Académique Documents
Professionnel Documents
Culture Documents
PHR = DPH x PO x PA x FE
Why did Pilz develop a new method
for assessing and evaluating risk?
Where:
Pilz spirit of continual improvement drives us
to evolve our services. We rely on the knowledge
of our global team of Machinery Safety Experts
and our quality reviews of thousands of successful
machinery safety projects to rene our services.
We contribute to and review new and emerging
standards including ISO 12100:2010 and
ANSI B11.0 - 2010 to dene best practice in the
delivery of our services. Our experience is based
on our international presence in more than 40
countries and our participation in all important
standard committees.
In light of evolving standards and our pursuit of
continuous improvement, Pilz have further rened
the estimation and evaluation of risk. The result is
Pilz Hazard Rating (PHR).
Why is Risk Estimation important
in the Risk Assessment process?
Risk Assessment is fundamental to the achievement of safety through design of new machinery and
for selecting safeguarding and other risk reduction
measures on existing machinery. Risk estimation is
a critical step in the process. It enables risk from
identied hazards to be qualied and quantied
in order to distinguish high-risk possibilities from
8-8-2-0-117, 2011-07
Pilz GmbH & Co. KG, 2011
Benets
Prot from the Pilz spirit of continual
improvement and our endeavours to bring state
of the art Services to our customers
Determine the Performance Level or Safety
Integrity Level of your Safety Related Control
System based on the PHR parameters assigned
Risk Estimation
Hazard identication
is a function of
Severity
of the possible harm that can
result from the considered hazard
Risk estimation
Risk evaluation
and
Probability of occurence
Machinery
safe?
Yes
No
Probability
of occurence of the event
Risk reduction
Possibility
to avoid or limit
End
Risk
Negligible Risk
From
0,0046875
To
10
11
20
Low Risk
21
45
Signicant Risk
46
160
High Risk
161
500
501
9750
Table above shows the description of risk for the range of PHR numbers in PHR system.
8-8-2-0-117, 2011-07
Pilz GmbH & Co. KG, 2011