Vous êtes sur la page 1sur 65

Material Requirement

Planning

Upendra Kachru

OPERATIONS MANAGEMENT

Material Requirements Planning


Materials requirements planning (MRP) is a means for
determining the number of parts, components, and
materials needed to produce a product
MRP provides time scheduling information specifying
when each of the materials, parts, and components should
be ordered or produced
Dependent demand drives MRP
MRP is a software system

Upendra Kachru

OPERATIONS MANAGEMENT

MATERIAL PLANNING
Master Production
Schedule (MPS)
(what we plan)

Inventory
Status
Records

(what we have)

Material
Requirements
Planning (MRP)

(what we require)

Product
Structure
Records

(what we need)

Purchasing
Upendra Kachru

Manufacturing
OPERATIONS MANAGEMENT

Primary Prerequisites
For MRP
1. A Master Production Schedule exists
and can be stated in bill of materials
form;
2. All inventory items are uniquely
identified;
3. A bill of material exists at the time of
planning
4. Inventory records contain data on the
status of every item;
5. There is integrity of file data.
Upendra Kachru

OPERATIONS MANAGEMENT

Master Data
Material Master

MRP Group - Group common MRP materials together


MRP Type - Planning Method.
Planning Time Fence - Restricts Activities
Lot Sizing - Lot Size determination
Storage Cost Indicators - For Optimum Lot sizing Only
Ordering Costs
Assembly Scrap - For Assembly Scrap Only
Procurement Type - Make or Buy Indicator.
Safety Stock

Upendra Kachru

OPERATIONS MANAGEMENT

Based on a master production


schedule, a material
requirements planning system:

Creates schedules identifying the


specific parts and materials
required to produce end items

Determines exact unit numbers


needed

Determines the dates when orders


for those materials should be
released, based on lead times

Upendra Kachru

Material
Requirements
Planning System

OPERATIONS MANAGEMENT

Primary MRP Reports


Planned orders to be released at a future time
Order release notices to execute the planned orders

Changes in due dates of open orders due to rescheduling


Cancellations or suspensions of open orders due to
cancellation or suspension of orders on the master
production schedule
Inventory status data

Upendra Kachru

OPERATIONS MANAGEMENT

Secondary MRP Reports


Planning reports, for example, forecasting inventory
requirements over a period of time

Performance reports used to determine agreement


between actual and programmed usage and costs
Exception reports used to point out serious
discrepancies, such as late or overdue orders

Upendra Kachru

OPERATIONS MANAGEMENT

Overview : BOM Explosion

Bill of Materials

Net Requirements Calculation


Lot- size calculation
Procurement type
Scheduling

BOM Explosion: Determine


the valid BOM for explosion

Upendra Kachru

OPERATIONS MANAGEMENT

Bill of Materials
The bill of materials is a materials list that provides information
useful to reconstruct the manufacturing process.
It is the master product definition that contains as-designed
information.
The information includes product description:

Materials
Parts
Components
Production sequence

Upendra Kachru

OPERATIONS MANAGEMENT

A Typical Engineering Bill of Materials


Level

Part-

Revision

Quantity

Description

Make/buy

16844-23003

Adapter

Make

16844-23004

Control Unit

Buy

16844-23010

Moisture
Tester

Make

16844-23023

Enclosure

Buy

16844-23024

Enclosure

Buy

16844-23025

Machine
Screw

Buy

16844-23033

Cover

Buy

16844-23030

AA

Precipitatory
Assy.

Make

16844-23040

Element

Buy

16844-23043

Housing

Buy

16844-23048

Machine

Buy

16844-23049

Precipitator

Buy

Upendra Kachru

OPERATIONS MANAGEMENT

The bill of material file provides


complete information on:
Raw materials in stock
Semi finished component parts in
stock
Finished component parts in stock
Sub-assemblies in stock
Component parts in process
Sub-assemblies in process

Upendra Kachru

BOM File
OPERATIONS MANAGEMENT

12

Each inventory item is carried as a


separate file
The bill of materials pegs materials i.e.
lists components of each assembly and
subassembly linking of individual item
bills which from the product, resulting
in a hierarchical, and pyramid like
structure with different levels.
It Identifies each parent item that
created demand

Upendra Kachru

Bill Of Materials
(BOM) File:

OPERATIONS MANAGEMENT

Typical Product Structure


P

Parent

Level 2

G
X

The bill of material file guides the explosion process.


Upendra Kachru

Level 1

OPERATIONS MANAGEMENT

Level 3

BOM Selection
BOM Selection ID
Planned order

Priority

Usage

Production

Engineering

Used if no valid production


BOM exists

Production
BOM

Upendra Kachru

Engineering
BOM

Costing
BOM

OPERATIONS MANAGEMENT

It is an artificial grouping of items


in bill of materials format, which
expresses the relationship of
multiple product features, variants
and options, where inventory
items are arranged in terms of
product modules each of which
can be planned as a group.
Modular bill kept for each major
subassembly
Simplifies forecasting and planning

Modular Bill of
Materials
Upendra Kachru

OPERATIONS MANAGEMENT

Modular BOM
X10
Automobile

Engines
(1 of 3)

Exterior color
(1 of 8)

Interior
(1 of 3)

Interior color
(1 of 8)

Body
(1 of 4)

4-Cylinder (.40)

Bright red (.10)

Leather (.20)

Grey (.10)

Sports coupe (.20)

6-Cylinder (.50)

White linen (.10)

Tweed (.40)

Light blue (.10)

Two-door (.20)

8-Cylinder (.10)

Sulphur yellow (.10)

Plush (.40)

Rose (.10)

Four-door (.30)

Neon orange (.10)

Off-white (.20)

Station wagon (.30)

Metallic blue (.10)

Cool green (.10)

Emerald green (.10)

Black (.20)

Jet black (.20)

Brown (.10)

Champagne (.20)

B/W checked (.10)

Combinations = 3 x 8 x 3 x 8 x 4 = 2,304 configurations


Combinations = 3 + 8 + 3 + 8 + 4 = 26 modular bills
Upendra Kachru

OPERATIONS MANAGEMENT

There are two somewhat different


objectives, in modularization.
To disentangle combination of
optimal product features.
To segregate common from unique,
or peculiar parts.

Objectives of
Modularization

The first is required to facilitate


forecasting.
The second is aimed at minimizing
inventories in components that are
common to option alternatives

Upendra Kachru

OPERATIONS MANAGEMENT

Net Requirements Calculation

Net Requirements
Calculation

Upendra Kachru

OPERATIONS MANAGEMENT

1. Individual item lead times are known;


2. Every inventory item goes into and out
of stock
3. All of the components of an assembly
are needed at the time of release of
assembly orders;
4. There is discrete disbursement and
usage of component materials
5. Process independence of manufactured
items is ensured.

Upendra Kachru

Assumptions

OPERATIONS MANAGEMENT

Net Requirements Calculation


MRP will compare the requirement and supply to get a
shortage gap. A comparison is made between
store/warehouse stock and the appropriate receipts and
issue.
1.
2.
3.

Upendra Kachru

Determine Available Store/


Warehouse Stock
Determine Planned Receipts (after
considering existing issues and
receipts)
Calculate the Shortage Quantity

OPERATIONS MANAGEMENT

MRP: Net Requirements Calculation


Matching Demand and Supply
Shortage

Lot Size
Sales Orders

Planned Orders
Planned Ind Reqmts
Production Orders
Compare

Dependent Reqmts

Purchase Requisitions
Reservations

Purchase orders
Warehouse Stock

Safety Stock

Supply

Demand

Upendra Kachru

OPERATIONS MANAGEMENT

How the Planning Run Works


In the net requirements calculation, a difference is made between
reorder point planning, forecast-based planning, and MRP. In each
procedure, the system calculates available stock differently.
Reorder Point Planning
When Available Stock falls below reorder level, planned orders are
generated in the planning run to order up to reorder level. Safety Stock
requirement is just for information
Available Stock = Plant Stock + Receipts
Forecast Based Planning
System only considers forecast requirements (any other requirements are not
considered). Planned orders are proposed when available stock is less than
forecast requirements.
Available Stock = Plant stock - Safety Stock + Receipts - Forecast Requirements

Upendra Kachru

OPERATIONS MANAGEMENT

BOM Explosion

Usage quantity

Items relevant to

Explosion date

/dates

production

Target

Dependent reqmts
quantities and dates
Component selection
Change status

Lot size

Usage

Upendra Kachru

OPERATIONS MANAGEMENT

BOM Explosion: Selection by Order Start


Order start

Order start
Order 1

BOM 1

Order 2

BOM 2

BOM 3

Time

Valid from
(relevant to
planning from )
Upendra Kachru

Valid from
(relevant to
planning from )

Valid from
(relevant to
planning from )

OPERATIONS MANAGEMENT

Explosion: Using the Order Finish Date


Order finish
Order 1

BOM 1

Valid from
(relevant to
planning from )
Upendra Kachru

Order finish

Order 2

BOM 2

Valid from
(relevant to
planning from )

BOM 3

Time
Valid from
(relevant to
planning from )

OPERATIONS MANAGEMENT

Safety Stock

Handling Safety Stock


Stock
Safety stock: To be set in material
master

Available
quantity
for planning

Safety stock
(not available
for planning)
Reqmt
Upendra Kachru

Time

Receipt
OPERATIONS MANAGEMENT

Planning Time Fence


Plan is protected from changes within the planning time fence.
End date of time fence determined from planning date.
You can configure system as to how you want the orders to react
within the time fence.

Upendra Kachru

OPERATIONS MANAGEMENT

Planning Time Fence


Outside the time fence, system creates order proposal as usual.
When new orders move into the time fence, they may be firmed
automatically depending on how the system is configured.
Firming Types for MRP Planned Materials :
Orders Moving Into
Firming Types TimeFence
Type 1
Firmed
Type 2
Firmed
Type 3
Not Firmed
Type 4
Not Firmed

Upendra Kachru

New Order
Proposals Creation
Outside Time Fence
No Orders Created
Outside Time Fence
No Orders Created

New Order
Status
Not Firmed
NA
Not Firmed
NA

OPERATIONS MANAGEMENT

Lot Size Calculations and Scheduling

Lot- size calculation


Procurement type
Scheduling

Upendra Kachru

OPERATIONS MANAGEMENT

Overview of Lot- Sizing Procedures


Definition in
Customizing

Entered in
Material master

Lot- sizing procedures


Static
procedures

Other
Period
procedures

Lot- for -lot order quantity

Fixed lot size

Optimal Lot sizing

EOQ

Determining the Lot Size


Upendra Kachru

OPERATIONS MANAGEMENT

Lot Sizing in MRP Programs

Upendra Kachru

Lot-for-lot (L4L)
Economic order quantity (EOQ)
Least total cost (LTC)
Least unit cost (LUC)
Which one to use?
The one that is least costly!

OPERATIONS MANAGEMENT

Optimum Lot- Sizing Procedures


Many deliveries /
High order costs

Few deliveries /
Low order costs

Upendra Kachru

Minimal stockkeeping/
Minimal storage costs

More extensive stockkeeping/


Higher storage costs

OPERATIONS MANAGEMENT

Procurement Types
Procurement Types

In- house
production

Production in
own plant

Stock transfer

Production in
another plant

Reservation in
another plant

External procurement

Subcontracting

Vendor

Components
Components

Procurement types
Special procurement types

Upendra Kachru

OPERATIONS MANAGEMENT

Backward Scheduling

Planned order
Opening period
Scheduling margin
key (MRP 2)

In-house production time


Lot- size dependent : MRP 2
Lot- size independent : work scheduling

Goods receipt
processing time
MRP 2

Time

Opening
date

Upendra Kachru

Order start
date

Order finish
date

Availability
date

OPERATIONS MANAGEMENT

Scheduling
The following times are taken into account :
Processing time required by purchasing department (workdays)
Planned delivery time of the material (calendar days)
Goods receipt processing time (workdays)

These times will be used to determine the release date of the


planned order or purchase requisition.

Upendra Kachru

OPERATIONS MANAGEMENT

MRP Example
Item
X
A
B
C
D

X
A(2)

C(3)

B(1)

C(2)

On-Hand Lead Time (Weeks)


50
2
75
3
25
1
10
2
20
2

D(5)

Requirements include 95 units (80 firm orders and 15 forecast) of X in


week 10

Upendra Kachru

OPERATIONS MANAGEMENT

Day:
X
LT=2

A(2)

It takes 2
As for
each X

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Upendra Kachru

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50

50

50

50

50

50

50

50

50

50
45
45

45
90
75

75

75

75

75

75

75

75
15
15

15
45
25

25

25

25

25

25

20
40

45
10

10

10

10

35

25

10
35
35
40

40
40
100

20

20

20

20

20

20

20
80
80

80

OPERATIONS MANAGEMENT

25
20
20

Day:
X
LT=2

A(2)

Onhand
50
A
LT=3

B(1)

It takes 1
B for
each X

Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Upendra Kachru

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50

50

50

50

50

50

50

50

50

50
45
45

45
90
75

75

75

75

75

75

75

75
15
15

15
45
25

25

25

25

25

25

20
40

45
10

10

10

10

35

25

10
35
35
40

40
40
100

20

20

20

20

20

20

20
80
80

80

OPERATIONS MANAGEMENT

25
20
20

Day:
X
LT=2

A(2)

Onhand
50
A
LT=3

B(1)

C(3)

Onhand
75
B
LT=1
Onhand
25
C
LT=2

It takes 3
Cs for
each A

Onhand
10
D
LT=2
Onhand
20

Upendra Kachru

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50

50

50

50

50

50

50

50

50

50
45
45

45
90
75

75

75

75

75

75

75

75
15
15

15
45
25

25

25

25

25

25

20
40

45
10

10

10

10

35

25

10
35
35
40

40
40
100

20

20

20

20

20

20

20
80
80

80

OPERATIONS MANAGEMENT

25
20
20

Day:
X
LT=2

A(2)

C(3)

Onhand
50
A
LT=3

B(1)

C(2)

Onhand
75
B
LT=1
Onhand
25
C
LT=2

It takes 2
Cs for
each B

Onhand
10
D
LT=2
Onhand
20

Upendra Kachru

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50

50

50

50

50

50

50

50

50

50
45
45

45
90
75

75

75

75

75

75

75

75
15
15

15
45
25

25

25

25

25

25

20
40

45
10

10

10

10

35

25

10
35
35
40

40
40
100

20

20

20

20

20

20

20
80
80

80

OPERATIONS MANAGEMENT

25
20
20

Day:
X
LT=2

A(2)

Onhand
50
A
LT=3

B(1)
D(5)

C(3)

C(2)

It takes 5 Ds
for each B

Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Upendra Kachru

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50

50

50

50

50

50

50

50

50

50
45
45

45
90
75

75

75

75

75

75

75

75
15
15

15
45
25

25

25

25

25

25

20
40

45
10

10

10

10

35

25

10
35
35
40

40
40
100

20

20

20

20

20

20

20
80
80

80

OPERATIONS MANAGEMENT

25
20
20

18-43

MRP - Closed Loop System


Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning

No
Feedback

Realistic?

Feedback

Yes
Execute:
Capacity Plans
Material Plans
Upendra Kachru

OPERATIONS MANAGEMENT

MRP Scheduling Terminology


Gross Requirements
Scheduled receipts
Projected available balance
Net requirements

Planned order receipt


Planned order release

Upendra Kachru

OPERATIONS MANAGEMENT

Forward Scheduling
Automatic, if order start date is in the
past during backward scheduling

Today
Planned order
In-house production time

Goods receipt
processing time

Time

Order start
date

Upendra Kachru

Order finish
date

Availability
date

OPERATIONS MANAGEMENT

ERP SYSTEMS

Upendra Kachru

OPERATIONS MANAGEMENT

What is ERP?
Enterprise Resource Planning
It attempts to integrate all data and processes of an organization into
a unified system. A typical ERP system will use multiple
components of computer software and hardware to achieve the
integration. A key ingredient of most ERP systems is the use of a
unified database to store data for the various system modules.

Upendra Kachru

OPERATIONS MANAGEMENT

Evolution of ERP

1960s: software packages with inventory control


1970s: MRP systems
Production schedule with materials management

1980s: MRPII systems


Adds financial accounting system

1990s: MRPII
Integrated systems for manufacturing execution

Late 1990s: ERP


Integrated manufacturing with supply chain

2000s: ERP II

Upendra Kachru

OPERATIONS MANAGEMENT

ERP - Definition
ERP is a process of managing all resources and their use in the entire
enterprise in a coordinated manner
ERP is a set of integrated business applications, or modules which carry out
common business functions such as general ledger, accounting, or order
management

Put simply, ERP systems tie together varied processes using data
from across the company. For instance, a typical ERP system
manages functions and activities as different as the bills of materials,
order entry, purchasing, accounts payable, human resources, and
inventory control, to name just a few of the modules.

Upendra Kachru

OPERATIONS MANAGEMENT

Problems of Legacy Systems


Automates existing processes
Normally not driven by organization strategy and business vision.
Develop one application at a time. No integration between applications just
transaction passing.
Decentralized applications.
Are relatively inflexible to accommodate changes in the business environment.
Written in language / platform prevalent at the time of development.
Up gradation to latest technology is difficult
Usually not well documented.
Maintenance is a problem largely because of poor documentation and staff
attrition.

Upendra Kachru

OPERATIONS MANAGEMENT

What makes ERP different


Supports business through optimizing, maintaining,
and tracking business functions

Upendra Kachru

Integrated modules
Common definitions
Common database
Update one module, automatically updates others
ERP systems reflect a specific way of doing business
Must look at your value chains, rather than functions

OPERATIONS MANAGEMENT

Process View of Business

Logistics
Function

Production
Function

Purchasing
Function

Accounting
Function

Sales
Function

Customer Order Process

Material Order Process


The basic ERP Model is based on a process view of the organization. Each of the tasks
may cross functional boundaries
Upendra Kachru

OPERATIONS MANAGEMENT

ERP Structure

The foundation of ERP systems is popularly called the Stool. The stool is made up of three
basic elements Market Sales and Distribution, the Product Materials Management and
Production and the Financial Accounting and Control.
Upendra Kachru

OPERATIONS MANAGEMENT

ERP System Drivers


Executive
Management

Middle
Management

Operational
Management

Operations
Finance

Upendra Kachru

Sales
DistributionProduction

Human
Resources

OPERATIONS MANAGEMENT

54

Financials
Financial and management accounting
Internal Controlling and Audit

Upendra Kachru

Financial Supply Chain Management


General Ledger
Financial Reporting
Costing
Budgeting
Accounts Payable
Accounts receivables

OPERATIONS MANAGEMENT

Human Capital Management

Upendra Kachru

Recruiting
Applicant data administration Compensation
Assessment
Development and Training
Personnel development planning
Payroll
Benefits administration
Workforce planning
Schedule & shift planning
Time management
Travel expense accounting
OPERATIONS MANAGEMENT

Marketing & Sales Management

Upendra Kachru

Lead tracking
Sales forecasting
Order management
Customer management
Customer service

OPERATIONS MANAGEMENT

Operations

Upendra Kachru

Materials management
Inventory management
Plant maintenance
Quality management
Production planning & control
Project management system

OPERATIONS MANAGEMENT

Example of How ERP Works


ERP delivers a single database that contains all data for the software
modules across an entire company. People in different departments all see
the same information and can update it. For example:
Step 1 : Brazilian retailer orders, via the Internet, 1,000 shoes
from International Shoe Co. A sales rep takes the order, routes it
to ERPs ordering module, ERP checks the retailer credit, price,
etc. The order is approved.
Step 2 : Simultaneously ERPs inventory module checks the
stocks and notifies the rep that half the order can be filled
immediately from stock. The other half will be manufactured
and delivered in 5 days directly from the factory in Taiwan.
Upendra Kachru

OPERATIONS MANAGEMENT

Example of How ERP Work


Step 3 : ERPs manufacturing module schedules the production in
Taiwan and instructs the warehouse (in China) to ship the shoes to
Brazil and print up an invoice (in Portuguese).
Step 4 : ERPs human resources module calculates labor
requirements. Due to a shortage, the personnel manager in Taiwan
is instructed to get temporary workers.
Step 5 : ERPs material planning module notifies the purchasing
manager about a shortage of purple dye. A purchase order is
automatically issued.

Upendra Kachru

OPERATIONS MANAGEMENT

Example of How ERP Work


Step 6 : The customer logs on via the extranet to the
companys sneakers division. He can see that 500 shoes were
shipped from the regional warehouse. This is done with ERP
tracing capabilities.
Step 7 : Based on data from ERPs forecasting and financial
modules, the CEO can determine both demand and
profitability per product. The financial module also converts
all foreign money to $U.S., whenever needed

Upendra Kachru

OPERATIONS MANAGEMENT

Benefits of ERP

Desire to standardize and improve processes


To improve the level of systems integration
To improve information quality
Common set of data
Help in integrating applications for decision making and
planning
Allow departments to talk to each other
Easy to integrate by using processed built into ERP software
A way to force BPR (reengineering)

Upendra Kachru

OPERATIONS MANAGEMENT

Difficulty in implementation

Very difficult
Extremely costly and time intensive
Typical: over $10,000,000 and over a year to implement
Company may implement only certain modules of entire
ERP system
You will need an outside consultant

Upendra Kachru

OPERATIONS MANAGEMENT

Common Pitfalls

Do not adequately benchmark current state


Did not plan for major transformation
Did not have executive sponsorship
Did not adequately map out goals and objectives
Highly customized systems to look like old MRP systems

Upendra Kachru

OPERATIONS MANAGEMENT

Click

Upendra Kachru

to

edit

company

slogan

OPERATIONS MANAGEMENT

Vous aimerez peut-être aussi