OVERALL SUMMARY
• Report on Bokor Phase III submitted on 14th October 2009 currently awaiting response from
Bokor PMT.
• Chiguetti Methanol Leak determined to be subsea ; Preparation is being made for
intervention to repair.
• 4 out of 11 PETRONAS Subsea Technical Manuals Rev. A1 have been submitted by OPR for
review
• Support the flow assurance analysis for Mauritania Banda Gas Development in
terms of reservoir fluid analysis and Subsea Compressor Study
• Continue with preparation of “Guideline of Feasibility Study for Subsea
Development”. Issuance for interdisciplinary review is planned end September.
Current stage is 8% progress.
• Review of “In-Progress” Subsea Field Development Benchmark of Technology
Project
• Support M4-Reactivation Project in terms of existing subsea wells activation
cost verification.
• Support JV – Block 16/19 Mozambique Field Development Study. Review the
field development options proposed by partner (Sasol Petroleum International)
1.1.1 SUBSEA HARDWARE(Zahid/Azri/Radzlan/ Fahmi)
• SKG 14.2 TI&R and descriptor presentation is with SKG 14 advisor for approval
from VP R&T.
• Review PSTM No. 10 – Subsea Distribution System for TP1
• Support Kanowit System Engineering and optimization study.
1.1.1 OTHERS
• Ongoing discussion on Subsea Engineering Interface Matrix
• Conducted a subsea in-house training classroom on topic:
Introduction to Subsea Field Architecture by Awaluddin Berwanto on
9th October 2009
• Completed 38% of overall subsea in-house training class
• Sequoia Development Project has been completed where the 1st gas has flown
from D1 (08/08/09) and the last from D4 (27/08/09). The PMT has now being
roll over to WDDM Phase VIIIa
• Report submitted on 14th October 2009 currently awaiting response from Bokor
PMT.
• No major highlights
• To provide OPR with all manual comments & review prior Integrated Review
Workshop for TP1.
• Continue with the write up of PSTM No 2 Field Development Benchmark & PSTM
No. 5 ROV Operation for Technology Project 1 (by OPR).
• Continue developing the level 2 & 3 training syllabus for SKG 12.5.
• Incorporating comments from JV partners, into Banda FDP and Tiof & Tevet
Technical Reports, before submission to Mauritania Government
• Plan to issue ITBD for Chinguetti Workover riser and control system Refurbishment
contract in two weeks time.