Date:20.01.2013
Sl.
No
Ownership
Type of
Fuel
Expected
Commissioning
Date
25
RPCL
Gas/FO
January, 2013
273
EGCB
Gas
March, 2013
Sub-Total (Public)(Jan.-June/13)
298
Capacity
(MW)
Remarks
3 Khulna 150 MW GT
150
NWPGC
Gas/HSD
July, 2013
139
EGCB
Gas
October, 2013
75
NWPGC
Gas/HSD
December, 2013
Contract signed
364
Sub-Total ( Public)
662
IPP
FO
June, 2013
Private Sector
Chittagong (Mohora) 50 MW
Power Plant
50
50
108
IPP
FO
July, 2013
108
IPP
Gas
July, 2013
4 Ashugonj 50 MW PP
51
IPP
Gas
July, 2013
500
Import
September, 2013
Kathpotti, Munshigonj 50 MW
Power Plant
53
IPP
FO
October, 2013
220
IPP
Gas/FO
October, 2013
102
IPP
FO
November, 2013
95
IPP
Gas/FO
December, 2013
108
IPP
FO
December, 2013
1395
2057
200
EGCB
Gas
June, 2014
150
BPDB- RPCL
Powergen Ltd.
FO/Gas
June, 2014
175
APSCL
Gas
June, 2014
1345
Sub-Total (Public)(Jan.-June/14)
525
Sl.
No
4 Chapai Nababganj
5 Kaptai Solar
6 Ashugonj 225 CCPP: SC GT Unit
Bagabari 100 MW Power Plant
Conversion
Shajibazar 70 MW Power Plant
8
Conversion
9 Sylhet 150 MW Power Plant
Conversion
Ashugonj 200 10% MW Modular
10
PP
7
Capacity
(MW)
Ownership
Type of
Fuel
Expected
Commissioning
Date
100
BPDB
FO
July, 2014
BPDB
Solar
September, 2014
150
APSCL
Gas
September, 2014
50
BPDB
Gas
December, 2014
35
BPDB
Gas
December, 2014
75
BPDB
Gas
December, 2014
20
IPP
APSCL
December, 2014
435
Sub-Total ( Public)
960
Remarks
Tender Under Evaluation
Private Sector
Contract Signed with CLC Power & Associate Ltd.
On 11.12.2011.
Contract Signed with JV Fujian Longking Co &
Dhaka West Power Ltd. On 12.10.2011
Contract Signed with Consortium of Union
Consultant (Pvt) & Venture Energy Resources Ltd
108
IPP
FO
January, 2014
108
IPP
FO
January, 2014
53
IPP
FO
March, 2014
100
IPP
FO
April, 2014
5 Nababgonj 50 MW PP
50
IPP
FO
June, 2014
6 Munshigonj 50 MW PP
50
IPP
FO
June, 2014
7 Manikganj 50 MW PP
50
IPP
FO
June, 2014
115
IPP
Gas/FO
July, 2014
145
IPP
Gas
December, 2014
Sub-Total(Private)(Jan.-June/14)
Meghnaghat 300-450 MW CCPP
8
nd
(2 Unit) : ST Unit
nd
Bhola 150-225 MW CCPP (2
9
unit):SC GT Unit
10 Kaliakair Peaking Plant, Gazipur
519
149
IPP
Gas/FO
December, 2014
11 Bhairab, Kishorgonj 50 MW PP
50
IPP
FO
December, 2014
12 Satkhira 50 MW PP
50
IPP
FO
December, 2014
135
EGCB
Gas
March, 2015
274
BPDB
Gas
March, 2015
131
BPDB
Gas
March, 2015
200
BPDB
Gas
June, 2015
75
APSCL
Gas
June, 2015
373
APSCL
Gas
June, 2015
150
BPDB
Gas/FO
June, 2015
1338
200
BPDB
Gas
September, 2015
126
BPDB
Gas
December, 2015
74
BPDB
Gas
December, 2015
75
BPDB
Gas/FO
December, 2015
509
1028
1988
11
475
1813
Capacity
(MW)
Ownership
Type of
Fuel
Expected
Commissioning
Date
IPP
Solar
January, 2015
PQ Invitation soon.
222
IPP
Gas
January, 2015
249
100
578
IPP
IPP
Gas/ HSD
Wind
March, 2015
March, 2015
73
IPP
Gas
September, 2015
119
IPP
Gas
October, 2015
118
IPP
Gas/ HSD
Deceber, 2015
Sl.
No
Remarks
Private Sector
1 Solar
nd
nd
Total (2015)
310
888
2701
100
BPDB
Gas
March, 2016
250
BPDB
Coal
March, 2016
360
NWPGC
Gas
May, 2016
PQ invited on : 04.12.2012
PQSubmission : 21.01.2013
100
BPDB
Gas
June, 2016
APSCL
Gas
July, 2016
283
IPP
Imp. Coal
March, 2016
283
IPP
Imp. Coal
March, 2016
222
IPP
Gas
March, 2016
522
IPP
Imp. Coal
July, 2016
225
IPP
LNG
October, 2016
119
IPP
Gas
December, 2016
810
450
Finance: JICA
450
1260
Private Sector
Chittagong 150-300 MW Coal
Fired Power Project
Khulna 150-300 MW Coal Fired
2
Power Project
1
st
788
st
Total (2016)
866
1654
2914
0
750
BPDB
Gas
September, 2017
Preliminary works
1200
BPDB
Imp. Coal
September, 2017
Preliminary works
PPP (Joint
Vent.) / IPP
Imp. Coal
June, 2017
1950
1950
Private Sector
1 Khulna 1300 MW Large Coal
1300
1300
Total (2017)
1300
3250
Sl.
No
Capacity
(MW)
Ownership
Type of
Fuel
Expected
Commissioning
Date
2014
(MW)
960
1028
1988
2015
(MW)
1813
888
2701
2016
(MW)
1260
1654
2914
2017
(MW)
1950
1300
3250
Total
(MW)
6645
6265
12910
2014
(MW)
889
1864
2753
2015
(MW)
1773
1087
2860
2016
(MW)
1285
1098
2383
2017
(MW)
450
2166
2616
2018
(MW)
1950
0
1950
Remarks
Summary:
Calender
Year
Public
Private
Total
2013
(MW)
662
1395
2057
763
50
813
Total (MW)
7110
6265
13375