a) 18* C to 24* C
c) 14* C to 24* C
b) 15* C to 18* C
d) 18* C to 28* C
11.This is used in soil stabilized road surface due to its high____
property, that is, it absorb and retain water.
a) Potassium Chloride
c) Magnesium Chloride
b) Calcium Chloride
d) Sodium Chloride
12.The mass % wear of soil aggregate used in cement/lime
proportions should not be more than____
a) 40 %
c) 45 %
b) 50 %
d) 55 %
13.The uniform rate at which the movable head of the CBR machine
travel
is_____ .
a) 0.05 in / min
c) 0.08 in /min
b) 0.10 in /min
d) 0.09 in /min
14.Cast in place concrete shall not be post tensioned until at
least____
and until the compressive strength has reached the strength
specified.
a) 7 days
c) 14 days
b) 10 days
d) 20 days
15.The penetration test is an indication of the____ of asphalt.
a) Consistency
c) Hardness
b) Softness
d) Flash Point
16.Specification requires one (1) Quality test for every____ of
asphalt
a) 20 tons
c) 50 tons
b) 200 tons
d) 40 tons
17.The____ is the most commonly used method in the design and
evaluation of bituminous concrete mixes.
a) Job mix formula
c) Marshall Stability
b) Design mix
d) Extraction
18.Vibration shall operate a frequency of 8,300 to 9,600 impulses per
minute under load at a maximum spacing of____ cm.
a) 30 cm
c) 60 cm
b) 50 cm
d) 40 cm
19.The specific gravity of Sodium Sulfate used in soundness test for
aggregate should be with in the range of____.
a) 1.151 to 1.174
c) 1.051 to 1.154
b) 1.250 to 1.178
d) 1.058 to 1.184
20.The specific gravity magnesium sulfate solution used in
soundness test for aggregate should be within the range of____ .
a) 1.280 to 1.408
c) 1.295 to 1.308
b) 1.180 to 1.308
d) 1.195 to 1.318
21.Aggregate accounts for 92 95 % of the weight of the bituminous
mixture asphalt accounts for 5 8 % of the weight of the mix. The
exact percentage to be used is determined by the_____
a) Trial mix
c) Job mix
b) Design mix
d) Job order
22._____ is an indication that the asphalt mix is overheated.
a) Blue smoke
c) Rising steam
b) Stiff appearance
d) Mix slumps in truck
23.In checking the temperature of the mix, the thermometer
should be inserted into the mix at least____.
a) 2 inches
c) 4 inches
b) 6 inches
d) 6.0 mm
24._____ is applied on existing bit, or cement concrete surface with
bituminous materials.
a) Bituminous Prime Coat
c) Bituminous Seal Coat
b) Bituminous Tack Coat
d) Bituminous Surface Treatment
25.The solution used in the soundness test of aggregate shall be
cooled to a temperature of 21 +or 1* C and maintain at that
temperature for at least
_____.
a) 24 hours
c) 48 hours
b) 36 hours
d) 18 hours
26.Proper compaction of the fill materials is very important, as it
will______.
a) Increase the shear strength
b) Decrease permeability
c) Minimize compressibility
d) All of the above
27.In which DPWH item is emulsified asphalt not suitable?
a) Item 301
c) Item 304
b) Item302
d) Item 308
28.Unconfined compressive strength test is usually performed on
______.
a) Sandy soils
c)Organic soils
b) Silty soils
d) Clayey soils
29.Consolidation test is usually performed on____ samples
a) Disturbed
c) Consolidated
b) Undisturbed
d) both a & b
30.A concrete core sample having a maximum height of less than
_____ of its diameter before capping or height less than its diameter
after capping shall not be tested.
a) 93 %
c) 95 %
b) 94 %
d) 96 %
31.The cohesion and internal friction of soil is tested by
a) Tri axial shear test
c) Bearing test
b) Direct shear test
d) All of the above
32.In concrete acceptance, core will be considered adequate if the
average
strength of the cores is equal to what?
a) 80% of specified strength & if no single core is less than 75% of
specified
strength
b) 90% of specified strength & if no single core is less
than 80% of specified strength
c) 85% of specified strength
& if no single core is less than 75% of specified strength
33.Before the cement is to be used, sampling must be done at least
_____ before use.
a) one week
c) two weeks
b) 14 days
d) 12 days
110. 110.Mass percent loose for fine aggregates when tested in Clay
lumps
is_____.
a) 0.10
c) 0.80
b) 0.25
d) 1.0
111. _________ is a type of cement which shall be transferred to an
elevated, air tight and weather proof bins storage.
a) Portland Cement
c) Bulk Cement
b) Pozzolan Cemenr
d) None of the above
112. Scales for weighing aggregates and cement shall be accurate
within_____.
a) 0.1%
c) 0.5%
b) 0.25%
d) 1.9%
113. The minimum thickness of conventional concrete as the surface
course in monolithic pavement is_____.
a) 50 mm
c) 100 mm
b) 75 mm
d) 150 mm
114._____________ determines the resistance of the emulsion to break
when mixed with mineral aggregate.
a) Viscosity Test
c) Spot test
b) Distillation Test
d) Cement Mixing
115._____________ is an instrument used for rapid in site
measurement of the structural properties of existing road pavement.
a) Pundit Ultra Sonic Concrete Tester
b) Dynamic Core Penetrometer
c) Falling Weight Deflectometer
d) Core Test
116. How many days does the emulsified asphalt must be tested
after
delivery at temperature 40*F(4.5*C).
a) 10 days
c) 14 days
b) 12 days
d) 16 days
117. In bituminous mixture asphalt content is 5 8% and 92 - 95%
aggregates, what will be the amount of additives?
a) not more than 2%
c) more than 2%
b) not more than 3%
d) more than 4%
118.___________ determines the effect of water on the cohesion of the
mixture
a) Stability Test
c) Distillation
b) Solubility
d) Immersion-Comprssion Test
119.The distance of the sample by grooving before rotating the brass
cup is
_____.
a)
c)
b)
d) 1
120. The most common method of assessing strength and stiffness
of both
subgrade and pavement is_______.
a) FDT
c) SPT
b) CBR
d)Non of the above
121. How many days do the specimen for CBR soaked?
a) 1 day
c) 3 days
b) 2 days
d) 4 days
122. When mixed at the site or a in central mixing plant, the mixing
time shall
not be less than _50__ seconds nor more than _90_ seconds unless
mixer
performance test prove adequate mixing of the concrete in a shorter
time
period.
123. The batches shall be so charged into the drum that a portion of
the
mixing water shall enter in advance of the cement and aggregate.
The flow
of water shall be uniform and all water should be in the drum by the
end of the _15_ seconds of the mixing period
128. Each lot shall be divided into _5_ equal segment and one core
will be obtained from each segment in accordance with AASHTO T24.
124. The time elapsed from the time water is added to the mix until
the concrete is deposited at the site shall not exceed _90_ minutes
when concrete is hauled in the truck.
126. Concrete not placed within _90_ minutes from the time the
ingredients were charge into the mixing drum should not be use.
127. The completed pavement shall be accepted on a lot basis. A lot
shall be considered as_50 0 _ linear meter double lane