Académique Documents
Professionnel Documents
Culture Documents
PROCEDURE
A.
2. The mix proportions are shown in Table 1. Calculate the quantity required for the beams
and cylinders. An extra 15% should be allowed for waste and also as a margin for possible
error in the assumed density of the concrete. The volume of the air test container is
7.07910-3 m3. If a density of 2350 kg/m3 is assumed, this calculation can be done in
advance to save time in the laboratory.
3. After making the moisture determinations on the aggregates and correcting for them,
each group will mix a batch. Groups 1 to 4 will add 25 grams of polypropylene fibres to
their batch. The laboratory mixers being used must first be dampened, spraying the
insides of the mixer with water from the hose and making sure that all sides of the
paddles are moistened then finally turning the mixer to the drain position for at least
three minutes.
4. The slump, fresh density and air content of the concrete should be measured and then
the beam and cylinders should be cast by rodding or vibrating depending on the slump.
5. The procedure for casting the beams is as follows:
Vibration (Slump less than 80 mm): One layer is used and the mold is over-filled so that
after consolidation the top of the concrete will be slightly above the edge of the mold.
Vibrate the concrete along the centreline of the mold at not less than 150 mm intervals.
Be careful not to touch the sides or bottom of the mold with the vibrator. Remove the
vibrator slowly after each insertion to eliminate voids. After vibrating, tap the sides of
the mold gently to dislodge any air bubbles.
Rodding (Slump greater than 80 mm): Two equal layers will be used. The number of
roddings per layer is specified as one for each 14 cm2 of surface area of the beam. After
rodding each layer spade around the sides of the beam with a trowel.
Table 1 Mix Design Proportions
SSD Mass
for Required
1 m3 (kg)
Design SSD
Masses (kg)
Cement
20.676
Water
9.924
CA
30.686
FA
38.714
Total
100.000
2350
6. The tops of the cylinders should be finished in the normal manner. The beams are to be
struck off level, finished with a sponge float and covered with plastic.
7. The following working day each group must strip and tag their beams and cylinders and
place them in the curing tanks, unless otherwise instructed.
B.
Figure 1 Third-Point Loading Proportion Requirements for PCC Flexural Strength Test
C:
Testing of Cylinders
1. After determining the hardened density of the cylinders, they should be capped and
tested in compression in the usual manner.
CALCULATIONS
1. The modulus of rupture is calculated as follows:
CASE I where fracture occurs within the middle third of the span:
R=
where
R
P
L
b
d
PL
b d2
CASE II where fracture occurs outside the middle third of the span as measured along
the beam bottom by no more than 5% of the span length (grace zone):
R=
where
3 P a
b d2
CASE III where fracture occurs more than 5% outside the middle third, the results of
the test are discarded (i.e. the test is indeterminate).
2. The constant k, which is sometimes used in converting compressive strength to modulus
of rupture is calculated as follows:
R
1000
k
fc
where
REPORT
1.
2.
The diagram in Datasheet 7.6b must be dimensioned and the fracture lines accurately drawn
thereon and their distance to the nearest support dimensioned. The appearance of the
specimens after stripping should also be reported, indicating whether there was any
honeycombing, large air bubbles, etc.
3.
The average Modulus of Rupture value obtained by your group should be evaluated in the
report against the OPS criterion.
4.
A tabular summary of the class results (posted on the instructors website) should also be
presented in the report with the non-reinforced data grouped separately from the fibre
reinforced data.
5.