Académique Documents
Professionnel Documents
Culture Documents
A) Overview of Contract:
Developing & Constructing New International Airport
B) Key Scope of works:
C) Main Constraints:
Procurement of bitumen 1,50,000 liters from Assam which is having lead time of
45 days
Hire charges per hour Rs. 850/- ; for 10 hours = Rs. 8500/-
Cost of diesel 7 liters per hour @ Rs. 70 per liter; considered for 10 hours =
4900/-
Total cost per day = Rs. 14,100/- X 4 Excavator required Rs. 56,400/- per
day and total cost estimated for 50 days = Rs. 28.20 lacs.
Hire charges per hour Rs. 1200/- ; for 10 hours = Rs. 12000/-
Cost of diesel 10 liters per hour @ Rs. 70 per liter; considered for 10 hours =
7000/-
Total cost per day = Rs. 19,700/- X 2.5(2+1 Excavator for 10 days)
Excavator required Rs. 49,250/- per day and total cost estimated for
45days = Rs. 22.16 lacs.
Hire charges per hour - Rs. 600/- ; for 10 hours = Rs. 6000/-
Cost of diesel 5 liters per hour @ Rs. 70 per liter; considered for 10 hours =
3500/-
Total cost per day = Rs. 10,200/- X 6 Excavator required Rs. 61,200/- per
day and total cost estimated for 56days = Rs. 34.27 lacs.
Selection of Equipment Dozer 1 no., Wheel loader 1 no., Tipper truck 18m3
capacity considering 800 m3 disposal of surplus earth/per day and completing
the work by 25 days.
o
Hire charges for dozer 1 no. per hour Rs.800 rate for 10 hrs = Rs. 8000/-
Hire charges for Wheel loader 1 no. per hour Rs. 600 rate for 10 hrs = Rs.
6000/-
Hire charges for tipper 8 No. per hour - Rs.400 rate, for 10 hrs = 32,000
Cost of diesel 5 litres per hour each @ 70 rs. Per litre , for 10 hours = 35,000/-
Total cost per day = Rs. 84,200/- and total cost estimated for 25 days is
Rs.21.20 lacs, unit rate arrived 20,000 m3 is Rs. 106/m3 also by using the
same equipments can be used or removing and stacking the balance
required earth at nearby site.
Cost of Showel for spreading and leveling the sand Depreciation cost
Rs.266/- per day X 15 days considered = Rs. 3990/- per day 200 cum
productivity considered, cost per cum = Rs. 19.95 per cum
Operator wages per month Rs. 20,000 per month required for 15 days,
cost per m3 = 10,000/200 = Rs. 50/m3
Diesel charges 4 ltrs per hour x Rs. 70 / ltr = Rs. 280 x 10 hrs = Rs. 2800/200 =
Rs. 14/m3 considered.
Wages for labour for compaction = Rs. 800/ per day, 800/200 = Rs.4/m3
Total cost = Rs. 437.95/m3 x total qty 3000 m3 = Rs. 13.14 lacs
Considering Total qty of area is 100m x 20m width = 2,000m2 will be started on
60th day as per programme.
o Cost of Showel and spreading and leveling the earth depreciation
cost Rs. 266 per day X 10 days considered = Rs. 2660
o Operator wages per month Rs.20,000 per month required for 10 days,
cost = Rs.6,666
o Diesel charges 4 litres per hour X Rs. 70/ ltr = Rs. 280 X 10 hrs = Rs.
28000/o Compaction using plate compactor / roller = Rs. 8000/day = Rs.80,000
o Operator food, accommodation and transport per day = Rs.300
o Total cost = Rs. 1.17 lacs
o Spraying of metal and bitumen mix in two layers:
o Supply cost for bitumen to be procured from Bongaingaon in Assam
1,50,000 liters @ Rs. 20/ liters considered cost for total qty = 30.00 Lacs
o Transportation cost per liter = Rs. 5.00/Liter = 7.50 Lacs
o Wastage 10% = 30 + 7.5 = 37.5 *10% = 3.75 Lacs
o Stocking and shifting to site = Re 1/ liter = Rs. 1.5 Lacs
o Cost of 10-20 mm metal delivery at site for 2000m2 X 0.2 mtr ht = 400m3
@ 600 rs/m3 = 2.4 Lacs
o Wastage 10% = 0.24 Lacs
o Cost of Hot mix plant Depreciation cost = RS. 4500/days X 40 days
required = 1.80 Lacs
o Transportation of hot bituminous mix through tipper truck = Rs.4000/
day including driver and diesel charges X 40 days = 1.60 Lacs
o Spreading and laying using paver Depreciation cost Rs. 8000 per day
cost for 40 days = RS. 3.20 Lacs
o Operator wages per month RS. 20,000 per month required for 40
days, cost = Rs. 27000 X 4 operators = 1.08 Lacs
o Diesel charges 10 litres per hour x Rs. 70/ ltr = Rs. 7000 X 40 days = Rs.
2.80 Lacs
o Compaction using roller 10 Ton Rs.8000 /day X 40 days = Rs. 3.20 Lacs
o Operator food, accommodation and transport per day = Rs. 300 X 8
days = 2400 X 40 days = 0.960 Lacs
TOTAL COST = Rs. 59.07 Lacs
J) Purchase Order Schedule
o
K) Programme Outline
Total scope will be executed in two parts
Part I
1. Excavation, dozing and disposal of surplus earth 1 to 25th days
2. Imported materials and sand filling start from 10th day to 25th day
3. Surface preparation, leveling and compaction 26th day to 46 days
4. Metal spreading 46th day to 60th day
5. Bitumen pavement 61st day to 80th day
Part II
1. Excavation, dozing and disposal of surplus earth 26th to 50th day
2. Imported materials and sand filling start from 26th day to 46 days
3. Surface preparation, leveling and compaction 47th day to 65th day
4. Metal spreading 66th day to 80th day
5. Bitumen pavement 81st day to 100th day
L) Cost Summary:
1. Cost for Excavation works = Rs. 22.16 Lacs
2. Cost for disposal works = Rs. 21.20 Lacs
3. Sand filling = Rs. 13.14 Lacs
4. Cost of Bitumen pavement = Rs. 60.24 Lacs
GRAND TOTAL COST = 116.74 Lacs
For each order qty of 30,000 ltrs X 5 orders, 3 trucks per order shall
be engaged for bringing in bitumen from refinery to airport site.
O) Recommendation / Conclusions
1. As the project to be executed with in short duration and it is time
bound, all materials and equipment shall be mobilized as per the
above plan and HO approvals on resources should not be delayed.
2. As bitumen is brought in from long distance and the lead time is
more, it is better to post a material expeditor and loading point for
better follow up and ensuring timely delivery at site.