Activity ID

Activity Name

Original Early Start Early Finish


May
Duration

2014
June
July
August
September
October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02

165 25-May-14 05-Nov-14

Interior fit out & MEP works for DIB Baniyas Branch, Abu Dhabi, UAE

2 25-May-14 27-May-14

General
A1000

Work order confirmation

1 25-May-14 25-May-14
25-May-14

25-May-14

A1010

Kick off meeting

1 26-May-14 26-May-14
26-May-14

26-May-14

A1540

Receipt of client documents & drawings

0 27-May-14
78 27-May-14 12-Aug-14

Pre-construction

39 27-May-14 10-Jul-14

Shop drawing approval


A1020

Shop drawing preparation

30 27-May-14 30-Jun-14
27-May-14

A1030

Shop drawing submission

25 08-Jun-14

06-Jul-14
08-Jun-14

A1040

Shop drawing approval

25 12-Jun-14

10-Jul-14 12-Jun-14

A1490

Receipt of Shop drawing approval

30-Jun-14
06-Jul-14
10-Jul-14

10-Jul-14

14 27-May-14 11-Jun-14

Sample approval
A1050

Preparation of samples

A1060

Submission of samples

10 27-May-14 07-Jun-14
27-May-14
1 08-Jun-14

08-Jun-14
08-Jun-14

07-Jun-14

A1070

Approval of samples

3 09-Jun-14

11-Jun-1409-Jun-14

A1500

Receipt of sample approval

11-Jun-14

08-Jun-14
11-Jun-14

22 27-May-14 17-Jun-14

Authority approval
A1080

Preparation of documents

6 27-May-14 02-Jun-14
27-May-14

02-Jun-14

A1090

Submission of documents

1 03-Jun-14

03-Jun-14
03-Jun-14

03-Jun-14

A1100

Authority approvals

10 04-Jun-14

17-Jun-14
04-Jun-14

65 09-Jun-14

12-Aug-14

Procurement & Production

17-Jun-14

A1110

Procurement of materials

28 09-Jun-14

06-Jul-1409-Jun-14

A1120

Joinery production

30 11-Jul-14

09-Aug-14

A1130

Delivery of materials to site

18 26-Jul-14

12-Aug-14

141 17-Jun-14

05-Nov-14

60 17-Jun-14

16-Aug-14
21-Jun-14

Access to site

4 17-Jun-14
0 17-Jun-14

Site mobilization

3 17-Jun-14

21-Jun-14

9 21-Jun-14
5 21-Jun-14

01-Jul-14
26-Jun-14

4 26-Jun-14

01-Jul-14

14 01-Jul-14
7 01-Jul-14

17-Jul-14
09-Jul-14

01-Jul-14

A2040 A/C ducting and connections

7 01-Jul-14

09-Jul-14

01-Jul-14

09-Jul-14

A2050 FF pipes installation

6 01-Jul-14

08-Jul-14

01-Jul-14

08-Jul-14

A2070 DB installation & connection

2 09-Jul-14

12-Jul-14

A2060 FF drops installation

2 15-Jul-14

17-Jul-14

Wall partiton works


A1790 Gypsum board lining & wall partitons

8 03-Jul-14
8 03-Jul-14

13-Jul-14
13-Jul-14

Steel works
A1810 Metal sheet cladding to block walls

4 01-Jul-14
2 01-Jul-14

06-Jul-14
03-Jul-14

Construction
Phase 01 (Men's Retail area)
General
A1140
A1150

Civil works
A1770 Demolition works
A1780 Solid concrete block works
MEP 1st and 2nd fix
A2030 Conduits & wiring installation

Project Start: 25-May-14

Actual Work
Remaining Work

Date: 19-May-14

Critical Remaining Work

06-Jul-14
11-Jul-14

17-Jun-14

12-Aug-14

21-Jun-14

21-Jun-14

26-Jun-14

26-Jun-14

Interior fit out MEP works for DIB Baniyas


Branch, Abu Dhabi, UAE

Page 1 of 5

09-Aug-14
26-Jul-14

01-Jul-14
09-Jul-14

09-Jul-14

12-Jul-14

15-Jul-14
03-Jul-14
01-Jul-14

17-Jul-14
13-Jul-14

03-Jul-14

Date

Revision

Checked Approved

Activity ID

Activity Name

Original Early Start Early Finish


May
Duration

A1820 Galvanized sheet cladding to ATM walls

2014
June
July
August
September
October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
03-Jul-14
06-Jul-14

2 03-Jul-14

06-Jul-14

21 09-Jul-14
4 09-Jul-14

03-Aug-14
14-Jul-14

A1880 Crema marfil floor tiles installation

3 26-Jul-14

29-Jul-14

26-Jul-14

29-Jul-14

A1890 Non-slip ceramic floor tiles installation

2 26-Jul-14

28-Jul-14

26-Jul-14

28-Jul-14

A1910 Raised access flooring with vinyl and marble finish

4 26-Jul-14

30-Jul-14

26-Jul-14

A1900 Vinyl flooring installation

2 29-Jul-14

31-Jul-14

A1920 Skirting installation

2 31-Jul-14

03-Aug-14

19 13-Jul-14
3 13-Jul-14

04-Aug-14
16-Jul-14

A1960 Polished ceramic wall tiling

2 20-Jul-14

22-Jul-14

A1970 Wall covering installation

2 26-Jul-14

28-Jul-14

A1940 Painting 1st and 2nd coat on walls & ceiling

2 29-Jul-14

31-Jul-14

A1950 Painting final coat on walls & ceiling

3 31-Jul-14

04-Aug-14

17 09-Jul-14
5 09-Jul-14

29-Jul-14
15-Jul-14

A2000 Inspection before ceiling closure

1 15-Jul-14

16-Jul-14

15-Jul-14

A2010 Boarding, taping & jointing

3 16-Jul-14

20-Jul-14

16-Jul-14

A1930 Primer and stucco on walls and ceiling

5 20-Jul-14

26-Jul-14

A2020 Fixing light boxes

3 26-Jul-14

29-Jul-14

26-Jul-14

29-Jul-14

18 26-Jul-14
3 26-Jul-14

16-Aug-14
29-Jul-14

26-Jul-14

29-Jul-14

A1860 Door panels & ironmongaries installaiton

3 29-Jul-14

02-Aug-14

A1840 Dry pantry cabinets installation

3 13-Aug-14 16-Aug-14

Floor finishes
A1870 laying of cement sand screed

Wall finishes
A1980 Glass fixing on partitions

Ceiling finishes
A1990 Framework for ceiling

Joinery items
A1850 Door frames installation

09-Jul-14

14-Jul-14

30-Jul-14

29-Jul-14

31-Jul-14

31-Jul-14
13-Jul-14

03-Aug-14

16-Jul-14

20-Jul-14

22-Jul-14

26-Jul-14

28-Jul-14

29-Jul-14

31-Jul-14

31-Jul-14
09-Jul-14

04-Aug-14

15-Jul-14
16-Jul-14
20-Jul-14

20-Jul-14

26-Jul-14

29-Jul-14

02-Aug-14

13-Aug-14

16-Aug-14

MEP final fixing


A2080 Switches, sockets & lights installation

3 26-Jul-14
3 26-Jul-14

29-Jul-14
29-Jul-14

26-Jul-14

29-Jul-14

A2090 AC grills and diffusers installation

3 26-Jul-14

29-Jul-14

26-Jul-14

29-Jul-14

A2100 FF & FA devices installation

3 26-Jul-14

29-Jul-14

26-Jul-14

29-Jul-14

8 29-Jul-14
4 29-Jul-14

07-Aug-14
03-Aug-14

29-Jul-14

03-Aug-14

A1670 Getting permanent power supply

3 29-Jul-14

02-Aug-14

29-Jul-14

02-Aug-14

A1600 Fire alarm testing & commissioning & panel programming

2 30-Jul-14

02-Aug-14

30-Jul-14

02-Aug-14

A1680 Electrical testing & commissioning

2 31-Jul-14

03-Aug-14

31-Jul-14

03-Aug-14

A1690 A/C air balancing & commissioning

2 02-Aug-14 04-Aug-14

02-Aug-14

04-Aug-14

A1710 Final inspection by client

2 04-Aug-14 06-Aug-14

A1720 Client possession

1 06-Aug-14 07-Aug-14

Phase 02 (Ladies banking area)

45 07-Aug-14 21-Sep-14

Snagging & Handover


A1760 Snagging works

General
A2110

Civil works
A2330 Demolition works

7 07-Aug-14 16-Aug-14
4 07-Aug-14 12-Aug-14

A2320 Solid concrete block works

3 12-Aug-14 16-Aug-14

MEP 1st and 2nd fix

06-Aug-14
07-Aug-14

07-Aug-14
12-Aug-14

12-Aug-14
16-Aug-14

14 16-Aug-14 01-Sep-14

Actual Work
Remaining Work

Date: 19-May-14

06-Aug-14

0 07-Aug-14 07-Aug-14
0 07-Aug-14

Access to site

Project Start: 25-May-14

04-Aug-14

Critical Remaining Work

Interior fit out MEP works for DIB Baniyas


Branch, Abu Dhabi, UAE

Page 2 of 5

Date

Revision

Checked Approved

Activity ID

Activity Name

Original Early Start Early Finish


May
Duration

2014
June
July
August
September
October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
16-Aug-14
24-Aug-14

A2440 Conduits & wiring installation

7 16-Aug-14 24-Aug-14

A2450 A/C ducting and connections

7 16-Aug-14 24-Aug-14

16-Aug-14

24-Aug-14

A2460 FF pipes installation

6 16-Aug-14 23-Aug-14

16-Aug-14

23-Aug-14

A2480 DB installation & connection

2 24-Aug-14 26-Aug-14

A2470 FF drops installation

2 30-Aug-14 01-Sep-14

Wall partiton works


A2150 Gypsum board lining & wall partitons

8 18-Aug-14 27-Aug-14
8 18-Aug-14 27-Aug-14

Steel works
A2130 Metal sheet cladding to block walls

4 16-Aug-14 20-Aug-14
2 16-Aug-14 18-Aug-14

A2140 Galvanized sheet cladding to ATM walls

2 18-Aug-14 20-Aug-14

Floor finishes
A2190 laying of cement sand screed

20 24-Aug-14 16-Sep-14
4 24-Aug-14 28-Aug-14

24-Aug-14

26-Aug-14

30-Aug-14
18-Aug-14

01-Sep-14
27-Aug-14

16-Aug-14

18-Aug-14

18-Aug-14

20-Aug-14

24-Aug-14

28-Aug-14

A2200 Crema marfil floor tiles installation

3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

A2210 Non-slip ceramic floor tiles installation

2 08-Sep-14 10-Sep-14

08-Sep-14

10-Sep-14

A2230 Raised access flooring with vinyl and marble finish

4 08-Sep-14 13-Sep-14

08-Sep-14

A2220 Vinyl flooring installation

2 11-Sep-14

A2240 Skirting installation

2 14-Sep-14 16-Sep-14

Wall finishes
A2380 Glass fixing on partitions

14-Sep-14

18 27-Aug-14 17-Sep-14
3 27-Aug-14 31-Aug-14

A2360 Polished ceramic wall tiling

2 03-Sep-14 06-Sep-14

A2370 Wall covering installation

2 08-Sep-14 10-Sep-14

A2340 Painting 1st and 2nd coat on walls & ceiling

2 11-Sep-14

A2350 Painting final coat on walls & ceiling

3 14-Sep-14 17-Sep-14

Ceiling finishes
A2400 Framework for ceiling

14-Sep-14

14-Sep-14
27-Aug-14

16-Sep-14

31-Aug-14

03-Sep-14

06-Sep-14

08-Sep-14

14-Sep-14

16 24-Aug-14 11-Sep-14
5 24-Aug-14 30-Aug-14

13-Sep-14

11-Sep-14

10-Sep-14

11-Sep-14

14-Sep-14

14-Sep-14
24-Aug-14

17-Sep-14

30-Aug-14

A2410 Inspection before ceiling closure

1 30-Aug-14 31-Aug-14

30-Aug-14

A2420 Boarding, taping & jointing

3 31-Aug-14 03-Sep-14

31-Aug-14

A2390 Primer and stucco on walls and ceiling

4 03-Sep-14 08-Sep-14

A2430 Fixing light boxes

3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

6 08-Sep-14 15-Sep-14
3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

A2170 Door frames installation

3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

A2180 Door panels & ironmongaries installaiton

3 11-Sep-14

Joinery items
A2160 Dry pantry cabinets installation

15-Sep-14

31-Aug-14
03-Sep-14

03-Sep-14

08-Sep-14

11-Sep-14

15-Sep-14

MEP final fixing


A2490 Switches, sockets & lights installation

3 08-Sep-14 11-Sep-14
3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

A2500 AC grills and diffusers installation

3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

A2510 FF & FA devices installation

3 08-Sep-14 11-Sep-14

08-Sep-14

11-Sep-14

Snagging & Handover


A2270 Snagging works

8 11-Sep-14
4 11-Sep-14

21-Sep-14
16-Sep-14

11-Sep-14

16-Sep-14

A2290 Getting permanent power supply

3 11-Sep-14

15-Sep-14

11-Sep-14

15-Sep-14

A2280 Fire alarm testing & commissioning & panel programming

2 13-Sep-14 15-Sep-14

13-Sep-14

15-Sep-14

A2300 Electrical testing & commissioning

2 14-Sep-14 16-Sep-14

14-Sep-14

16-Sep-14

A2310 A/C air balancing & commissioning

2 15-Sep-14 17-Sep-14

15-Sep-14

Project Start: 25-May-14

Actual Work
Remaining Work

Date: 19-May-14

Critical Remaining Work

Interior fit out MEP works for DIB Baniyas


Branch, Abu Dhabi, UAE

Page 3 of 5

Date

17-Sep-14

Revision

Checked Approved

Activity ID

Activity Name

Original Early Start Early Finish


May
Duration

A2250 Final inspection by client

2 17-Sep-14 20-Sep-14

A2260 Client possession

2014
June
July
August
September
October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
17-Sep-14
20-Sep-14

1 20-Sep-14 21-Sep-14

20-Sep-14

21-Sep-14

45 21-Sep-14 05-Nov-14

Phase 03 (Customer Service area)


General
A2520 Access to site

0 21-Sep-14 21-Sep-14
0 21-Sep-14

Civil works
A2740 Demolition works

8 21-Sep-14 30-Sep-14
4 21-Sep-14 25-Sep-14

A2730 Solid concrete block works

21-Sep-14

4 25-Sep-14 30-Sep-14

MEP 1st and 2nd fix


A2850 Conduits & wiring installation

25-Sep-14

25-Sep-14

30-Sep-14

14 30-Sep-14 16-Oct-14
7 30-Sep-14 08-Oct-14

30-Sep-14

A2860 A/C ducting and connections

7 30-Sep-14 08-Oct-14

30-Sep-14

08-Oct-14

A2870 FF pipes installation

6 30-Sep-14 07-Oct-14

30-Sep-14

07-Oct-14

A2890 DB installation & connection

2 08-Oct-14

11-Oct-14

A2880 FF drops installation

2 14-Oct-14

16-Oct-14

Wall partiton works


A2560 Gypsum board lining & wall partitons

8 02-Oct-14
8 02-Oct-14

12-Oct-14
12-Oct-14

Steel works
A2540 Metal sheet cladding to block walls

4 30-Sep-14 05-Oct-14
2 30-Sep-14 02-Oct-14

A2550 Galvanized sheet cladding to ATM walls

08-Oct-14

08-Oct-14

11-Oct-14

14-Oct-14
02-Oct-14

16-Oct-14
12-Oct-14

30-Sep-14

02-Oct-14

2 02-Oct-14

05-Oct-14

20 08-Oct-14
4 08-Oct-14

01-Nov-14
13-Oct-14

A2610 Crema marfil floor tiles installation

3 23-Oct-14

27-Oct-14

23-Oct-14

27-Oct-14

A2620 Non-slip ceramic floor tiles installation

2 23-Oct-14

26-Oct-14

23-Oct-14

26-Oct-14

A2640 Raised access flooring with vinyl and marble finish

4 23-Oct-14

28-Oct-14

23-Oct-14

A2630 Vinyl flooring installation

2 27-Oct-14

29-Oct-14

A2650 Skirting installation

2 29-Oct-14

01-Nov-14

18 12-Oct-14
3 12-Oct-14

02-Nov-14
15-Oct-14

A2770 Polished ceramic wall tiling

2 19-Oct-14

21-Oct-14

A2780 Wall covering installation

2 23-Oct-14

26-Oct-14

A2750 Painting 1st and 2nd coat on walls & ceiling

2 27-Oct-14

29-Oct-14

A2760 Painting final coat on walls & ceiling

3 29-Oct-14

02-Nov-14

16 08-Oct-14
5 08-Oct-14

27-Oct-14
14-Oct-14

A2820 Inspection before ceiling closure

1 14-Oct-14

15-Oct-14

14-Oct-14

A2830 Boarding, taping & jointing

3 15-Oct-14

19-Oct-14

15-Oct-14

A2800 Primer and stucco on walls and ceiling

4 19-Oct-14

23-Oct-14

A2840 Fixing light boxes

3 23-Oct-14

27-Oct-14

23-Oct-14

27-Oct-14

6 23-Oct-14
3 23-Oct-14

30-Oct-14
27-Oct-14

23-Oct-14

27-Oct-14

A2580 Door frames installation

3 23-Oct-14

27-Oct-14

23-Oct-14

27-Oct-14

A2590 Door panels & ironmongaries installaiton

3 27-Oct-14

30-Oct-14

3 23-Oct-14

27-Oct-14

Floor finishes
A2600 laying of cement sand screed

Wall finishes
A2790 Glass fixing on partitions

Ceiling finishes
A2810 Framework for ceiling

Joinery items
A2570 Dry pantry cabinets installation

MEP final fixing

Project Start: 25-May-14

Actual Work
Remaining Work

Date: 19-May-14

Critical Remaining Work

Interior fit out MEP works for DIB Baniyas


Branch, Abu Dhabi, UAE

Page 4 of 5

02-Oct-14

05-Oct-14

08-Oct-14

13-Oct-14

28-Oct-14

27-Oct-14

29-Oct-14

29-Oct-14
12-Oct-14

01-Nov-14

15-Oct-14

19-Oct-14

21-Oct-14

23-Oct-14

26-Oct-14

27-Oct-14

29-Oct-14

29-Oct-14
08-Oct-14

14-Oct-14
15-Oct-14
19-Oct-14

19-Oct-14

27-Oct-14

Date

Revision

02-Nov-14

23-Oct-14

30-Oct-14

Checked Approved

Activity ID

Activity Name

Original Early Start Early Finish


May
Duration

2014
June
July
August
September
October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
23-Oct-14
27-Oct-14

A2900 Switches, sockets & lights installation

3 23-Oct-14

27-Oct-14

A2910 AC grills and diffusers installation

3 23-Oct-14

27-Oct-14

23-Oct-14

27-Oct-14

A2920 FF & FA devices installation

3 23-Oct-14

27-Oct-14

23-Oct-14

27-Oct-14

8 27-Oct-14
4 27-Oct-14

05-Nov-14
01-Nov-14

27-Oct-14

A2700 Getting permanent power supply

3 27-Oct-14

30-Oct-14

27-Oct-14

30-Oct-14

A2690 Fire alarm testing & commissioning & panel programming

2 28-Oct-14

30-Oct-14

28-Oct-14

30-Oct-14

A2710 Electrical testing & commissioning

2 29-Oct-14

01-Nov-14

29-Oct-14

01-Nov-14

A2720 A/C air balancing & commissioning

2 30-Oct-14

02-Nov-14

30-Oct-14

02-Nov-14

A2660 Final inspection by client

2 02-Nov-14 04-Nov-14

A2670 Client possession

1 04-Nov-14 05-Nov-14

Snagging & Handover


A2680 Snagging works

Project Start: 25-May-14

Actual Work
Remaining Work

Date: 19-May-14

Critical Remaining Work

Interior fit out MEP works for DIB Baniyas


Branch, Abu Dhabi, UAE

Page 5 of 5

01-Nov-14

02-Nov-14
04-Nov-14

Date

Revision

Checked Approved

04-Nov-14
05-Nov-14