Académique Documents
Professionnel Documents
Culture Documents
TechNotes
Sprinkler TechNotes
March/April 2007
Page 2
Signage (5.9.5.4) Where the system demand pressure exceeds 150 psi, a sign is
required on the FDC that contains the demand pressure.
Post Indicator Valves (6.3) Unless the requirements in the next sentence are met,
every connection from a private main into a building needs a PIV. A PIV can be
eliminated if the AHJ allows it and if a valve is installed to isolate the fire protection
system from the private main.
Grounding and Bonding (10.6.8) In no case can the underground piping be used as
the grounding electrode. Bonding for lighting protection in accordance with NFPA 780
is okay. Bonding together multiple grounding mechanisms that include the underground
fire protection piping is okay and required by the NEC (NFPA 70).
Inspections Prior to Installation (10.7.1) All pipes, valves, hydrants and fittings will
be required to be inspected when they are received and again prior to installation.
Installation contractors will be asked to state that they have done this on the acceptance
test form.
Restrained Joint Systems (10.8.3) A new section was added to clarify that restrained
joints includes one or more of the following:
Locking mechanical or push-on joints
Mechanical joints utilizing setscrews retainer glands
Bolt Flange joints
Heat-fused or welded joints
Pipe clamps and tie rods
Other approved methods or devices
Hydrostatic Test Pressure (10.10.2.2) The standard was clarified regarding the
pressure to use during the hydrostatic test. The base requirements of a test pressure of
200 psi or 50 psi over the maximum system working pressure are pretty standard. But
the new rule is a tolerance during the test of 5 psi for 2 hrs. The committee also
clarified that the pressure is to be recorded at a hydrant or the lowest point in the system
where no hydrant is provided.
Hydrostatic Test (10.10.2.2) The committee also clarified the following four items with
respect to the performance of the hydrostatic test:
A test of the fire department connection piping is also required
Thrust blocks need to be hardened before testing
Backfill between joints is permitted to prevent movement of the piping, but
covering joints is discouraged so that leaks can be observed
An annex section recommends pre-stabilizing the system and an intermediate
check of the system 1-hour into the test for leakage
Sprinkler TechNotes
March/April 2007
Page 3
Leakage (10.10.2.2.4) The old leakage test has been replaced with a Hydrostatic
Testing Allowance. The allowance will be based on the following formula:
L=
SD P
148,000
Sprinkler TechNotes
March/April 2007
Page 4
Inside Diameter of Pipe (A.10.1.6) A new Table A.10.1.6 has been added to the
standard with the actual inside diameter for different classes of lined ductile iron pipe.
The new table has been necessary because people have been forgetting to subtract the
lining thickness when performing hydraulic calculations. Most people have been getting
the pipe criteria from the manufacturer and using the inside diameter of the unlined pipe,
forgetting about the lining thickness. This new table is only good for manufacturers that
use standard thickness linings. Some manufacturers use double thickness linings, so the
actual inside diameter of their pipe will be even less than what is in the standard.
Flow Testing and Hydrant Marking (Annex) NFPA 291 used to be a recommended
practice that outlined the procedures to use in conducting flow tests of private fire service
mains (water supplies) and also recommended methods of painting fire hydrants different
colors in order to tell how much flow was available from the hydrants. Several years ago,
the NFPA contemplated eliminating this recommended practice because few proposals
ever came in to revise the documents, so the NFPA thought that they were not being
used. When the NFPA floated the idea out to the public to eliminate the recommended
practice, they got a lot of feedback that it would not be a good idea. So, the
recommended practice was given to the NFPA 24 committee, which decided that it would
be good to continue printing this material in NFPA 24 as annex material. Two new
annexes have been added to the standard: