Vous êtes sur la page 1sur 6

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Item

Descripcin

01

SISTEMA DE AGUA POTABLE

Und.

MES 01
Metrado

Precio S/.

Parcial S/.

MONTO

MES 02
%

MES 03
%

MONTO

MES 04
%

ACUMULADO
%

MONTO

566,559.70

01.01

OBRAS PROVISIONALES

01.01.01

Campamento Provisional de Obra

m2

20.00

107.76

2,155.20

2,867.13
100%

2,155.20

0.00
0%

0%

0%

100%

2,155.20

01.01.02

Cartel de Identificacion de Obra 3.60X2.40m

und

1.00

711.93

711.93

100%

711.93

0%

0%

0%

100%

711.93

01.02

TRABAJOS PRELIMINARES

01.02.01

Movilizacin y Desmovilizacin de Equipos

glb

1.00

1,645.04

1,645.04

100%

1,645.04

0%

01.02.02

Desbroce y Limpieza

m2

3,475.00

0.80

2,780.00

100%

2,780.00

0%

0.00

0%

0.00

0%

0.00

2.56

0.51

1.31

100%

1.31

0%

0.00

0%

0.00

0%

19.89

100%

19.89

4,425.04

0.00
0%

0%

0.00

100%

1,645.04

100%

2,780.00

0.00

100%

1.31

0%

01.03

CAPTACION C-1 (QUILLO 01 UNIDAD)

01.03.01

Trazo, Nivelacin y Replanteo de Estructura

m2

01.03.02

Excavacion Manual en Material Conglomerado

m3

1.66

11.98

0%

0.00

0%

0.00

0%

0.00

100%

01.03.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.12

272.18

32.66

100%

32.66

0%

0.00

0%

0.00

0%

0.00

100%

32.66

01.03.04

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

10.31

27.14

279.81

100%

279.81

0%

0.00

0%

0.00

0%

0.00

100%

279.81

01.03.05

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

34.38

4.57

157.12

100%

157.12

0%

0.00

0%

0.00

0%

0.00

100%

157.12

01.03.06

Concreto f'c=210 kg/cm2

m3

0.81

391.34

316.99

100%

316.99

0%

0.00

0%

0.00

0%

0.00

100%

316.99

01.03.07

Relleno de Concreto Pobre en Piso de Filtro (1:12)

m3

0.24

277.49

66.60

100%

66.60

0%

0.00

0%

0.00

0%

0.00

100%

66.60

01.03.08

Encofrado y Desencofrado de Aletas

m2

7.20

27.25

196.20

100%

196.20

0%

0.00

0%

0.00

0%

0.00

100%

196.20

01.03.09

Concreto f'c=210 kg/cm2 para aletas y sellado

m3

0.54

391.34

211.32

100%

211.32

0%

0.00

0%

0.00

0%

0.00

100%

211.32

01.03.10

Material Granular Filtrante en Captacin (grava-arena)

m3

1.26

156.35

197.00

100%

197.00

0%

0.00

0%

0.00

0%

0.00

100%

197.00

01.03.11

Tarrajeo Interior con Impermeabilizante, 1:2, e=1 cm

m2

3.29

17.09

56.23

100%

56.23

0%

0.00

0%

0.00

0%

0.00

100%

56.23

01.03.12

Tarrajeo Exterior (mortero 1:4), e=1 cm

m2

4.24

11.83

50.16

100%

50.16

0%

0.00

0%

0.00

0%

0.00

100%

01.03.13

Tarrajeo Exterior de Aletas y Sellado (mortero 1:4), e=1cm

m2

4.70

12.49

58.70

100%

58.70

0%

0.00

0%

0.00

0%

0.00

100%

58.70

01.03.14

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

153.60

153.60

100%

153.60

0%

0.00

0%

0.00

0%

0.00

100%

153.60

01.03.15

Accesorios de Salida y Rebose/Desage C-1, LC=1", Desage und

1.00

310.14

310.14

100%

310.14

0%

0.00

0%

0.00

0%

0.00

100%

310.14

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

28.85

100%

28.85

01.03.16

2,300.09

und

0.00
19.89

50.16

1.00

28.85

0%

0.00

0%

0.00

0%

0.00

100%

28.85

01.03.17

Dado de Concreto (1:6) 0.3x0.3x0.3m, desague 3", tapn perfound

1.00

40.93

40.93

100%

40.93

0%

0.00

0%

0.00

0%

0.00

100%

40.93

01.03.18

Pintura en Exterior

8.94

6.00

53.64

100%

53.64

0%

0.00

0%

0.00

0%

0.00

100%

53.64

01.03.19

Empedrado, e=0.125m,a=0.6-0.8m.

m2

2.76

19.01

52.47

100%

52.47

0%

0.00

0%

0.00

0%

0.00

100%

52.47

01.03.20

Eliminacin de Material de Desmonte

m3

2.00

8.24

16.48

100%

16.48

0%

0.00

0%

0.00

0%

0.00

100%

16.48

m2

01.04

CAPTACION C-1 (NUEVO MILAN 01 UNIDAD)

01.04.01

Trazo, Nivelacin y Replanteo de Estructura

m2

6.32

0.51

3,101.98
3.22

100%

3.22

0%

0.00

0%

0.00

0%

0.00

100%

3.22

01.04.02

Excavacion Manual en Material Conglomerado

m3

8.51

11.98

101.95

100%

101.95

0%

0.00

0%

0.00

0%

0.00

100%

101.95

0.00

01.04.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.14

272.18

38.11

100%

38.11

0%

0.00

0%

0.00

0%

0.00

100%

38.11

01.04.04

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

9.75

27.14

264.62

100%

264.62

0%

0.00

0%

0.00

0%

0.00

100%

264.62

01.04.05

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

78.62

4.57

359.29

100%

359.29

0%

0.00

0%

0.00

0%

0.00

100%

359.29

01.04.06

Concreto f'c=210 kg/cm2

m3

1.35

391.34

528.31

100%

528.31

0%

0.00

0%

0.00

0%

0.00

100%

528.31

01.04.07

Relleno de Concreto Pobre en Piso de Filtro (1:12)

m3

0.24

277.49

66.60

100%

66.60

0%

0.00

0%

0.00

0%

0.00

100%

01.04.08

Encofrado y Desencofrado de Aletas

m2

7.20

27.25

196.20

100%

196.20

0%

0.00

0%

0.00

0%

0.00

01.04.09

Concreto f'c=210 kg/cm2 para aletas y sellado

m3

0.81

391.34

316.99

100%

316.99

0%

01.04.10

Material Granular Filtrante en Captacin (grava-arena)

m3

1.26

156.35

197.00

100%

197.00

0%

0.00

0%

0.00

0%

01.04.11

Tarrajeo Interior con Impermeabilizante, 1:2, e=1.5 cm

m2

4.00

17.09

68.36

100%

68.36

0%

0.00

0%

0.00

0%

0%

66.60

100%

196.20

100%

316.99

0.00

100%

197.00

0.00

100%

68.36

0%

01.04.12

Tarrajeo Exterior (mortero 1:4), e=1.5 cm

m2

4.54

11.83

53.71

100%

53.71

0%

0.00

0%

0.00

0%

0.00

100%

53.71

01.04.13

Tarrajeo Exterior de Aletas y Sellado (mortero 1:4), e=1cm

m2

4.70

12.49

58.70

100%

58.70

0%

0.00

0%

0.00

0%

0.00

100%

58.70

01.04.14

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

141.73

141.73

100%

141.73

0%

0.00

0%

0.00

0%

0.00

100%

141.73

01.04.15

Accesorios de Salida y Rebose/Desage C-1, LC=1", Desage und

1.00

324.48

324.48

100%

324.48

0%

0.00

0%

0.00

0%

0.00

100%

324.48

01.04.16

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

1.00

28.85

28.85

100%

28.85

0%

0.00

0%

0.00

0%

0.00

100%

28.85

01.04.17

Dado de Concreto (1:6) 0.3x0.3x0.3m, desague 3", tapn perfound

1.00

40.93

40.93

100%

40.93

0%

0.00

0%

0.00

0%

0.00

100%

40.93

01.04.18

Pintura en Exterior

9.24

6.00

55.44

100%

55.44

0%

0.00

0%

0.00

0%

0.00

100%

55.44

01.04.19

Empedrado, e=0.125m,a=0.6-0.8m.

m2

9.12

19.01

173.37

100%

173.37

0%

0.00

0%

0.00

0%

0.00

100%

173.37

01.04.20

Eliminacin de Material de Desmonte=30m

m3

10.21

8.24

84.13

100%

84.13

0%

0.00

0%

0.00

0%

0.00

100%

84.13

01.05

CAPTACION RESERVORIO (01 UNIDAD)

01.05.01

Demolicion Estructura Existente en Captacion

100%

63.53

0%

0.00

0%

0.00

0%

0.00

100%

63.53

01.05.02

Trazo, Nivelacin y Replanteo de Estructura

m2

2.56

0.51

1.31

100%

1.31

0%

0.00

0%

0.00

0%

0.00

100%

1.31

01.05.03

Excavacion Manual en Material Conglomerado

m3

1.66

11.98

19.89

100%

19.89

0%

0.00

0%

100%

19.89

01.05.04

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.06

272.18

16.33

100%

16.33

0%

0.00

0%

0.00

0%

0.00

100%

16.33

01.05.05

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

13.65

370.46

100%

370.46

0%

0.00

0%

0.00

0%

0.00

100%

01.05.06

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

81.42

4.57

372.09

100%

372.09

0%

0.00

0%

0.00

0%

0.00

100%

372.09

01.05.07

Concreto f'c=210 kg/cm2

m3

2.70

391.34

1,056.62

100%

1,056.62

0%

0.00

0%

0.00

0%

0.00

100%

1,056.62

01.05.08

Relleno de Concreto Pobre en Piso de Filtro (1:12)

m3

0.26

277.49

72.15

100%

72.15

0%

0.00

0%

0.00

0%

0.00

100%

72.15

01.05.09

Encofrado y Desencofrado de Aletas

m2

7.20

27.25

196.20

100%

196.20

0%

0.00

0%

0.00

0%

0.00

100%

196.20

01.05.10

Concreto f'c=210 kg/cm2 para aletas y sellado

m3

0.54

391.34

211.32

100%

211.32

0%

0.00

0%

0.00

0%

0.00

100%

211.32

01.05.11

Material Granular Filtrante en Captacin (grava-arena)

m3

1.58

156.35

247.03

100%

247.03

0%

0.00

0%

0.00

0%

0.00

100%

247.03

01.05.12

Tarrajeo Interior con Impermeabilizante, 1:2, e=1 cm

m2

13.82

17.09

236.18

100%

236.18

0%

0.00

0%

0.00

0%

0.00

100%

236.18

01.05.13

Tarrajeo Exterior (mortero 1:4), e=1 cm

m2

14.94

11.83

176.74

100%

176.74

0%

0.00

0%

0.00

0%

0.00

100%

176.74

01.05.14

Tarrajeo Exterior de Aletas y Sellado (mortero 1:4), e=1cm

m2

4.70

12.49

58.70

100%

58.70

0%

0.00

0%

0.00

0%

0.00

100%

01.05.15

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

153.60

153.60

100%

153.60

0%

0.00

0%

0.00

0%

0.00

100%

153.60

01.05.16

Accesorios de Salida y Rebose/Desage C-4, LC=1", Desage und

1.00

437.93

437.93

100%

437.93

0%

100%

437.93

m2

4,042.92
glb

1.00

63.53

27.14

63.53

0.00

0%

0%

0%

370.46

58.70

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Und.

MES 01

Descripcin

01.05.17

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

1.00

28.85

01.05.18

Dado de Concreto (1:6) 0.3x0.3x0.3m, desague 3", tapn perfound

1.00

40.93

01.05.19

Pintura en Exterior

19.64

6.00

01.05.20

Empedrado, e=0.125m,a=0.6-0.8m.

m2

8.08

19.01

01.05.21

Eliminacin de Material de Desmonte

m3

1.41

8.24

01.06

CERCO PERIMETRICO EN CAPTACION

01.06.01

Trazo y Replanteo

32.00

01.06.02

Excavacion manual en terreno normal

m3

1.87

01.06.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.14

272.18

38.11

50%

19.05

50%

19.05

01.06.04

Concreto f'c=140kg/cm2 +30% piedra

m3

1.73

237.49

410.86

50%

205.43

50%

205.43

01.06.05

Poste de tubo de Fierro Galvanizado. D=2"

und

18.00

84.62

1,523.16

50%

761.58

50%

761.58

m2

Metrado

Precio S/.

Parcial S/.

MES 02

Item

MONTO

28.85

100%

28.85

0%

40.93

100%

40.93

0%

117.84

100%

117.84

153.60

100%

11.62

100%

MES 03

MES 04

MONTO

0.00

0%

0.00

0%

0.00

100%

0.00

0%

0.00

0%

0.00

100%

40.93

0%

0.00

0%

0.00

0%

0.00

100%

117.84

153.60

0%

0.00

0%

0.00

0%

0.00

100%

153.60

11.62

0%

0.00

0%

0.00

0%

0.00

100%

11.62

9,142.53
0.43
11.98

13.76

50%

22.40

50%

ACUMULADO

6.88

50%

11.20

50%

6.88
11.20

MONTO
28.85

0%

0.00
13.76

0%

0.00

0%

0.00

100%

0%

0.00

0%

0.00

100%

0%

0.00

0%

0.00

100%

38.11

0%

0.00

0%

0.00

100%

410.86

0%

0.00

0%

0.00

100%

1,523.16

22.40

01.06.06

Cerco de tubo de fierro negro y malla olimpica

48.20

126.40

6,092.48

50%

3,046.24

50%

3,046.24

0%

0.00

0%

100%

6,092.48

01.06.07

Puerta C/Malla Olimpica y marco Fierro D=11/2" 0.85X2.10m

und

2.00

280.88

561.76

50%

280.88

50%

280.88

0%

0.00

0%

0.00

100%

561.76

01.06.08

Pintura Esmalte

m2

80.00

6.00

480.00

50%

240.00

50%

240.00

0%

0.00

0%

0.00

100%

480.00

01.07

LINEA DE CONDUCCION (L=3288.80m)

01.07.01

Trazo, Nivelacin y Replanteo.

707.65

0%

0.00

0%

0.00

100%

884.56

01.07.02

Excavacion Manual de Zanja en Conglomerado, 0.50x0.80m.

m3

01.07.03

Excavacion en Roca Suelta

m3

01.07.04

Refine, Nivelacion y Compactacion

m2

01.07.05

Refine y Nivelacin de Zanja, a=0.45 m.

01.07.06

Cama de Apoyo para Tubera, e=0.10m., a=0.50m.

01.07.07

Tuberia de HDPE PE-80 SDR-17, 32mm.

303.71

9.85

2,991.54

20%

598.31

80%

01.07.08

Anclaje de Tuberia HDPE D:32mm

und

61.00

24.88

1,517.68

20%

303.54

80%

68,976.77

0.00

3,402.14

0.26

884.56

20%

176.91

80%

991.50

11.98

11,878.17

20%

2,375.63

80%

9,502.54

0%

0.00

0%

0.00

100%

11,878.17

247.87

60.49

14,993.66

20%

2,998.73

80%

11,994.93

0%

0.00

0%

0.00

100%

14,993.66

1,239.37

0.60

743.62

20%

148.72

80%

594.90

0%

0.00

0%

0.00

100%

743.62

3,098.43

0.69

2,137.92

20%

427.58

80%

1,710.33

0%

0.00

0%

0.00

100%

2,137.92

3,098.43

1.30

4,027.96

20%

805.59

80%

3,222.37

0%

0.00

0%

0.00

100%

4,027.96

2,393.23

0%

0.00

0%

0.00

100%

2,991.54

1,214.14

0%

0.00

0%

0.00

100%

1,517.68

100%

9,078.40

01.07.09

Tuberia de PVC SAP Clase 10, 1"x5m.

3,098.43

2.93

9,078.40

20%

1,815.68

80%

7,262.72

0%

0.00

0%

01.07.10

Accesorios en linea de conduccin

glb

1.00

93.32

93.32

20%

18.66

80%

74.66

0%

0.00

0%

0.00

100%

93.32

01.07.11

Relleno y Apisonado de Zanja

m3

991.50

17.65

17,499.98

20%

3,500.00

80%

13,999.98

0%

0.00

0%

0.00

100%

17,499.98

01.07.12

Doble Prueba Hidraulica y desinfeccin

3,129.97

3,402.14

0.92

20%

625.99

80%

2,503.98

0%

0.00

0%

0.00

100%

3,129.97

01.08

PASE AEREO EN LC (L=8 m 04 UNIDADES)

01.08.01

Trazo, Nivelacin y Replanteo.

52.08

0.26

13.54

0%

0.00

100%

13.54

0%

0.00

0%

0.00

100%

13.54

01.08.02

Excavacion Manual en Material Conglomerado

m3

6.91

11.98

82.78

0%

0.00

100%

82.78

0%

0.00

0%

0.00

100%

82.78

01.08.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.38

272.18

103.43

0%

0.00

100%

103.43

0%

0.00

0%

0.00

100%

103.43

01.08.04

Concreto f'c=140kg/cm2 +30% piedra

m3

2.69

237.49

638.85

0%

0.00

100%

638.85

0%

0.00

0%

0.00

100%

638.85

01.08.05

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

154.10

4.57

704.24

0%

0.00

100%

704.24

0%

0.00

0%

0.00

100%

704.24

01.08.06

Encofrado y Desencofrado de Torres

m2

12.80

24.20

309.76

0%

0.00

100%

309.76

0%

0.00

0%

0.00

100%

309.76

01.08.07

Concreto f'c=210 kg/cm2

m3

2.37

391.34

927.48

0%

0.00

100%

927.48

0%

0.00

0%

0.00

100%

927.48

01.08.08

Tarrajeo caseta de Valvulas, e=1 cm, 1:4

m2

12.80

13.27

169.86

0%

0.00

100%

169.86

0%

0.00

0%

0.00

100%

169.86

01.08.09

Pintura en Exterior

m2

12.80

6.00

76.80

0%

0.00

100%

76.80

0%

0.00

0%

0.00

100%

76.80

01.08.10

Cruce Areo, Cable de Acero Flexible 3/8" (Inc. montaje)

66.00

9.30

613.80

0%

0.00

100%

613.80

0%

0.00

0%

0.00

100%

613.80

01.08.11

Cruce Areo, Accesorios de Anclaje

und

8.00

45.20

361.60

0%

0.00

01.08.12

Cruce Areo, Pndolas y Accesorios de Suspensin de Tuberam

0%

0.00

01.08.13

Tuberia de FG, 1"x6m. y accesorios

01.09

CAMARA ROMPE PRESION TIPO CRP-6 (12 UNIDADES)

01.09.01

Trazo, Nivelacin y Replanteo de Estructura

m2

01.09.02

Excavacion Manual en Material Conglomerado

m3

01.09.03

Concreto Simple f'c = 100 kg/cm2 (para solado y falsa columna m3

01.09.04

Encofrado y Desencofrado-Losa de Fondo y Muros

01.09.05

Acero fy=4200 kg/cm2 Grado 60, 3/8"

01.09.06

Concreto f'c=210 kg/cm2

m3

01.09.07

Tarrajeo Interior con Impermeabilizante, 1:2, e=1.5 cm

m2

01.09.08

Tarrajeo Exterior (mortero 1:4), e=1.5 cm

m2

01.09.09

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

4,546.82

0.00

0%

0.00

100%

361.60

0%

0.00

9.20

16.04

147.57

0%

0.00

100%

147.57

0%

0.00

34.00

11.68

397.12

0%

0.00

100%

397.12

0%

62,385.88
48.00

0.51

0%

100%

147.57
397.12
24.48

0.00

24.48

80%

19.58

20%

361.60

100%
100%

0.00

4.90

0%

0.00

0%

0.00

100%

4.57

11.98

54.75

80%

43.80

20%

10.95

0%

0.00

0%

0.00

100%

0.73

272.18

198.69

80%

158.95

20%

39.74

0%

0.00

0%

0.00

100%

198.69

82.20

27.14

2,230.91

80%

1,784.73

20%

446.18

0%

0.00

0%

0.00

100%

2,230.91

0%

0.00

0%

0.00

100%

2,088.31

0%

0.00

0%

0.00

100%

4,512.15

0.00

0%

0.00

100%

566.02

0%

0.00

0%

0.00

100%

31,353.29

m2
kg

456.96

4.57

2,088.31

80%

1,670.65

11.53

391.34

4,512.15

80%

3,609.72

20%

902.43

33.12

17.09

566.02

80%

452.82

20%

113.20

0%

2,650.32

11.83

31,353.29

80%

25,082.63

20%

6,270.66

20%

417.66

54.75

12.00

153.60

1,843.20

80%

1,474.56

20%

368.64

0%

0.00

0%

0.00

100%

1,843.20

01.09.10

Accesorios de Entrada, Salida, Rebose/Desage CRP-6, LC=1"und

12.00

138.11

1,657.32

80%

1,325.86

20%

331.46

0%

0.00

0%

0.00

100%

1,657.32

01.09.11

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

12.00

28.85

346.20

80%

276.96

20%

69.24

0%

0.00

0%

0.00

100%

346.20

01.09.12

Dado de Concreto (1:6) 0.2x0.3x0.2m, desague 2", tapn perforund

12.00

52.73

632.76

80%

506.21

20%

126.55

0%

0.00

0%

0.00

100%

632.76

01.09.13

Pintura en Exterior

m2

2,650.32

6.00

15,901.92

80%

12,721.54

20%

3,180.38

0%

0.00

0%

0.00

100%

15,901.92

01.09.14

Empedrado, e=0.125m,a=0.6-0.8m.

m2

48.96

19.01

930.73

80%

744.58

20%

186.15

0%

0.00

0%

0.00

100%

930.73

01.09.15

Eliminacin de Material de Desmonte

m3

5.48

8.24

45.16

80%

36.12

20%

9.03

0%

0.00

0%

0.00

100%

45.16

01.10

RESERVORIO DE 2.0 M3 (01 UNIDAD)

01.10.01

Trazo, Nivelacin y Replanteo de Estructura

m2

4.00

0.51

2.04

10%

0.20

90%

1.84

0%

0.00

0%

0.00

100%

2.04

01.10.02

Excavacion Manual en Material Conglomerado

m3

0.57

11.98

6.83

10%

0.68

90%

6.15

0%

0.00

0%

0.00

100%

6.83

01.10.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.36

272.18

97.98

10%

9.80

90%

88.19

0%

0.00

0%

0.00

100%

97.98

01.10.04

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

23.98

27.14

650.82

10%

65.08

90%

585.74

0%

0.00

0%

0.00

100%

650.82

01.10.05

Encofrado y Desencofrado - Losa Superior

m2

29.03

10%

2.90

90%

26.13

0%

0.00

0%

0.00

100%

01.10.06

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

109.15

4.57

498.82

10%

49.88

90%

448.93

0%

0.00

0%

0.00

100%

498.82

01.10.07

Concreto f'c=210 kg/cm2

m3

2.59

391.34

1,013.57

10%

101.36

90%

912.21

0%

0.00

0%

0.00

100%

1,013.57

01.10.08

Mortero 1:5 en losa de fondo (pendiente 1%)

m2

2.56

12.09

30.95

10%

3.10

90%

27.86

0%

0.00

0%

0.00

100%

30.95

3,392.57

1.12

25.92

0.00

29.03

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Und.

MES 01

Item

Descripcin

Metrado

Precio S/.

01.10.09

Tarrajeo Interior con Impermeabilizante, 1:2, e=1.5 cm

m2

13.80

15.17

01.10.10

Tarrajeo Exterior (mortero 1:4), e=1.5 cm

m2

23.29

12.60

01.10.11

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

01.10.12

Sistema de Ventilacin, 2/Estruct. (con tapn perforado)

und

01.10.13

Gancho PVC hipoclorador

01.10.14

Pintura en Exterior

01.10.15
01.10.16

Parcial S/.

MES 02

MONTO

209.35

10%

20.93

90%

293.45

10%

29.35

90%

153.60

153.60

10%

15.36

1.00

54.96

54.96

10%

und

1.00

13.71

13.71

m2

17.29

6.00

103.74

Empedrado, e=0.125m,a=0.6-1.8m.

m2

12.00

19.01

Eliminacin de Material de Desmonte

MES 03

MES 04

MONTO

188.41

0%

0.00

0%

264.11

0%

0.00

0%

90%

138.24

0%

0.00

5.50

90%

49.46

0%

10%

1.37

90%

12.34

10%

10.37

90%

93.37

228.12

10%

22.81

90%

5.60

ACUMULADO
%

MONTO

0.00

100%

209.35

0.00

100%

293.45

0%

0.00

100%

153.60

0.00

0%

0.00

100%

0%

0.00

0%

0.00

100%

13.71

0%

0.00

0%

0.00

100%

103.74

205.31

0%

0.00

0%

0.00

100%

228.12

54.96

m3

0.68

8.24

10%

0.56

90%

5.04

0%

0.00

0%

0.00

100%

5.60

01.11

CASETA DE VALVULAS (01 UNIDAD)

01.11.01

Encofrado y Desencofrado

m2

5.86

32.27

189.10

10%

18.91

90%

170.19

0%

0.00

0%

0.00

100%

189.10

01.11.02

Acero fy=4200 kg/cm2 Grado 60, 1/4"

kg

15.79

4.54

71.69

10%

7.17

90%

64.52

0%

0.00

0%

0.00

100%

71.69

01.11.03

Concreto f'c=175 kg/cm2

0%

0.00

0%

0.00

100%

147.55

01.11.04

Tarrajeo Exterior e Interior (mortero 1:4), e=1.0 cm

m2

2.37

12.46

29.53

10%

2.95

90%

26.58

0%

0.00

0%

0.00

100%

29.53

01.11.05

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

141.73

141.73

10%

14.17

90%

127.56

0%

0.00

0%

0.00

100%

141.73

01.11.06

Caseta de Vlvulas, Tubo de Entrada y Control Esttico, By-pasund

1.00

167.17

167.17

10%

16.72

90%

150.45

0%

0.00

0%

0.00

100%

167.17

01.11.07

Caseta de Vlvulas, Rebose y Desage (vlv. y acces de 2")

und

1.00

306.08

306.08

10%

30.61

90%

275.47

0%

0.00

0%

0.00

100%

306.08

01.11.08

Caseta de Vlvulas, Tubo de Salida (vlv. y acces=1")

und

1.00

106.13

106.13

10%

10.61

90%

95.52

0%

0.00

0%

0.00

100%

106.13

01.11.09

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

1.00

28.85

28.85

10%

2.89

90%

25.97

0%

0.00

0%

0.00

100%

28.85

01.11.10

Dado de Concreto (1:6) 0.2x0.2x0.2m, desague 2", tapn perforund

1.00

52.73

52.73

10%

5.27

90%

47.46

0%

0.00

0%

0.00

100%

52.73

01.11.11

Pintura en Exterior

0.69

6.00

4.14

10%

0.41

90%

3.73

0%

0.00

0%

01.12

RESERVORIO DE 3.0 M3 (01 UNIDAD)

01.12.01

Trazo, Nivelacin y Replanteo de Estructura

m2

3.61

0.51

1.84

0%

01.12.02

Excavacion Manual en Material Conglomerado

m3

1.08

11.98

12.94

0%

01.12.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.36

272.18

97.98

01.12.04

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

16.24

27.14

440.75

01.12.05

Encofrado y Desencofrado - Losa Superior

m2

9.00

25.92

233.28

0%

01.12.06

Acero fy=4200 kg/cm2 Grado 60, 3/8"

181.23

4.57

828.22

01.12.07

Concreto f'c=210 kg/cm2

m3

2.07

391.34

810.07

01.12.08

Mortero 1:5 en losa de fondo (pendiente 1%)

m2

1.96

12.09

23.70

0%

01.12.09

Tarrajeo Interior con Impermeabilizante, 1:2, e=1.5 cm

m2

10.12

15.17

153.52

01.12.10

Tarrajeo Exterior (mortero 1:4), e=1.5 cm

m2

13.89

12.60

01.12.11

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

153.60

01.12.12

Sistema de Ventilacin, 2/Estruct. (con tapn perforado)

und

1.00

54.96

54.96

01.12.13

Gancho PVC hipoclorador

und

1.00

13.71

01.12.14

Pintura en Exterior

m2

13.89

01.12.15

Empedrado, e=0.125m,a=0.6-1.8m.

m2

01.12.16

Eliminacin de Material de Desmonte

m3

01.13

CASETA DE VALVULAS (01 UNIDAD)

01.13.01

Encofrado y Desencofrado

01.13.02

Acero fy=4200 kg/cm2 Grado 60, 1/4"

01.13.03

Concreto f'c=175 kg/cm2

m3

01.13.04

Tarrajeo Exterior e Interior (mortero 1:4), e=1.0 cm

m2

01.13.05

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

1.00

1,244.70

m3

m2

0.44

335.35

147.55

0.00

10%

14.76

90%

132.80

3,283.75

kg

0.00

0.00

100%

4.14

0.00

0%

0.00

100%

1.84

0%

0.00

0%

0.00

100%

1.84

0.00

100%

12.94

0%

0.00

0%

0.00

100%

12.94

0%

0.00

100%

97.98

0%

0.00

0%

0.00

100%

97.98

0%

0.00

100%

440.75

0%

0.00

0%

0.00

100%

440.75

0.00

100%

233.28

0%

0.00

0%

0.00

100%

233.28

0%

0.00

100%

828.22

0%

0.00

0%

0.00

100%

828.22

0%

0.00

100%

810.07

0%

0.00

0%

0.00

100%

810.07

0.00

100%

23.70

0%

0.00

0%

0.00

100%

23.70

0%

0.00

100%

153.52

0%

0.00

0%

0.00

100%

153.52

175.01

0%

0.00

100%

175.01

0%

0.00

0%

0.00

100%

175.01

153.60

0%

0.00

100%

153.60

0%

0.00

0%

0.00

100%

153.60

0%

0.00

100%

54.96

0%

0.00

0%

0.00

100%

54.96

13.71

0%

0.00

100%

13.71

0%

0.00

0%

0.00

100%

13.71

6.00

83.34

0%

0.00

100%

83.34

0%

0.00

0%

0.00

100%

83.34

10.00

19.01

190.10

0%

0.00

100%

190.10

0%

0.00

0%

0.00

100%

190.10

1.30

8.24

10.71

0%

0.00

100%

10.71

0%

0.00

0%

0.00

100%

10.71

0.00

0%

0.00

0%

0.00

100%

49.70

1,088.85
m2

1.54

32.27

49.70

kg

15.79

4.54

0.44

335.35

1.05

12.46

13.08

141.73

141.73

0.00

0.00

0%

0.00

100%

49.70

0%

71.69

0%

0.00

100%

71.69

0%

0.00

0%

0.00

100%

71.69

147.55

0%

0.00

100%

147.55

0%

0.00

0%

0.00

100%

147.55

0%

0.00

100%

13.08

0%

0.00

0%

0.00

100%

13.08

0%

0.00

100%

141.73

0%

0.00

0%

0.00

100%

141.73

01.13.06

Caseta de Vlvulas, Tubo de Entrada y Control Esttico, By-pasund

1.00

167.17

167.17

0%

0.00

100%

167.17

0%

0.00

0%

0.00

100%

167.17

01.13.07

Caseta de Vlvulas, Rebose y Desage (vlv. y acces de 2")

und

1.00

306.08

306.08

0%

0.00

100%

306.08

0%

0.00

0%

0.00

100%

306.08

01.13.08

Caseta de Vlvulas, Tubo de Salida (vlv. y acces=1")

und

1.00

106.13

106.13

0%

0.00

100%

106.13

0%

0.00

0%

0.00

100%

106.13

01.13.09

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

1.00

28.85

28.85

0%

0.00

100%

28.85

0%

0.00

0%

0.00

100%

28.85

01.13.10

Dado de Concreto (1:6) 0.2x0.2x0.2m, desague 2", tapn perforund

1.00

52.73

52.73

0%

0.00

100%

52.73

0%

0.00

0%

0.00

100%

52.73

01.13.11

Pintura en Exterior

0.69

6.00

4.14

0%

0.00

100%

4.14

0%

0.00

0%

0.00

100%

4.14

01.14

CERCO PERIMETRICO EN RESERVORIOS

01.14.01

Trazo y Replanteo

50.00

0.43

21.50

0%

01.14.02

Excavacion manual en terreno normal

m3

1.87

11.98

22.40

0%

01.14.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.14

272.18

38.11

0%

0.00

100%

38.11

0%

01.14.04

Concreto f'c=140kg/cm2 +30% piedra

m3

1.73

237.49

410.86

0%

0.00

100%

410.86

0%

01.14.05

Poste de tubo de Fierro Galvanizado. D=2"

und

18.00

84.62

1,523.16

0%

0.00

100%

1,523.16

01.14.06

Cerco de tubo de fierro negro y malla olimpica

48.20

126.40

6,092.48

0%

0.00

100%

6,092.48

01.14.07

Puerta C/Malla Olimpica y marco Fierro D=11/2" 0.85X2.10m

und

2.00

280.88

561.76

0%

0.00

100%

561.76

01.14.08

Pintura Esmalte

m2

100.00

6.00

600.00

0%

0.00

100%

m2

9,270.27
0.00

100%

21.50

0%

100%

22.40

0%

0.00

0%

0.00

0%

0.00

100%

21.50

0%

0.00

100%

22.40

0.00

0%

0.00

100%

38.11

0.00

0%

0.00

100%

410.86

0%

0.00

0%

0.00

100%

1,523.16

0%

0.00

0%

0.00

100%

6,092.48

0%

0.00

0%

0.00

100%

561.76

600.00

0%

0.00

0%

0.00

100%

600.00

01.15

RED DE DISTRIBUCION (L=5,473.60 m)

01.15.01

Trazo, Nivelacin y Replanteo.

5,419.40

0.26

97,165.79
1,409.04

80%

1,127.24

10%

140.90

10%

140.90

0%

0.00

100%

1,409.04

01.15.02

Excavacion Manual de Zanja en Conglomerado

m3

1,474.08

11.98

17,659.48

80%

14,127.58

10%

1,765.95

10%

1,765.95

0%

0.00

100%

17,659.48

0.00

01.15.03

Excavacion en Roca Suelta

m3

260.13

60.49

15,735.26

80%

12,588.21

10%

1,573.53

10%

1,573.53

0%

0.00

100%

15,735.26

01.15.04

Refine y nivelacin de zanja, a=0.40m

5,419.40

0.69

3,739.39

80%

2,991.51

10%

373.94

10%

373.94

0%

0.00

100%

01.15.05

Cama de Apoyo para Tubera, e=0.10m., a=0.40m.

5,419.40

1.30

7,045.22

80%

5,636.18

10%

704.52

10%

704.52

0%

0.00

100%

7,045.22

01.15.06

Tuberia de PVC SAP Clase 10, 1"x5m.

4,615.10

2.93

13,522.24

80%

10,817.79

10%

1,352.22

10%

1,352.22

0%

0.00

100%

13,522.24

01.15.07

Tuberia de PVC SAP Clase 10, 3/4"x5m.

804.30

2.91

2,340.51

80%

1,872.41

10%

234.05

10%

234.05

0%

0.00

100%

2,340.51

3,739.39

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Und.

MES 01
Metrado

Precio S/.

Parcial S/.

MONTO

MES 02
%

MES 03
%

MONTO

MES 04

Item

Descripcin

01.15.08

Accesorios, Tee PVC SAP 1"x1"

und

6.00

8.95

53.70

80%

42.96

10%

5.37

10%

5.37

0%

01.15.09

Accesorios, Reduccion PVC SAP 1" a 3/4"

und

3.00

8.35

25.05

80%

20.04

10%

2.51

10%

2.51

0%

01.15.10

Accesorios, Tapn PVC SAP 1"

und

1.00

6.63

6.63

80%

5.30

10%

0.66

10%

0.66

01.15.11

Accesorios, Tapn PVC SAP 3/4"

und

1.00

5.61

5.61

80%

4.49

10%

0.56

10%

0.56

01.15.12

Accesorios, Codo PVC SAP 1"x45

und

4.00

7.25

29.00

80%

23.20

10%

2.90

10%

01.15.13

Doble Prueba Hidraulica

5,419.40

0.92

4,985.85

80%

3,988.68

10%

498.58

10%

01.15.14

Relleno y Apisonado de Zanja

m3

1,734.21

17.65

30,608.81

80%

24,487.05

10%

3,060.88

10%

3,060.88

01.16

CAMARA ROMPE PRESION TIPO CRP-7 (09 UNIDADES)

01.16.01

Trazo, Nivelacin y Replanteo de Estructura

m2

16.20

0.51

8.26

70%

5.78

20%

1.65

10%

01.16.02

Excavacion Manual en Material Conglomerado

m3

8.10

11.98

97.04

70%

67.93

20%

19.41

10%

01.16.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

0.81

272.18

220.47

70%

154.33

20%

44.09

10%

01.16.04

Encofrado y Desencofrado-Losa de Fondo y Muros

m2

92.88

27.14

2,520.76

70%

1,764.53

20%

504.15

10%

01.16.05

Encofrado y Desencofrado - Losa Superior

m2

85.80

70%

60.06

20%

17.16

10%

8.58

01.16.06

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

423.11

4.57

1,933.61

70%

1,353.53

20%

386.72

10%

193.36

01.16.07

Concreto f'c=210 kg/cm2

m3

9.45

391.34

3,698.16

70%

2,588.71

20%

739.63

10%

369.82

01.16.08

Tarrajeo Interior con Impermeabilizante, 1:2, e=1 cm

m2

30.96

01.16.09

Tarrajeo Exterior (mortero 1:4), e=1 cm

m2

73.58

11.83

870.45

70%

609.32

20%

174.09

10%

87.05

01.16.10

Tapa Sanitaria Metlica de 0.60x0.60m. con llave tipo buja

und

9.00

153.60

1,382.40

70%

967.68

20%

276.48

10%

138.24

01.16.11

Accesorios de Ingreso CRP-7 (RD=1", valv. y acces. de 1")

und

54.00

124.18

6,705.72

70%

4,694.00

20%

1,341.14

10%

670.57

01.16.12

Accesorios de Salida y Desague-Rebose CRP-7 (RD=1", Des=und

33.00

103.78

3,424.74

70%

2,397.32

20%

684.95

10%

01.16.13

Sistema de Ventilacin, 1/Estruct. (con tapon perforado)

und

9.00

28.85

259.65

70%

181.76

20%

51.93

10%

01.16.14

Dado de Concreto (1:6) 0.3x0.2x0.2m, desague 2", tapn perforund

9.00

52.73

474.57

70%

332.20

20%

94.91

10%

01.16.15

Pintura en Exterior

m2

73.58

6.00

441.48

70%

309.04

20%

88.30

01.16.16

Empedrado, e=0.125m,a=0.6-0.8m.

m2

41.04

19.01

780.17

70%

546.12

20%

01.16.17

Eliminacin de Material de Desmonte

m3

9.72

8.24

80.09

70%

56.06

20%

01.17

VALVULA DE REGULACION EN RD (10 UNIDADES)

01.17.01

Trazo, Nivelacin y Replanteo de Estructura

m2

4.20

01.17.02

Excavacion Manual en Material Conglomerado

m3

01.17.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

01.17.04

Encofrado y Desencofrado

m2

01.17.05

Concreto f'c=175 kg/cm2

m3

2.37

01.17.06

Tarrajeo Exterior e Interior (mortero 1:4), e=1.0 cm

m2

37.60

12.46

01.17.07

Tapa sanitaria metlica de 0.50x0.40m. con llave tipo buja

und

10.00

139.93

01.17.08

Valvula de Control y Accesorios, 1"

und

8.00

67.35

01.17.09

Valvula de Control y Accesorios, 3/4"

und

2.00

01.17.10

Pintura en Exterior

m2

01.17.11

Grava Fina

m3

01.17.12

Eliminacin de Material de Desmonte

ACUMULADO
%

MONTO

0.00

100%

53.70

0.00

100%

25.05

0%

0.00

100%

6.63

0%

0.00

100%

2.90

0%

0.00

100%

29.00

498.58

0%

0.00

100%

4,985.85

0%

0.00

100%

30,608.81

0.83

0%

0.00

100%

8.26

9.70

0%

0.00

100%

97.04

22.05

0%

0.00

100%

220.47

252.08

0%

0.00

100%

2,520.76

0%

0.00

100%

85.80

0%

0.00

100%

1,933.61

0%

0.00

100%

3,698.16

0%

0.00

100%

0%

0.00

100%

870.45

0%

0.00

100%

1,382.40

0%

0.00

100%

6,705.72

342.47

0%

0.00

100%

3,424.74

25.97

0%

0.00

100%

259.65

47.46

0%

0.00

100%

474.57

10%

44.15

0%

0.00

100%

441.48

156.03

10%

78.02

0%

0.00

100%

780.17

16.02

10%

8.01

0%

0.00

100%

80.09

1.07

50%

1.07

0%

0.00

100%

2.14

23,512.48

3.31

25.92

17.09

529.11

5.61

0.00

70%

370.37

20%

105.82

10%

52.91

4,725.77

529.11

0.00

0.51

2.14

0%

0.00

50%

15.37

11.98

184.13

0%

0.00

50%

0%

0.00

100%

184.13

0.42

272.18

114.32

0%

0.00

50%

57.16

50%

57.16

0%

0.00

100%

114.32

23.30

32.27

751.89

0%

0.00

50%

375.95

50%

375.95

0%

0.00

100%

751.89

335.35

794.78

0%

0.00

50%

397.39

50%

397.39

0%

0.00

100%

468.50

0%

0.00

50%

234.25

50%

234.25

0%

0.00

100%

468.50

1,399.30

0%

0.00

50%

699.65

50%

699.65

0%

0.00

100%

1,399.30

538.80

0%

0.00

50%

269.40

50%

269.40

0%

0.00

100%

538.80

65.92

131.84

0%

0.00

50%

65.92

50%

65.92

0%

0.00

100%

131.84

19.60

6.00

117.60

0%

0.00

50%

58.80

50%

58.80

0%

0.00

100%

117.60

0.50

140.89

70.45

0%

0.00

50%

35.22

50%

35.22

0%

0.00

100%

70.45

m3

18.45

8.24

152.03

0%

0.00

50%

76.01

50%

76.01

0%

0.00

100%

152.03

92.07

50%

5,355.59

92.07

0.00

794.78

01.18

VALVULAS DE PURGA EN RD (08 UNIDADES)

01.18.01

Trazo, Nivelacin y Replanteo de Estructura

m2

18.00

0.51

9.18

0%

0.00

50%

4.59

50%

4.59

0%

0.00

100%

9.18

01.18.02

Excavacion Manual en Material Conglomerado

m3

3.02

11.98

36.18

0%

0.00

50%

18.09

50%

18.09

0%

0.00

100%

36.18

0.00

01.18.03

Encofrado y Desencofrado

m2

32.96

32.27

1,063.62

0%

0.00

50%

531.81

50%

531.81

0%

0.00

100%

1,063.62

01.18.04

Concreto f'c=175 kg/cm2

m3

1.52

335.35

509.73

0%

0.00

50%

254.87

50%

254.87

0%

0.00

100%

509.73

01.18.05

Tarrajeo Exterior e Interior (mortero 1:4), e=1.0 cm

m2

32.00

12.46

398.72

0%

0.00

50%

199.36

50%

199.36

0%

0.00

100%

398.72

01.18.06

Tapa sanitaria metlica de 0.50x0.40m. con llave tipo buja

und

8.00

139.93

1,119.44

0%

0.00

50%

559.72

50%

559.72

0%

0.00

100%

1,119.44

01.18.07

Valvula de Purga y Accesorios, 1"

und

8.00

97.80

782.40

0%

0.00

50%

391.20

50%

391.20

0%

0.00

100%

782.40

01.18.08

Valvula de Purga y Accesorios, 3/4"

und

8.00

98.18

785.44

0%

0.00

50%

392.72

50%

392.72

0%

0.00

100%

785.44

01.18.09

Pintura en Exterior

m2

15.68

6.00

94.08

0%

0.00

50%

47.04

50%

47.04

0%

0.00

100%

94.08

01.18.10

Dado de Concreto (1:6) 0.30x0.20x0.20m, desague 2", tapn und

8.00

15.14

121.12

0%

0.00

50%

60.56

50%

60.56

0%

0.00

100%

121.12

01.18.11

Grava Fina

m3

2.88

140.89

405.76

0%

0.00

50%

202.88

50%

202.88

0%

0.00

100%

405.76

01.18.12

Eliminacin de Material de Desmonte

m3

3.63

8.24

29.91

0%

0.00

50%

14.96

50%

14.96

0%

0.00

100%

29.91

01.19

CONEXIONES DOMICILIARIAS (76 UNIDADES)

01.19.01

Trazo y Replanteo en CD (hasta caja de paso)

50%

541.50

50%

541.50

100%

1,083.00

01.19.02

Excavacion Manual de Zanja en Conglomerado, 0.40x0.50m.

m3

01.19.03

Cama de Apoyo para Tubera, e=0.10m., a=0.30m.

01.19.04

Tuberia de PVC SAP Clase 10, 1/2"x5m.

1,900.00

01.19.05

Accesorios en Conexin (RD=1")

und

01.19.06

Accesorios en Conexin (RD=3/4")

und

01.19.07

Caja de Paso C/Tapa (concreto 1:6)

und

76.00

28.99

01.19.08

Accesorios en Caja de Paso

und

76.00

25.79

01.19.09

Doble Prueba Hidraulica

1,900.00

0.92

01.19.10

Relleno y Apisonado de Zanja

m3

228.00

17.65

22,587.66

0.00

1,900.00

0.57

1,083.00

0%

0%

456.00

11.98

5,462.88

0%

0.00

0%

0.00

50%

2,731.44

50%

2,731.44

100%

5,462.88

1,900.00

0.61

1,159.00

0%

0.00

0%

0.00

50%

579.50

50%

579.50

100%

1,159.00

2.13

4,047.00

0%

0.00

0%

0.00

50%

2,023.50

50%

2,023.50

100%

4,047.00

66.00

11.55

762.30

0%

0.00

0%

0.00

50%

381.15

50%

381.15

100%

762.30

10.00

13.80

138.00

0%

0.00

0%

0.00

50%

69.00

50%

69.00

100%

138.00

2,203.24

0%

0.00

0%

0.00

50%

1,101.62

50%

1,101.62

100%

2,203.24

1,960.04

0%

0.00

0%

0.00

50%

980.02

50%

980.02

100%

1,960.04

1,748.00

0%

0.00

4,024.20

0%

0%

0.00

50%

874.00

50%

874.00

100%

1,748.00

0%

0.00

50%

2,012.10

50%

2,012.10

100%

4,024.20

01.20

LAVADEROS DOMICILIARIOS (75 UNIDADES)

01.20.01

Trazo y replanteo

m2

110.25

0.92

91,431.64
101.43

20%

20.29

40%

40.57

20%

20.29

20%

20.29

100%

0%

101.43

01.20.02

Excavacion manual en terreno normal

m3

441.45

11.98

5,288.57

20%

1,057.71

40%

2,115.43

20%

1,057.71

20%

1,057.71

100%

5,288.57

0.00

01.20.03

Concreto en Cimiento 1:8 + 30% PM.

m3

14.18

240.52

3,410.57

20%

682.11

40%

1,364.23

20%

682.11

20%

682.11

100%

3,410.57

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Und.

MES 01
Metrado

Precio S/.

Parcial S/.

MES 02

MONTO

19,900.52

20%

3,980.10

40%

10,563.53

20%

2,112.71

40%

4.54

11,278.72

20%

2,255.74

17.09

1,636.54

20%

327.31

6,546.51

20%

1,309.30

40%

2,891.25

20%

578.25

40%

5,418.75

20%

1,083.75

40%

MES 03

Item

Descripcin

01.20.04

Encofrado y desencofrado de Lavadero

m2

499.01

39.88

01.20.05

Concreto f'c=175 kg/cm2

m3

31.50

335.35

01.20.06

Acero fy=4200 kg/cm2 Grado 60, 1/4"

kg

2,484.30

01.20.07

Tarrajeo Interior con Impermeabilizante, 1:2, e=1 cm

m2

95.76

01.20.08

Tarrajeo exterior de muros, e=1 cm, 1:4

m2

524.14

12.49

01.20.09

Accesorios lavadero, agua

und

75.00

38.55

01.20.10

Accesorios lavadero, desague

und

75.00

72.25

01.20.11

Empedrado, e=0.125m, Emboquillado mortero 1:4

m2

01.20.12

Zanjas de Infiltracin (zanja 0.40x0.80 + Tubera perf. + Gravas m

01.21

LAVADERO CENTRO EDUCATIVO (03 UND.)

01.21.01

Trazo y replanteo

01.21.02

Excavacion manual en terreno normal

m3

01.21.03

Eliminacin de Material de Desmonte

m3

2.68

8.24

22.08

01.21.04

Cimiento corrido mezcla 1:10 Cemento-Hormigon 30% Piedra m3

0.29

203.63

59.05

01.21.05

Encofrado y desencofrado de Lavadero

m2

5.09

39.88

202.99

01.21.06

Concreto en losa superior f'c=175 kg/cm2.

m3

0.62

373.09

231.32

01.21.07

Acero fy=4200 kg/cm2 Grado 60, 1/4"

kg

51.32

4.54

232.99

01.21.08

Tarrajeo Interior con Impermeabilizante, 1:2, e=1 cm

m2

1.98

17.09

33.84

0%

01.21.09

Tarrajeo exterior de muros, e=1 cm, 1:4

m2

9.77

12.49

122.03

0%

0.00

0%

0.00

0%

01.21.10

Suministro e Instalacion de accesorios en lavadero tipo I.E

und

1.00

229.58

229.58

0%

0.00

0%

0.00

01.21.11

Tubera PVC D=1/2"

5.00

3.59

17.95

0%

0.00

0%

0.00

01.21.12

Asentado de Piedra con Concreto

m2

0.70

151.50

106.05

0%

0.00

0%

0.00

MES 04

MONTO

7,960.21

20%

3,980.10

20%

4,225.41

20%

2,112.71

20%

40%

4,511.49

20%

2,255.74

40%

654.62

20%

327.31

2,618.60

20%

1,156.50

20%

2,167.50

20%

MONTO

3,980.10

100%

19,900.52

2,112.71

100%

10,563.53

20%

2,255.74

100%

11,278.72

20%

327.31

100%

1,309.30

20%

1,309.30

100%

6,546.51

578.25

20%

578.25

100%

2,891.25

1,083.75

20%

1,083.75

100%

5,418.75

1,636.54

52.50

23.85

1,252.13

20%

250.43

40%

500.85

20%

250.43

20%

250.43

100%

1,252.13

187.50

123.43

23,143.13

20%

4,628.63

40%

9,257.25

20%

4,628.63

20%

4,628.63

100%

23,143.13

1,287.23
m2

ACUMULADO
%

2.86
2.23

0.92
11.98

2.63
26.72

0%

0.00

0%

0.00

0%

0.00

0%

0.00

100%

2.63

100%

2.63

0%

0.00

0%

0.00

0%

0.00

100%

26.72

100%

26.72

0%

0.00

0%

0.00

0%

0.00

100%

22.08

100%

0%

0.00

0%

0.00

0%

0.00

100%

59.05

100%

59.05

0%

0.00

0%

0.00

0%

0.00

100%

202.99

100%

202.99

0%

0.00

0%

0.00

0%

0.00

100%

231.32

0%

0.00

0%

0.00

0%

0.00

0%

22.08

100%

231.32

100%

232.99

100%

232.99

100%

33.84

100%

33.84

0.00

100%

122.03

100%

122.03

0%

0.00

100%

229.58

100%

229.58

0%

0.00

100%

17.95

100%

17.95

0%

0.00

100%

106.05

100%

106.05

0%

01.22

PRUEBA DE CONTROL

01.22.01

Diseos de Mezclas (F'c=175kg/cm2 ; F'c=210kg/cm2)

und

2.00

350.00

700.00

20%

140.00

20%

140.00

30%

210.00

30%

210.00

100%

700.00

01.22.02

Prueba de Calidad de Concreto (Rotura de probeta)

und

15.00

30.00

1,150.00
450.00

20%

90.00

20%

90.00

30%

135.00

30%

135.00

100%

450.00

0%

0.00

9,110.00

15%

1,366.50

15%

1,366.50

35%

3,188.50

35%

3,188.50

100%

9,110.00

24,738.80

24,738.80

01.23

MITIGACION AMBIENTAL

01.23.01

Mitigacion del Medio Ambiente

glb

1.00

9,110.00

01.23.02

Seguridad e Higiene Ocupacional

33,848.80
glb

1.00

24,738.80

01.24

FLETE (AGUA)

01.24.01

Flete Terrestre (Sistema de Agua)

glb

1.00

45,354.38

Flete Rural (Sistema de Agua)

glb

1.00

60,071.09

01.24.02

0.00

15%

3,710.82

15%

3,710.82

35%

8,658.58

35%

8,658.58

100%
0%

0.00

45,354.38

80%

36,283.50

20%

9,070.88

0%

0.00

0%

0.00

100%

45,354.38

60,071.09

80%

48,056.87

20%

12,014.22

0%

0.00

0%

0.00

100%

60,071.09

151.60

30%

45.48

40%

60.64

30%

45.48

0%

0.00

100%

151.60

880.21

30%

264.06

40%

352.08

30%

264.06

105,425.47

02

SANEAMIENTO

335,589.96

02.01

CASETA DE UNIDAD BASICA DE SANEAMIENTO (75 UNIDADES)

259,678.97

02.01.01

Trazo, Nivelacin y Replanteo de Estructura

m2

445.88

02.01.02

Excavacion Manual en Material Conglomerado

m3

91.88

0%

0.00

100%

02.01.03

Concreto Simple f'c = 100 kg/cm2 (para solado)

m3

18.38

261.47

4,805.82

30%

1,441.75

40%

1,922.33

30%

1,441.75

0%

0.00

100%

4,805.82

02.01.04

Concreto f'c=140kg/cm2 +30% piedra

m3

55.13

230.28

12,695.34

30%

3,808.60

40%

5,078.13

30%

3,808.60

0%

0.00

100%

12,695.34

02.01.05

Acero fy=4200 kg/cm2 Grado 60, 3/8"

kg

02.01.06

Encofrado y Desencofrado

m2

02.01.07

Concreto f'c=175 kg/cm2 en muros

m3

65.40

02.01.08

Encofrado y Desencofrado - Losa Superior

m2

211.50

02.01.09

Concreto f'c=175 kg/cm2 en losa

m3

29.53

02.01.10

Concreto ciclopeo f'c=140 kg/cm2 +70 % PM

m3

148.50

144.37

02.01.11

Muro de Ladrillo K-K, Soga-Caravista, amarre/Cemento-Arena m2

600.00

02.01.12

Tarrajeo Interior (mortero 1:4), e=1.0 cm.

m2

333.75

15.03

5,016.26

02.01.13

Armazon techo caseta doble compostera con madera tornillo

und

75.00

136.43

10,232.25

02.01.14

Cobertura con Calamina Galvanizada

m2

75.00

126.52

9,489.00

02.01.15

Suministro e Instalacin de Tubera PVC SAL, 2"

225.00

4.61

1,037.25

02.01.16

Aparatos y Accesorios Sanitarios - Desague

und

75.00

220.28

16,521.00

02.01.17

Suministro e Instalacin de Tubera PVC , 1/2"

375.00

5.13

1,923.75

02.01.18

Aparatos y Accesorios sanitarios - Agua

und

75.00

146.06

10,954.50

02.01.19

Puerta (madera, calamina, etc.) con marco de madera

und

75.00

54.82

4,111.50

0%

02.01.20

Ventanas metalicas de extraccion de compost

und

75.00

150.97

11,322.75

02.01.21

Baranda de tubo negro D=11/2

210.00

159.04

02.01.22

Eliminacin de Material de Desmonte

m3

110.25

3.75

02.01.23

ZANJA DE PERCOLACION

0.00

02.01.23.01

OBRAS PRELIMINARES

0.00

02.01.23.01.01 Limpieza y desbrose de terreno manual


02.01.23.01.02 Trazo, Nivelacin y Replanteo.
02.01.23.02

m2

0.34
9.58

0.00
0.00

2,028.60

4.72

9,574.99

30%

2,872.50

40%

3,830.00

30%

2,872.50

0%

0.00

100%

9,574.99

754.88

28.73

21,687.70

30%

6,506.31

40%

8,675.08

30%

6,506.31

0%

0.00

100%

21,687.70

310.19

20,286.43

30%

6,085.93

40%

8,114.57

30%

6,085.93

0%

0.00

100%

20,286.43

31.26

6,611.49

30%

1,983.45

40%

2,644.60

30%

1,983.45

0%

0.00

100%

6,611.49

310.19

9,159.91

30%

2,747.97

40%

3,663.96

30%

2,747.97

0%

0.00

100%

9,159.91

21,438.95

30%

6,431.68

40%

8,575.58

30%

6,431.68

0%

0.00

100%

21,438.95

0%

0.00

0%

0.00

60%

17,733.60

40%

11,822.40

100%

29,556.00

0%

0.00

0%

0.00

60%

3,009.76

40%

2,006.51

100%

5,016.26

0%

0.00

0%

0.00

60%

6,139.35

40%

4,092.90

100%

10,232.25

0%

0.00

0%

0.00

60%

5,693.40

40%

3,795.60

100%

0%

0.00

0%

0.00

60%

622.35

40%

414.90

100%

1,037.25

0%

0.00

0%

0.00

60%

9,912.60

40%

6,608.40

100%

16,521.00

0%

0.00

0%

0.00

60%

1,154.25

40%

769.50

100%

1,923.75

0%

0.00

0%

0.00

60%

6,572.70

40%

4,381.80

100%

10,954.50

0.00

0%

0.00

60%

2,466.90

40%

1,644.60

100%

4,111.50

0%

0.00

0%

0.00

60%

6,793.65

40%

4,529.10

100%

11,322.75

33,398.40

0%

0.00

0%

0.00

60%

20,039.04

40%

13,359.36

100%

33,398.40

413.44

0%

0.00

0%

0.00

60%

248.06

40%

165.38

100%

413.44

283.50

49.26

0.45

29,556.00

127.58

02.01.23.02.02 Excavacion en Roca Dura (5%)

9,489.00

0.00
0.00

0%

0.00

0%

0.00

50%

63.79

50%

63.79

100%

127.58

283.50

0.33

93.56

0%

0.00

0%

0.00

50%

46.78

50%

46.78

100%

93.56

m3

170.10

5.31

903.23

0%

0.00

0%

0.00

50%

451.62

50%

451.62

100%

903.23

3,925.91

100%

7,851.82

MOVIMIENTO DE TIERRAS

02.01.23.02.01 Excavacion en material conglomerado (95%)

880.21

0.00
m3

170.10

0%

0.00

0%

0.00

50%

3,925.91

50%

02.01.23.02.03 Refine y compactacion de fondos

m2

283.50

0.60

170.10

0%

0.00

0%

0.00

50%

85.05

50%

85.05

100%

170.10

02.01.23.02.04 Relleno con grava redodnde de 1 a 5 cm

m3

37.01

88.82

3,287.23

0%

0.00

0%

0.00

50%

1,643.61

50%

1,643.61

100%

3,287.23

02.01.23.02.05 Relleno con terreno natural

m3

37.01

1.16

42.93

0%

0.00

0%

0.00

50%

21.47

50%

21.47

100%

42.93

02.01.23.03

SISTEMA DE DESAGUE

46.16

7,851.82

0.00

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO


OBRA

INSTALACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO DE


: LAS LOCALIDADES DE SAN PEDRO DE QUILLO Y NUEVO MILAN DE PACCHANAN
DISTRITO DE CHACCHO, PROVINCIA ANTONIO RAYMONDI, REGION ANCASH

DIAS CALENDARIO = 30

Ubicacin : CHACCHO-ANTONIO RAYMONDI- ANCASH


Item

Descripcin

02.01.23.03.01 Accesorios para zanjas de infiltracion

Und.

MES 01
Metrado

Precio S/.

Parcial S/.

und

75.00

79.12

5,934.00

MES 02

MONTO

0%

0.00

0%

0.00

75,910.99

0.00

MES 03

MES 04

MONTO

50%

2,967.00

50%

0.00

0.00

ACUMULADO
%

2,967.00

100%

MONTO
5,934.00

02.02

FLETE (SANEAMIENTO)

0.00

0%

0.00

02.02.01

Flete Terrestre chaccho

glb

1.00

36,760.90

36,760.90

80%

29,408.72

20%

7,352.18

0%

0.00

0%

0.00

100%

36,760.90

02.02.02

Flete Rural Chaccho

glb

1.00

39,150.09

39,150.09

80%

31,320.07

20%

7,830.02

0%

0.00

0%

0.00

100%

0.00
COSTO DIRECTO (S/.)

902,149.66

380,518.12

235,117.07

180,659.35

105,855.12

GASTOS GENERALES (8.69%)

78,400.00

33,068.37

20,432.51

15,699.94

9,199.18

UTILIDAD (6.31%)
SUBTOTAL
IGV(18%)
COSTO D ELA OBRA
SUPERVICION DE LA OBRA

39,150.09
902,149.66

56,925.64

24,010.69

14,835.89

11,399.60

6,679.46

1,037,475.30

437,597.19

270,385.46

207,758.89

121,733.76

186,745.55

78,767.49

48,669.38

37,396.60

21,912.08

1,224,220.86

516,364.68

319,054.84

245,155.49

143,645.84

38,468.00

4,513.70

16,225.44

10,025.48

7,703.38

AVANCE ACUMULADO MENSUAL(%)

42.18%

26.06%

20.03%

11.73%

PORCENTAJE DE AVANCE ACUMULADO

42.18%

68.24%

88.27%

100.00%

902,149.66

100.00%

Vous aimerez peut-être aussi