Project Experience List

10/30/2014

Project Experience
Significant Projects
Projects-Plant
Plant Services
Detailed Project List Plant Services

Scope Covered
Piping works
EDC modification works(around 20,000 inch dia of various piping works)
Scaffold area of 16,000 m3
Duration
45 days (including pre fabrication)

Project Highlights
Manpower strength of 658
On time completion without LTI
10/30/2014

AbdullahA.AlBarrack&Sons

Scope Covered
Piping repair works
Cutting and replacement of prefabricated spools
Isolation
Isolation blinding and de
de-blinding
blinding.
Replacement of Valves-repositioning, inspection, cleaning,replacing,gaskets of
leaking flanges.

Duration
20 days
Project Highlights

Manpower strength of 140

Scope Covered
Complete Maintenance of Equipment and piping etc

Project Highlights
Columns = 17
Completion Period = 30 Days

Planned Manpower Deployment = 1250

Heat Exchanger = 77
Completion Period = 30 Days

Equipment Deployment = 68

Remaining Drums/Tanks/Vessels= 67
Completion
Completion Period = 30 Days

Equipment Deployed
Cranes,
Cranes, Hydro Jetting, Welding, Gensets, Super Sucker, Blasting Equipment,
Bundle Pullers, Bolt Torquing, Scaffolding and other vehicles
10/30/2014

AbdullahA.AlBarrack&Sons

Special
Appreciation
award from
client

Scope Covered

Isolation of equipment

Blinding & De-blinding

Hydro jet Cleaning of Towers & Drums

Removing of Ball Ring , replacement of trays, Deimister Pads

Waste Disposal

Piping Modification

Shifting of Slug & waste from Tower & Drums through Super Sucker &
Dumping to Waste Yard.

Completed Equipments

Project
j
Highlights
g g
Scheduled Completion Period = 25 Days
Actual Completion = 22 Days
Manpower of 300

10/30/2014

Columns = 20
Drums/Tanks/Vessels= 47

ABIS Equipment Deployment


Cranes, Hydro Jetting, Gensets,
Super Sucker,
Sucker Blasting Equipment,
Equipment
Bolt Torquing and other vehicles

AbdullahA.AlBarrack&Sons

MAJOR PROJECT DETAILS


DETAILS-PLANT
PLANT -COMPLETED
COMPLETED
SR.NO
1

Client

Project Title

Scope Of Work

Schedule

Saudi Aramco-Riyadh Refinery

Demolition of Piping
Associated with Steam
Turbines

Removal & Re-Installation of


Piping

16-Apr-14 To 14May-14

Saudi Aramco-Riyadh Refinery

Samsung-Saudi Aramco Riyadh


Refinery

SAUDI ARAMCO
YANBU
10/30/2014

Piping fabrication , Erection


Installation of Mechanical EDC 21/10 Package (Mechanical ,
Seal Leakage detection Electrical & Instrumentation work) ,
system
EDC 10/10 , EDC 25/10 , EDC 05/08
, EWO-12C220
El t i l cable
Electrical
bl Conduiting
C d iti
, NDT,
NDT
March-14 to MayBlasting & Painting, Scaffolding
14
works, Lifting Equipment during
Elimination of Single Point
Prefab in Contractor scope ,
of Failure
during TA Aramco will Provide,
Installation of Control Valves,
Valves
Supply & Installation of Structure ,
Plates
Early Works of Riyadh
Tie In works, Hydro testing &
Refinery - Clean
Removal & Re-Installation of
April-14 to April-14
Transportation fuels at
V l
Valves
Riyadh Refinery Project
Cutting and replacement of prefabricated spools,
Isolation /blinding and deblinding Cold Cutting
blinding,
Replacement of valves
Piping Repair Work 2014 TRS
Repositioning, Inspection,
Feb-14 To Mar-14
cleaning, replacing, gasket of
Abdullah A. Al Barrack & Sons
7
leaking flanges as per scope of
work, Welding Machines ,

SR.NO

Client

Project Title

Isolation of equipment,
Blinding & De-blinding
Hydro jet Cleaning of Towers & Drums
T & I of Towers & Drums
Removing
R
i
off B
Ballll Ring
Ri
, replacement
l
t off ttrays ,
at operation zones
Deimister Pads, Shifting of Slug & waste from Tower
& Drums through Super Sucker & Dumping to Waste
Yard

Saudi Aramco
Aramco-Jeddah
Jeddah
Refinery

Saudi Aramco-Riyadh
Refinery
y

EDC Modification
Works during
g 2014 TRS

Suadi Aramco-Riyadh
R fi
Refinery

IWS Piping
R l
Replacement
tW
Works
k

10/30/2014

Scope Of Work

Blinding
Bli di
& De-blinding
D bli di
Erection of Scaffolding as per requirement.
Shifting of free issue material from main store to
workshop
Pre fabrication
Sand blasting and painting .
Shifting of Pre fabricated spool from workshop to
Site location
Dismantling existing piping and Erection of new
fabricated spools

AbdullahA.AlBarrack&Sons

Schedule

Nov 13 to
Nov-13
Dec-13

March-14 to
May-14
y

15-Mar-13 to
J
June-14
14

SR.NO

Client

AR-Razi SABIC

AR-Razi SABIC

10

AR-Razi SABIC

11

12

AR-Razi SABIC

SAUDI ARAMCO
YANBU CRUDE OIL
TERMINAL
10/30/2014

Project Title

Scope Of Work

Inspection & Erection Services of Stationary


Equipment Services (Heat Exchangers, Columns,
Replacement of 20" Vessels & Drums) at Plant 1&2
RG Line form CS TO SS Replacement of 20
20" RG Line from CS to SS 304,
304
prefabrication, Installation & Erection Work
including Design & Procurement of Materials.

P-1 CMA
C
Line
i
Replacement PCRReplacement of carbon steel 8" CMA service
1886
piping with stainless steel
Dismantling of existing CS line as per scope of
work
work.
Erection of new SS line as per scope of work.
P-2 CMA Line
Crane 55 ton ,Scaffolding, NDT
Replacement PCR1886

RG Line Replacement
PCR-1886

Replacement of 20" RG Line from CS to SS 304,


prefabrication, Installation & Erection Work
including Design & Procurement of Materials.

Prefabrication & Installation of 36" Dia Pipeline of


Installation of five (5)
CS Material including Sand Blasting Painting.
Jumpovers on bunker
Civil Works like Manual Excavation, Sleepers &
fuel System
Foundation Preparation.
AbdullahA.AlBarrack&Sons
E&I, Installation Control Valves and Cable Laying

Schedule
September2012
30 Days

SSeptemberb
2012
30 Days

September2012
30 Days

September2012
30 Days

Apr-12 to
Dec12
9

SR.NO

Client

13

SAUDI ARAMCO
UDHALIYAH

14

SABIC-SHARQ

Piping and Valves


Modification, Prefabrication & Installation of CS Piping
May-12 to JulReplacment during 1&2 upto 16" Dia. Valve Replacement upto 30" Dia at 1EG &
12
PE tam 2012
1 UTL Plant including Scaffolding and Insulation

15

SABIC-PETROKEMYA

Line Replacement Job at CS Line Replacement upto 24" Dia at Petrokemya PVC May-12 to JulPetrokemya TA-12
Plant including Prefabrication, NDT & Painting
12

16

SABIC-HADEED
JUBAIL

Overhauling of Furnace
Charging Equipment Module D

Removal Reinstallation and repair of Pipes & Thermo


couples. Mechanical
i
repair
i

Apr-12 to Apr12

17

SAUDI ARAMCO
HARADH

Mechanical Preparation
of TR/L-1 @ HRDH, G-3 for
Insitu Coating
g

Cold Cutting of Pipe, cutting of 20" TR/L Pin hole Leak


portion, Butwelding, Hydro testing, Plug test, Repre-Fabricated Spool
p
Installationof p

Nov-11 to
Dec-11

18

SAUDI ARAMCO
UDHALIYAH

Replacement of
Corroded pipe

Fabrication of new 10" Piping, 150 Meter Long. RT &


Hydrotesting of Weld Joints.

Jul-11 to Aug11

19

SSAUDI
U ARAMCO
CO
UDHALIYAH

Modification of 16" & 12"

Modification
od ca o of
o Suction
Suc o & Descharge
esc a ge p
piping
p go
on 10
0 No.
o.
Valve upto 16" Dia, NDT of Weld Joints

Jun-11 to
Ju
o JunJu
11

20

SAUDI ARAMCO
10/30/2014
YANBU

Project Title

Scope Of Work

Installation of Two New


Installation of Two New Shipper Pumps, Preparation of
Shipper Pumps @ UGOSPFoundation and associated Piping Fabrication &
g & Painting
g
13
Installation,, Sand Blasting

welded
ld d body
b d valves
l
att
disposal system

Piping works atAbdullahA.AlBarrack&Sons


Yanbu
Removal & Reinstallation of Miscelleneous Diameter
Refinery during TRS 2011
Piping at different Location

Schedule
May-12 to
Dec-12

Feb-11
10 to Feb11

SR.NO

Client

Project Title

Scope Of Work

Schedule

21

SAUDI ARAMCO
RAS TANURA

Pipe girders replacement


Pipe girders replacement and Epoxy coating - Plant Oct-10 to
and Epoxy coating - Plant
53 Temporary Pipe Supports,
53,
Supports Sleepers Constructions
Dec 10
Dec-10
53

22

SABIC - SHARQ
JUBAIL

Piping & Valves Repair 1&2 Removal & Installation of 20'' Pipe and valves 54 nos. Nov-10 to
PE TAM 2010
Grit Blasting / Painting. NDT and Insulation
Dec-10

23

SABIC - PETROKEMYA
JUBAIL

Replacement of 800 Meters CS Pipe Line,


Line Replacement Work May-10 to
Prefabrication of Spool & Installation on site. Blinding
PVC/VCM
Jun-10
/ Deblinding, Hydro testing & RT
North
N
th / SSouth
th Ground
G
d
1" Pipeline
Pi li
Replacement
R l
t off North
N th & South
S th G
Ground
d
Flares Valves Replacement
Flares, Replacement of 3" Valves,
Dismantling/Installation of 48'' Pipeline
- Plant 57

Mar-10 to
Jun-10

24

SAUDI ARAMCO

25

SAUDI ARAMCO
RAS TANURA

Drums, Heater, Silencers


Work at RTR for Plant J-72

Cleaning and testing, Welding Repair inside Drums


i l di
including
NDT.
NDT Installation
I t ll ti
& Removal
R
l off IInternal
t
l
Scaffolding

May 10 to
May-10
Jun-10

26

SHARQ
(SABIC
(S
C affiliate))

Piping and Valves


replacement
g Annual TA 33 EG/UTL
G/U
during
Plant

Pipeline Fabrication & Installation, Painting,


SScaffolding
g & Insulation Removal & Installation

Apr-09 to
JJun-09
09

27

SAUDI ARAMCO
10/30/2014
(Riyadh)

Crticial Piping
Piping Removal, Installation, Monal Welding
replacement workAbdullahA.AlBarrack&Sons
during
Hydrotesting
TRS 2009

Mar-09 to
11
May-09