Académique Documents
Professionnel Documents
Culture Documents
(D ) 2. AS-BUILT PLAN
( H ) 3. OCCUPANT LOADS
(E ) 7. INSIDE LOT
( L ) 8. CORNER LOT
( B ) 9. THROUGH LOT
1. R. A. 9266
(H )
2. PROJECTING SIGN
(F)
3. DISPLAY WINDOW
(B )
4. BUILDING LINE
(I)
5. ARCADE
(K)
6. STRUCTURE
(L )
7. CHAMFER
(A)
8. SKYLIGHTS
G. The mark of floor plan directly touching the ground, the perimeter
of which is seen.
(E )
(H )
2. COMBINATION STAND-PIPE
(M )
3. DRY STANDPIPE
(I)
(B )
(J)
6. FIRE WALL
(D )
(L)
(P)
9. FUMIGANT
(O)
H. Pipeline system filled with water supply for the use of the
service and the occupants of the building solely for fire
suppression purposes.
(N)
(G)
12 PLENUM
13. INCINERATOR
(F)
14. TURNSTILES
(A )
(E )
E. OFFICE PRACTICE
(M)
(F)
(J )
(N)
4. COMPENSATION BY MEANS OF
PERCENTAGE CONSTRUCTION COST
(K )
5. COMPENSATION BY MEANS OF
MULTIPLE OF DIRECT PERSONNEL
EXPENSES.
(A)
6. COMPENSATION BY MEANS OF
PROFESSIONAL FEE PLUS EXPENSES
(L)
(P )
(D)
9. ARBITRATION
E. OFFICE PRACTICE
(C)
(I)
(B )
(G )
(E )
(H )
F. CONTRACTS
(H )
(C)
(E )
(G )
(D)
5. ADMINISTRATION CONTRACT
(A )
6. MANAGEMENT CONTRACT
(B)
(F )
8. TURNKEY PROJECT
G. BIDDING
(H )
1.DESIGN STANDARD
(L )
2. FIELD SURVEY
(G)
3. CONTRACT PLANS
(I)
(A)
(J )
4. QUANTITIES
5. SPECIAL PROVISIONS
6. UNIT PRICE
(D )
(K)
8. BID/TENDER DOCUMENTS
(P )
9. PROGRAM OF WORK
(M )
(O )
11. OBLIGATIONS
(E)
G. BIDDING
(B )
(F )
(C)
(N )
1. SCHEDULING
(F)
2. PLANNING
(H )
3. PROGRAMMING
(B )
4. EFFICIENCY RATIOS
(G )
(C )
(A )
7. NETWORK
(E)
8. DUMMY
I. PROJECTS
(H)
(F )
2. EXECUTIVE SUMMARY
(E )
3. CASH FLOW
(A)
4. GENERAL CONDITION
(G )
5. SPECIFICATIONS
(B)
6. JOINT VENTURE
(D)
7. SOLE PRORIETORSHIP
(C )
8. CORPORATION
J. CONTRACT DOCUMENTS
___D__ 1. Which of the following may the owner NOT do?
A. Stop work if the contractors performance in not satisfactory or in variance with the contract documents.
B. Carry on the work and deduct costs normally due to the contractor for these corrections.
C. Stop the work if the Architect reports safety problems on the site.
D. Refuse, with good cause, to give the contactor proof the owner can meet the financial obligations of the
project.
__C___ 2. If, during bidding, your client asked you to provide a full-time staff member on the job site during construction,
you would be entitled to extra compensation . Under what provision would this be?
A. CONTRACT SUM
B. CONTIGENT ADDITIONAL SERVICES
C. PROJECT REPRESENTATION BEYOND BASIC SERVICES
D. OPTIONAL ADDITIONAL CHARGES
__B___ 3. The standard owner-architect agreement separates the architect from the contractor with what?
A. DUTIES TO THE CONTRACTOR
B. PRIVITY
C. ARCHITECTS SERVICES
D. THIRD PARTY RELATIONSHIP
__A___ 4. What is used to encourage the contractor to finish the job or to satisfy mechanics lien claims by sub-contractors?
A. RETAINAGE
B. FIXED LIMIT
C. SURETY BOND
D. LIQUIDATED DAMAGES
__B___ 5. What fee method would you prefer if your Client was doing the first project and did not yet have a program?
A. FIXED SUM
B. MULTIPLE OF DIRECT PERSONNEL EXPENSE
C. PERCENTAGE PF CONSTRUCTION COST
D. UNIT COST BASED ON SQUARE METER
__D___ 6. A project is about 60 percent complete when the owner begins receiving field reports from the Architect stating
that the contractor is failing to properly supervise the job, resulting in incorrect work. After several weeks of this,
the owner becomes worried and asks the Architect what to do. What should be done if the work is being
performed under the terms and conditions of the BUILDING CONTRACT?
A. After receiving the Architects field reports, the owner should stop the work and arrange for a meeting
between the owner, the owner, Architect and the contractor to determine the cause of the problems and what the
contractor intends to do. If the contractor does not correct the work, the owner should carry out the work with
other contractors and deduct the cost by change order from the original contractors construction cost.
B. The Architect should recommend that the owner give the contractor written notice of non-conformance with
the contract documents and if, after seven days the contractor has not begun corrective measures, terminate the
contract.
C. The Architect and owner should discuss the problem to see if the owner would be willing to accept it in
exchange for the reduction in the contract sum. If not, the owner should give seven days written notice to
terminate the contract and find another contractor to finish the job.
D. The Architect should, with the owners knowledge, reject non-conforming work and notify the contractor that
it must be corrected promptly. The Architect should remind the owner that the owner can have the work
corrected after giving the contractor two (2) seven day written notices to correct the work.
A. I, III, and V
B. I, II, III, and V
C. II, III, IV, and V
D. all of the above
___A__ 10. Which of the following is NOT an accurate statement?
A. The Architect is responsible for the defect in the work if he or she sees it but fails to report it to the
contractor.
B. The owner has the sole right to make changes in the work but must do it through the Architect.
C. The Architect does not have to verify and test reports given by the owner.
D. By the time construction documents are almost completed, the architect still does not have to give a
reasonably accurate construction price.
__B___ 11. Which of the following would be used to formally incorporate a substitution into the work prior to the award of
the contract?
A. CHANGE ORDER
B. ADDENDUM
C. ALTERNATE LISTING
D. CONSTRUCTION CHANGE DIRECTIVE
___D__ 12. Which of the following are part of the bidding documents?
I. SPECIFICATIONS II. INVITATION TO BID 111. LIST OF SUB CONTRACTORS
IV. OWNER-CONTRACTOR AGREEMENT V. PERFORMANCE BOND
A, I,II, IV, and V
B. II, III, and IV
C. II, III, IV, and V
D. all of the above
owner.
D. all of the above.
__D___ 8. During the periodic visit to the site the Architect notices what appears to be an undersized variable air volume
box
being installed. What should the Architect do?
A. Notify the mechanical engineer to look at the situation during the next site visit by the engineer. Note the
observation on a field report.
B. Find the contractor and stop work on the installation until the size of the unit can be verified by the
mechanical engineer and compared against the contract documents.
C. Notify the owner in writing that the work is not proceeding according to the contract documents. Arrange a
meeting with the mechanical engineer to resolve the situation.
D. Notify the contractor that the equipment may be undersized and have the contactor check on it. Ask the
mechanical engineer to verify the size of the unit against the specifications and report to the Architect.
__C___ 9. An Architect would use this instrument if the building department required additional exit signs beyond those
shown on the approved plans when the project is 90 percent completed?
A. order for minor change
B. addendum
C. change order
D. construction change directive
__B___ 10. The contractor is solely responsible for:
I. field reports to the owner
V. reviewing shop drawings
III. scaffolding
L. MISCELLANEOUS QUESTIONS.
__A___ 1. Which of the following would NOT be found in a project manual?
A. bid log
B. subsurface soil condition report
C. site work specifications
D. bid bond
__D___ 2. A performance specification:
A. allows innovation by the contractor
B. required more work by the Architect
C. is not appropriate for normal building products
D. all of the above
__D___ 3. What is likely to occur if the drawings and specifications are NOT thoroughly coordinated?
I. a decrease of the actual cost from the estimated cost because the contractor bid on a less expensive material
shown on the drawings while the same was called out as a more expensive type in the specifications.
II. a lawsuit
III. the need for a change order during construction to account for modifications required to correct discrepancies
in the two documents.
IV. an increase of cost because the contractor bid the least expensive choice between two conflicting requirements
when the client wanted the more expensive option.
A. I, III, and IV
B. I and III
C. II, IV, and V
D. III, IV and V
Question 4 refers to the following excerpt from the specification.
Part 2 Products
2.01 Metal Support Material
General: To the extent not otherwise indicated, comply with ASTM C734 for metal system supporting gypsum
wallboard.
Ceiling suspension main runners: 11/2 inches steel channels, cold rolled
Hanger wire: ASTM A641, soft, Class 1 galvanized, pre-stretched: sized in accordance with ASTM C754.
Hanger anchorage devices: size for 3 x calculated loads, except size direct-pull concrete inserts for 5 x
calculated loads.
Steel: ASTM C645: 25 gauge, 21/2 inches deep, except as otherwise indicated.
ASTM C645:25 gauge, 3 inches deep, ASTM C645: 20 gauge, 6 inches deep.
Runners: Match studs: type recommended by stud manufacturer for floor and ceiling support of studs,
and for vertical abutment or drywall work and other work
Furring members: ASTM C65: 25 gauge, hat-shaped
Fasteners: Type and size recommended by furring manufacturer for the substrate and application indicated.
__C___ 4. Which item is described as a performance specification?
A. fasteners
B. hanger wire
C. hanger anchorage devices
D. ceiling suspension main runners
__B___ 5. In specifying asphalt roofing shingles, which of the following types of specification would you probably NOT
use?
A. descriptive
B. base bid or equal
C. reference standard
D. base bid with alternate approved manufacturers
__A___ 6. Which of the following are generally true of specifications?
1. Both narrow scope and broad scope sections can be used in the project manual.
II. For the contractor, drawings are more binding than the specification if there is a conflict.
III. Specifications show quality: drawings show quantity.
IV. Proprietary specifications are the same as prescriptive specifications.
V. They should not be open to interpretation if they are the base bid type.
A. I, III, IV and V
B. I, III, and V
C. II, III, and IV
D. all of the above
__D___ 7. Where would you find requirements for testing a plumbing system?
A. in a section of Division 1 of the specification
B. in Part 1 of Section 15400, Plumbing
C. in Part 2 of Section 15400, Plumbing
D. in Part 3 of Section 15400, Plumbing
(G)
(F)
(I )
4. Pag-Ibig Fund
(B)
(J)
(A )
(C)
(E)
(D)
J.