Académique Documents
Professionnel Documents
Culture Documents
10/22/2010
Case Study 1
Building Boundary
CBP Wall
(5 rows Ground
Anchors)
4
(9 rows of JackIn Anchors)
10/22/2010
Tunnel Construction in
progress
Building
Jack-In Anchors
CBP Wall
Tunnel Construction in
progress
5
Layer 1 Fill
(Clayey
Silt)
Depth (m)
10
15
Layer 2 Clayey
Silt
Layer 3 Sandy Silt
20
25
Legend
LL
PL
MC
30
16
17
18
19
20
10
20
30
SPT'N
40
20
40
60
80
400 00
80000
10/22/2010
Mobilised
Average Shaft Resistance with Time
Pull Out Shaft Resistance of SGE Jacked Anchors vs Time
Mobilised Average Shaft Resistance (kPa)
80
60
13.2
210 days
to
270 days
14
11.5
20.5
22
14.2
11.5
10
14
8.5
20.5
7.5 5.5 12
12.5 3
23.8
25
40
14.5
16.1
7.5
11
5.5
10.8 13.7
14.8
32.7 10
4.85
13.6
10.3
Legend
19.6
Level 1
Level 2
Level 3
Level 4
Level 5
Level 6
Level 7
Level 8
Level 9
22.4
24
26.7
12.5
20
8.35
6.4
8
26.5
37.3
10.6 28.1
21.8
7.27
32
10
15
20
25
30
35
Time (Days)
10/22/2010
0.6m
1.6m
VWSG - C
VWSG - B
3.0m
VWSG - C
6.0m
VWSG - D
9.0m
VWSG - F
12.0m
15.0m
200
150
100
P ull-Out Test
Test 1 ( 5 Days)
15-Jan-2002
Test 2 (14 Days)
25-Jan-2002
Test 3 (21 Days)
1-Feb-2002
50
4.6m
VWSG - D
10.6m
VWSG - F
7.6m
VWSG - E
250
Jacked
Anchor at
Level 4
250
VWSG - E
VWSG - A
Jacked
Anchor at
Level 7
200
150
Pull-Out Test
Test 1 ( 6 Days)
04-Mar-2002
Test 2 (14 Days)
12-Mar-2002
Test 3 (24 Days)
22-Mar-2002
100
50
0
10
20
30
40
80
120
10
20
30
40
80
120
140
130
120
110
Lo a d (k N )
100
90
80
70
60
50
40
30
20
10
0
0
50
100
150
200
250
10
300
Time (Days)
10/22/2010
550
500
450
L o ad (kN )
400
350
300
250
Load cell : 22/02/2002
200
150
100
50
Level 2 - PLAXIS
Level 3 - PLAXIS
Level 4 - PLAXIS
Level 5 - PLAXIS
0
0
50
100
150
200
11
250
300
Time (Days)
Wall Movement
Ground Anchor Wall
10
20
30
40
3
4
8
8
14
16
18
20
22
26
40
50
10
Depth (m)
Depth (m)
12
24
30
8
10
20
2
4
10
12
14
16
18
20
22
24
26
10/22/2010
S e t tle m e n t (m m )
Ground Settlement at
20
40
60
80
100
120
13
140
Time (Days)
14
10/22/2010
Beam Element
(CBP Wall and Soldier Piled Wall)
Interface Element
15
16
10/22/2010
17
25
20
15
10
0.05
0.1
Clough & ORourke
(1990)
0.15
18
0.2
10/22/2010
0.0x10
3.0x10
6.0x10
9.0x10
1.2x10
1.5x10
1.8x10
0
Legend
Interpreted E' (PMT)
Interpreted E' (SPT)
Depth(m)
10
15
20
25
19
30
10
10/22/2010
RECOMMENDATIONS
To avoid flexural effect, strain
gauges shall be installed in pairs at
jacked anchor section.
Research on generation of excess
pore water pressure & its
dissipation around and along the
jacked anchor shall be carried out.
Locked in tensile stress under
compressive injection may increase
movement within reinforced earth21
mass
Case Study 2
High rise development
with 5 storey
basement car park
Deep excavation:
7m-14.5m
22
11
10/22/2010
Plan
High rise development
with 5 storey
basement car park
Deep excavation:
7m-14.5m
23
Cross Section
12
10/22/2010
TOPOGRAPHIC
Original hilly ground with natural valley & stream
Loose sandy silt overlaying a thin deposited soft
compressible material at valley area
15m high
filled slope
25
SUBSURFACE CONDITIONS
BH-4
BH-IM4
BH-IM1
BH-SP1
BH-3
BH-2
BH-1
26
13
10/22/2010
27
3 rows of
subsoil drains
Permanent RC
props against
basement
structure
28
14
10/22/2010
INSTRUMENTATION MONITORING
29
Depth (m)
10
15
20
25
30
35
40
45
50
10
15
20
25
30
35
40
45
50
-2
-2
-4
-4
-6
-6
-8
-8
-10
-10
-12
-12
-14
-14
-16
-16
-18
-18
-20
-20
-22
-22
-24
-24
-26
-26
-28
-30
-32
-34
-36
-38
-28
Legend
20/9/2004
23/10/2004
04/11/2004
09/11/2004
24/11/2004
21/12/2004
24/01/2005
21/02/2005
22/03/2005
12/11/2005
SPT-N
IM-01
-30
-32
Legend
09/11/2004
24/11/2004
21/12/2004
24/01/2005
21/02/2005
22/03/2005
12/11/2005
SPT-N
IM-04
-40
-34
-36
-38
30
-10
10
20
30
40
50
60
70
80
90
100 110
10
20
30
40
50
60
70
80
90
-40
100 110
15
10/22/2010
Ground Settlement
01/08/04
10/09/04
20/10/04
29/11/04
08/01/05
17/02/05
29/03/05
08/05/05
17/06/05
10
10
-10
-10
-20
-20
-30
-30
-40
-40
-50
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-60
Legend
SM01
SM02
SM03
SM04
SM05
SM06
SM07
SM08
SM09
SM10
SM11
SM12
-70
-80
-90
-100
-110
-120
Sheet Pile
Installation
-130
-140
Construction
-150
Post-Construction
-150
-160
-160
01/08/04
10/09/04
20/10/04
29/11/04
08/01/05
17/02/05
29/03/05
08/05/05
17/06/05
31
Date
Groundwater Table
01/08/04 20/09/04 09/11/04 29/12/04 17/02/05 08/04/05 28/05/05 17/07/05
SP 01
Groundwater Table (RL m)
50
49
48
47
46
45
44
43
42
41
50
49
48
47
46
45
44
43
42
41
40
SP 03
Post-Construction
32
50
49
48
47
46
45
44
43
42
41
50
49
48
47
46
45
44
43
42
41
40
16
10/22/2010
Back Analysis
Soil Parameters
Layer
Material
Ave
SPT-N
b
(kN/m3)
Su
(kPa)
c
(kPa)
(
)
E
(kPa)
Eur
(kPa)
Back
Analysed
E
(kN/m2)
RL57m
RL49m
Sandy
Silt
(Fill)
12
18.5
32
30,000
90,000
18,000
RL49m
RL43m
Sandy
Silt
(Fill)
18.5
32
22,500
67,500
16,200
RL43m
RL40m
Sandy
Clay
(Weak
Zone)
18
40
0.5
(5)#
20
32,500
97,500
32,500
RL40m
RL37m
Sandy
Silt
10
18.5
5 (10) #
32
25,000
75,000
25,000
RL37m
RL21m
Sandy
Silt
20
18.5
5 (10) #
32
50,000
150,000
50,000
Below RL21m
Gravelly
Sand
50
19.5
32
125,000 375,000
125,000
34
# Improved apparent cohesion adopted in FE back analysis at the last few stages.
17
10/22/2010
10
20
30
40
50
10
20
30
40
50
60
70
10
20
30
40
50
60
70
10
20
30
40
50
60
70
60
60
12m Soil Nail
55
55
Shotcrete
50
50
45
Depth (RL m)
45
40
18m Soil Nail
40
Sheet Pile
35
35
30
30
Legend
Legend
Measured
Measured
Back-analysed
Back-analysed
25
25
20
Stage: Progressive
nailing
Stage: Completion of
excavation and soil
nail stabilisation
Stage: Post-installation
15
20
35
0
10
20
30
SPT'N'
40
50
10
20
30
40
50
60
70
10
20
30
40
50
60
70
10
20
30
40
50
60
70
INTERPRETATION
18
10/22/2010
Ground Settlement
30
28
26
24
22
20
18
16
14
12
10
10
10
Settlement (mm)
-10
-10
-20
-20
-30
-30
-40
-40
-50
-50
-60
-60
-70
-80
Legend
Back-Analysed
Measured
-70
-80
-90
-100
-90
-100
-110
37
30
28
26
24
22
20
18
16
14
12
10
-110
INTERPRETATION
Larger ground settlement as compared to FE
back-analysis
Possible reasons:
High compressed air flushing the soil to form open
hole (micro tunneling)
Excessive ground loss and stress relief
Ground deformation continues at a decreasing rate
38
19
10/22/2010
Settlement (mm)
30
28
26
24
22
20
18
16
14
12
10
10
10
-10
-10
-20
-20
-30
-30
-40
-40
-50
-50
-60
-60
-70
Legend
Back-Analysed
Measured
-70
-80
-80
-90
-100
-90
-100
-110
-110
30
28
26
24
22
20
18
16
14
12
10
39
INTERPRETATION OF FEM
Large shear strain developed along the
potential slip surface immediately behind the
reinforced soil mass
Settlement trough profile at active wedge
Band of potential slip surface running through
the soft clayey deposit reinforced soil mass
slides laterally
Soil nails have restricted the development of
40
active zones within the reinforced soil mass
20
10/22/2010
42
21
10/22/2010
Case Study 3
43
Site Location
44
22
10/22/2010
Site Layout
45
Introductions
4V:1H soil-nailed slope
Entire stretch is approximately
60m at uncontrolled fill over a
valley
Existing 8m to 11 m high
Reinforced Soil wall was 23m
away from soil-nailed slope
46
23
10/22/2010
47
48
24
10/22/2010
49
Tension Cracks
50
25
10/22/2010
Subsoil Profiles
Decayed Wood
51
Instrumentation Schemes
Two (2) inclinometers (namely
IN-1 & IN-2) to monitor the
nailed slope performance
Ten (10) ground settlement
markers were installed
An additional inclinometer (IN5) was installed
52
26
10/22/2010
Instrumentation Layout
GSM - 3
GSM - 1
GSM - 2
****GSM-1 (WILL
BE BOLD )
53
Groundwater Level
Two (2) observational wells
(SP-1 and SP-2) to measure
groundwater level during period
of unexpected prolonged rain
storm between March and April
2008
Groundwater fluctuated
drastically between August and
December 2008 during
construction of soil nailing work
54
27
10/22/2010
Rain Hyetograph
(Kuala Lumpur Rain Gauge Station)
Sheet Pile Installation & Top Row
Anchored Nail Installation
Abnormal storm
01/04/2008 First
Surface Collapse
08/07/2008 SP1
Installation
55
Inclinometers Results
Section A-A
Towards Excavation Side
Towards RS Wall
50
100
87
87
86
86
85
85
84
84
83
83
82
82
81
81
80
80
79
79
78
78
77
77
76
76
75
75
74
74
73
73
72
72
71
71
70
70
69
69
68
68
IN-1
IN-2
56
28
10/22/2010
Inclinometer Results
IN-5
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
360
380
400
420
440
460
480
500
Towards RS Wall
83
82
81
80
79
78
77
76
75
74
73
72
71
70
69
68
67
66
65
64
63
62
61
60
59
57
Remedial Solutions
Instrumentation Monitoring
(During & After Slope Distress)
Additional ten (10) numbers of
displacement markers were
installed; 5 numbers were
located near the crest of slope
while the rest of 5 number were
positioned at lower tier of RS
wall
58
29
10/22/2010
DSM-3
DSM-4
DSM-2
30
15
DSM-1
45
60
Displacement (mm)
50
13.05.2008
14.05.2008
17.05.2008
23.05.2008
26.06.2008
08.08.2008
14.08.2008
DSM-7
DSM-8
DSM-9
DSM-10
Displacement (mm)
50
100
150
200
250
23.06.2008
26.06.2008
30.06.2008
02.07.2008
30.07.2008
14.08.2008
18.08.2008
59
60
30
10/22/2010
61
25
50
75
Elapsed Days
125
150
100
175
200
225
250
275
220
220
200
Passive Berm
Excavation
Waler Beam
Installation
200
180
04/04/09
15/03/09
02/23/09
0
03/02/09
20
0
14/01/09
40
20
25/12/08
60
40
05/12/08
80
60
11/15/08
100
80
26/10/08
120
100
06/10/08
140
120
16/09/08
160
140
27/08/08
160
08/07/08
180
Date
Level A
Level B
Level C
62
31
10/22/2010
63
Average
SPT N
Bulk
Density,
b (kN/m3)
Effective
Cohesion,
c (kN/m2)
Effective
Friction
Angle,
(o)
Loose Fill
Material
17
18
Original Granitic
Residual Soils
20
20
31
Very Hard
Weathered
Granite
100
20
40
64
32
10/22/2010
65
Tension
Cracks
Surface
Slippage
66
33
10/22/2010
67
5.0 Conclusions
34
10/22/2010
Thank You
69
35