Vous êtes sur la page 1sur 71

CHAPTER-1

INTRODUCTION TO ESTIMATION AND COSTING


Introduction
For all engineering works it is required to know beforehand the probable cost of
construction is known as the Estimated Cost. If the estimated cost is greater than the
money available, then attempts are made to reduce the cost by reducing the work or by
changing the specifications. From this the importance of estimate for engineers may be
understood. In preparing an estimate, the quantities of different items of work are
calculated by simple mensuration method and from these quantities the cost is calculated.
The subject of estimating is simple, nothing much to understand, but knowledge of
drawing is essential. In preparing an estimate one has to go into the details of each item,
big or small, nothing can be left or missed. Estimating makes one through, superficial
work does not do, and one has to go deep into details.
There is no hard and fast rule for finding out the dimensions from the drawings
(plans, elevations, sections, etc.) but for quick certain principles may be followed. An
estimator should picture the object (Building, structure, etc.) in his mind from the study
of drawings and specifications.
Our building is a G+3 Residential building located at Kukatpally Housing Board
colony, phase IV, Hyderabad, 500072. Its land area is up to 260.13 sq.m., where it has
got all the facilities like easy transport and scarce water. It is a place where the promoter
can make a good amount of profit for his construction of work. The soil strength is good
enough so that we don't have to go for deep foundations.
We need to estimate the cost which is going to be incurred while during the
construction of this building. In order to estimate the cost of a building we need to
segregate the building into various item of work and to quantify it.

Objective
Objective is to quantify and arrive the cost of the project with minimum profit which is
going to be incurred by the promoter for the construction of G+3 Residential building.
1

1.1 Definition of estimating


Estimating is the technique of calculating or computing the various quantities and
the expected Expenditure to be incurred on a particular work or project.
In case the funds available are less than the estimated cost the work is done in part
or by reducing it or specifications are altered, the following requirement are necessary for
preparing an estimate.
a) Drawings like plan, elevation and sections of important points.
b) Detailed specifications about workmanship & properties of materials etc.
c) Standard schedule of rates of the current year.

1.2 Need for estimation


1. Estimate gives an idea of the cost of the work and hence its feasibility can be
determined i.e. whether the project could be taken up with in the funds available or not.
2. Estimate gives an idea of time required for the completion of the work.
3. Estimate is required to invite the tenders and Quotations and to arrange contract.
4. Estimate is also required to control the expenditure during the execution of work.
5. Estimate decides whether the proposed plan matches the funds available or not.

1.3 Procedure of estimating or method of estimating.


Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate

1.4 Data required to prepare an estimate


1. Drawings i.e. plans, elevations, sections etc.
2. Specifications
3. Rates

1.4.1 Drawings
If the drawings are not clear and without complete dimensions the preparation of
estimation become very difficult. So, it is very essential before preparing an estimate.

1.4.2. Specifications
a) General Specifications: This gives the nature, quality, class and work and materials in
general terms to be used in various parts of wok. It helps no form a general idea of
building.
b) Detailed Specifications: These gives the detailed description of the various items of
work laying down the Quantities and qualities of materials, their proportions, the method
of preparation workmanship and execution of work.

1.4.3. Rates
For preparing the estimate the unit rates of each item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor, etc.

1.5 Lumpsum
While preparing an estimate, it is not possible to work out in detail in case of
petty items. Items other than civil engineering such items are called lumpsum items or
simply L.S.Items.
The following are some of L.S. Items in the estimate.
1. Water supply and sanitary arrangements.
2. Electrical installations like meter, motor, etc.,
3. Architectural features.
4. Contingencies and unforeseen items.

In general, certain percentage on the cost of estimation is allotted for the above
L.S.Items Even if sub estimates prepared or at the end of execution of work, the actual
cost should not exceed the L.S.amounts provided in the main estimate.

1.6 Complete Estimate


Most of the people think that estimate of a structure includes cost of land, cost of
materials and labour. But many other direct and indirect costs included and are shown
below

The complete estimate

Cost of land

P.S & contingencies at 5%

legal expenses

Actual cost Cost of Cost of


Brochorage
of land Surveying verification
and execution
of deeds

cost of structure

Cost of Cost of Consulting Permit fee


materials labour Engineers fee for water,
electricity

cost for
cost for
preparation of
supervision
plan, estimate and
design

Figure 1: Complete Estimate


1.7 Work charged establishment:
During the construction of a project considerable number of skilled supervisors,
work assistance, watch men etc., are employed on temporary basis. The salaries of these
persons are drawn from the L.S. amount allotted towards the work charged establishment.
That is, establishment which is charged directly to work. An L.S.amount of 1 to 2% of
the estimated cost is provided towards the work charged establishment.

CHAPTER-2
MEASUREMENT OF MATERIALS AND WORKS

2.1 Units of measurements


The units of measurements are mainly categorized for their nature, shape and size
and for making payments to the contractor and also. The principle of units of
measurements normally consists the following:
a) Single units work like doors, windows, trusses the etc., are expressed in numbers.
b) Works consists linear measurements involve length like cornice, fencing, hand rail,
bands of
specified width etc., are expressed in (RM)
c) Works consists areal surface measurements involve area like plastering, white
washing,
partitions of specified thickness etc., are expressed in square meters (m2)
d) Works consists cubical contents which involve volume like earthwork, cement
concrete,
Masonry etc are expressed in Cubic meters.

Table 1: Units of Measurement


S.No
1

Particulars of items
Earth work:
1. Earth work in Excavation
2. Earthwork in filling in foundation
trenches
3. Earth work in filling in plinth
Concrete:
1. Lime concrete in foundation
2. Cement concrete in Lintels
3. R.C.C.in slab
4. C.C. or R.C.C. Chujja, Sunshade
5. L.C. in roof terracing
(thickness specified)
6. Cement concrete bed
7. R.C. Sunshade (Specified
Width & Height)

Damp Proof Course (D.P.C):


(Thickness should be mentioned)

Brick work:
1. Brickwork in foundation
2. Brick work in plinth
3. Brick work in super structure
4. Thin partition walls
5. Brick work in arches
6. Reinforced brick work
(R.B.Work)

Stone Work:
Stone masonry
Wood work:
1. Doors and windows frames
or chowkhats, rafters & beams
2. Shutters of doors and windows
(thickness specified)
3. Doors and windows fittings (like hinges,
tower bolts, sliding bolts, handles)

Units of
measurement

Units of
payment

cum

Per%cum

cum
cum

Per%cum
Per%cum

cum
cum
cum
cum

percum
percum
percum
percum

sqm
cum

persqm
per cum

cum

1rm

sqm

persqm

cum
cum
cum
sqm
cum
cum

per cum
per cum
per cum
per cum
per cum
per cum

cum

per cum

cum

per cum

sqm

per sqm

Nos.

per Nos.

Steel work
1. Steel reinforcement bars etc in R.C.C.
and R.B.work.
2. Bending, binding of steel Reinforcement
3. Rivets, bolts, & nuts, Anchor bolts, Lewis
bolts, Holding down bolts.
4. Iron hold fasts
5. Iron railing (height and types specified)
6. Iron grills

Quintal
Quintal

per quintal
per quintal

Quintal
Quintal
Quintal
Sqm

per quintal
per quintal
per quintal
per sqm

cum

per cum

sqm
sqm
sqm

per sqm
per sqm
per sqm

sqm
sqm

per sqm
per sqm

sqm

per sqm

sqm
sqm

per sqm
per sqm

Flooring:
1. 25mm cement concrete over 75mm lime
concrete floor (including L.C.)
2. 25mm or 40mm C.C. floor
3. Doors and window sills (C.C. or cement
mortar plain)

sqm
sqm

per sqm
per sqm

sqm

per sqm

11

Rain water pipe /Plain pipe

1RM

per RM

12

Steel wooden trusses

1No

per 1No

13

Glass panels(supply)

sqm

per sqm

14

Fixing of glass panels or Cleaning

Nos.

per Nos.

10

Roofing
1. R.C.C. and R.B.Slab roof
(excluding steel)
2. L.C. roof over and inclusive of tiles or
brick or stone slab etc (thickness specified)
3. Centering and shuttering form work
4. A.C.Sheet roofing
Plastering, points finishing
1. Plastering-Cement or Lime
Mortar (thickness and proportion specified)
2. Pointing
3. White washing, colour washing, cement
wash (number of coats specified)
4. Distempering (number of coats specified)
5.Painting, varnishing(no of coats specified)

2.2 Rules for measurement


The rules for measurement of each item are invariably described in IS- 1200.
However some of the general rules are listed below.
1. Measurement shall be made for finished item of work and description of each item
shall include materials, transport, labour, fabrication tools and plant and all types of
overheads for finishing the work in required shape, size and specification.
2. In booking, the order shall be in sequence of length, breadth and height or thickness.
3. All works shall be measured subject to the following tolerances.
i) Linear measurement shall be measured to the nearest 0.01m.
ii) Areas shall be measured to the nearest 0.01 sq.m
iii) Cubic contents shall be worked-out to the nearest 0.01 cum
4. Same type of work under different conditions and nature shall be measured separately
under separate items.
5. The bill of quantities shall fully describe the materials, proportions, workmanships and
accurately represent the work to be executed.
6. In case of masonry (stone or brick) or structural concrete, the categories shall be
measured separately and the heights shall be described:
a) From foundation to plinth level
b) From plinth level to first floor level
c) From First floor to second floor level and so on.

2.3 Methods of taking out quantities


The quantities like earth work, foundation concrete, brickwork in plinth and super
structure etc., can be workout by any of following two methods:
2.3.1 Long wall - short wall method
2.3.2 Centre line method.
2.3.3Partly centre line and short wall method.

2.3.1 Long wall-short wall method


In this method, the wall along the length of room is considered to be long wall
while the wall perpendicular to long wall is said to be short wall. To get the length of
8

long wall or short wall, calculate first the centre line lengths of individual walls. Then the
length of long wall, (out to out) may be calculated after adding half breadth at each end to
its centre line length. Thus the length of short wall measured into in and may be found by
deducting half breadth from its centre line length at each end. The length of long wall
usually decreases from earth work to brick work in super structure while the short wall
increases. These lengths are multiplied by breadth and depth to get quantities.

2.3.2 Centre line method


This method is suitable for walls of similar cross sections. Here the total centre
line length is multiplied by breadth and depth of respective item to get the total quantity
at a time. When cross walls or partitions or verandah walls join with main wall, the centre
line length gets reduced by half of breadth for each junction. Such junction or joints are
studied carefully while calculating total centre line length .The estimates prepared by this
method are most accurate and quick.

2.3.3 Partly centre line and partly cross wall method


This method is adopted when external (i.e., all-round the building) wall is of one
thickness and the internal walls having different thicknesses. In such cases, centre line
method is applied to external walls and long wall-short wall method is used to internal
walls. This method suits for different thicknesses walls and different level of foundations.
Because of this reason, all Engineering departments are practicing this method.

CHAPTER-3
TYPES OF ESTIMATES

3.1 Detailed estimate


The preparation of detailed estimate consists of working out quantities of various
items of work and then determines the cost of each item. This is prepared in two stages.

i) Details of measurements and calculation of quantities


The complete work is divided into various items of work such as earthwork
concreting, brick work, R.C.C. Plastering etc. The details of measurements are taken
from drawings and entered in respective columns of prescribed Performa. The quantities
are calculated by multiplying the values that are in numbers Column to Depth column as
shown below:

Table 2: Details of measurements form:

S.No

Description

Nos.

Length

Breadth

Depth/

(L)

(B)

Height

(D/H) m

of Item

Quantity

Explanatory
Notes

ii) Abstract of Estimated Cost


The cost of each item of work is worked out from the quantities that already
computed in the details measurement form at workable rate. But the total cost is worked
out in the prescribed form is known as abstract of estimated form.4%of estimated Cost is
allowed for Petty Supervision, contingencies and Unforeseen items.
10

Table 3: Abstract Estimate Form:

Item
No.

Description/
Particulars

Quantity

Unit

Rate

Per
(Unit)

Amount

The detailed estimate should accompanied with


i) Report
ii) Specification
iii) Drawings (plans, elevation, sections)
iv) Design charts and calculations
v) Standard schedule of rates.
3.1.1. Factors to be considered While Preparing Detailed Estimate:
i) Quantity and transportation of materials: For bigger project, the requirement of
materials is more. Such bulk volume of materials will be purchased and transported
definitely at cheaper rate.
ii) Location of site: The site of work is selected, such that it should reduce damage or in
transit during loading, unloading, stocking of materials.
iii) Local labour charges: The skill, suitability and wages of local laborers are
considered while preparing the detailed estimate.

3.2 Data
The process of working out the cost or rate per unit of each item is called as Data.
In preparation of Data, the rates of materials and labour are obtained from current
standard scheduled of rates and while the quantities of materials and labour required for
one unit of item are taken from Standard Data Book (S.D.B)

11

3.2.1 Fixing of Rate per Unit of an Item:


The rate per unit of an item includes the following:
i) Quantity of materials & cost: The requirements of materials are taken strictly in
accordance with standard data book (S.D.B). The cost of these includes first cost, freight,
insurance and transportation charges.
ii) Cost of labour: The exact number of labourers required for unit of work and the
multiplied by the wages/ day to get of labour for unit item work.
iii) Cost of equipment (T&P): Some works need special type of equipment, tools and
plant. In such case, an amount of 1 to 2% of estimated cost is provided.
iv) Overhead charges: To meet expenses of office rent, depreciation of equipment
salaries of staff postage, lighting an amount of 4% of estimate cost is allocated.

3.3 Methods of preparation of approximate estimate


Preliminary or approximate estimate is required for studies of various aspects of
work of project and for its administrative approval. It can decide, in case of commercial
projects, whether the net income earned justifies the amount invested or not. The
approximate estimate is prepared from the practical knowledge and cost of similar works.
The estimate is accompanied by a report duly explaining necessity and utility of the
project and with a site or layout plan. A percentage 5 to 10% is allowed for
contingencies. The following are the methods used for preparation of approximate
estimates.
3.3.1 Plinth area method
3.3.2 Cubical contents methods
3.3.3 Unit base method.

3.3.1 Plinth area method:


The cost of construction is determined by multiplying plinth area with plinth area
rate. The area is obtained by multiplying length and breadth (outer dimensions of
building). In fixing the plinth area rate, careful observation and necessary enquiries are
made in respect of quality and quantity aspect of materials and labour, type of foundation,
height of building, roof, wood work, fixtures, number of storeys etc.,
12

As per IS 3861-1966, the following areas include while calculating the plinth area of
building.
a) Area of walls at floor level.
b) Internal shafts of sanitary installations not exceeding 2.0m2, lifts, air-conditioning
ducts etc.,
c) Area of barsati at terrace level: Barsati means any covered space open on one side
constructed on one side constructed on terraced roof which is used as shelter during rainy
season.
d) Porches of non cantilever type.
Areas which are not to include
a) Area of lofts.
b) Unenclosed balconies.
c) Architectural bands, cornices etc.,
d) Domes, towers projecting above terrace level.
e) Box louvers and vertical sun breakers.

3.3.2 Cubical Contents Method:


This method is generally used for multistoried buildings. It is more accurate that
the other two methods viz., plinth area method and unit base method. The cost of a
structure is calculated approximately as the total cubical contents (Volume of buildings)
multiplied by Local Cubic Rate. The volume of building is obtained by Length x breadth
x depth or height. The length and breadth are measured out to out of walls excluding the
plinth off set. The cost of string course, cornice, corbelling etc., is neglected.
The cost of building= volume of buildings x rate/ unit volume.

3.3.3 Unit Base Method:


According to this method the cost of structure is determined by multiplying the
total number of units with unit rate of each item. In case schools and colleges, the unit
considered to be as 'one student' and in case of hospital, the unit is 'one bed'. the unit rate
is calculated by dividing the actual expenditure incurred or cost of similar building in the
nearby locality by the number of units.
13

CHAPTER-4
MAIN ITEMS OF WORK
4.1 Earthwork
Earthwork in excavation and Earthwork in filling are taken out separately under
different items, and quantities are calculated in cu m. Foundation trenches are usually dug
to the exact width of foundation with vertical sides. Earth in excavation in foundation is
calculated by taking the dimensions of each trench length x breadth x depth. Filling in
trenches after the construction of masonry is ordinarily neglected. If the trench filling is
accounted, this may be calculated by deducting the masonry from the excavation.
Earthwork in plinth filling is calculated by taking by taking the internal
dimensions in between plinth wall (length x breadth) which are usually less than the
internal dimensions of the room by two off-sets of plinth wall i.e. 10 cm (4.5) and height
is taken after deducting the thickness of concrete in floor, usually 7.5cm (3). If sand
filling is done in plinth, this should be taken separately. The length and breadth for each
filling may be same as the internal dimensions of the room if there is no off-set in plinth
wall.
Excavated earth is used in trench filling and plinth filling and usually not paid for
separately, but may also be included under a separate item Return fill and ram or
backfill and paid at a lesser rate .Extra earth if required for filling is brought from
outside. If there is surplus earth after trench and plinth filling, this may be utilized in
leveling and dressing of site or carted away and removed.

4.2 Concrete In Foundation


The concrete is taken out in cu m by length x breadth x thickness. The length and
breadth of foundation concrete are usually the same as for excavation, only the depth or
thickness differs. The thickness of concrete varies from 20 cm to 45 cm, usually 30 cm
(9 to 18, usually 12). Foundation concrete consists of lime concrete or weak cement
concrete.

14

PCC Plain Cement Concrete:


After the process of excavation, laying of plain cement concrete that is PCC is
done. A layer of 100mm was made in such a manner that it was not mixed with the soil.
It provides a solid base for the foundation and a mix of 1:4:8 that is, 1 part of cement to 4
parts of fine aggregates and 8 parts of coarse aggregates by volume were used in it. Plain
concrete is vibrated to achieve full compaction.
Concrete placed below ground should be protected from falling earth during and
after placing.
Concrete placed in ground containing deleterious substances should be kept free
from contact with such a ground and with water draining there from during placing and
for a period of seven days.

Figure 2: P.C.C

4.3 Soling
When the soil is soft or bad, one layer of dry brick or stone soling is applied
below the foundation concrete. The soling layer is computed in sq m (Length x Breadth)
specifying the thickness.

4.4 Damp Proof Course


D.P.C. usually of 2.5 cm (1) thick rich cement concrete 1:1.5:3 or 2 cm, (3/4)
thick rich cement mortar 1:2, mixed with standard waterproofing material, is provided at
the plinth level to full width of plinth wall , and the quantities are computed in sq m,
(Length x Breadth). Usually D.P.C. is not provided at the sills of doors veranda openings,
for which deductions are made. (One kg of Cem-seal or impermo or other standard
waterproofing compound per bag of cement is generally used).

15

4.5 Masonry
Masonry is computed in cu m (Length x Breadth x Height). Foundation and plinth
masonry is taken under one item, and masonry in superstructure is taken under a separate
item. In storied building the masonry in each story as ground floor above plinth level,
first floor, etc. is computed separately. In taking out quantities the walls are measured as
solid and then deductions are made for openings as doors, windows, etc. and such other
portions as necessary. Masonry of different types or classes, masonry with different
mortar, etc. are taken out under separate items.

4.6 Lintels Over Openings


Lintels are made of R.C.C or R.B., quantities are calculated in cu.m. Length of the
lintel is equal to the clear span plus two bearings. If dimension of bearings are not given
the bearing may be taken as same as the thickness of lintel with a minimum of 12cm
(4.5).

4.7 R.C.C and R.B. work


R.C.C and R.B work may be in roof or floor slab, in beams, lintels, columns,
foundations, etc. and the quantities are calculated in cu m. Length, breadth and thickness
are found correctly from the plan, elevation, and section or from other detailed drawings.
Bearings are added with the clear span to get the dimensions. The quantities are
calculated in cu m exclusive of steel reinforcement and its being but inclusive of
centering and shuttering and fixing and binding reinforcement in position. The
reinforcement including its taken up separately under steel, if other details are not given.
The volume of steel is not required to be deducted from the R.C.C. or R.B.
Columns:
Columns are the vertical members which are used to transfer the loads from the
roof beams to the footings. Based on the loads different sizes of columns are designed.
The various sizes of columns are used in our site those are 750x400, 400x600, 250x900,
230x300mm etc.

16

Roof Beams:
Roof beams are horizontal members which transfers the loads from the slab to
columns. Based on the loads different sizes of roof beams are designed. The various
sizes of roof beams are used in our site those are 400x600, 400x750, 250x750mm etc.
Slabs:
Slab covers over roof beams which can take the live loads and transfers it to the
roof beams.
Generally the slabs are divided into two categories. When the ratio of long span
to short span is greater or equal to 2 then the slab is known as single way slab, when the
ratio of long span to short span is less than 2 then the slab is known as two way slabs.

R.C.C and R.B. work may also be estimated inclusive of steel and centering and
shuttering for the complete works, if specified.
Centering and shuttering (from work) are usually included in the R.C.C or R.B.
work, but may also be taken separately in sq m of surface in contact with concrete.
In R.C.C work plastering is not taken separately, but the exposed surface are
finished with thin rich cement sand mortar plastering to give smooth and even surface ,
which usually is not taken into consideration.
Reinforcement:
Steel reinforcements are used, generally, in the form of bars of circular cross
section in concrete structure. They are like a skeleton in human body. Plain concrete
without steel or any other reinforcement is strong in compression but weak in tension.
Steel is one of the best forms of reinforcements, to take care of those stresses and to
strengthen concrete to bear all kinds of loads. Grade Fe 415 is being used most
commonly nowadays. This has limited the use of plain mild steel bars because of higher
yield

stress and bond strength resulting in saving of steel quantity. Some companies

have brought Thermo Mechanically Treated (TMT) and Corrosion Resistant Steel (CRS)
bars with added features. Among these types we used TMT bars in our construction.
17

Figure 3: Slab Reinforcement

Terms Used In Reinforcement:


Bar-bending-schedule
Bar-bending-schedule is the schedule of reinforcement bars prepared in
advance before cutting and bending of bars. This schedule contains all details of size,
shape and dimension of bars to be cut.
Lap length

Figure 4: Lap Joint


Lap length is the length overlap of bars tied to extend the reinforcement
length. Lap length is about 50 times the diameter of the bar is considered safe. Laps of
neighboring bar lengths should be staggered and should not be provided at one level/line.
18

At one cross section, a maximum of 50% bars should be lapped. In case, required lap
length is not available at junction because of space and other constraints, bars can be
joined with couplers or welded (with correct choice of method of welding).

Anchorage Length
This is the additional length of steel of one structure required to be inserted
in other at the junction. For example, main bars of beam in column at beam column
junction, column bars in footing etc. The length requirement is similar to the lap length
mentioned in previous question or as per the design instructions

Figure 5: Anchorage
Cover Block
Cover blocks are placed to prevent the steel rods from touching the
shuttering plates and thereby providing a minimum cover and fix the reinforcements as
per the design drawings.

The cover blocks used for different individuals are:


Footings

40mm

Beams

25mm

Columns

40mm

Retaining wall

25mm for earth face

Slabs

15mm

20mm for other face


19

Figure 6: Cover Block

4.8 Flooring and Roofing


(i) Ground Floor The base lime concrete and floor finishing of C.C. or stone or
Marble or Mosaic, etc. are usually taken as one job or one item (combined in one item)
and the quantity is calculated in sq m multiplying the length and breadth. The length and
breadth are measured as inside dimensions of wall to wall of superstructure. Both the
works of base concrete and floor finishing are paid under one item.
(ii) First floor, Second floor, etc. Supporting super structure is taken separately
is cu.m. as R.C.C., R.B. etc.. and the floor finishing is taken separately in sq m as 2.5 cm
or 4 cm C.C. (Cement Concrete) or marble or Mosaic, etc. if a cushioning layer of lime
concrete is given in between the slab and the floor, the cushioning concrete may be
measured with the floor under one item or taken separately.
(iii) Roof Supporting structure is taken separately in cu.m and the lime concrete
terracing is computed in sq. M with thickness specified, under a separate item including
surface rendering smooth. The compacted thickness of lime concrete terracing is 7.5 cm
to 12 cm. L.C. terracing may also be calculated in cu m with average thickness.

4.9 Plastering and Pointing


Plastering usually 12mm (0.5) thick is calculated in sq m. For walls the
measurements are taken for the whole face of the wall for both sides as solid, and
deductions for openings are made. Plastering of ceiling of 12mm thick is computed in sq
20

m under a separate head as this work is done with rich cement mortar. For R.C.C work
usually no plastering is allowed but for fair finish a thin plaster of rich cement mortar
may be allowed which should not be taken in the measurement separately.
Pointing Pointing in walls is calculated in sq m for whole surface and deductions
similar to plastering are made.

4.10 Columns
Columns are the vertical members which are used to transfer the loads from the
roof beams to the footings. Based on the loads different sizes of columns are designed.
The various sizes of columns are used in our site those are 750x400, 400x600, 250x900,
230x300mm etc.

4.11 Doors and Windows Wood Work- Chowkhat or Frame


Door and window frames or Chowkhats are computed in cu.m. Length is obtained
by adding all the members of the chowkhat, top and two verticals if there is no sill
member, and adding bottom also if there is sill, and the length is multiplied by the two
dimensions of the cross section of the member.

4.12 White washing or Colour Washing or Distempering and Painting


The quantities are computed in sq m and are usually same as for plastering. The
inside is usually white washed or distempered and this item will be same as for inside
plaster. The outside is colour washed and the quantities of colour washing will be same as
for the outside plaster. Number of coats of white washing or colour washing is taken as
one job or work and the rates cover for number of coats which should not be multiplying
factor. The number of coats should be mentioned in the item. Deductions are dealt in the
same manner as for plastering.
Painting or Varnishing of doors and windows are computed in sq m, the
dimensions should be taken for outer dimensions of the chowkhat i.e., outer dimensions
of doors and windows. The area is measure flat. No separate measurement is taken for the
chowkhat, the area is same as the area of opening.
21

The methods of measurement of white washing, colour washing, distempering


and painting of building surfaces in civil engineering works.

The following rules are to be followed:


1 Clubbing of Items
Items may be clubbed together provided these are on the basis of detailed
description of item, stated in this standard.
2 Booking of Dimensions
In booking of dimensions the order shall be consistent and generally in the
sequence of length, breadth or width and height.
3 Descriptions of Items
Description of each item shall unless otherwise stated, be held to include, where
necessary, conveyance; delivery; handling; unloading; storing; waste; return of packings;
necessary scaffolding; protective cover; and cleaning stains from floors, walls, glass
panes, etc.
4 Bills of Quantities
Item of work shall fully describe materials and workmanship, and accurately
represent the work to be executed.
5 Numbers of Coats
Decorative treatment shall be fully described stating the number of coats in each
case.
6 Preparatory Works
Preparatory work, such as brooming down, steel wire brushing, scrapping
washing and rubbing down, shall be described and included in the main item. Preparatory
work on new surfaces and primary coats, if any, shall be described and included in the
main item.
7 Classifications
Various decorative treatments shall be measured separately under the various
classifications as given below and materials and type of surfaces to be treated shall be
fully described:

22

a) Whitewash, colour wash, etc;


b) Non-washable distemper;
c) Washable distemper;
d) Waterproof paint (colour/colourless);
e) Chalk whiting to cloth or hessian surface;
f) Linseed oil and cement to steel and iron work; and
g) Cement slurry wash.
Priming and alkali neutralizing treatments, scrapping of surface, washing surfaces
spoilt by smoke soot, removal of oil and grease spots, treatment for disinfection with
efflorescence, moulds moss, fungi, algae and kitchen shall be measured separately and
materials described.
8 Walls, Ceilings, etc.
Work on walls, ceilings and sloping roofs shall each be measured separately.
9 Old Treated Surfaces
Work on old treated surfaces shall be measured separately and so described.

4.13 Lump-sum Item


Sometimes a lump-sum rate is provided for certain small items for which detailed
quantities cannot be taken out easily or it takes sufficient time to find the detail, as front
architectural or decoration work of a building, fire-place, site cleaning and dressing etc.

4.14 Electrification, Sanitary and Water supply Works


For Sanitary and Water supply works 8% and for electrification 8% of the
estimated cost of the building works are usually provided in estimate.

23

CHAPTER-5
RATE ANALYSIS

5.1 Definition
In order to determine the rate of a particular item, the factors affecting the rate of
that item are studied carefully and then finally, a rate is decided for that item.This process
of determining the rate of an item is termed as the analysis of rate or rate analysis.

5.2 Purposes of rate analysis


Following are the two main purposes of carrying out the rate analysis of an item :
1. To determine the actual cost per unit of item ; and
2. To examine the item for economic processes and economic uses of materials
involved in making the item.

5.3 Factors affecting Rate Analysis


The factors which affect the rare analysis of an item can broadly be divided into the
following two categories.
1. Major factors
2. Minor factors

1.

Major factors : There are mainly two factors on which the rate of an item
depends namely.

i)

Materials

ii)

Labour
Hence, in ordinary procedure of rate analysis, only these two forces are taken into

account and the rate of an item is derived. The points to be remembered for these two
factors will now be briefly mentioned.

24

Materials :The quantities of various materials required for the construction of an item
can be easily worked out by knowing the specification of that item.The prices of various
materials required are fixed. But their prices are variable from place to place and from
time to time as they depend on the prevailing market conditions. Hence, before starting
the rate analysis of an item, it is essential to collect the prices of such materials from the
market at that instant.
It is the duty of the person framing the rate analysis to see that the materials available in
the market are in accordance with the specification of the item. It is also necessary to
include a certain percentage for waste of all materials to cover breakages, losses, cutting
waste, etc .However , the average percentage to be adopted for wastage will vary for
different trades and operations. With the help of the quantities of various materials and
prices of the materials, the cost of materials for a particular item can be calculated.
Labour: The labour force will be necessary to arrange the materials in a proper way so
that the item can be completed. For instance, heaps of bricks, cement and sand cannot be
used in the construction of brickwall, unless some masons, coolies and bhisties are
available. The amount of labour force required to carry out a unit of a particular item is
decided from the past experience or in case of a complicated item, it is decided by
carrying out a sample of that item. In any case , it is quite clear that the labour force
required will depend on the efficiency of the labourers and hence, this force will be
variable from place to place also, the price or wage of labour is a variable factor and will
vary from place to place, person to person and time to time.Hence the efficiency of the
labourer and the wage of the labourer should be properly studied before starting the rate
analysis for a particular item, By knowing the amount of labour force and the wage of
labourer, the cost of labour of a particular item is calculated.
2) Minor factors: These are the factors which come into force under special
circumstances and should, therefore, be given proper weight, when such conditions are to
exist following are some of such factors.

25

i) Special equipment : If the execution of an item requires the use of some special
equipment or plant, the cost of using such special equipment on the rental basis should be
included in the rate analysis of that item.
ii) Place of work : The site of work will also have some effect on the rate of an item
under certain conditions. If it is too far, more amount will have to be spent on carting
similarly, if it is situated in a highly congested area, it will not be possible to take the
materials directly to the site. The materials will have to be stacked on the main road and
then they will have to be taken in hand lorries. This will increase the cost of transport of
the materials and consequently, the rates of the items are to be modified.
iii) Nature of work : If the work consist of large quantities of the items , the rates may be
less and vice versa.
iv) Conditions of contract : If the conditions of contract are very stiff, the rates of the
various items will be high and vice versa.
v) Profit of the contractor : The usual percentage of the profit of the contractor is ten.
But if it is more or less, the rate of the item will be correspondingly affected. The profit
of the contractor will includes his overhead charges also. These overhead charges are to
be reasonably ascertained and suitably allocated to various jobs carried out concurrently
by the contractor. The overhead expences can broadly be divided into two categories.

a) Expenses relating to the works such as expenses incurred for tools, testing , supervision ,
insurance , amenities at site, power, plant , stores , etc.
b) Expenses relating to the office establishment such as expenses incurred for postage , rent
, travelling, satisfactory, taxes, telephone, etc.
vi) Specifications :If the specifications of work provide for rigid type tolerances and
superior quality turn out, the rates will be on the higher side.
vii) Site conditions : If the site conditions are such that difficulties will be experienced
during execution of work, such as foundations involving water troubles, the rates will be
on the higher side, on the other hand, if site conditions are ideally suited for the
construction activities, the contractor may quote slightly lower rates .
26

viii) Miscellaneous : The other remaining miscellaneous factors affecting rates of items
include time of completion of the project, climatic conditions , reproduction of the
contracting firm, discipline of the organization , etc.
From the above discussion, it is clear that the accuracy of rate analysis will depend on the
skill, knowledge, experience, precision and judgement of the person entrusted with the
work of rate analysis.

5.4 Importance of Rate Analysis


The process of rate analysis gives a clear picture of various forces acting behind
the performance of a particular item. It should be remembered that the rate analysis of
any item is never complete, for instance, in the rate analysis of brickwork, a definite rate
for bricks is assumed. But this rate for bricks is derived by the manufacturer of bricks by
his own rate analysis for preparing bricks. Thus, theoretically, the rate analysis of an item
is incomplete, but in practice, it serves as a useful guide to arrive at a reasonable rate for
a particular item.

5.5 Essentials of Rate Analysis


For arriving t the correct rate analysis of a particular item, the following essentials are
necessary for the person carrying out the rate analysis.
1) Good knowledge of construction work and familiarity with the trade.
2) Information regarding costs of materials, labour and equipment and
3) Output of labourer i.e. task works per day for various trades.

5.6 Schedule of Rates


A schedule or list of rates of various items is prepared after the analysis of rates of
these items. Such a document is known as the schedule of rates or S.O.R. It is prepared
by large concerns or public bodies. It becomes very useful, especially deciding the rate
of an extra item, carried out by the contractor.

27

Normally, a clause in the conditions of contract is inserted, stating that , any extra
item that might occur during the execution of the work shall be paid as per rate in the
schedule of rates.
In some cases, the contractor may be asked to submit his tender by simply quoting
the percentage above or below the S.O.R for carrying out the construction work.
The schedule of rates consists of groups of items such as demolishing items,
excavation items, concrete items, brickwork items, etc. and also information, regarding
the present wages of labour and prices of different items , is given in it.
As the rates of items mentioned in the schedule of rates are likely to vary, the
schedule of rates is periodically revised, usually after three years.
The Central Public Works Department ( CPWD ) if the premier construction
organisation of the Govt.of India and it has been responsible for the planning and design,
construction and maintenance of a variety of building projects like mass housing
complexes, hospitals, educational institutions , sport complexes, highways, airports,
industrial buildings, bridges, etc. Hence, the schedule of rates serves as an important
document for the CPWD.
The CPWD schedule of rates contains the basic rates of materials, labour,
Carriage etc. of about 2500 items and the finished rates of about 3000 items of work
covered under different subheads like building work, road work, water supply and
drainage items etc. The rates of the finished items are worked out by the analysis of rates
with the standard requirements of material, labour and necessary sundries like water
charges, contractors profit, etc.
Due to continuous changes in the market rates of materials, wages of labour, cost
of carriage ,etc. the schedule of rates document requires revision frequently. The updating
of this document manually proved to be extremely difficult task, as it involved careful
analysis and thorough checking of several of items in the schedule. The use of computers
was found to be an ideal solution in the preparation and quick updating of this document
in minimum possible time without any chance of human errors.
28

The CPWD has evolved the coding procedure and file organization of the
computer programme for the schedule of rates document. This is an important step in the
modernisation of the public work system and perhaps,

the CPWD is the first

organization to take this measure in the country. It is likely that in future, an integrated
package of an easily updatable all India schedule of rates can be developed and it will
serve as an important national document useful for all the construction agencies in the
country.

29

CHAPTER-6
ANALYSIS

PLANS
&
DRAWINGS

30

31

32

33

34

QUANTITY ESTIMATION
6.2.1. Foundations
a)Footing1:
Details of the Foundation 1:
Footing Size: 5'6"X 5' X 12"
Total Number: 4
Note: As per IS1200, Any footing must have a buffer of 600mm extra on either side from
the face of the footing.
Table 6.2.1.1 detailed estimation of foundation 1
S.No.

Item
Description

Length

(m)
5'6"+2(0.
6)
=2.88
6'0"
= 1.83

Earthwork
Excavation

P.C.C
(1:4:8)
R.C.C work
a)In Footing1 5'6"
= 1.68
b)In
Column1
21"
Until ground = 0.53
surface

Breadth

(m)
5'+2(0.6)
=2.72

Height
Or
Thickness
(m)
5'0"
=1.52

5'6"
= 1.68

6"
= 0.15

5'
= 1.52

12"
= 0.3

0.77

9"
= 0.23

3'6"
= 1.07

0.13

Total R.C.C.

0.90

Earth work refilling= Earth work excavation-(R.C.C+P.C.C)


=11.91-0.90-0.46
=10.55m

35

Quantity

Remarks

(m)
11.91

0.46

H= 5'-6"-12"
= 3'6"

In Footing1:
Table 6.2.1.2 final quantities of foundation 1
Item
Earthwork
Excavation
P.C.C (1:4:8)
R.C.C Work
-In Footing
-In Column (Until
G.S)
Total R.C.C
Earthwork Refilling
Steel
b) Footing2:

For 1 unit
11.91 m3

Total No.
4

Total Quantity
47.64 m3

0.46 m3

1.84 m3

0.77 m3
0.13 m3

4
4

3.08 m3
0.52 m3

0.90 m3
10.55 m3
31.10Kg

4
4
4

3.6m3
42.2 m3
124.40 Kg.

Details of the Footing2:


Footing Size: 6'X 5'6"X 12"
Total Number: 8
Note: As per IS1200, Any footing must have a buffer of 600mm extra on either side from
the face of the footing.
Table 6.2.1.3 detailed estimation of foundation 2
S.No.

1
2
3

Item
Description

Earthwork
Excavation
P.C.C
(1:4:8)
R.C.C
Work
a) In
Footing 1
b) In
Column1
Until
ground
surface

Length

Breadth

(m)
6'+2(0.6)
=3.03
6'6"
=1.98

Height
Or
Thickness
(m)
(m)
5'6"+2(0.6) 5'0"
=2.88
=1.52
6'
6"
=1.83
=0.15

6'
=1.83

5'6"
=1.68

12"
=0.3

Quantity

(m)
13.26
0.54

0.92
H=5'-6"12"=3'6"
0.15

24"
=0.61

9"
=0.23

3'6"
=1.07

Total R.C.C. 1.07


36

Remarks

Earth work refilling= Earth work excavation-(R.C.C+P.C.C)


=13.26-1.07-0.54
=11.65m
In Foundation 2:
Table 6.2.1.4 final quantities of foundation 2
Item
Earthwork
Excavation
P.C.C (1:4:8)
R.C.C Work
-In Footing
-In Column (Until
G.S)
Total R.C.C
Earthwork Refilling
Steel

For 1 unit
13.26 m3

Total No.
8

Total Quantity
106.08 m3

0.54 m3

4.32 m3

0.92m3
0.15 m3

8
8

7.36 m3
1.2 m3

1.07 m3
11.65 m3
38.22Kg.

8
8
8

8.56 m3
93.2 m3
305.76Kg.

Reinforcement for footing :


footing dimensions 5'6'' X 5'

As per standards end cover for


footing = 2

Length of steel along longer


span= length of footing -2 x end
cover + 2 x hooks

L1= 56-2x2+2x9x0.012
= 1.79m
Figure 7: Footing Plan

N0.0f bars = {(length of footing end cover) /centre to centre distance }+1
= (56-2x2)/6 +1 = 11.33 = 12

37

Total length of bar = no. of bars x length of one steel bar =21.48 m
Unit weight of steel = 7850 kg/m
Diameter of the bar = 12mm
Total weight of steel = unit weight of steel x area of the bar x length of the bar
= 7850 x (/4 x 0.012) x 21.48
=19.07 kg
Cost of steel = Rs 40/kg
Total cost of steel in footings = 40 x 19.07
= Rs 768.80
Similar calculations are made for footings in shorter span direction.
Table 6.2.1.5 barbending schedule of footings
S.NO

Description Shape
of item

Column
C1-4 nos
a) longer
direction

Diameter No
( mm)

Length
( m)

Total
length
(m)

Unit
weight

Total
weight
(kg)

(kg/m)

12

40

1.8

72

0.89

64.08

b) shorter
direction
Column
C2-8 nos
a)longer
direction

12

44

1.54

67.76

0.89

60.30

12

88

1.94

170.72

0.89

151.94

b)shorter
Direction

12

96

1.8

172.8

0.89

153.79

Total

430.16

Total quantities in foundation:


Total earthwork excavation

= 47.64+106.08

38

= 153.72 m3
Total quantity of p.c.c (1:4:8) =1.84+4.32
= 6.16 m3
Total Quantity Of R.C.C. = 3.6+8.56
= 12.16 m3
Total Earthwork Refilling = 42.2+93.2
= 135.4 m3
Total Steel Quantity In Footings = 430.16kgs (Excluding Column part)

39

6.2.2 Plinth Beams R.C.C Work


S.No.

Description
of item

Beam 1

Beam 2
2

No.

Length

Width

(m)
55'6''
=16.92

(m)
9''
=0.23

Depth
Or
Height
(m)
12''
=0.3

26'6''
=8.08

9''
=0.23

12''
=0.3

3.35

21''
=0.53

9''
=0.23

12''
=0.3

-0.15

24''
=0.61

9''
=0.23

12''
=0.3

Quantity

Total
quantity

(m)

(m)

2.33

Deductions
at junctions
of beam1&2
At column1

At column 2

( Table -6.2.2.1)

Filling inside
plinth beams
40mm HBG
Metal &
earth filling

15.54

0.8

5.19

94.73
Total

94.73

(Table 6.2.2.2)

Reinforcement in Plinth Beams


S.NO. Description Shape
of item
1
Beam 1
Main bar

7.62

- 0.34
Total

Diameter N0.

Length

Total
length

Unit
weight

Total
quantity

16

17.16

137.28

1.58

216.9

Extra bar

16

10.71

42.84

1.58

67.68

Beam 2
Main bar

16

24

8.32

199.68

1.58

315.5

Extra bar

16

12

7.51

90.12

1.58

142.39

Stirrups

456

1.11

506.16

0.39
Total

197.4
939.87

40

Table 6.2.3.1

6.2.3 Compound Wall


S.NO.

Description NO.
of item

Length

Breadth

(m)

(m)

Height
Quantity
Or depth
(m)
(m)

Total
quantity
(m)

Earth work
excavation
Long wall

21.34

0.8

0.5

17.07

Short wall

10.6

0.8

0.5

8.48
Total

25.55

R.R
masonry
Long wall

20.94

0.4

0.5

8.38

Short wall

11

0.4

0.5

4.4
Total

12.78

Earth work
refilling
Long wall

21.34

0.4

0.5

8.54

Short wall

10.6

0.4

0.5

4.24
Total

12.78

Brick work
Long wall

20.77

0.23

1.5

14.33

Short wall
Deduction
of gate

10.83

0.23

1.5

7.47

0.23

1.5

-1.38
Total

20.42

Plastering
(C.M 1:4)
External

64.34

1.5

96.51

Internal

62.96

1.5

94.44
Total

41

190.95
m

6.2.4 Columns:
a)In columns above ground surface :
Total Height of Column = (No. of Floors * Floor Height) - (No. of beams on column
*beam Thickness)
= (4*3m) - (3*18'')
= 10.63m
From N.G.L. to Plinth top, Height = 12''
Therefore Total Height of Column above G.S or G.L = 10.63+ 12'' =10.93 m
(G.S = Ground Surface)
Table 6.2.4.1 C.C. work in columns
Column
No.
C1
C2

Specification Length
9 X 21
9 X 24

Breadth

Height

Quantity

(m)
(m)
(m)
(m3)
9=0.23m 21=0.53m 10.93m
1.33
9=0.23m 24=0.61m 10.93m
1.53

Therefore, Total Column Concrete Quantity above G.S = 17.56 m3

42

Total
No.

Total
Quantity
(m3)
4
5.32
8
12.24
Total
17.56

b) Reinforcement for columns :


S.No.

Description
Of item

Main bars
upto plinth
level for

Shape

( Table -6.2.4.2 )

Diameter

Nos.

(mm)

a)Column
C1-4 nos
b)Column
C2-8 nos

(m)

Total
Length
(m)

Unit
Weight
(kg/m)

Total
Weight
(kg)

20

24

2.28

54.72

2.46

134.61

16

16

2.13

34.08

1.58

53.84

25

32

2.36

75.52

3.85

290.75

20

48

2.28

109.44

2.47

270.31

40

2.288

91.52

0.39

35.7

80

2.3

184

0.39

71.76

20

24

14.01

336.24

2.47

830.51

16
25

16
32

14.01
14.01

224.16
448.32

1.58
3.85

354.17
1726

20

48

14.01

672.48

2.47

1661

12

352

2.432

856

0.89

761.84

12

352

2.432

856

0.89

761.84

Stirrups
upto plinth
level for
a)column
c1-4 nos
b)column
c2-8 nos
Main bars
from plinth
level to
G+3 for
a)Column
C1-4 nos
b)Column
C2-8 nos

Length

Stirrups
from plinth
level to
G+3 for
column
C1-4 nos
column
C2-8 nos

43

6.2.5 Beams
Table 6.2.5.1 C.C. work in roof beams
S.NO. Description
of item
1
Beam 1

Beam 2

NO.
3

Small beam1
(b/w 5&6)

Small beam1
(b/w 1&2)

Length

Breadth

Height

Quantity Total
quantity

51'
=15.55

9''
=0.23

12''
=0.30

3.21

34'
=10.36

9''
=0.23

12''
=0.30

4.29

10'3''
=3.12

9''
=0.23

12''
=0.30

0.22

11'6''
=3.51

9''
=0.23

12''
=0.3

0.24
Total

C.C work in roof beams for single floor = 7.96 m


for total building = no. of floors X C.C work in single floor
= 4 X 7.96
= 31.84 m

44

7.96

d) Beam Reinforcement Calculation:

Figure 8: Beam Reinforcement


Beam dimension = 139 x 9 x 12
Length of main bar in beam = total length of beam 2* end
cover + 2* hooks
= 139 2*1+ 2* 9* 0.016
=4.43 m
We have 4 bars of this type in one beam so ,
Total length of main bar = 4* 4.43
=17.72 m
Extra bars at ends, length of extra bar

=
= 2*( 13/4 + 9 -1 + 2*9* 0.016)
= 2.96 m
We have 2 extra bars for this beam so,
Total length of extra bars in this beam

= 2* 2.96
= 5.92 m

Total length 16 mm dia bars in this beam

= length of main bar +length of extra bars


= 17.72+5.92
= 23.64 m

45

Unit weight of steel = 7850 kg/m


Area of bar = /4 * 0.016
Total weight of bars = unit weight * area* total length
= 7850 * /4 * 0.016 * 23.64
= 37.31kg

Dimension of stirrup = 20.5 X 7


Total Length of one stirrup = 2*( L+B + hooks )
= 2*(20.5+7-9*0.008)
=1.25m
No. of stirrups = ( length of beam 2*end cover)/center to center distance of stirrups + 1
= ( 139- 2* 1)/ 7 +1
= 24.28
= 25
Total length of all stirrups = no. of stirrups * length of single stirrup = 25 *1.25
=31.25
Unit weight of steel = 7850 kg/m
Area of bar = /4 * 0.008
Weight of stirrups = unit weight * area * total length of stirrups
= 7850 * /4 * 0.008*31.25
=12.33 kg

46

Beam Reinforcement Details


Table 6.2.5.2 bar bending schedule of roof beams
S.No
.

Description of
item

Shape

Diameter

No

(mm)
1

Length
(m)

Total
length
(m)

Unit
weight
(kg/m)

Total
weight
(kg)

BEAM 1
Main bars

16

12

17.92

215.04

1.58

339.76

Extra bars

16

10.71

64.26

1.58

101.53

16

3.82

15.28

1.58

24.14

16

2.55

5.1

1.58

8.06

Main bar

16

3.97

15.88

1.58

25.09

Extra bar

16

2.74

5.48

1.58

8.66

Beam1

288

1.2236

355.97

0.39

138.83

Small beam1
b/w 6&5

21

1.236

25.96

0.39

10.12

Small beam1
b/w 1&2
BEAM 2

23

1.236

28.43

0.39

11.09

Main bar

20

24

10.6

254.4

2.47

628.37

Extra bar

20

12

10.16

121.92

2.47

301.14

SMALL
BEAM 1
(b/w 6&5)
Main bar
Extra bar
SMALL
BEAM 1
(b/w 1&2)

STIRRUPS

STIRRUPS

47

8mm@6''c/c

8mm@7''c/c

264

1.54

406.56

0.39

158.56

264

0.32

84.48

0.39

32.95

138

1.54

212.52

0.39

82.88

138

0.32

44.16

0.39

17.22

Total

1888.4

Total steel required in all beams in single floor = 1888.4 kg


total steel required for beams in building = no. of floors X steel required in each floor
= 4 X 1888.4
=7553.6 kg

48

6.2.6 Slabs
In Ground Floor:
slab dimensions :
Length= 55'6''
Breadth=34'
slab area = total slab area - openings of lift -opening of stair case
total Slab Area =55'6'' X 34' = 175.29 m2
Lift dimensions :
L = 6'
B = 4'6''
Lift Area = 6' X 4'6'' = 2.51 m2
Stair case dimensions
L = 12'6''
B = 6'
Staircase area = 12'6'' X 6' = 6.97 m2
Slab area = 175.29- 2.51 - 6.97 = 165.81
Thickness of the Slab = 4.5
Slab Quantity = 165.81X 4.5 = 18.95 m3
Therefore Ground Floor Slab Quantity = 18.95 m3
For all the floors, Slab Properties are the same and henceforth same quantity
Total Slab Concrete Quantity = 75.8 m3

49

Slab Reinforcement Sample Calculations:


Sample slab dimensions 20 X 11
End cover for slabs 20mm
Along long span
Length of straight bar =length of slab (2* end cover)+ 2*hooks
= 20-(2*0.02)+(2*9*0.008)
=6.2 m Length of cranked bar= length of straight bar +( 0.42*d)* no. of
cranks

= 6.2+( 0.42*0.008*2)
= 6.21 m
No. of bars = (length of slab- 2*end cover )/spacing of bars +1
= (20- 2*0.02)/ 6 +1
= 40.73=41 numbers
Unit weight of steel = 7850 kg/m
Area of bar = /4 *0.008
Total weight of steel = unit weight *area*length
=7850* /4 *0.008 *254.4= 100.4kg

50

i) Slabs Reinforcement Details


table 6.2.6.1 bar bending schedule of slabs
S.No Description
of item
1

Shape

Diameter No.

Length

(mm)

(m)

Total
length
(m)

Unit
weight
(kg/m)

Total
Weight
(kg)

Along
shorter span
1)b/w 1&2
a) straight
bar
b) crancked
bar

16

13

10.46

135.98

1.58

214.85

16

13

10.48

136.24

1.58

215.26

16

13

10.46

135.98

1.58

214.84

16

12

10.47

125.64

1.58

198.51

16

5.05

35.35

1.58

55.85

16

5.06

30.36

1.58

47.97

16

14

10.46

146.44

1.58

231.38

16

14

10.47

146.58

1.58

231.6

16

12

10.46

125.52

1.58

198.32

16

12

10.448

125.76

1.58

198.7

2) b/w 2&3
a) straight
bar
b) crancked
bar
3) b/w 3&4
a) straight
bar
b) crancked
bar
4) b/w 4&5
a) straight
bar
b) crancked
bar
5) b/w 5&6
a) straight
bar
b) crancked
bar

51

Along
longer span
1) b/w
staircase &
lift
a) straight
bar
b) crancked
bar
2) side of
lift
a) straight
bar
b) crancked
bar
3) side of
staircase
a) straight
bar
b) crancked
bar

17

17.4

295.8

0.39

115.36

17

17.44

296.48

0.39

115.63

12

7.65

91.8

0.39

35.8

12

7.67

92.04

0.39

35.9

26

7.65

198.9

0.39

77.57

26

7.67

199.42

0.39

77.77

Total
Total weight of steel in slab for one floor

2265.11

= 2265.11 kg

Total weight of steel required for building in slabs = number of slabs X total weight of
steel in single slab
= 4 X 2265.11
= 9060.44 kg

52

6.2.7 BRICK WORK


Table 6.2.7 - Brick work
S.no.

Description of
item

External walls
(9")
a) long wall
(along beam
B1)
b)short wall
(along beam
B2)
Internal walls
(4'')
a)main bed
room
1)long wall

Nos.

Length

Breadth

(m)

(m)

55'6''
=16.92

Height
Or
depth
(m)

Quantity

Total
quantity

(m)

(m)

9''
=0.23

2.7

21

32'6''
=9.91

9''
=0.23

2.6

23.7

12'10''
=3.91

4"
=0.1

2.7

2.1

11'
=3.35

4''
=0.1

2.6

1.74

12'10''
=3.91

4''
=0.1

2.6

2.03

2)short wall

b)kitchen
1)long wall

2) short wall

7'10.5''
=2.4

4''
=0.1

2.7

2.6

c)Toilet wall

4'
=1.22

4''
=0.1

2.7

1.32

d) Balcony wall

10'
=3.05

4''
=0.1

1.83

e) C.Bed Room
1)long wall

12'7''
=3.81

4''
=0.1

2.7

1.03

2) short wall

10'
=3.05

4''
=0.1

2.6

0.8

53

f) C.Bed Room
1) long wall

11'4''
=3.45

4''
=0.1

2.7

0.93

2)short wall

10'
=3.05

4''
=0.1

2.6

0.8

Total

DEDUCTIONS
DOORS
a) main door

b) door (D)

C) door (D1)

WINDOWS
a) window (W)

b)window (W1)

c)window(W2)

d) kitchen
window (K/W)
5

VENTILATOR
(V)
COLUMNS
a) column (C1)

b) column (C2)

2
2

3'6''
=1

9"
=0.23

6'9''
=2

-0.92

3'
=0.91

4''
=0.1

6'9''
=2

-0.73

2'6''
=0.76

4''
=0.1

6'9''
=2

-1.22

6'
=1.8

9''
=0.23

4'
=1.2

-1

4'
=1.2

4''
=0.1

4'
=1.2

-1.3

3'
=0.9

4''
=0.1

4'
=1.2

-0.11

2'
=0.6
2'
=0.6

4''
=0.1
4''
=0.1

1'6''
=0.45
1'6''
=0.45

21''
=0.53

9''
=0.23

2.6

-1.27

29''
=0.74

9''
=0.23

2.6

-3.5

54

-0.05
-0.05

59.88
= 60

BALCONY
a)Wide balcony

b)kitchen
balcony

c) staircase
landing

10'
=3.05

9''
=0.23

1.68

-3

7'9''
=2.36

9''
=0.23

1.83

-2

6'
=1.83

9''
=0.23

1.83

-0.77
Total
deduction

Total quantity of brick for one floor

-15.92
=(-)16

= total brick work + deductions


= 60-16
= 44 m

total quantity of brick work in building

= no.of floors X single floor brick work


= 3 X 44
=132 m

total no.of bricks =


brick size

= 0.19 X 0.09 X 0.09 m

brick size along with cement mortor = 0.2 X 0.1 X 0.1 m


total no. of bricks

=
= 66000

55

6.2.8 PLASTERING
Table 6.2.8.1 plastering work
S.no.

Decsription of
item

Nos.

Length

Breadth

(m)

(m)

Height
or
depth
(m)

Quantity

Total
quantity

(m)

(m)

18mm cement
plastering 1:4
in walls
1

Main bed room


a) long wall

b) short wall

c) slab

d) column
2

Kitchen room
a)long wall

b)short wall

c)slab
3

Toilets
(6' X 4')
a) long wall

b)short wall

c) slab

12'6''
=3.81

10'
=3.05

46.48

11'
=3.35

10'
=3.05

40.87

12'6''
=3.81

11'
=3.35

25.53

4'5''
=1.35

8'6''
=2.59

14

9'
=2.74

10'
=3.05

33.43

7'10.5''
=2.4

10'
=3.05

29.28

9'
=2.74

7'10.5''
=2.4

13.15

6'
=1.83

10'
=3.05

22.33

4'
=1.22

10'
=3.05

14.88

6'
=1.83

4'
=1.22

56

4.47

Toilets
(6'2'' X 4')
a)long wall

6'2''
=1.88

10'
=3.05

22.94

b) short wall

4'
=1.22

10'
=3.05

14.88

c) slab

6'2''
=1.88

Dining hall
(10' X 8'4.5'')
a) long wall

b)short wall

c)slab
Dining hall
(10' X 9'7.5'')
a) long wall

b)short wall

c)slab
7

Living hall
(20'4.5'' X
12'3'')
a) long wall

b)short wall

c) slab

Living hall
(20'4.5'' X 11')
a)long wall

4'
=1.22

4.59

10'
=3.05

10'
=3.05

9.3

8'4.5''
=2.55

10'
=3.05

15.56

10'
=3.05

8'4.5''
=2.55

7.78

10'
=3.05

10'
=3.05

9.3

9'7.5''
=2.93

10'
=3.05

17.87

10'
=3.05

9'7.5''
=2.93

8.94

20'4.5''
=6.21

10'
=3.05

18.94

12'3''
=3.73

10'
=3.05

22.75

20'4.5''
=6.21

12'3''
=3.73

20'4.5''
=6.21

23.16

10'
=3.05

57

18.94

b) short wall

c) slab
8

C.BED ROOM
(11' X 10')
a) short wall
b) short wall

c) slab

d)columns

C.BED ROOM
(12'3'' X 10')
a)long wall

b) short wall

c)slab

d) column

Lift
a) long wall

b) short wall
10

Wide corridor
a) long wall

b) short wall

2
2

11'
=3.35

10'
=3.05

20'4.5''
=6.21

11'
=3.35

11'
=3.35
10'
=3.05

20.8

10'
=3.05
10'
=3.05

10'
=3.05

20.44

11'
=3.35

20.44
18.61

10.22

4.5''
=0.11

8'6''
=3

1.32

12'3''
=3.73

10'
=3.05

22.75

10'
=3.05

10'
=3.05

18.61

10'
=3.05

12'3''
=3.73

11.38

4.5''
=0.11

8'6''
=3

1.32

6'
=1.83

10'4.5''
=3.16

11.57

4'6''
=1.37

10'4.5''
=3.16

8.66

16'6.5''
=5.04

10'
=3.05

30.74

6'
=1.83

10'
=3.05

5.58

58

c) slab
11

WIDE
BALOCNY
a) long wall

4
b) short wall
2
c) slab
2
d) short long
wall
2

12

e) short long
wall top
Kitchen wash
a) long wall

b) short wall

c) slab

13

d) short long
wall

e) short long
wall top
Out side
a) long wall

b) short wall

16'6.5''
=5.04

10'
=3.05

15.37

10'
=3.05

10'
=3.05

18.61

3'
=0.91

10'
=3.05

11.10

10'
=3.05

3'
=0.91

10'
=3.05

5.55
3'
=0.91

10'
=3.05

9''
=0.23

5.55

1.4

8'1''
=2.46

10'
=3.05

15

3'6''
=1.07

10'
=3.05

13.05

8'1''
=2.46

3'6''
=1.07

8'1''
=2.46

5.26
3'
=0.91

8'1''
=2.46

9''
=0.23

4.48

1.13

55'6''
=16.92

10'4.5''
=3.16

106.93

34'
=10.36

10'4.5''
=3.16
Total

65.48
910.72

59

Deductions
DOORS
1) M.D

2)D

3)D1

WINDOWS
1) W

2)W1

3)W2

4) K/W

5) V

16

18

3'6''
=1.07

6'9''
=2.06

-8.82

3'
=0.91

6'9''
=2.06

-15

2'6''
=0.76

6'9''
=2.06

-25.05

6'
=1.83

4'
=1.22

-8.93

4'
=1.22

4'
=1.22

-26.8

4'
=1.22

3'
=0.91

-2.22

3'
=0.91

2'6''
=0.76

-2.77

2'
=0.61

1'6''
=0.46

-1.12

OUT SIDE
OPENINGS
a) wide
balcony

2
b) kitchen
wash

10'
=3.05

7'
=2.13

-13

7'10.5''
=2.4

7'
=2.13

-10.22

Total
deducti
on

-113.91

Painting is similar to plastering .

60

6.2.9 Stair case


Table 6.2.9.1 C.C. work in stair case
S.NO

Description of
item
Stair case
R.c.c bed

No Length Breadth Height Quantity Total


Remarks
quantity
(m)
(m)
(m)
(m)
(m)
2
3'
5''
3.09
0.91
0.127
0.71
1

Landing area

6'
1.83

3'6''
1.07

5''
0.127

0.25
Total

0.96

Reinforcement in staircase
Table 6.2.9.2 bar bending schedule of stair case
S.NO.

Description
of item
Main
reinforcement
Distribution
reinforcement

shape

diameter NO.

Length

Total
length

Unit
weight

Total
quantity

12

14

3.68

51.52

0.89

45.85

32

0.86

27.53

0.39
Total

10.73
56.58

reinforcement in staircase for single floor = 56.58 kg


reinforcement in total staircase = no. of floors X reinforcement in single floor
= 4 X 56.58
= 226.32 kg

61

6.2.10 LINTELS
Table 6.2.10.1 C.C. work in lintels
S. NO

Description
of item

NO.

Over
M.D
D
D1
W
W1
W2
K/W
V

2
4
8
2
9
1
2
2

Length

Breadth

Height
Quantity
Or depth

Total
quantity

(m)

(m)

(m)

(m)

1.37
1.22
1.07
2.13
1.52
1.22
1.22
1.07

0.23
0.1
0.1
0.23
0.23
0.1
0.1
0.23

0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1

(m)
0.06
0.05
0.09
0.1
0.31
0.01
0.02
0.05
TOTAL

0.69

For three floors = 3 X 0.69


= 2.07 m

6.2.11 SKIRTING
Table 6.2.11.1 - skirting
S.NO.

Description NO.
of item
M.BED
C.BED
Living,
dining hall
Kitchen
Wide
balcony
K/wash
Toilets

Length

Breadth

Height

(m)

(m)

2
2

(RM)
14.32
13.56

2
2

25.11
10.29

50.22
20.58

2
2
4

7.92
7.06
6.1

15.84
14.12
24.4
Total

62

Quantity Total
quantity
(RM)
(RM)
28.64
27.12

180.92

6.2.12 AREA UNDER TILES


S.NO. Description of
item

N0.

( table 6.2.12.1)
Length

Breadth

(m)

(m)

Depth
Or height
(m)

Quantity
(m)

Total
quantity
(m)

1
Common bed
room
(12'3'' X 10')

12'3''
=3.73

10'
=3.05

11.38

Dining hall
(10' X 9'7.5'')

10'
=3.05

9'7.5''
=2.93

8.94

Living hall
(20'4.5'' X
11')

20'4.5''
=6.21

11'
=3.35

20.8

10'
=3.05

3'
=0.91

5.55

9'
=2.74

7'10.5''
=2.4

13.15

7'10.5''
=2.4

3'6''
=1.07

5.13

6'
=1.83

4'
=1.22

4.47

6'2''
=1.88

4'
=1.22

4.47

Wide balcony

Kitchen

Kitchen wash
area
Toilets
(6' X 4')
Toilets
(6'2'' X 4')
1

20'4.5''
=6.21

12'3''
=3.73

23.16

Living hall
(20'4.5'' X
12'3'')

10'
=3.05

8'4.5''
=2.55

7.78

Dining hall
(10' X 8'4.5'')

11'
=3.35

10'
=3.05

10.22

Common bed
room
(11' X 10')

16'6.5''
=5.04

6'
=1.83

9.22

Wide corridor
(16'6.5'' X 6')
Total

63

124.27

64

65

66

67

68

RESULTS
Table 7.1.1
S.No
Description of item
1
Earth work excavation
2
P.C.C bed concrete quantity
3
Total R.C.C work
4
Total Cement mortar
a) for bricks
b) plastering
c) under tiles
5
Total bricks
6
Steel
8mm dia bars
12mm dia bars
16mm dia bars
20mm dia bars
25mm dia bars
Total Steel
7
Total cement bags ( 50kg / bag)
8
Fine aggregates (sand ) in tones
9
Coarse aggregates in tones

Quantity
179.27 m
6.16 m
148.48 m
36.02 m
15.96 m
7.88 m
78130
3986.5kg
2137.24kg
10408.56 kg
6614.47 kg
2106.75 kg
25,251kgs
1045 bags
150 tonnes
122 tonnes

1m 20mm aggregate

= 1.43 metric tonnes

1m of cement

= 1440 kg

1m of sand

= 1602 kg

Land cost per sq. yard

= 42, 000

Total area

= (40' X 70')
= 311.11 sq. yards

Total cost of land

= Rs 1,30,66,667/-

Total construction cost

= Rs 65,92,902/-

Total cost

= cost of land + cost of construction


= 1,30,66,667 + 65,92,902

= Rs 1,96,59,569/69

CONCLUSION
The estimate also gives an idea of the time required for the completion of the
work, i.e. the probable time of completion can also be calculated. Also before the start of
any work, at least probable cost has to be found out, here estimation and costing plays an
important role. The estimate is also required for inviting tenders and to arrange contract
and to control the expenditure during execution.

The primary object of an estimate is to enable one to know, beforehand, the cost
of work. The actual cost is known only after the completion of the work from the account
of completed work. The estimate may be prepared approximately as a preliminary
estimate by various methods without going into the details of different items of work, to
know the approximate cost or rough cost.

Estimation and Analysis of Rates of various Items of Building are calculated and
presented in this documentation. All the calculations are based on the Design Drawings
provided, Standard Schedule of Rates, Andhra Pradesh, 2013-14 and Standard Data
Book. Reading the drawings, which is the essential feature of a Civil Engineer, has been
learned all through this project.

70

REFERENCES

[1] IS: 1200 Hand Book of Method of Measurement of Building Works


[2] SP-34 Hand book on Concrete Reinforcement and Detailing
[3] Estimating and Costing in Civil Engineering by B.N. Dutta, 26th revised
Edition, UBS Publishers Distributors pvt. Ltd. , 2007, pages 1, 4-11, 13-20, 213-214,
448-449, 472-517, 564.
[4] Standard Schedule of Rates (SSR), Andhra Pradesh, 2013-14
[5] Standard Data Book For Material and Labour Constants

71

Vous aimerez peut-être aussi