlights

5.0 WORK PLANNED FOR NEXT TWO WEEKS(All)

• Continue to support Kanowit Subsea Development Project.

• Continue to support Mauritania Development Project.

• To provide OPR with all manual comments & review prior Integrated Review
Workshop for TP1.

• To conduct tele-conference with OPR Lead Consultant to discuss on comments


submitted for TP1 Petronas Subsea Technical Manual.

• Continue with the write up of PSTM No 2 Field Development Benchmark & PSTM
No. 5 ROV Operation for Technology Project 1 (by OPR).

• Continue developing the level 2 & 3 training syllabus for SKG 12.5.
• Incorporating comments from JV partners, into Banda FDP and Tiof & Tevet
Technical Reports, before submission to Mauritania Government

• Plan to issue ITBD for Chinguetti Workover riser and control system Refurbishment
contract in two weeks time.

• Preliminary Subsea concept selection on Chinguetti Phase 3: Drilling 2-Infill Wells


(WSW & C13 Blocks)

• Meeting on Banda SCMS application with DFMC

• Continue discussion on Subsea Engineering Interface Matrix

• Conduct feasibility study for Baran EOR Project.

• Continue to assist Chinguetti team in preparations to intervene and repair


methanol leak