Vous êtes sur la page 1sur 1

2014

2015

2016

2017

2018

2019

2020

Net MW a

Current Contracted Capacity


Ghubrah

430

235

235

235

Rusail

687

687

687

687

687

687

687

Wadi Al Jizzi
Manah

333
273

252
273

160
273

160
273

160
273

129
273

98
273

Al Kamil

282

282

282

Barka I

435

435

435

435

Sohar I

590

590

590

590

590

590

590

Barka II

679

678

678

678

678

678

678

Sohar II

742

740

739

738

738

738

738

Barka III

742

740

739

738

738

738

738

Surb

2000

1992

1988

1985

1983

1983

1983

TOTAL

7193

6904

6806

6519

5847

5816

5785

All capacities are rated on a net basis (i.e. after allowing for auxiliary consumption inside the plants) at 45C ambient temperature.
b
Although the Sur IPP is contracted to start at full capacity in April 2014, there is expected to be a delay in the commissioning
schedule such that the full capacity of 2000 MW will be available after the start of the summer period.

Non-Firm Resources under Contract


In addition to the contracted capacity described above, OPWP has contracts with a number of other sources of
power for the MIS, although these contracts are not for firm capacity commitments. These include:

the 220 kV interconnect with the Abu Dhabi power system at Mahadha;

the 132 kV interconnect with the PDO power system at Nizwa; and

the surplus generation of industries (and other parties) with captive power generation facilities used
mainly for self-supply.

A 220 kV interconnection between the MIS and the Abu Dhabi power system was commissioned in 2011 and
has been commercially operational since May 2012. This double circuit link currently supports reliable
transfers of up to 200 MW. It is technically capable to carry up to 400 MW in emergencies, and has proven this
latter capacity on numerous occasions. The main purpose of this interconnect as currently envisioned is for
emergency support and reserve sharing, subject to the availability of surplus generation in either system. The
link is being utilized actively to provide emergency reserves support to the benefit of Oman, the UAE, and
other GCCIA member countries. It is expected that this link will be upgraded to 400 kV by Transco Abu Dhabi,
doubling the reliable transfer capability to 400 MW; hence the emergency capability support will also be
doubled up to 800 MW.
The MIS is connected with the power system of PDO at Nizwa via a single 132 kV link with a nominal transfer
capacity of around 60 MW. The main purpose of this interconnect is to support reserve sharing between the
MIS and the PDO system, providing improved reliability in both systems by allowing each system access to
unused reserve in the other system in contingency scenarios. Thus, subject to the availability of surplus
generation in the PDO system at the time required, up to around 60 MW of support can be provided to the
MIS to help manage contingencies.
7-Year Statement (2014-2020)

Page 10

Vous aimerez peut-être aussi