Académique Documents
Professionnel Documents
Culture Documents
42.0
42.1
If at any time before the whole of the Works have reached practical
Completion pursuant to clause 39, the Government with the consent of the
Contractor (which consent shall not be unreasonably withheld) shall take
possession of and occupy any part or parts of the same (any such part being
hereinafter in this Clause referred to as the relevant part), then
notwithstanding anything expressed or implied elsewhere in this Contract,
carrying out works on the site. If there is a contractual right for the contractor to
rectify defects, and the employer either does not notify the contractor that
rectification is needed or refuses access to the site, then the employer may be in
breach of contract. The claim is likely to be limited to the amount it would have
cost the original contractor to carry out the works, but the employer will still
have a claim for the cost of rectifying the defects. It will not be able to claim for
remedial works or working methods found not to be strictly necessary.
Employers should therefore give a consideration to the provisions in the
contract before hiring a new contractor to carry out remedial works.
employer. In other words, the Contractor is not permitted to carry out any work
under the Contract unless and until the performance bond is given. The failure of
the Contractor to give the performance bond may amount to a fundamental
breach of contract entitling the Government to discharge the Contract and sue
the Contractor for damages accordingly. By clause 37(b), the performance bond
is required to be maintained for such period as provided in the PWD Bond, until
6 months after the expiry of the Defects Liability Period stated in the Contract
calculated from the date of completion of the Works or any authorized extension
or if the contract is determined, until one year after the date of determination.
There is in principle nothing to prohibit the applicability of this clause even if the
Works are to be executed in phases following clause 41 of these conditions
provided that the relevant part is taken over practical completion of that phase.
This clause makes it obligatory on the Contractor to give all necessary assistance
including access and provision of information such as designs, records and etc to
the Government or other such person or bodies authorized by the Government
for the purpose of determining the cause of any accident, failure or other
incidents that has occurred to or in connection with the Works. Typical examples
of such incidents include site incidents that may have resulted in death personal
injury or collapse of constructed structures of the Works. The accident
investigation process involves the report the accident occurrence to a designated
person within the organization, provide first aid and medical care to injured
person and prevent further injuries or damage, investigate the accident, identify
the causes, report the findings, develop a plan for corrective action, implement
the plan, evaluate the effectiveness of the corrective action and make changes for
continuous improvement. In this way, one is most likely to be able to observe the
conditions as they were at the time, prevent disturbance of evidence, and
identify witnesses. The tools that members of the investigating team may need
which is pencil, paper, camera, film, camera flash, tape measure, and etc should
be immediately available so that no time is wasted. Preconceived notions may
result in some wrong paths being followed while leaving some significant facts
uncovered, as mentioned above, an open mind is necessary in accident
investigation. The information that follows is intended to be a general guide for
supervisors. Always look for deeper causes. There are few reasons to investigate
a workplace accident, which is most importantly, to find out the cause of
accidents and to prevent similar accidents in the future, to fulfil any legal
requirements, to determine the cost of an accident, to determine compliance
with applicable safety regulation and to process workers' compensation claims.
Incidents that involve no injury or property damage should still be investigated
to determine the hazards that should be corrected. Some jurisdictions provide
guidance such as requiring that it must be conducted jointly, with both
management and labour represented, or that the investigators must be
knowledgeable about the work processes involved.