Vous êtes sur la page 1sur 2

Your most complete professional resource.

The American Institute of Chemical Engineers.


Kansas City Chapter Technical Article

Featured in 02/01/2007, Issue #5 Newsletter

OSBL Tips for Process Engineers


By Karen Bray
Many capital projects are divided into two parts, inside the battery limits (ISBL) and outside the
battery limits (OSBL). ISBL is typically the process units and the focus of the project, whether it is
a grassroots facility or a revamp of an existing unit. OSBL consists of all connections necessary to
make ISBL function: feed and product streams, utilities, waste streams, etc. Often times OSBL
does not get as much attention as the ISBL during the life of the project. However, it can easily
amount to one third of the total project cost or more. Diligently working to minimize the OSBL
scope can have a significant impact on overall project cost. Lessons learned from past OSBL
projects are presented below to help highlight potential money savings opportunities for process
engineers to focus on.
1. Ask questions to learn as much about the ISBL process as possible.
On large projects, there may be separate contractors doing the ISBL and OSBL work. The ISBL
contractor may not be able (due to proprietary work or other agreements) or may not be willing
to share the process with the OSBL contractor. For the sake of overall project cost, the more
information that can be shared, the better. As an example, OSBL may be installing new pumps
to deliver feed to the unit, and ISBL may also be installing new pumps to raise the feed
pressure further. In some cases, one set of pumps might be able to be eliminated, or
optimizing the size of the pumps in series could result in a cost savings to the project.
A second example is a common case of ISBL utilizing product pumps that have high enough
head to require the system to be 300#. Analyzing the overall ISBL-OSBL flow scheme may
make it possible to drop to a 150# class system in the OSBL, thereby reducing project cost with
the help of a strategically placed relief valve.
2. Define the incoming and outgoing streams as much as possible.
Defining the streams will allow for educated decisions on where to pipe the streams to and
from. For instance, ISBL may require steam. Delivering 600 psig steam could be overkill if 150
psig would suffice.
On one project, ISBL had three vent streams products. The first instinct for OSBL was to pipe
them to the front end of the gas recovery (propane and butane) and treatment (H2S removal)
unit. Doing so increased the throughput of the unit significantly, triggering upgrades to
compressors, exchangers, and other equipment. When the vent stream compositions were
defined further, it became evident that two of the three vent streams had no significant
propane and butane to recover. Therefore the client was able to save considerable capital by
routing those two streams directly to the H2S removal section of the unit.

By Karen Bray

Page 1/2

Your most complete professional resource.


The American Institute of Chemical Engineers.
Kansas City Chapter Technical Article

Featured in 02/01/2007, Issue #5 Newsletter

3. Spend time with the tank farm personnel when working in an existing facility.
The majority of the cost for OSBL often comes from piping and tankage costs. The tank farm
personnel are the best resource to help the project understand the flexibility that exists in the
current system and are often not included in project planning. There may be out of service
piping that can be tested and reused, or simple jumpers that can be made to eliminate new pipe
or the need for new tankage. Taking the time to do research on the existing system can
potentially save significant money on a project.
4. Define insulation and tracing requirements early in the project.
Adding an inch and a half of insulation to a six inch line increases the space occupied by that line
on a pipe rack by 50 percent. Missing this insulation on even one line can sometimes cause a
complete change in civil/structural scope if there is no longer room to hold it in the rack. Having
to add a level or expand a pipe rack size late in a project can be a detriment to both budget and
schedule.
Tracing in the OSBL can be difficult to define until exact pipe routings are known. There may
not be steam in certain areas or even electricity available. Simply assuming steam or electricity
is available and applying a factor to pipe length to cover tracing costs early in a project can lead
to significantly low estimates. While this is not necessarily a cost-saving tip for OSBL, it is a
lesson learned and something that is easily missed in OSBL scope.
5. When working in an existing facility, meet as many people as possible.
The ISBL portion of the project is typically located in a well-defined area of a facility, and the link
to the rest of the existing facility is the OSBL. It is therefore important that those on the OSBL
are good ambassadors for the project. It tends to be those on the OSBL that end up in the
existing control rooms, units, and even the cafeteria answering questions about what the new
ISBL project is all about. On many projects, especially if it is a grassroots unit, the ISBL will not
have a large need to spend time in the existing facility. The better the relationships are between
the OSBL and the operators, engineers, and managers of that facility, the better the entire
project will likely go.
The tips presented above are a few key lessons learned based on past OSBL projects. Many of
them may seem straightforward or even obvious, but they can often be forgotten during todays
fast-paced capital projects. Hopefully taking time to think about these things can save your project
significant time and money overall.
By Karen Bray

Page 2/2

Vous aimerez peut-être aussi