Académique Documents
Professionnel Documents
Culture Documents
Investment Management
BY
P.SUPRIYA
(HT.No: 098 060 132)
DECLARATION
hereby
declare
that
this
Project
Report
titled
INVESTMENT
ANNEXURE II
CERTIFICATION
This is to certify that the Project Report title Logistics Management
submitted in partial fulfillment for the award of MBA Programme of
Department of Business Management, O.U. Hyderabad, was carried out by
K.V.Ramana Reddy under my guidance. This has not been submitted to any
other
University
or
Institution
for
the
award
of
degree/diploma/certificate.
Principal
any
Abstract
Logistic Management is a cross functional approach to managing the
movement of raw materials into an organisation, certain aspects of the
internal
processing
of
materials
into
finished
goods
and
then
the
movement of the finished goods out of the organisation towards the end
c o n s u m e r.
As
organisation
strive
focus
on
core
competencies
and
purpose
of
Logistics
management
is
to
improve
trust
and
ACKNOWLEDGEMENT
I a m d e e p l y i n d e b t e d t o my H e a d o f t h e d e p a r t me n t a n d g u i d e
M r.Vis w a n a t h w h o h a v e b e e n a gr e a t s o u r c e o f s t r e n g t h a n d
i n s p i r a t i o n a t e v e r y s t a g e o f pr o j e c t w o r k .
I
would
like
to
Mrs.IndiraReddy,
Director
of
acknowledge
principal
St.Pauls
P.G .
my
and
sincere
M r.
College
for
thanks
Raghava
making
to
Reddy
all
the
(K.V.RAMANA REDDY)
Table of Contents
Page No.
Chapter 1: Introduction
Introduction
Objectives
Methodology
Scope
1
2
3
4
Introduction
Logistics Problems
Suggestions to improve
Introduction to retail industry
Organized retailing in India
6
14
15
17
24
29
31
33
37
38
Introduction
Inbound Logistics
42
48
Outbound Logistic
Inventory Management
60
73
Conclusions
Limitations
Suggestions
Bibliography
81
82
83
84
Appendices
Organisational Structure
Store Details
Manual trip sheet
Bin categorization and stocking details
ii
vii
viii
Chapter
-1
Introduction
METHODOLOGY
To achieve a fore said objective the following methodology has been adopted. The
information for this report has been collected through the primary and secondary
sources.
Primary sources:
It is also called as first handed information the data is collected through the
observation in the organization and interviews with officials. By asking questions
with the accounts and other persons in the financial department. A part from these
some information is collected through the seminars, which were held by
APGENCO.
Secondary sources:
These secondary data is existing data which is collected data which is collected by
others that is sources are financial journals, annual reports of the APGENCO Ltd.,
APGENCO website, and other publications of APGENCO.
Lack of time is another limiting factor the schedule period 6 weeks are
not sufficient to make the study independently regarding Capital budgeting
in APGENCO Ltd.
HISTORY OF APGENCO:
When APSEB came in to existence in 1959, APSEB started functioning with the
objectives of maintaining the power sector efficiently and economically
simultaneously ensuring demand meets the supply. During the last decade
inadequate capacity addition and low system frequency operation of less than
48.5 Hz for more then half a decade considerably reduced the power supply
reliability. The imbalance of the revenues against the cost of production, no
significant reduction in technical losses and energy thefts, high costs
purchases from IPPs other SEBs gradually worsened the financial position
of APSEB.
ABOUT APGENCO:
Andhra Pradesh Power Generation Corporation Limited is one of the Pivotal
organizations of Andhra Pradesh, engaged in the business of power generation.
Apart from operation and maintenance of the of the power plants it has undertaken
the execution of the ongoing and new power projects scheduled under capacity
addition programme and is taking up renovation and modernization works of the
old power stations.
APGENCO came into existence on 28.12.1998 and commenced operations from
01.02.1999. This was a sequel to Governments reforms in power sectors to
unbundle the activities relating to Generation, transmission and Distribution of
power. All the generating stations owned by erstwhile APSEB were transferred to
the control of APGENCO.
The installed capacity of APGENCO AS ON 31.12.2005 IS 6550.9 MW
comprising 2962.50 MW Thermal, 3586.4 MW Hydro and 2MW Wind power
stations, and contributed about half the total Energy Requirement of Andhra
Pradesh. APGENCO is the third largest power generating utility in the country next
to NTPC and Maharastra; its installed Hydro Capacity of 3586.4 MW is the highest
among the country.
APGENCO has an equity base of Rs.2107 crores with 10273 dedicated employees
as on 30.09.2003. The company has an asset base of approximately Rs.12000
crores.
OUR VISION:
To be the best power utility in the country and one of the best in the world.
OUR MISSION:
To generate adequate and reliable power most economically, efficiently
and Eco-friendly.
To spearhead accelerated power development by planning and
implementing new power projects.
To implement Renovation and Modernization of all existing units and
enhance their performance.
CORE VALUES:
To proactively manage change to the liberalized environment and global
trends.
To build leadership through professional excellence and quality.
To build a team based organization by sharing knowledge and
empowering employees.
To treat everyone with personal attention, openness, honesty and respect
they deserve.
To break down all departmental barriers for working together.
To have concern for ecology and environment.
19
Thermal plants are consistently winning the Gold and Silver medals for
Meritorious Productivity Award.
Availability of thermal plants has been (over a decade) well above the
national average.
Nagarjuna Sagar Left canal powerhouse is the first hydro station in the
country to use SCDCA for operation of the units from control room besides
enhancing the Excitation and Governor system with microprocessor controls.
The average PLF of 89.7 % during 2004-05 is the highest ever achieved
and highest in the country when compared with the utilities having
comparable installed capacity and vintage.
20
Since 1994-95 VTPS and RTPP are occupying top two positions in terms
of PLF rankings, except in the year 1999-00 in which RTPP stood second.
VTPS stood FIRST in the country during 1994-95,1995-96,1996-97,199798and 2001-02 and RTPP stood first in the country during 1998-99,200001,2002-03 and 2003-04.
RTPP has been receiving meritorious productivity Award for last six
consecutive years and bagged Gold Medal five years in a row since 1998-99.
VTPS has been receiving Meritorious Productivity Award for last twenty
consecutive years and bagged Gold Medal 9 times in a row since 1994-95.
KTPS V Stage has been receiving Meritorious Productivity Award for last
four consecutive years and bagged gold medal four times in a row since
1999-00.
21
INSTALLED CAPACITY-THERMAL
NAME OF THERMAL POWER
STATION
VTPS (210MW)
RTPP (210MW)
KTPS -ABC (4x60MW&4x120MW)
KTPS-V (250MW)
RAMAGUNDAM THERMAL
NO.OF
UNITS
6
2
8
2
1
STATION
TOTAL THERMAL CAPACITY
19
INSTALLED
CAPACITY
1260MW
420MW
720MW
500MW
62MW
2962MW
Capacity
stat
ion
NTPC
MAHAGENCO
APGENCO
23,345MW
10,331MW
6,551MW
CAPACITY
3586.4 MW
3135.4 MW
2773.0 MW
22
OPERATIONAL PERFOMANCE
OVERALL PERFOMANCE OF APGENCO
YEAR
2004-
GENARATION
(MU)
ALL
APGENCO AVERAGE
INDIA RANKING
I
05
2003-
23360
04
2002-
22455.2
03
2001-
23032
02
2000-
22245
01
1999-
21934
00
1998-
21499
99
1997-
19834
98
1996-
19019
97
1995-
16720
96
1994-
15103
95
10842
89.7
74.8
III
56
72.7
II
88.9
72.1
I
86.3
70.0
I
85.1
68.7
II
83.2
67.5
III
77.6
64.6
I
82.3
64.9
I
78.1
64.5
I
78.2
63.1
II
70.1
60.1
PLF %
2005-06
2003- 2004(APR04
05
NOV)
91.84 89.2
84.8
23
RTTP
KTPS
KTPS-V
RTS-B
NTS
3401.6
4225.9
4038.3
471.28
153.94
3353.8
5364.1
4140.2
496.2
154.4
1511
3362.9
2508.2
282
7.42
92.2
68.7
91.95
85.8
58.4
91.2
87.5
94.5
90.6
58.8
54.5
72.8
76
68.4
16.9
THERMAL
CAPACITY(MW)
2972.5
PLF %
89.7
24
GUJARAT SECL
NTPC
ORISSA PGC
RAJASTHAN RVUNL
KARNATAKA PCL
PUNJAB SEB
TAMILNADU SEB
NEYVELI
LIGNITE
CORPORATION
MAHARASTRA SEB
CHATTISGARH SEB
MADHYA PRADESH GPCL
SOUTHERN REGION
ALL INDIA
420.0
20185.0
420.0
2295.0
1470.0
2120.0
2970.0
87.5
87.3
86.0
85.1
83.2
77.5
76.9
2490.0
6396.0
1240.0
2272.5
13892.5
67165.9
76.8
76.6
72.9
72.1
84.1
74.8
25
26
ENVIRONMENTAL CONCERNS
Environmental policy (unwritten)
Comply with relevant environmental legislations and regulatory
requirements for establishment and operation of the power stations.
Commitment
to
continual
improvement
in
the
environmental
of
collection efficiency
and reduction of
power
27
AFFORESTATION
Green belt is provided with different species to act as sink for absorbing
pollutants, sound barrier and to maintain Bio-diversity. About4lakh plants
are available at all stations.
ASH UTILISATION
The annual generation of fly ash from Thermal Power Plants of APGENCO is
presently around 6.8 million tons/annum. APGENCO has been implementing
following measures.
28
Dry fly ash and pond ash are issued free of cost to all consumers.
Brick plants are set up at VTPS, RTPP and KTPS.
Research and field tests are underway through Acharya NG Ranga
Agricultural University (ANGRAU) and Department of Agriculture,
GOAP to establish benefits with fly ash use for agriculture for all crops in
the different agro-climate zones of Andhra Pradesh.
Feasibility of ash stowing to mines is under study. Ash utilization has
witnessed improvement year by year as shown in the bar chart.
29
30
Organizational Chart
Sri A.K.Goyal (I.A.S)
Chairman
Sri Ajay Jain (I.A.S)
Managing Director
Sri. G.Adisheshu
Director (Hydel)
31
32
CAPITAL BUDGETING
Introduction:
The term Capital Budgeting refers to long term planning for proposed capital
outlay and their financing. It includes raising long-term funds and their
utilization. It may be defined as a firms formal process of acquisition and
investment of capital.
Capital Budgeting May also be defined as The decision making process by
which a firm evaluates the purchase of major fixed assets. It involves firms
decision to invest its current funds for addition, disposition, modification and
replacement of fixed assets.
It deals exclusively with investment proposals, which an essentially long term
projects and is concerned with the allocation of firms scarce financial resources
among the available market opportunities.
Some of the examples of Capital Expenditure are
(i) Cost of acquisition of permanent assets as land and buildings.
(ii) Cost of addition, expansion, improvement or alteration in the fixed
assets.
(iii) R&D project cost, etc.,
Definitions:
Capital budgeting is long term planning for making and financing proposed
capital outlays.
T.HORNGREEN
33
34
They have a long terms are significant effect on the profitability of the
concern.
They involve huge funds.
They are irreversible decisions. They are strategic decisions associated
with high degree of risk.
IMPORTANCE OF CAPITAL BUDGETING:
The importance of capital budgeting can be understood from the fact that an
unsound investment decision may prove to be fatal to the very existence of the
organization.
The importance of capital budgeting arises mainly due to the following:
1.Large investment:
Capital budgeting decision, generally involves large investment of funds. But
the funds available with the firm are scarce and the demand for funds for
exceeds resources. Hence, it is very important for a firm to plan and control its
capital expenditure.
3. Irreversible nature:
The Capital expenditure decisions are of irreversible nature. Once, the decision
for acquiring a permanent asset is taken, it becomes very difficult to dispose of
these assets without incurring heavy losses.
35
6. Notional Importance:
Investment decision though taken by individual concern is of national
importance because it determines employment, economic activities and
economic growth.
36
From the point of view of firm's existence: The capital budgeting decisions
may be taken by a newly incorporated firm or by an already existing firm.
a) New Firm: A newly incorporated firm may be required to take
different decisions such as selection of a plant to be installed, capacity
utilization at initial stages, to set up or not simultaneously the ancillary
unit etc.
b) Existing: Firm: A firm which is already existing may also be required
to take various decisions from time to time to meet the challenges of
competition or changing environment. These decision may be :
(i)
(ii) Expansion: Some times, the firm may be interested in increasing the
installed production capacity so as to increase the market share. In such a case,
the finance manager is required to evaluate the expansion program in terms of
marginal costs and marginal benefits.
37
(ii)
(i) Independent Project Decision:This is a fundamental decision in Capital Budgeting. It is also called as acceptreject criterion. If the project is accepted the firm does not invest in it. In
general all these proposals, which yield a rate of return greater, than ascertain
required rate of return on cost of capital, are accepted and the rest are rejected.
By applying this criterion all independent project with one another in such a
way that the acceptance of one precludes the possibility of acceptance of
another. Under the accept-reject decision all independent projects that satisfy
the minimum investment criterion should be implemented.
(ii) Mutually Exclusive Projects Decision:Mutually Exclusive projects are those, which compete with other projects in
such a way that the acceptance of one will exclude the acceptance of the other
projects. The alternatives are mutually exclusive and only one may be chosen.
Suppose a company is intending to buy a new machine. There are three
competing brands, each with a different initial investment adopting costs. The
three machines represent mutually exclusive alternatives as only one of these
38
can be selected. It may be noted that the mutually exclusive alternatives, as only
one of these can be selected. It may be noted here that the mutually exclusive
projects decisions are not independent of the accept reject decisions.
(iii) Capital Rationing Decisions: In a situation where the firm has unlimited funds all independent investment
proposals yielding return greater than some pre-determined levels are
accepted. However this situation does not prevail in most of the business
firms in actual practice. They have a fixed capital budget. A large number
of investment proposals compete for these limited funds the firm must
therefore ration them. The firm allocates funds to projects in a manner
that it maximizes long run returns this, capital rationing refers to a
situation in which a firm has more acceptance investment than it can
finance. It is concerned with the selection of a group of investment
proposals acceptable. Under the accept-reject decision capital rationing
employees ranking of the acceptable investments projects. The projects
can be ranked on the basis of a predetermined criterion such as the rate of
return. The projects are ranked in the descending order of the rate of
return.
PROBLEMS AND DIFFICULTIES IN CAPITAL BUDGETNG:
The problems in capital budgeting decisions may be as follows:
a) Future uncertainty: Capital budgeting decisions involve long term
commitments. However there is lot of uncertainty in the long term. The
uncertainty may be with reference to cost of the project, future expected
returns, future competition, legal provisions, political situation etc.
b) Time Element: The implications of a Capital Budgeting decision are
scattered over a long period. The cost and benefits of a decision may
occur at different points of time. The cost and benefits of a decision may
occur at different points of time. The cost of a project is incurred
39
accepted or rejected on the strength of its merits alone. The proposal will not be
considered in combination with other proposals to consider the maximum
utilization of available funds.
41
Performance Review:
The last stage in the process of capital budgeting is the evaluation of the
performance of the project. The evaluation is made by comparing actual and
budgeted expenditures and also by comparing actual anticipated returns. The
unfavorable variances, if any should be looked in to and the causes of the same
be identified so that corrective action may be taken in future.
43
Traditional Methods
1. Pay back
2. Accounting rate of return
Traditional methods:
(I) Payback period method (P.B.P)
(II) Accounting Rate of return method (A.R.R)
Time adjusted or discounting techniques:
(I) Net Present value method (N.P.V)
(II) Internal rate of return method (I.R.R)
(III) Profitability index method (P.I)
44
ADVANTAGES:
Simple to understand and easy to calculate.
It saves in cost; it requires lesser time and labour as compared to other
methods capital budgeting.
In this method, as a project with a shorter pay back period is preferred
to the one having a longer pay back period, it reduces the loss through
obsolescence.
Due to its short-term approach, this method is particularly suited to a
firm which has shortage of cash or whose liquidity position is not
good.
DISADVANTAGES:
45
It does not take into account the cash inflows earned after the pay back
period and hence the true profitability of the project cannot be
correctly assessed.
This method ignores the time value of the money and does not
consider the magnitude and timing of cash inflows.
It does not take into account the cost of capital, which is very
important in making sound investment decisions.
It is difficult to determine the minimum acceptable pay back period,
which is subjective decision.
It treats each asset individually in isolation with other assets, which is
not feasible in real practice.
46
Under this method average profit after tax and depreciation is calculated and
then it is divided by the total capital out lay.
ADVANTAGES:
It is very simple to understand and easy to calculate.
It uses the entire earnings of a project in calculating rate of return and
hence gives a true view of profitability.
As this method is based upon accounting profit, it can be readily
calculated from the financial data.
DISADVANTAGES:
It ignores the time value of money.
It does not take in to account the cash flows, which are more important
than the accounting profits.
It ignores the period in which the profits are earned as a 20% rate of
return in
2 years is considered to be better than 18% rate if return in 12 years.
This method cannot be applied to a situation where investment in
project is to be made in parts.
3. NET PRESENT VALUE METHOD:
The NPV method is a modern method of evaluating investment proposals. This
method takes in to consideration the time value of money and attempts to
calculate the return on investments by introducing time element.
The net
47
present values of all inflows and outflows of cash during the entire life of the
project is determined separately for each year by discounting these flows with
firms cost of capital or predetermined rate. The steps in this method are
1. Determine an appropriate rate of interest known as cut off rate.
2.
Compute the present value of cash outflows at the above-determined
discount rate.
3. Compute the present value of cash inflows at the predetermined rate.
4. Calculate the NPV of the project by subtracting the present value of cash
outflows
From present value of cash inflows.
Decision rule
Accept the project if the NPV of the project is 0 or +ve that is present value of
cash inflows should be equal to or greater than the present value of cash
outflows.
ADVANTAGES:
It recognizes the time value of money and is suitable to apply in a
situation with
It takes in to account the earnings over the entire life of the project and
gives the true view of the profitability of the investment
Takes in to consideration the objective of maximum profitability.
DISADVANTAGES:
More difficult to understand and operate.
48
It may not give good results while comparing projects with unequal
investment of funds.
It is not easy to determine an appropriate discount rate.
K = cost of capital.
DETERMINANTION OF IRR
a) When annual cash flows are equal over the life of the asset.
Initial Outlay
FACTOR = --------------------------- x 100
Annual Cash Inflow
b) When the annual cash flows are unequal over the life of the asset:
Pv of cash inflows at lower rate - Pv of cash outflows
IRR = LR + ------------------------------------------------------------------------- (hr-lr)
49
ADVANTAGES:
Unlike net present value, the profitability index method is used to rank
the projects even when the costs of the projects differ significantly.
It recognizes the time value of money and is suitable to applied in a
situation with uniform cash outflows and uneven cash inflows.
It takes into an account the earnings over the entire life of the project and
gives the true view of the profitability of the investment.
Takes into consideration the objective of maximum profitability.
DISADVANTAGES:
More difficult to understand and operate.
51
It may not give good results while comparing projects with Unequal
investment funds.
It is not easy to determine and appropriate discount rate.
It may not give good results while comparing projects with unequal lives
as the project having higher NPV but have a longer life span may not be
as desirable as a project having some what lesser NPV achieved in a
much shorter span of life of the asset
52
53
DATA ANALYSIS
The essential
Profitability Index
All these methods of capital budgeting techniques are explained in detail below:
54
In case of unequal cash inflows, the pay back period can be computed by
calculating the cumulative cash inflow and checking weather the values are
recovered to the original outlay and taking the remaining amount and apply the
formulae i.e.,
Required CFAT
PBP = base year + ---------------------------Next year CFAT
ACCEPTANCE RULE:
Many firms use the payback period as an accept for reject criterion as well as a
method of ranking projects. If the payback period calculated for a project is less
than the maximum or standard pay back period set by management, it would be
accepted, if not, it would be rejected. As a ranking method, it gives highest
55
ranking to the project, which has the shortest payback period and lowest ranking
to the project, which has highest payback period.
56
INC
TAX
PAT
DEP
58.8
58.8
10.95
10.95
69.75
69.75
237.75
58.8
10.95
58.8
10.95
58.8
10.95
58.8
10.95
58.8
10.95
58.8
10.95
58.8
10.95
58.8
10.95
168.00 237.75
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
237.75
168.00
2433.28
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
0
0
0
0
0
0
0
0
0
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
CFAT CCFAT
22.5
22.5
41.78
41.78
14.00
14.00
55.78
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
22.5
41.78
14.00
55.78
14.00
55.78
14.00
55.78
22.5
22.5
41.78
41.78
475.00
713.25
951.00
1188.75
1426.50
1664.25
1902.00
2139.75
2377.50
2489.06
2544.84
2600.62
2656.40
2712.18
2767.96
2823.74
2879.52
2935.30
2991.08
3046.86
3102.64
3158.42
3214.20
Interpretation:
As per pay back period, the project is accepted because to get the initial
investment of 2100 crores, it is taking a time of 8.83 years. So the project can be
accepted.
58
ROE
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
INC
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
TAX
0
0
0
0
0
0
0
0
0
0
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
PAT
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
1324.20
CALCULATION OF ARR:
59
Average NPAT
= 1324.2/25
Average Investment
ARR
52.968
= ---------- X 100
1050
= 2100/2
52.968.
=
1050
= 5.04%
Interpretation:
From the point of ARR method, project should be accepted, as its ARR is less
than the required rate return (5.04% < 12%).
60
It correctly
postulates that cash flows arising at different time periods differ in value and the
comparable only when their equivalents present values are found out.
The following steps are involved in the calculation of NPV.
61
Acceptance Rule:
The project should be accepted if NPV is positive it should be clear that the
acceptance rule using NPV method is to accept the investment project if its net
present value is negative (NPV CASH OUTFLOW). The positive net present
value will result only if the project generates cash inflows at rate higher than the
opportunity cost of capital.
A project may be accepted in NPV = 0.
62
63
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
INC
TAX
PAT
DEP
CFAT
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
0
0
0
0
0
0
0
0
0
0
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
41.78
41.78
PV@
12%
1.000
0.893
0.797
0.712
0.636
0.567
0.507
0.452
0.404
0.361
0.322
0.287
0.257
0.229
0.205
0.183
0.163
0.146
0.130
0.116
0.104
0.093
0.083
0.074
0.066
0.059
PV
CFAT
212.31
189.49
169.28
151.21
134.80
120.54
107.46
96.05
85.83
76.56
16..01
14.34
12.77
11.43
10.21
9.09
8.14
7.25
6.47
5.80
5.18
4.63
4.13
3.68
3.29
1465.97
CASH
O.F
420.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
PV OF
COF
420.00
150.02
133.90
119.62
106.85
95.26
85.18
75.94
67.87
60.65
54.10
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1369.39
64
65
PROFITABILITY INDEX:
It is also called as Benefit Cost Ratio. It is also a time-adjusted method of
evaluating the investing proposals. It is the relationship between present value
of cash inflows and the present value of cash outflows. Thus
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
INC
TAX
PAT
DEP
CFAT
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
0
0
0
0
0
0
0
0
0
0
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
PV@
12%
1.000
0.893
0.797
0.712
0.636
0.567
0.507
0.452
0.404
0.361
0.322
0.287
0.257
0.229
0.205
0.183
0.163
0.146
0.130
0.116
0.104
0.093
0.083
0.074
0.066
0.059
PV OF
CFAT
212.31
189.49
169.28
151.21
134.80
120.54
107.46
96.05
85.83
76.56
16..01
14.34
12.77
11.43
10.21
9.09
8.14
7.25
6.47
5.80
5.18
4.63
4.13
3.68
3.29
1465.97
CASH
O.F
420.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
PV OF
COF
420.00
150.02
133.90
119.62
106.85
95.26
85.18
75.94
67.87
60.65
54.10
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1369.39
66
PV of cash inflows
Profitability Index = -------------------------PV of cash out flows
NPV
Net Profitability Index = -------------------------Initial cash outlay
From the above table calculated values are
Present value of cash inflow = 1465.97
Present value of cash outflow = 1369.39
Profitability Index
1465.97
= ------------------1369.39
=
1.071
96.58
--------------1369.39
0.071
67
68
ACCEPTANCE RULE
The accept project rule, using the IRR method, is to accept the project if its
internal rate of return is higher than the opportunity cost of capital (r>k) note
that k is also known as the required rate of return or cut-off rate. The project
shall be rejected if its internal rate of return is lower than the opportunity cost of
capital. Thus the IRR acceptance rules are:
Accept if r>k
Reject if r<k
May accept if r=k
69
YR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
ROE
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
58.8
INC
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
10.95
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
5.48
TAX
0
0
0
0
0
0
0
0
0
0
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
22.5
PAT
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
69.75
DEP
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
168.00
CFAT
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
237.75
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
41.78
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
14.00
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
55.78
PV @
12%
0.893
0.797
0.712
0.636
0.567
0.507
0.452
0.404
0.361
0.322
0.287
0.257
0.229
0.205
0.183
0.163
0.146
0.130
0.116
0.104
0.093
0.083
0.074
0.066
0.059
PV OF
PV @
CFAT@12% 13%
212.31
0.885
189.49
0.783
169.28
0.693
151.21
0.613
134.80
0.543
120.54
0.480
107.46
0.425
96.05
0.376
85.83
0.333
76.56
0.295
16..01
0.261
14.34
0.231
12.77
0.204
11.43
0.181
10.21
0.160
9.09
0.141
8.14
0.125
7.25
0.111
6.47
0.098
5.80
0.087
5.18
0.077
4.63
0.068
4.13
0.060
3.68
0.053
3.29
0.047
PV OF
CFAT@13%
210.41
186.16
164.76
145.74
129.10
114.12
101.04
89.39
79.17
70.14
14.56
12.89
11.38
10.10
8.92
7.86
6.97
6.19
5.47
4.85
4.30
3.79
3.35
3.00
2.62
1465.97
1396.26
70
Therefore, IRR
PV @ L R - C O F
LR + --------------------------------- x Rate Difference
PV @ L R - PV @ H R
1465.97 1369.39
12% + ------------------------- x 1
1465.97 1396.26
96.58
12% + --------- x 1=12% + 1.39%=13.39%
69.71
Interpretation:
Therefore, IRR lies at 13.39%. It is a point where outflow = inflow.
And IRR>K, Therefore it is accepted.
WORKINGS
71
ROE
420 x 14% =
58.8
Incentive
Pisa
= 3942
500 MW x 24 x 365
= --------------------------- X 85 %
1000
= 3723
X 80 %
= 3504
Therefore, Incentive
For the first 10 y = (3942 3504) x 0.25
109.5 = 10.95
10
54.75 = 5.48
10
72
Depreciation
73
74
FINDINGS:
The power sector is a service sector which falls in basic infrastructure sector the
motto of investment is to serve the society rather than profit making hence the
social cost benefit analysis method to be followed.
The VTPS-IV will take long period to recover the initial investment.
The average rate of return is very less because the motto is not to earn
profits. This is compensated by good benefits to the society.
The unit cost and other expenditures are eligible to claim from the
potential buyer as approved by the Regulatory Commission.
75
76
SUGGESTIONS
For society with lower income levels or below poverty line company
should go for subscribed rates and for industries it should increase its rate
marginally to cover the losses.
The risk is associated with the project, since the generation period is high.
77