SCOPE & SPECIFICATION FOR NEW PEB BLDG

HITECH is looking for supplier with the right capacities to cater it`s need for New Pre
Engineered Building for it`s new facility at Gram Bardari , Distt Indore ( MP )
Below is the scope and brief description of the building :

SCOPE OF PROJECT
Design & Supply pre-engineered steel building ( PEB ) to the specification as defined further.
The Scope briefly consists of Design , Engineering , Material supply , Fabrication & Safe
erection of the said building to the satisfaction of HiTech. The PEB shall consist of all required
sections necessary to erect the designed specified structure like Primary , Secondary steel
sections , foundation anchor bolts together with few templates , wind bracings , sag rods , sag
angles , wall & roof purlins sections , girt sections , wall & roof cladding sections , required
hardware necessary for on site erection , partition walls , Mezzanine floor with section
decking , high tensile nuts & bolts along with all necessary steel sections required to erect
specified PreEngineered Building. The details are further defined below .

DESCRIPTION OF BUILDING
The brief description of building & scope is as follows :
FEATURES / TYPE
DESCRIPTION
Building Type
Multi Span Steel Building
Width of Building
106 ft ( 32.3 m) O/O of Steel Line
Length of Building
164 ft ( 50 m ) O/O Steel Line
Height of Building
8 m eve
Roof Slope
1: 10 with Centre crown , sloping both sides
Front End Frame
Rigid Frame
Back End Frame
Rigid Frame
Roof Bracing

Diagonal Angle / Bright bar Bracings as per design

Wall Bracing

Diagonal Bright bar Bracings as per design

Girts

Side wall girts & end wall girts are mounted on


exterior face of main columns

Roof & Wall Panels


Roof Panel
Wall Panel

0.47 mm Galvalum bare profiled sheet 550 Mpa


0.5mm both side colour coated Galvalum profiled
550 MPa sheet. External colour shall be Off white &
internal shall be light steel grey

Brickwork
Brick work height

2.5 m ( by others )

Crane EOT
Crane EOT

5 Ton Cap in one width module only

Crane Beams for long travel

Required of suitable size for the crane selected

Shutters
Number of Frame openings

3 nos

Size of Frame Openings

2 nos of 5m width x 5m height & 1 no of 3 m width x 4 m ht )

Other Miscellaneous Items


Sky light Panels

Cross reinforced profiled fibre sheet 2mm thk , 18m long on each
side in each bay

Vents

Turbo ventilators , numbers to be advised

Down take Pipe

Every bay at 6.25 meters column

Sheeting Fasteners

Hex Head self tapping screws with neoprene / metal washers duly
zinc plated

Accessories like Flashings, trims , Eave gutters &


Down pipes, Ridge corners sloping & corner vertical
etc

Required

Sealer & rope seals

To be applied on all sidelaps & endlaps of roof panels and around


self flashing windows. Sealer shall be asbestos fibre filled ,
pressure sensitive butyle tape. It shall be non non shrinking ,
nontoxic type with superior adhesion to metals

Closures & Filler Strips/ Flashings

Solid or closed cell ETP closures matching the profile of the panel
shall be installed along the eaves , rake & other locations as
required

Paint on Structural members


Anchor bolts & templates

One coat of Grey primer at Factory & 2 coats of finish Synthetic


Enamel paint at site with spray or brush
Required in numbers as required

Design Loads
Roof Live Load

59 Kg / sqm

Wind Speed

39 m / sec for Indore

Additional Load

Load from 5 T Capacity EOT Crane operation in one Width module


& 5Ton future crane in second width module

Mezzanine Load

300 Kg / m2 Live load + 3" thk RCC Slab Dead Load

Seismic Zone ( Zone Z )


Deflection in Main Frame
Vertical
Lateral
Purlins

III ( 0.16 ), As per IS 1893 , Rev 2002 for Indore


L /180
EH / 100
L / 180

Applicable Codes
PEB Building
Steel Member Design
Steel Member Analysis / Finite element
analysis

IS 875- III 1987 ( reaffirmed in 1997 ) Code of Practice for Design


Loads for buildings & structures for Loads
Design as per IS -800 2007 LSD parameters
STAD - 2007 software

Cold Formed Members

Design as per IS 801 - 1975 code of practice

Welding

Full Welding on both sides of the flange with Web

MATERIAL SOURCE
HR Plates / HR Coils
Angle / Channel / Beam / Round Bars
G I Pipe
M S Pipe
SAW Wire SAW Flux
MIG Wire / Welding Electrode
Primer / Enamel paint
Galvalum Coil for Roof & Wall panels
Hardware
Fibre glass

ESSAR / ISPAT / JSW


ISPAT / JSW
TATA / ISPAT / IISCO
SURYA / JINDAL
HD Wire /ESAB / ADOR
ESAB / ADOR / D & H
BERGER / NEROLAC / ASIAN
ISPAT or to be advised by Supplier
To be advised
To be advised

OTHER TERMS & CONDITION


* One set of Structural calculation for the building shall be provided.
* You shall provide all fabrication & other drawings in soft copy with minimum 2 sets of hard
copy.
* A Letter of Certification to the structural stability of Building is required
* As Built Drgs required 2 sets together with soft copy after incorporating all changes during
construction.
* HITECH shall have Right of Inspection of material during fabrication at your office / site
* Unloading & proper storage of all material at site shall be responsibility of Supplier
* Site Manager during construction period shall be required

* WC / PF to be covered for all site workers


* Idemnify HITECH against any accident or govt liability due to work in your scope
* Warranty for 1 year from Completion against any manufacturing / material defect. Supplier /
Erector shall check any leak from the structure / sheeting after first monsoon spell. You shall
repair leak or defect , if any , at no extra cost

DELIVERY TIME
GA Drawing / Foundation Layout Drawing
/ Foundation Load Data / Fabrication
drawings

Within 3 weeks of contract award

Supply of all materials at Site

Within 10 weeks from contract award

Vital Erection Completion of Building

Within 15 weeks from contract award

Final Completion of Building

Within 20 weeks from contract award

COMMERCIAL
To be advised with complete cost break up together with Technical commercial details