Académique Documents
Professionnel Documents
Culture Documents
time in unproductive meetings than in performing functional activities. In addition, the nature of the task force position caused many individuals to shift membership within the informal organization. Many functional managers then placed nonqualified and inexperienced
individuals on task forces. The result was that the group soon became ineffective because
they either did not have the information necessary to make the decisions, or lacked the authority (delegated by the functional managers) to allocate resources and assign work.
Development of the task force concept was a giant step toward conflict resolution:
Work was being accomplished on time, schedules were being maintained, and costs were
usually within budget. But integration and coordination were still problems because there
were no specified authority relationships or individuals to oversee the entire project
through completion. Attempts were made to overcome this by placing various people in
charge of the task force: Functional managers, division heads, and even upper-level management had opportunities to direct task forces. However, without formal project authority relationships, task force members remained loyal to their functional organizations, and
when conflicts came about between the project and functional organization, the project always suffered.
Although the task force concept was a step in the right direction, the disadvantages
strongly outweighed the advantages. A strength of the approach was that it could be established very rapidly and with very little paperwork. Integration, however, was complicated; work flow was difficult to control; and functional support was difficult to obtain because it was almost always strictly controlled by the functional manager. In addition, task
forces were found to be grossly ineffective on long-range projects.
The next step in the evolution of work integration was the establishment of liaison departments, particularly in engineering divisions that perform multiple projects involving a
high level of technology (see Figure 33). The purpose of the liaison department was to
ENGINEERING
DIVISION
LIAISON DEPT
ELECTRONICS
THERMODYNAMICS
STRUCTURES
LEGEND
FORMAL AUTHORITY FLOW
INFORMAL/REPORTING
AUTHORITY FLOW
FIGURE 33.
R&D
98
ORGANIZATIONAL STRUCTURES
handle transactions between functional units within the (engineering) division. The liaison
personnel received their authority through the division head. The liaison department did
not actually resolve conflicts. Their prime function was to assure that all departments
worked toward the same requirements and goals. Liaison departments are still in existence
in many large companies and typically handle engineering changes and design problems.
Unfortunately, the liaison department is simply a scaleup of the project coordinator
within the department. The authority given to the liaison department extends only to the
outer boundaries of the division. If a conflict arose between the manufacturing and engineering divisions, for example, it would still be referred to upper management for resolution. Today, liaison departments are synonymous with project engineering and systems engineering departments, and the individuals in these departments have the authority to span
the entire organization.
102
ORGANIZATIONAL STRUCTURES
Participants must spend full time on the project; this ensures a degree of loyalty.
Horizontal as well as vertical channels must exist for making commitments.
There must be quick and effective methods for conflict resolution.
GENERAL MANAGER
ENGINEERING
PROJECT MGR.
Y
PROJECT MGR.
Z
FIGURE 36.
FUNCTIONAL RESPONSIBILITY
PROJECT MGR.
X
OPERATIONS
FINANCIAL
PROJECT RESPONSIBILITY
OTHERS
103
There must be good communication channels and free access between managers.
All managers must have input into the planning process.
Both horizontally and vertically oriented managers must be willing to negotiate for
resources.
The horizontal line must be permitted to operate as a separate entity except for administrative purposes.
Before describing the advantages and disadvantages of this structure, the organization
concepts must be introduced. The basis for the matrix approach is an attempt to create synergism through shared responsibility between project and functional management. Yet this
is easier said than done. No two working environments are the same, and, therefore, no two
companies will have the same matrix design. The following questions must be answered
before a matrix structure can be successful:
If each functional unit is responsible for one aspect of a project, and other parts are
conducted elsewhere (possibly subcontracted to other companies), how can a synergistic environment be created?
Who decides which element of a project is most important?
How can a functional unit (operating in a vertical structure) answer questions and
achieve project goals and objectives that are compatible with other projects?
The answers to these questions depend on mutual understanding between the project
and functional managers. Since both individuals maintain some degree of authority, responsibility, and accountability on each project, they must continuously negotiate.
Unfortunately, the program manager might only consider what is best for his project (disregarding all others), whereas the functional manager might consider his organization
more important than each project.
In order to get the job done, project managers need organizational status and authority. A
corporate executive contends that the organization chart shown in Figure 36 can be modified
to show that the project managers have adequate organizational authority by placing the department manager boxes at the tip of the functional responsibility arrowheads. With this approach, the project managers appear to be higher in the organization than their departmental
counterparts but are actually equal in status. Executives who prefer this method must exercise
caution because the line and project managers may not feel that there is still a balance of power.
Problem-solving in this environment is fragmented and diffused. The project manager
acts as a unifying agent for project control of resources and technology. He must maintain
open channels of communication to prevent suboptimization of individual projects.
In many situations, functional managers have the power to make a project manager
look good, if they can be motivated to think about what is best for the project.
Unfortunately, this is not always accomplished. As stated by Mantell11:
There exists an inevitable tendency for hierarchically arrayed units to seek solutions and
to identify problems in terms of scope of duties of particular units rather than looking
11. Leroy H. Mantell, The Systems Approach and Good Management. Reprinted with permission from
Business Horizons, October 1972 (p. 50). Copyright 1972 by the Board of Trustees at Indiana University.
112
ORGANIZATIONAL STRUCTURES
GENERAL
MANAGER
DIRECTOR:
PROJECT MGMT
DIRECTOR:
ENGINEERING
DIRECTOR:
OPERATIONS
OTHERS
PROJECT MGR.
X
PROJECT MGR.
Y
PROJECT MGR.
Z
FIGURE 37.
managers. The desired span of control, of course, will vary from company to company and
must take into account:
As companies expand, it is inevitable that new and more complex conflicts arise. The
control of the engineering functions poses such a problem:
Should the project manager have ultimate responsibility for the engineering functions of a project, or should there be a deputy project manager who reports to the director of engineering and controls all technical activity?
Although there are pros and cons for both arrangements, the problem resolved itself in
the company mentioned above when projects grew so large that the project manager became
unable to handle both the project management and project engineering functions. Then, as