Académique Documents
Professionnel Documents
Culture Documents
Fallen branches and outdoor furniture were not being shifted by mower
operators, resulting in untidy grounds.
Over the last winter period heating in barracks often fell below the 15 degrees
overnight minimum.
The non-compliance report cited various reasons for this, but focused on
the failure of coal deliveries from Australia.
Five items were deleted from the Base capital works programme due to a
lack of finance.
One of these items was the planned upgrade to the mediumtemperature hot water system.
The contractor has repeatedly reminded the Base WKS OFFR of the
inefficiencies in the current reticulation system.
Five recent accidents at the main entrance to base have highlighted the danger
faced by both base personnel and contractor staff. Furthermore, the movement
of heavy equipment across SH 446 creates further traffic hazards.
The contractor has quoted for an underground road and rail system to
allow cross traffic and improve traffic flow into and out of the base.
The contract requires the contractor to provide adequate pressure at all fire
hydrants, both on base and in the housing area.
Summary
All issues from the 2000 contract report have been dealt with. Nine issues have
been identified in the draft 2001 report. The most urgent issue is that of water
supply to the base. DLOG advises that new capital bids will be required within
four weeks.
J D Kay
J.D. KAY
W/O
WKS W/O
DTelN: 388-7717
28 Jun 01
Authorities Consulted:
DLOG
Enclosures:
1. NZDF Contract 446/99 Facilities Maintenance of RNZAF Base Dairy Flat
dated 15 Jan 99
2. 2000 Annual Report Contract 446/99 dated 11 Jul 2000
3. 2001 Annual Report Contract 446/99 (draft)
4. Capital Works Programme 2001- RNZAF dated 30 Aug 01
3
File
DOTPOINT BRIEF FOR COL BLOGGS
DOT POINT BRIEF EXAMPLE SUBJECT - DATE
Heading
N.A.ME
RANK
Position
Phone Number
Date