Académique Documents
Professionnel Documents
Culture Documents
for
TANKS AND SILOS
These are guidance notes that cover the mechanics of the various tasks detailed. They only
refer to issues directly connected with the execution of the works. Only authorised
persons/contractors adequately supervised, correctly equipped and trained in all aspects of
the risks involved and the equipment to be used should be employed to carry out this work.
They must also be familiar with the safety data sheets of all products used.
It is the responsibility of the person/contractor undertaking these works to consider each
particular installation, its environment and the specific risks involved.
Whilst every care has been taken to ensure the accuracy of this guide through 1 May 2010,
Permastore shall have no liability for any loss or damage (direct, indirect, special or
consequential) arising out of or in connection with this guide. This guide is subject to
supplementation or change at any time without notice at Permastore's sole discretion. This
guide does not constitute a representation or warranty of any kind in favour of the customer,
and the customer's sole warranty is that which is provided in its sales contract with the
distributor. This guide does not amend or change such sales contract in any way.
Permastore Limited
Eye, Suffolk,
IP23 7HS,
England
Tel
: +44 (0) 1379 870723
Fax
: +44 (0) 1379 870530
E-mail : sales@permastore.com
Doc Ref: P132 Rev 9
1/5/10
Page 1 of 102
LIST OF CONTENTS
PART
SECTION
TITLE
PAGE
FOREWORD
3-6
One
7-8
One
9-11
One
Planning
12-14
One
15-19
One
Sheet Identification
20-21
One
22-23
One
24-25
One
26-28
One
Structure Dimensions
29-30
Two
31-34
Two
35-36
Three
37-39
Four
40-45
Four
46-47
Four
48-50
Five
Annular Tanks
51-52
Five
Backfilled Tanks
53-56
Six
57-58
Six
59-60
Six
61-63
Six
64-65
Six
66-68
Six
69-70
Six
71-72
Seven
Glass-Fused-to-Steel Floors
73-75
Eight
Cones
76-79
Nine
Ancillaries
80-89
Ten
Checklist
90-91
Ten
92-93
Eleven
Troubleshooting
94-97
A1-A4
Appendix A
1/5/10
Page 2 of 97
FOREWORD
1/5/10
Page 3 of 102
Foreword
c)
d)
e)
f)
g)
h)
i)
j)
k)
b)
1/5/10
2.
b)
Page 4 of 102
d)
e)
f)
3.
Foreword
Handling Hints
Chemical products used on site may have a
limited shelf life, which is dependent on storage
temperature.
Do not order these products
prematurely, to avoid deterioration. They should
be stored in areas which are cool, dry, well
ventilated and secure. Refer to the
manufacturer's instructions or accompanying
safety data sheet.
Sealants: Can burn if subjected to intense heat
or direct flames. To extinguish burning sealant,
use CO/foam or dry powder extinguisher.
Remove splashes of sealant on skin immediately
with an industrial hand cleanser. Sealants
normally present no inhalation problems given
good ventilation. Scrape up spilled sealant or
drips from excessive application, then wash the
area affected with a strong industrial detergent in
hot water.
Primers and Cleaners: Contain solvents and
are flammable. Use them only in well ventilated
areas.
Do not smoke when using them and keep away
from all naked flames, intense heat or sparking
equipment. To extinguish a fire use CO/foam or
dry powder extinguisher or, in an emergency,
dry sand or earth.
Remove splashes on the skin with an industrial
hand cleanser. Dry the skin with disposable
paper towels, not with a cloth towel.
Solvent vapours, even under conditions of low
rates of evaporation, can quickly build up in
enclosed areas lacking adequate ventilation.
Wear a suitable air mask. If you feel drowsy,
nauseous or if you experience breathing
difficulties, move into fresh air.
1/5/10
Site Safety
All relevant site safety regulations must be
observed. In general, these would include the
following requirements:a)
b)
c)
d)
e)
f)
g)
h)
Page 5 of 102
5.
Foreword
Site Practice
To ensure that all work is carried out to the
required standard of quality, observe the
following rules:a) Tank kits are shrink-wrapped prior to
shipment; they should not be accepted for
delivery to the site more than 4-6 weeks
before commencement of installation.
b) Store kits off the ground and clear of any
surface water. Avoid storing kits in busy
areas where they may suffer damage.
c) Whenever possible, transport the sheets to the
tank site on their original packing skids. Use
care when lifting sheets off the stack.
d) Keep the storage time of sealants to a
minimum, as they have a limited shelf life,
especially at high ambient temperatures.
6.
1/5/10
Page 6 of 102
1/5/10
Page 7 of 97
1/5/10
Page 8 of 97
1/5/10
Page 9 of 97
2.
3.
Ratchet spanner.
4.
1.
5.
6.
Cold chisel.
7.
8.
Screwdriver set.
9.
Putty knife x 8.
reamer.
See
See
22. Pliers.
23. Scissors.
24. Broom.
25. Shovels x 2.
1/5/10
Page 10 of 97
2.
3.
4.
5.
6.
7.
8.
9.
2.
3.
4.
See
1/5/10
Page 11 of 97
PART ONE
Section 3
Planning
1/5/10
Page 12 of 97
Planning
PLANNING
ON ARRIVAL AT SITE
1.
1.
b)
2.
c)
3.
d)
e)
f)
g)
4.
5.
6.
a)
b)
The customer.
b)
ii)
2.
1/5/10
3.
During Construction
Supervision checks should be made:a)
b)
4.
Planning
c)
d)
e)
1/5/10
Page 14 of 97
1/5/10
Page 15 of 97
3.
4.
5.
6.
7.
CAUTION
2.
1/5/10
Page 16 of 97
12. All ancillary items bolted to Glass-Fused-toSteel sheets such as angles and brackets must be
fully coated with sealant on contact surfaces to
prevent leakage.
13. All levels must always be maintained at + or
1.5mm (1/16 inch).
Circularity
Up to 13.7m (45ft)
6mm ( inch)
(90ft)
and
25mm (1 inch)
1/5/10
Page 17 of 97
Length
(mm)
25
32
38
44
51
64
Length
(inches)
1
1
1
1
2
2
Length
(mm)
51
64
76
Length
(inches)
2
2
3
Special Bolts:Colour
Brown
Mauve
Yellow
Doc Ref: P132 Rev 9
1/5/10
Page 18 of 97
17. CAUTION:
If Glass-Fused-to-Steel panels
require cutting on site the operation must always
be carried out using a jig-saw type cutter (refer
to Part Eleven Section 1).
1/5/10
Page 19 of 97
1/5/10
Page 20 of 97
Sheet Identification
SHEET IDENTIFICATION
TAPER IDENTIFICATION
In order to ensure trouble free sheet to sheet assembly,
Series 1400 sheets are produced with a slight taper to
accommodate the horizontal overlap. Dependent on
the sheet thickness and tank diameter one of the
following options will be provided. The absence of
any notch would signify a straight sheet with no taper.
MATERIAL THICKNESS IDENTIFICATION
To indicate the sheet thickness the standard horizontal
bolt holes are used as datum points.
Notch 1
Notch 1 & 2
Notch 1, 2 & 3
Notch 1, 2, 3 & 4
1/5/10
Page 21 of 97
1/5/10
Page 22 of 97
SEALANTS,
CLEANERS
NOTE 2: It is recommended practice for GlassFused-to-Steel surfaces to be clean and dry prior to
the application of the sealant. Glass-Fused-to-Steel
panels are wrapped after manufacture to ensure that
they are clean and dry at the time of construction.
When it is necessary to clean the surface use Sika
Cleaner 205 or alternatively, pure xylene,
methylethylketone (MEK) or isopropylalcohol (IPA).
Do not use any solvents or cleaners that might leave a
residue or contain turpentine, white spirits, phenols,
organic acids, surfactants or silicones. If in doubt
check with Permastore prior to use.
Always follow the manufacturer's advice on Health
and Safety and guidelines for application and curing
times.
1/5/10
Page 23 of 97
1/5/10
Page 24 of 97
2.
WITH
SILICONE
3.
4.
5.
1/5/10
6.
7.
8.
9.
Page 25 of 97
1/5/10
Page 26 of 97
1/5/10
Page 27 of 97
1/5/10
Page 28 of 97
1/5/10
Page 29 of 97
Structure Dimensions
Sheets
Per
Ring
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
Nominal Radius
Metres
Feet and
Inches
1.708
2.135
2.562
2.988
3.415
3.842
4.269
4.696
5.123
5.550
5.977
6.404
6.831
7.258
7.685
8.112
8.359
8.965
9.392
9.819
10.246
10.673
11.100
11.527
11.954
12.380
12.808
13.235
13.662
14.089
14.516
14.942
15.369
15.796
16.223
16.650
17.077
17.504
17.931
18.358
18.785
19.211
19.638
20.065
20.492
20.919
21.346
21.773
5'
7'
8'
9'
11'
12'
14'
15'
16'
18'
19'
21'
22'
23'
25'
26'
28'
29'
30'
32'
33'
35'
36'
37'
39'
40'
42'
43'
44'
46'
47'
49'
50'
51'
53'
54'
56'
57'
58'
60'
61'
63'
64'
65'
67'
68'
70'
71'
7"
4"
9"
2"
7"
"
4"
9"
2"
7"
"
4"
9"
2"
7"
"
5"
9"
2"
7"
"
5"
9"
2"
7"
"
5"
9"
2"
7"
"
5"
9"
2"
7"
"
5"
10"
2"
7
"
5"
10"
2"
7"
"
5"
Model
Diameter
Reference
146
148
151
154
157
160
162
165
168
171
174
176
179
182
185
188
190
193
196
199
202
204
207
210
213
216
219
221
224
227
230
233
236
239
242
245
248
251
254
257
260
262
265
268
271
274
277
280
Sheets
Per
Ring
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
Metres
22.200
22.627
23.054
23.481
23.908
24.335
24.762
25.189
25.616
26.042
26.470
26.896
27.323
27.750
28.177
28.604
29.031
29.458
29.885
30.311
30.738
31.166
31.593
32.020
32.447
32.873
33.300
33.727
34.154
34.581
35.008
35.436
35.863
36.290
36.717
37.144
37.571
37.998
38.425
38.851
39.278
39.705
40.132
40.559
40.986
41.413
41.840
42.267
Feet and
Inches
72'
74'
75'
77'
78'
79'
81'
82'
84'
85'
86'
88'
89'
91'
92'
93'
95'
96'
98'
99'
100'
102'
103'
105'
106'
107'
109'
110'
112'
113'
113'
116'
117'
119'
120'
121'
123'
124'
126'
127'
128'
130'
131'
133'
134'
135'
137'
138'
10"
2"
7"
"
5"
10"
2"
7"
"
5"
10"
3"
7"
"
5"
10"
3"
7"
"
5"
10"
3"
7"
"
5"
10"
3"
7"
"
5"
10"
3"
8"
"
5"
10"
3"
8"
"
5
10"
3"
8"
"
5"
10"
3"
8"
For tank diameters larger than those charted above please contact Permastore for further advice.
Doc Ref: P132 Rev 9
1/5/10
Page 30 of 97
1/5/10
Page 31 of 97
DESIGN
AND
1/5/10
Page 32 of 97
b)
c)
d)
e)
f)
1/5/10
Page 33 of 97
1/5/10
Page 34 of 97
1/5/10
Page 35 of 97
2.
2.
3.
3.
4.
2.
3.
LEVELLING SYSTEM
1.
1/5/10
Page 36 of 97
PART THREE
Section 1
Assembly of Tanks
From the Base Ring Upwards
1/5/10
Page 37 of 97
Assembly Methods
7.
2.
Diameter
Circularity
Up to 13.7m (45ft)
6mm ( inch)
From 14.5m to 26.5m
12.5mm ( inch)
(48ft to 87ft)
27.5m (90ft) and
25mm (1 inch)
above
8.
9.
3.
4.
6.
1/5/10
Page 38 of 97
Assembly Methods
INTERMEDIATE RINGS
1.
2.
3.
7.
8.
9.
Fully expand
concentricity.
vertical
joints
and
check
5.
6.
1/5/10
Page 39 of 97
PART FOUR
Section 1
1/5/10
Page 40 of 97
Assembly Methods
k)
l)
Important Information
a)
b)
c)
d)
e)
f)
h)
2.
3.
4.
5.
g)
i)
j)
1/5/10
Daily Checks
1.
2.
3.
4.
Weekly Checks
1.
2.
3.
4.
Page 41 of 97
Assembly Methods
3.
Slave Gearboxes
One advantage associated with the low-level
jacks is the opportunity to utilise 'slave
gearboxes' for a specified range of applications.
Slave gearboxes are low cost units that allow
safe construction utilising a reduced number of
jack legs.
2.
1/5/10
2.
3.
4.
5.
Page 42 of 97
7.
8.
Assembly Methods
OPERATION OF JACKS
1.
2.
3.
4.
5.
7.
8.
9.
1/5/10
Assembly Methods
Model Diameter
(ft)
17
20
22
25
28
31
34
36
39
42
45
48
50
53
56
59
62
64
67
70
73
76
78
81
84
87
90
92
95
98
101
104
Jack Legs
(No of units)
6
7
8
9
10
11
9
9
10
10
10
10
10
10
11
11
12
12
13
13
14
14
15
15
16
16
17
17
18
18
19
19
Slave Gearbox
(No of units)
0
0
0
0
0
0
3
4
4
5
6
7
8
9
9
10
10
11
11
12
12
13
13
14
14
15
15
16
16
17
17
18
1/5/10
Page 44 of 97
Assembly Methods
Model Diameter
(ft)
106
109
112
115
118
120
123
126
129
132
134
137
140
143
146
Jack Legs
(No of units)
20
20
21
21
22
22
23
23
24
24
25
25
26
26
27
1/5/10
Slave Gearbox
(No of units)
18
19
19
20
20
21
21
22
22
23
23
24
24
25
25
Page 45 of 97
PART FOUR
Section 2
1/5/10
Page 46 of 97
Assembly Methods
6.
Continue
installation
Part Four - Section 1.
as
described
in
2.
3.
4.
5.
1/5/10
Page 47 of 97
PART FOUR
Section 3
Assembly of
Double Skin Tank Sheets
1/5/10
Page 48 of 97
Assembly Methods
2.
3.
4.
5.
6.
7.
8.
Assembly rig
VIEW OF ASSEMBLED INNER AND OUTER DOUBLE SKIN SHEETS ON ASSEMBLY RIG
1/5/10
Page 49 of 97
9.
Assembly Methods
1/5/10
Page 50 of 97
PART FIVE
Section 1
1/5/10
Page 51 of 97
ANNULAR TANKS
Annular tank systems are generally used for
continuous process applications. They provide a costeffective solution where floor space is at a premium.
The basic concept is two circular tanks of equal
height, one inside the other.
1.
2.
3.
1/5/10
Page 52 of 97
PART FIVE
Section 2
1/5/10
Page 53 of 97
BACKFILLED TANKS
Backfilled tanks are designed to be constructed either
wholly or partially below ground level.
IMPORTANT NOTICE:
All work must be
undertaken by competent building crews familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work, to
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1.
2.
3.
4.
5.
6.
7.
1/5/10
8.
RECEPTION PITS
Important Notice
All work must be undertaken by competent
building crews familiar with the relevant
regulations with particular regard to Health and
Safety. Furthermore, it is the responsibility of the
building crew undertaking these works to consider
each particular installation, its environment and
the specific risks therein prior to commencement
of work, to determine the protective equipment
required by personnel and to plan the safe system
of work that should be adopted in order for the
task to be carried out safely.
1.
2.
2.
Page 54 of 97
2.
3.
4.
5.
7.
8.
9.
1/5/10
Page 55 of 97
1/5/10
Page 56 of 97
PART SIX
Section 1
Roof Construction
1/5/10
Page 57 of 97
Roof Construction
INTRODUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
As a general rule all roofs should be constructed at
ground level.
Dependent upon the type of roof being installed, site
and
environmental
conditions
and
other
project-specific factors, roofs can be constructed at
varying stages of the installation process.
In some extreme cases alternative methods of roof
construction may affect the roof design.
It is therefore extremely important to evaluate this
subject at the earliest opportunity and plan
accordingly.
The construction methods described within this
section may not apply to all installations.
For advice on alternative methods of construction
please contact Permastore.
1/5/10
Page 58 of 97
PART SIX
Section 2
1/5/10
Page 59 of 97
Roof Construction
7.
8.
9.
1.
2.
3.
4.
5.
6.
1/5/10
Page 60 of 97
PART SIX
Section 3
1/5/10
Page 61 of 97
Roof Construction
2.
3.
5.
6.
Fit the centre roof cap onto the roof cap centre
support column.
7.
8.
9.
10. Do not tighten the panels to the roof cap until the
whole assembly is complete.
4.
1/5/10
Page 62 of 97
Roof Construction
SPECIAL NOTES
1.
1/5/10
Page 63 of 97
PART SIX
Section 4
1/5/10
Page 64 of 97
Roof Construction
2.
3.
4.
6.
7.
8.
9.
1/5/10
Page 65 of 97
PART SIX
Section 5
1/5/10
Page 66 of 97
Roof Construction
3.
4.
5.
6.
7.
8.
9.
1/5/10
Page 67 of 97
Roof Construction
1/5/10
Page 68 of 97
PART SIX
Section 6
1/5/10
Page 69 of 97
Roof Construction
2.
3.
4.
5.
6.
7.
8.
1/5/10
Page 70 of 97
PART SIX
Section 7
Pressure Testing of
Roofs
1/5/10
Page 71 of 97
Roof Construction
2.
6.
7.
8.
9.
a)
Electric blower
required.
pressure
b)
c)
d)
e)
f)
Knapsack sprayer.
capable
of
3.
4.
5.
CAUTION:
WHEN
FILLING
AND/OR
DRAINING A TANK IN PREPARATION FOR
OR FOLLOWING ROOF PRESSURE TESTING
IT IS IMPORTANT TO ENSURE THAT ROOF
INSPECTION HATCHES, VENTS, APERTURES
ETC ARE LEFT OPEN TO PREVENT AN
OVER-PRESSURE OR VACUUM SITUATION
OCCURING WHICH MAY RESULT IN
PERMANENT DAMAGE TO THE TANK
STRUCTURE.
1/5/10
Page 72 of 97
PART SEVEN
Section 1
Construction of
Glass-Fused-to-Steel Floors
1/5/10
Page 73 of 97
GLASS-FUSED-TO-STEEL FLOOR
CONSTRUCTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
FLOOR LAYOUT
14. Lay subsequent panels in sequential order as
specified on construction drawing.
15. Fit tapered inserts at the sheet overlap areas
between the floor sheets and the base angles.
16. Fit full rows of sheets before tightening bolts
using the standard torque settings to assist with
alignment.
17. Fillet all sheet edges.
1/5/10
Page 74 of 97
FLOOR PLATE
1/5/10
Page 75 of 97
PART EIGHT
Section 1
1/5/10
Page 76 of 97
Cone Construction
IMPORTANT NOTICE:
All work must be
undertaken by competent building crews familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore it is the
responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work, to
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
Introduction
1.
2.
3.
4.
5.
6.
7.
1/5/10
1.
2.
Check all relevant drawings and assemble hipjoint leaving out section at jack positions and
ensure that correct length bolts are used, do not
fit those where stiffener ring is to be connected.
Leave bolt finger tight.
3.
4.
5.
6.
7.
Page 77 of 97
Cone Construction
1.
2.
1/5/10
3.
4.
5.
6.
Page 78 of 97
Cone Construction
2.
3.
1/5/10
Page 79 of 97
PART NINE
Section 1
1/5/10
Page 80 of 97
Ancillary Products
1/5/10
Page 81 of 97
Ancillary Products
FLANGE CONNECTORS
1.
2.
2.
3.
3.
4.
1.
4.
1/5/10
Page 82 of 97
Ancillary Products
1.
1.
2.
3.
4.
5.
1/5/10
2.
3.
4.
5.
6.
7.
8.
Page 83 of 97
Ancillary Products
2.
3.
4.
5.
6.
fitted
to
7.
8.
1/5/10
Page 84 of 97
Ancillary Products
1/5/10
Page 85 of 97
Ancillary Products
5 RING TANK
4 RING TANK
1/5/10
3 RING TANK
Page 86 of 97
Ancillary Products
CIRCUMFERENTIAL LAUNDERS
1.
2.
5.
6.
7.
8.
9.
1/5/10
Page 87 of 97
Ancillary Products
2.
3.
4.
5.
2.
3.
4.
5.
6.
7.
8.
BAFFLE WALL
1.
1/5/10
Page 88 of 97
Ancillary Products
2.
3.
4.
5.
6.
7.
8.
1/5/10
SACRIFICIAL
ANODE
PROTECTION SYSTEM
CATHODIC
1.
2.
Page 89 of 97
PART TEN
Section 1
1/5/10
Page 90 of 97
Checklist
a)
b)
a)
c)
d)
b)
e)
2.
3.
4.
Have all ancillaries attached to Glass-Fused-toSteel coated sheets been fully coated with sealant
on contact surfaces before being bolted?
5.
6.
7.
8.
9.
1/5/10
Page 91 of 97
PART TEN
Section 2
1/5/10
Page 92 of 97
Testing on Site
1/5/10
Page 93 of 97
PART ELEVEN
Section 1
Troubleshooting
1/5/10
Page 94 of 97
Troubleshooting
inside of the structure) and cover the bolt
head area of the sheet liberally with sealant.
TROUBLESHOOTING
Introduction
This section has been compiled to assist the
construction team to resolve minor assembly issues
and undertake replacement or modification work.
One of the features of a Glass-Fused-to-Steel bolted
construction tank is the ability to modify the structure
on site to accommodate new or changed process
conditions. It is also possible to extend some
structures in height using either a top or bottom
extension but in all cases reference should be made to
Permastore to ensure suitability of proposed change.
2.
c)
d)
b)
c)
d)
e)
LEAKAGE REPAIRS
f)
g)
3.
b)
c)
d)
b)
1/5/10
Page 95 of 97
Troubleshooting
THE
1.
WARNING: Do not use disc grinders or flamecutting equipment to cut holes in Glass-Fused-to-Steel
sheets. Always use electric drill and jig-saw.
2.
CUTTING OPENINGS
1.
2.
3.
2.
PERMASTORE
REPAIR
INSTRUCTIONS FOR USE
KIT
1.
2.
Surface Preparation
Steel should be clean and free from any loose
Glass-Fused-to-Steel coating, oil, grease or rust.
Abrade the surface and surrounding 25mm (1
inch) of sound Glass-Fused-to-Steel with
medium grit emery cloth.
1/5/10
Page 96 of 97
Troubleshooting
5.
Properties
Mix ratio
Working life
Drying time
Touch
Hard
Over coating
Min
Max
Application temp Min
Max
Handling Precautions
6.
Data Sheets
Material Safety and data sheets for all sealants,
primers and cleaners used to build Permastore
structures are generally provided with the project
documentation but are also available on request.
Whilst every care has been taken to ensure accuracy throughout this guide Permastore shall have no
liability for any loss or damage, (direct or indirect or consequential) arising out of or in connection
with this guide.
This guide is subject to supplementation or change at any time without notice at Permastore's sole
discretion.
Copyright 2009 Permastore Limited
1/5/10
Page 97 of 97
APPENDIX A
1/5/10
Page A1
APPENDIX A
12
10
13
11
1/5/10
Page A2
APPENDIX A
14
17
15
18
16
1/5/10
Page A3
APPENDIX A
19
20
21
Doc Ref: P132 Rev 9
1/5/10
Page A4