Inspection and Test Plan for

Installation of Static Equipment

ITP No.:
Rev.:
Date:
Page:

ITP-MAG-IPP4-003
0
10.Jul.2013
1 of 1

IPP4 Power Project


ITP Subject: Installation of Static Equipment
Test
Description of Required Tests & Checks
Code
1
Procedures / Documents
1.1 Review of Installation Drawings, Vendor's
Manual & Technical Documents
1.2 Installation of Static Equipment Method
Statement Review & Approval
2
Material Receipt
2.1 Check Equipment Tag Number Identification

Reference
Documents

Certification Form

MAG

Involvement
WARTSILA

Drawing & Vendor


Manual

xx

Drawing & Vendor


Manual

xx

Packing Lists

xx

Packing Lists

xx

Installation Drawings

Survey Report
IPP4-QA-FR-G-002

Method Statement

Grout Report
IPP4-QA-FR-G-013

Method Statement

Grout Report
IPP4-QA-FR-G-013

2.2

Check Incoming Material

3
3.1

3.3

Pre-Installation Activities
Check Foundation for Location & Orienation of
Anchor Bolts, Bolt Pocket Leveling, Sole Plates,
Axis Marks of Foundation
Check Chipping & Brushing of Foundation
Surface under Base Plates
Check Cleanliness of Pocket

3.4

Check Base Plate Elevation

Equipment Drawing

Leveling Report
IPP4-QA-FR-G-014

4
4.1

Installation of Equipment
Check Verticality, Orientation & the Equipment
Leveling after Tightening of Anchor Bolts

Equipment Drawing

Leveling Report
IPP4-QA-FR-G-014

3.2

ITP-MAG-IPP4-003 Rev 0

Owner

Remarks

Inspection and Test Plan for


Installation of Static Equipment

ITP No.:
Rev.:
Date:
Page:

ITP-MAG-IPP4-003
0
10.Jul.2013
1 of 1

IPP4 Power Project


ITP Subject: Installation of Static Equipment
Test
Description of Required Tests & Checks
Code
4.2 Equipment Base Grouting
4.3
5

Ensure all Mechanical Completion Check List is


Completed
Punch List Clearance

Legends
S: Surveillance or Monitoring Point

ITP-MAG-IPP4-003 Rev 0

Reference
Documents

Certification Form

MAG
H

Involvement
WARTSILA
S

Equipment Drawing &


Method Statement

Grout Report
IPP4-QA-FR-G-013

As Per Mechanical
Completion Check List

Check List
IPP4-QA-FR-G-015

AS Per Punch List

Punch List
IPP4-QA-FR-G-009

R: Review of Documant or Report

W: Witness

Owner

H: Hold Inspection

Remarks

Project:

IPP4 Power Project


Document Title

Inspection and Test Plan for


Installation of Static Equipment
Document Number:

ITP-MAG-IPP4-003
Revision History
Rev. No.

Description / Reason for Issue

Date

Issued for Approval

10.Jul.2013

Prepared By

Checked By

B.Rihani

N.Abu Ghattas

Approved By
WARTSILA