System Process Document

Creating Non-standard Jobs

Department
Responsibility/Role
File Name 27599130.doc
Revision
Document Generation Date 14/01/2010 14:04:00
Date Modified 1/14/2010 02:04:00 PM
Last Changed by
Status

Creating Non-standard Jobs


Trigger:

Concept
Non-standard discrete jobs can be used to control materials and resources and to collect costs for
a wide variety of miscellaneous manufacturing activities such as rework, field service repair
upgrades, and engineering prototypes. You can optionally assign an assembly to a non-standard
job, and choose whether to specify a job quantity.

In this topic, you will define a non-standard job on the Discrete Jobs page.

Required Field(s) Comments

Output - Result(s) Comments

Additional Information

Last changed on: 1/14/2010 02:04:00 PM Page 1


System Process Document
Creating Non-standard Jobs

Procedure

Step Action
1. Begin by navigating to the Discrete Jobs page.

Click the vertical scrollbar.

Page 2 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
2. Click the Discrete Jobs link.

Last changed on: 1/14/2010 02:04:00 PM Page 3


System Process Document
Creating Non-standard Jobs

Step Action
3. The Find Discrete Jobs page is used to search for existing jobs, or to create new
job records.

Step Action
4. Click the New button.

Page 4 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
5. The Discrete Jobs page is used to manually create jobs. A number of features are
available including:
• Defining standard, non-standard, and project jobs
• Assigning bills and routings for requirements
• Attaching explanatory files

Last changed on: 1/14/2010 02:04:00 PM Page 5


System Process Document
Creating Non-standard Jobs

Step Action
6. Click in the Job field.

Page 6 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
7. Enter the desired information into the Job field. Enter "Rework1234".

Step Action
8. Click the Type option.

Last changed on: 1/14/2010 02:04:00 PM Page 7


System Process Document
Creating Non-standard Jobs

Step Action
9. Click the Non-standard list item.

Page 8 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
10. In non-standard jobs you have the option to assign an assembly. For rework
assemblies, you can manually create rework operations or use a predefined rework
routing.

Click in the Assembly field.

Step Action
11. Enter the desired information into the Assembly field. Enter "AS18947".

Last changed on: 1/14/2010 02:04:00 PM Page 9


System Process Document
Creating Non-standard Jobs

Step Action
12. Non-standard discrete jobs do not earn overhead on completion - material overhead
at completion is posted directly to the subinventory material overhead account.
Select an asset type nonstandard accounting class because the job is building assets.

Click in the Class field.

Page 10 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
13. Enter the desired information into the Class field. Enter "Rework".

Last changed on: 1/14/2010 02:04:00 PM Page 11


System Process Document
Creating Non-standard Jobs

Step Action
14. When you define a job, its status defaults to Unreleased but can be changed.

Click in the Status field.

Step Action
15. Enter the desired information into the Status field. Enter "Released".

Page 12 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
16. For non-standard jobs, to perform move and completion transactions, the start
quantity must be greater than zero.

Click in the Quantities: Start field.

Last changed on: 1/14/2010 02:04:00 PM Page 13


System Process Document
Creating Non-standard Jobs

Step Action
17. Enter the desired information into the Quantities: Start field. Enter "10".

Page 14 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
18. The MRP Net quantity is derived from the job start quantity. For non-standard
discrete jobs without
assemblies, the default is zero.

Step Action
19. Click in the Dates: Start field.

Last changed on: 1/14/2010 02:04:00 PM Page 15


System Process Document
Creating Non-standard Jobs

Step Action
20. Enter the desired information into the Dates: Start field. Enter "10-APR-2008
12:00:00".

Page 16 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
21. Click in the Dates: Completion field.

Step Action
22. Enter the desired information into the Dates: Completion field. Enter "10-APR-
2008 16:00:00".

Last changed on: 1/14/2010 02:04:00 PM Page 17


System Process Document
Creating Non-standard Jobs

Step Action
23. Click the Save button.

Page 18 Last changed on: 1/14/2010 02:04:00 PM


System Process Document
Creating Non-standard Jobs

Step Action
24. You have completed the Creating Non-standard Jobs procedure.
End of Procedure.