400 KV Switchyard Testing Schedule

Sl.NO Equipment Description

Current Transformer

Qty in No Testing Scope

54

Kit Required

Start Date Complete Date

1.Polarity
2.Magnetising Current (Knee point voltage test for PS
Class CTs)
3.Ratio Ckeck
4.RCT
5.Tan Delta Test
6.IR Test Before & After the all above tests
7.Primary injection and verification of readings in all
the associated equipments in control room

CT Analyser

15-May-13

22-May-13

CT Analyser

15-May-13

22-May-13

CT Analyser
CT Analyser
Tan Delta Kit
Megger

15-May-13
15-May-13

22-May-13
22-May-13

17-May-13

21-May-13

Capacitive Voltage Transformer

18

1.Polarity
2.Ratio Test
3.IR Test
4.Induced Voltage test

CT Analyser
CT Analyser
Megger

23-May-13
23-May-14
21-May-13

25-May-13
25-May-14
23-May-13

Electro Magnetic Voltage


Transformer (EMVT)

1.Polarity
2.Ratio Test
3.IR Test
4.Induced Voltage test

CT Analyser
CT Analyser
Megger

26-May-13
26-May-13
24-May-13

27-May-13
27-May-13
25-May-13

1.IR Test
2.CRM Test
3.Timing Test
4. Reduced voltage test for Trip & Close operation

Megger
CRM Kit
Timer Kit

26-May-13
17-May-13
19-May-13

28-May-13
21-May-13
23-May-13

400kV Circuit Breaker

400kV Isolator

1.IR Test

Megger

29-May-13

31-May-13

2.CRM Test

CRM Kit

21-May-13

27-May-13

Lighting Arrester (LA)

24

1.IR Test
2.Surge Counter Test

Megger
A/c supply

Wave Trap (WT)

1. IR Test

Megger

1.IR Test
2.Tan Delta Test
3.Winding Resistance
4.Testing of Bushing CT's
5.Magnetising characteristics
6.Stability test of differential and REF protection

Megger
Tan Delta Kit
TRM
CT Analalyser

400 kV C & R panel

Lot

IR test for control circuit as well as primary


circuit
1. Operational test shall be performed from
both Relay panels and Control Panels
2. All interlocks shall be checked
3. All spare contacts of Isolator shall be
checked.

34

Reactor

Circuit Breaker timing (Close, Trip and CO)

1. Operational test shall be performed from


both Relay panels and Control Panels
2. All interlocks shall be checked
3. All spare contacts of CB shall be checked.

3. Operational Test

IR test for control circuit as well as primary


circuit

12
5. Operational Test

NA
IR for secondary as well as primary

Loading Tr &Variac

Remarks

1.Scheme checking and simulation of operation


confirming the interlock for the other associated
equipment in the control room, AC Kiosk, switch-room
and switchyard
2.IR test for control circuit
Megger
3.Checking of readings of all indicating / recording
instruments confirming their accuracy classce

1-Jun-13
24-May-13

3-Jun-13
25-May-13

3-Jun-13

4-Jun-13

4-Jun-13
22-May-13
22-May-13
28-May-13

4-Jun-13
22-May-13
22-May-13
28-May-13

10

400kV Switchyard Earthing

Measurement of earth resistance for individual treated Earth Resistance


earth pit - 10 nos. approx
Meter

Note:
1.Assisting Labours to be provided for 5 Engrs
2.Continuos of power supply required
3.Witness form Client for all testing
4.Working Hrs min 8 Hrs
5. All test results shall be properly noted down in Test report format or Protocol and same shall be signed by Customer, Siemens Representative and Testing Engineer.