EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION


DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM,
EN LA PROVINCIA DE HUANUCO
Armenio Flaubert Galindez Ore1, Julia Y. Acua Azarte2
SUMMARY
This research was made at Huanuco province, it was based in the pursuit of six
watering work, they were located in the following small watersheds : a) Cochatambo: Taprag
Canal Improvement, Millpo Canal Improvement and Nocturnal Reservoirs Construction. b)
Mito: Cedron Canal Construction, San Pablo de Mitotambo Canal Construction. c) Acomayo:
Nueva Independencia Reservoir Construction. d) Pusucraga: La Esperanza, the Forest
Nursery, Reservoirs Construction. In this buildings it was register and systematized the
perfomance and units cost by budget approvement. The period of evaluation was since the
instalation until the finichied of work (January 1997 to January 1998).
It got values of perfomance of labor, especifically in the construction of canals and
reservoirs, ecuation of zones with similar climatic condition, topographics and the common
peoples organization, unit costs and budget for each buildings in pursuit. Finally the real
time of ejecution of the six works in research was slowed down in 100% as a consequence
of the expansion of the initial phisical goals we obtain values of profit hand work especifially
in the buildins of canals and reservoirs for the common people contribution and the own
difficulties of transport of materials (Lima Huanuco).
RESUMEN
El presente estudio se desarroll en la provincia de Hunuco, a base del seguimiento de seis obras de riego; ubicadas en las siguientes microcuencas que seguidamente se detallan. En Cochatambo: Mejoramiento Canal Taprag, Mejoramiento Canal Millpo y
Construccin Reservorio Nocturno.En Mito:Construccin Canal Cedrn y Construccin Canal
San Pablo de Mitotambo. En Acomayo:Construccin Reservorio Nueva Independencia. Por
ltimo en Pusucraga: Construccin Reservorio Vivero Forestal La Esperanza. En estas
obras se registr y sistematiz datos de rendimientos y costos unitarios por partida ejecuProfesor Principal de la Facultad de Ingeniera Agrcola, en el Dpto. de Mecanizacin Agrcola

Egresada de la UNALM

284

Anales Cientficos UNALM

tada en cada obra. El, periodo de evaluacin comprendi desde la instalacin hasta la liquidacin de obra (Enero 1997 a Enero 1998).
Se obtuvo valores de rendimientos de mano de obra especficamente en la construccin de canales y reservorios, ecuaciones de estimacin para zonas con similares
condiciones climticas, topogrficas y de organizacin comunal, costos unitarios y presupuestos por cada obra en seguimiento. Finalmente el tiempo real de ejecucin de las seis
obras en estudio se retras el 100%, como consecuencia de la ampliacin de las metas
fsicas iniciales originado por el aporte comunal y las dificultades propias de transporte de
materiales (Lima- Hunuco ).
I. INTRODUCCION
Existen valores estandarizados de rendimientos de mano de obra, emitidos por la
Cmara Peruana de Constructores (CAPECO),
para obras de edificacin urbanas. Rendimientos que han sido obtenidos con cuadrillas totalmente remuneradas. Por carencia de sta
informacin para obras de riego, slo se estiman tomando como base lo especificado por
CAPECO. Sobre la base de esta estimacin,
se formulan los expedientes tcnicos de los
proyectos para obras rurales; ocasionando
desfases en el cumplimiento de la programacin e incompatibilidad entre las valorizaciones presupuestadas y las reales.
Por lo tanto, se realiz la evaluacin
de rendimientos y costos unitarios en la construccin de canales y reservorios; ejecutadas
con apoyo de mano de obra comunal. Estrategia de trabajo que al Ministerio de Agricultura le permite financiar la construccin de
mayor nmero de pequeas obras de riego
en las zonas andinas del Per, con la finalidad de satisfacer la demanda de agua de
agricultores, ganaderos, empresas de saneamiento, etc., siendo las comunidades las
mayores beneficiadas quienes con su aporte
de mano de obra contribuyen en la ejecucin
del proyecto. Empero, la desventaja que presenta esta metodologa es la prolongacin del
plazo de ejecucin, debido a factores sociales, topogrficos y climticos influyendo en

el rendimiento de la mano de obra y por consiguiente en los costos unitarios de cada partida ejecutada.
Por todo lo antes mencionado el objetivo que
se plantea es :
Determinar y evaluar los rendimientos y costos unitarios en la construccin de canales
y reservorios con participacin comunal en
la provincia de Hunuco .
II. REVISION BIBLIOGRAFICA
2.1 LAS CUENCAS HIDROGRFICAS Y
SU MANEJO
La cuenca hidrogrfica, es el rea delimitada por la divisoria de aguas, y
esta comprendida dentro de una formacin topogrfica en la cual las
aguas de escurrimiento concurren a
un mismo cauce.
La cuenca es definida como el espacio geogrfico idneo, que sirve de
base para la planificacin de actividades, constituye el marco prctico
y objetivo para el desarrollo y crecimiento econmico con equidad y
sustentabilidad ambiental.
La disponibilidad de agua a nivel
mundial viene disminuyendo por di-

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

versos motivos como : la deforestacin de las cuencas, el uso irracional de sus recursos naturales y
la contaminacin creciente de los
cursos del agua, factores que nos
estn llevando a una dramtica situacin en la que la demanda de
agua es mayor que la oferta, hacindo es necesario optimizar el
manejo del recurso hidrulico ejecutando un conjunto de acciones
para el uso y control del agua en
todas sus formas y manifestaciones con el fin de incrementar su
oferta.
ROCHA (1993) menciona que los proyectos de aprovechamiento y control
de los recursos hidrulicos contribuyen al desarrollo social, econmico
y calidad de vida. Consta de 3 elementos: el agua, el hombre y la naturaleza. Todo proyecto de aprovechamiento hidrulico buscar cubrir la
demanda hdrica de los cultivos y disminuir la errtica distribucin temporal y espacial.
Las comunidades campesinas son
las ms vinculadas al agro y estn
localizadas en la Sierra Sur y Sierra
Central entre los 2000 a 4000 m.s.n.m.,
en las regiones Quechua y Suni y
pocas se encuentran en la Sierra Norte y son mnimas en la regin costa
y selva del Per.
La Ley de la Reforma Agraria y el
Estatuto Especial de Comunidades
Campesinas define a las comunidades campesinas, como una agrupacin de familias que poseen y se
identifican con un determinado territorio y estn ligados por rasgos sociales y culturales comunes, por el
trabajo comunal y ayuda mutua.

285

2.2 RENDIMIENTO DE MANO DE OBRA


El rendimiento de la mano de obra
se define como la cantidad de trabajo desarrollado por persona o cuadrilla en una unidad de tiempo(da u
hora).
Por Resolucin Ministerial 175 del 9/
04/1968 rigen normas para la aplicacin de los rendimientos mnimos oficiales de la mano de obra en la Industria de la Construccin Civil, en
el Ramo de Edificacin para las provincias de Lima y Callao, ms no
para obras de riego ejecutadas en zonas urbanas y rural; estimndose a
base de ello las correspondientes
para obras de riego ejecutadas con
aporte comunal.
COTRINA (1995) menciona que lo
ms indicado para la consistencia de
rendimientos en mano de obra es el
promedio aritmtico o el promedio
geomtrico y utiliza el aritmtico por
ser el ms exacto.
2.3 ANALISIS DE COSTOS
En el anlisis de costos se deber
tener en cuenta los siguientes aspectos:
Partidas.- Se entiende por Partida a
la estructura de gastos para fines de
medicin, evaluacin y pago.
Costos.- son los valores econmicos
de recursos reales o financiados utilizados para producir un bien, producto o servicio. Esta conformada por recursos de capital, esfuerzo de trabajo y tiempo. La forma comn de clasificar es por el objeto de gasto en
costos directos e costos indirectos;

286

Anales Cientficos UNALM

y de acuerdo a la variacin de la cantidad producida en costos fijos y costos variables.


Costo unitario.- Es el costo que corresponde a una sola unidad de medida de un determinado bien, producto o servicio. El anlisis de costos
unitarios se evala por unidades de
medicin establecidas (m3, m2, kg,
m) que contienen las cantidades va
lorizadas e insumos de materiales
que necesita dicha unidad.
2.3.1 COSTOS DIRECTOS
El costo directo (CD) comprende los
gastos incurridos directamente en la
construccin de las obras; como materiales, mano de obra, equipos y herramientas necesarios para construccin de una obra. Los precios unitarios y coeficientes de aporte de cada
elemento se obtuvieron como sigue:
1.

Materiales.- Son bienes de consumo utilizados, que pueden


cuantificarse en unidades de comercializacin. Ejemplo: bolsas
(bls) de cemento, metro cbico
(m3) de arena, pie cuadrado (p2)
de madera o kilogramo (kg) de
acero. Los precios de adquisicin deben ser actualizados
para el anlisis de costos en funcin al tiempo de ejecucin, condiciones topogrficas; a stos
deben adicionarse el costo de
transporte. El coeficiente de
aporte es la cantidad de materiales que intervienen en la produccin de una partida de acuerdo a condiciones preestablecidas fsicas o geomtricas.
Para fines de evaluacin de la
presente se obtuvo de tablas

ajustadas con el 3% de desper


dicios.
2.

Mano de Obra .- Es la fuerza


de trabajo utilizada en la ejecucin de las obras, cuyo coeficiente de aporte se estima a
base del rendimiento diario, jornada de 8 horas da (h/d) .Se
calcula para cada categora del
personal. Ejemplo:
Coeficiente pen = No de peones x No de horas de trabajo/
rendimiento diario

3.

Herramientas y Equipo-Maquinaria.- El costo por herramientas, se determina por un coeficiente de uso, determinado
de acuerdo a la experiencia. En
el caso de equipos-maquinarias
su costo se determina en funcin del rendimiento de cada unidad. El coeficiente esta en funcin a la incidencia de utilizacin de herramientas. Generalmente se designa el 5% del costo total de la mano de obra de
una partida especfica. Para el
caso de equipos-maquinaria se
recopilo de la publicacin mensual del Grupo S-10 (Costos,
mayo1998) .

2.3.2 COSTOS INDIRECTOS


Los costos indirectos estn conformadas por la suma de todos los
gastos que no intervienen de manera intrnseca en el avance de una obra;
pero que son necesarios y aplicables
en su construccin; estos gastos
son aquellos que deben incurrirse
para el apoyo y administracin durante la construccin. Los costos indirectos estn constituidos por:

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

A.

B.

Gastos generales no relacionados con el tiempo de ejecucin


de obra. Este, corresponde a los
gastos requeridos en el proceso de contratacin e instalacin.
Gastos generales relacionados
con el tiempo de ejecucin de
la obra, son gastos que representan el mayor porcentaje de
los gastos generales y esta
comprendido por Sueldos del residente, Gastos de traslado del
personal: maestro de obra, Botiqun (accidentes del personal
tcnico), Papelera y tiles de
escritorio, Gastos en pasajes y
viticos para viajes del personal
administrativo, etc.

Aspectos Concernientes a los Proyectos de Riego en Estudio


En las cuatro microcuencas seleccionadas se ubican las 11 comunidades en estudio, donde se ejecutaron 10 obras; de las cuales se seleccionaron slo seis obras a base de
los criterios de accesibilidad, altura
sobre el nivel del mar y la distancia
de la ciudad de Hunuco a la obra.
Las caractersticas de cada uno de
ellos fueron:
1.

MATERIALES
Los materiales utilizados para realizar el presente estudio fueron los siguientes:
Teodolito, Mira, Altmetro, Wincha,
Cronmetro, Escalmetro, Carta E:1/
100000 de la Provincia de Hunuco,
Expedientes Tcnicos, Liquidaciones de Obra y Cuadernos de Obra.

3.2 METODOLOGIA
Area de estudio
El presente estudio, se desarroll
en el mbito de trabajo del PRONAMACHCS-Hunuco, ubicadas en
las microcuencas: Cochatambo,
Acomayo, Mito y Pusucraga. Ubicndose en ellas 6 obras de riego:
5 ejecutadas con mano de obra
calificada ms aporte comunal y
1 (uno) sin aporte comunal.

Proyecto Costruccin Canal


Cedrn (P1)
Se ubica en las coordenadas de
Latitud 9524 y Altitud de 3,276
m.s.n.m.; comunidad de Raccha Cedrn-Microcuenca Mito,
al margen derecho del ro Mito.
Beneficia a 25 familias con la
captacin de 6 lts./seg. de la
quebrada Raccha e incorpora 12
hectreas bajo riego. La accesibilidad a la obra es relativamente tediosa por la presencia de
una topgrafa abrupta entre
45% a 55 % de pendiente. La
distancia de la ciudad de Hunuco a la obra es de 35 Km. Y
las metas fsicas a alcanzar fueron: construccin de una bocatoma de concreto ciclpeo con
fc = 140 Kg/cm2 + 30%PG, 1.0
Km. De canal y obras de arte
de concreto simple, en un plazo de ejecucin de 3 meses.

III. MATERIALES Y METODOS


3.1

287

2.

Proyecto Construccin Canal


San Pablo de Mitotambo (P2)
Se ubica en las coordenadas
geogrficas de Latitud de 9 7
31, Longitud 76 25 18 y Alti-

288

Anales Cientficos UNALM

tud de 3200 m.s.n.m.; perteneciente a la comunidad San Pablo de Mitotambo-Microcuenca


Mito, al margen izquierdo del ro
Mito. Beneficia a 50 familias con
la captacin de 30 Lts/seg. de
la quebrada Uncumarca y Huancamarca. Incorpora 60 Has. bajo
riego; la accesibilidad a la obra
es moderadamente dificultosa,
limitada por una topografa cuya
pendiente est entre los 35% a
45%. Las distancia a la ciudad
de Hunuco es de 29 Km. Las
metas fsicas a ejecutarse fueron: Construccin de bocatoma
en concreto ciclpeo fc = 140
Kg./cm2 + 30% P.G., 1.7 Km.
de canal y obras de arte en concreto simple, en un plazo de ejecucin de 3 meses.
3.

Proyecto Mejoramiento Canal Millpo y Construccin


Reservorio Nocturno (P3)
Se ubica en las coordenadas
geogrficas de Latitud 9 14 15,
Longitud 762 35, Alitud 3150
m.s.n.m.; perteneciente a la co
munidad San Rafael de Millpo.
Microcuenca Cochatambo. Beneficia a 60 familias, con la captacin de 6 lts/seg. de la quebrada Tinhuinllin e incorpora 30
Has bajo riego. La accesibilidad
a la obra es limitada por la topografa abrupta de 45% a 55% de
pendiente. La distancia a la ciudad de Hunuco es 35 Km. Las
metas fsicas a ejecutarse fueron: La construccin de una bocatoma de concreto armado fc
= 175 Kg/cm2, reservorio de 250
m3 de capacidad, apoyado en
tierra, 1.5 Km de canal y obras

4.

de arte de concreto simple, con


un plazo de ejecucin de 3 me
ses.
Proyecto Mejoramiento Canal Taprag (P4)
Se ubica en las coordenadas
geogrficas de Latitud 9 14 46,
Longitud 76230 y Altitud 2800
m.s.n.m.; perteneciente a la comunidad de Nuevo Progreso de
Taprag- Microcuenca Cochatambo. Beneficia a 80 familias,
con la captacin de 30 lts/seg.
de la quebrada Cochatambo e
incorpora 60 Has bajo riego. La
accesibilidad a la obra es moderada pues la topografa es
de 30% a 40% de pendiente.
La distancia a la ciudad de
Hunuco es 33 Km. Las metas
fsicas a ejecutarse fueron: La
construccin de una bocatoma
de concreto ciclpeo fc = 175
Kg/cm2 + 30 %PG., 1.6 Km. de
canal y obras de arte de concreto simple, con un plazo de
ejecucin de 3 meses.

5. Proyecto Construccin
Reservorio Nueva Independencia (P5)
Se ubica en las coordenadas geogrficas de Latitud 9 13 54, Longitud 7649 y Altitud 2400 m.s.n.m.;
perteneciente a la comunidad de
Nueva Independencia- Microcuenca
Acomayo. Beneficia a 35 familias,
con la captacin de 6 lts/seg. de la
quebrada Micharragra e incorpora
40 Has bajo riego. La accesibilidad
a la obra es moderada pues la topografa es de 30% a 40% de pendiente. La distancia a la ciudad de
Hunuco es 30 Km. Las metas fsi-

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

cas a ejecutarse fueron: La construccin de un reservorio de 640 m3


de capacidad, impermeabilizado
con GV1 y obras de arte de concreto simple, con un plazo de ejecucin de 2.5 meses.
6. Proyecto Construccin Reservorio Vivero Forestal La Esperanza (P6)
Se ubica en las coordenadas geogrficas de Latitud 9 6 6, Longitud 761258 y Altitud 1940
m.s.n.m.; perteneciente a la comunidad La Esperanza - Microcuenca
Pusucragra. Beneficia a 12 familias,
con la captacin de 6 lts/seg. de la
quebrada Pusucragra e incorpora 12
Has bajo riego. La accesibilidad a
la obra es suave pues la topografa
es de 10% a 20% de pendiente. La
distancia a la ciudad de Hunuco
es 5 Km. Las metas fsicas a ejecutarse fueron: La construccin de
un reservorio de 90 m3 de capacidad, en concreto armado, fc = 175
Kg/cm2 y obras de arte de concreto
simple, con un plazo de ejecucin
de 1.5 meses.
Aspectos Concernientes al Levantamiento de Informacin
El registro de informacin se realiz a base de los siguientes criterios:
1. Clasificacin de la informacin de
ubicacin geogrfica de las seis
obras segn el grado de accesibilidad, altitud y costo de transporte.
2. Elaboracin y distribucin de
formatos para la recopilacin de rendimientos y costos unitarios a los

289

respectivos residentes y operarios


de cada obra.
3. Las mediciones de avance de obra
por partida, se efectuaron a base del
reglamento de metrados para obras,
el tiempo efectivo en la ejecucin y
el nmero de participantes de la
comunidad por partida ejecutada. La
toma de datos fue diaria en los proyectos P2 y P5; semanalmente en
los proyectos P1, P3, P4, P6 Las caractersticas de las obras se detalla en el Anexo N 01.
Procedimiento de Evaluacin
a) Evaluacin de Rendimientos de
Mano de Obra
Para determinar los rendimientos de
mano de obra se analiz los datos
de avances y tiempos de ejecucin
por partidas consolidndose con el
anlisis de tendencia central, como
son los promedios de las tres medias: aritmtica, gemtrica y armnica. Los factores de accesibilidad
fortaleza fsica y organizacin comunal, no intervinieron en el anlisis, por ser variables cualitativas y
hasta cierto punto subjetivas. Los
rendimientos se han evaluado para
1h, 5.5 h y 8 h (ver Anexo 1.3), remunerndose a la cuadrilla conformada por capataz (cap), operario
(op), oficial (of) y pen (pn). Para
evitar confusiones, el aporte comunal se identific como faenero. La
valorizacin de los jornales tanto, del
capataz, oficial y pen, se hizo en
funcin al grado de participacin de
estos en las diferentes actividades.
La evaluacin se efectu entre los
valores de rendimientos presupues-

290

Anales Cientficos UNALM

tados, a base de una estimacin de


los rendimientos mnimos para
obras de edificacin; y los ejecutados en el campo. Se agrup en partidas de primer orden, determinndose por unidad de cuadrilla, para
su anlisis.

maquinaria, se recopil de las tablas CAPECO y se reajust con el


3% por desperdicios y desgaste.
Los presupuestos reales por obra,
se obtuvo a base de los costos unitarios evaluados, el metrado de liquidacin; adicionndose los gastos generales (6% C.D.). El tiempo
de ejecucin se esquematiz con
el diagrama de Gantt y la ruta crtica con el mtodo PERT-CPM.

La variabilidad de este resultado con


respecto a los datos de las observaciones, se calcul con la frmula
de Desviacin Estndar.
La estimacin de rendimientos consider la influencia sobre ste, a
cuatro variables cuantificables:
Tiempo Efectivo, cantidad de participantes comunales, temperatura
promedio diaria y precipitacin diaria. Siendo afianzada por un anlisis de regresin mltiple. Los datos de precipitacin, temperatura
mxima y mnima diarios, fueron
obtenidos de la Estacin Meteorolgica Cayhuayna y San Rafael,
ubicados a una altitud de 1950 y
2950 m.s.n.m. en las provincias de
Hunuco y Ambo respectivamente.
b) Evaluacin de Costos Unitarios
La determinacin de los costos unitarios, comprendi cotizaciones de
materiales, herramientas, equipo y
maquinaria de tres empresas ubicadas en la ciudad de Hunuco,
estimndose el precio promedio de
cada artculo. Los costos de mano
de obra fueron los valores remitidos
por la Direccin Tcnica de Infraestructura Rural (DTIR), donde consideraba que la hora hombre (hh) capataz, operario, oficial es de S/.
4.62, S/. 4.22, S/.3.83 respectivamente. El coeficiente de aporte para
materiales, herramientas, equipos y

IV.
4.1

RESULTADOS Y DISCUSION
RENDIMIENTOS DE MANO DE OBRA
En el Cuadro No 1 se muestra los
rendimientos de mano de obra, habindose obtenido un resultado ptimo para P3 con 200 m2/d/h y el
menor rendimiento de 175 m2/d/ h
para P4. Para reservorios se realiz
manualmente, observndose que los
resultados estuvieron en funcin de
las dimensiones de la capacidad de
almacenamiento.
En el Cuadro No 2 se presenta los
rendimientos por acarreo de materiales: hormign, piedras, cemento
y tubos. Considerndose los
parme-tros de fuente de extraccin,
distancia de acarreo y modalidad de
traslado.
En el Cuadro No 3. La excavacin
de plataforma(remocin de ladera de
1.3m de ancho por 1m de altura) y
zanjas (secciones cuadradas). El
mayor rendimiento fue desarrollado
por P4 en material suelto, normal
seco y roca suelta, justificndose que
a mayor compactacin de los suelos, los rendimientos de mano de

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

obra disminuyen. En el caso de relleno con material propio en canales,


P 4 obtuvo 4.14 m3/d/h y para
reservorio (P 6 ), fue de 1.42 m3/d/h,
observndose una diferencia del
34.30%.

291

termin 3.64 m3/d/h y para (P3), se


consigui 2.59 m3/d/h, diferencindose en 28.85%; ya que al P1 se les
remuner en mano de obra en esta
actividad. Y en la excavacin a maquinaria (cargador frontal WA 320) P6
obtuvo 147.6 m3/d/h en material suelto y para el P5 se lleg a 70.97 m3/
d/h en material de rocas suelta.

En el Cuadro N 4 que corresponde


a la excavacin manual (P1), se de-

CUADRO No 1. RENDIMIENTOS EN TRAZO, NIVELES Y REPLANTEO. CANALES


Rend. Presupuestado
Proyectos

Cuadrilla
Ca

op

Top

Rend. Ejecutado

Rendimiento

Cuadrilla

Rendimiento

pn

m2/d

m2/d/h

cap

op

Top

fae

m2/d

m2/d/h

p
C. Cedrn (P1)

400

80.00

1600

200.00

C. Mitotambo (P2)

500

83.33

1350

192.86

C. Millpo (P3)

400

80.00

1200

200.00

C. Taprag (P4)

400

80.00

1400

175.00

323

40.38

RESERVORIOS
R. Cedrn (P1)

No presupuestado

R. Millpo (P3)

390

55.71

R. Independencia(P5)

No presupuestado
1

400

80.00

285

40.71

R. La Esperanza (P6)

100

33.33

2*

408

102.0

CUADRO No 2. RENDIMIENTOS EN ACARREO MATERIALES


Rend. Ejecutado
Proyectos

Cuadrilla

Hormign
m 3/d

m 3/d/h

Piedra
M 3/d

Cemento

m 3/d/h

Cap

Fae

C. Cedrn (P 1). A 0.3km

0.1

1*

1.40

1.27

C. Mitotam. (P 2). A 0.3km

0.1

2.20

2.00

1.05

0.95

C. Taprag (P 4) . A 0.3km

0.1

0.95

0.86

0.92

0.84

C. Millpo (P 3). A 0.3 km

0.1

0.82

C. Millpo (P 3) . A 0.5km

0.1

0.88

0.80

R. Indepen. (P 5). A 0.05km

0.1

2.30

2.09

C. Cedrn (P 1) . A 1km

0.1

1*

1.0

0.91

C. Mitotambo (P 2). A 1.5km

0.1

2*

bls/d

Tubos

bls/d/h

u/d

u/d

3.64

2.73

12

10.9

0.75

3.64

2.73

11

10.0

1.50

1.36

4.55

5.45

8.2

12

5.71

Con esfuerzo humano

Con esfuerzo animal

*pen, a excepcin del acarreo de tubos en P 1 que se realiz con faenero.

292

Anales Cientficos UNALM

CUADRO No
ENEN
MOVIMIENTO
DE DE
TIERRA.
PLATAFORMA
- ZANJAS
CUADRO
N 3.
3.RENDIMIENTOS
RENDIMIENTOS
MOVIMIENTO
TIERRA.
PLATAFORMA-ZANJAS
Rend. Presupuestado
Proyectos

Cuadrilla
3

Rend. Ejecutado
Mat. Suelto

Normal seco

Roca suelta
3

Cap

pn

m /d

m /d/h

m /d

M /d/h

m /d

m /d/h

m /d

m3/d/h

C. Cedrn (P1)

0.1

3.5

3.18

2.65

2.41

2.35

2.14

1.85

1.68

C. Millpo (P3)

0.1

3.5

3.18

2.80

2.55

2.20

2.00

2.00

1.82

C. Taprag (P4)

0.1

3.5

3.18

3.20

2.91

2.55

2.32

2.35

2.14

C. Cedrn (P1)

0.1

3.5

3.18

3.20

2.91

3.00

2.73

2.10

1.91

C. Mitotambo (P2)

0.1

3.5

3.18

3.40

3.09

2.75

2.50

2.30

2.09

C. Millpo (P3)

0.1

3.5

3.18

3.00

2.73

3.12

2.84

2.30

2.09

C. Taprag (P4)

0.1

3.5

3.18

3.80

3.18

3.30

3.00

2.45

2.23

EX.DE PLATAFORMA

EX. DE ZANJAS

En el Cuadro No 5 se muestran los


resultados de los rendimientos de
mano de obra en encofrado y
desencofrado (E-D) de reservorio para
el P5, donde se obtuvo 7.74, 6.45,
5.00 m2/d/h para alturas de trabajo
de 1.2, 2.4 y 3.6 m respectivamente.
Para E-D de obras de arte a doble
muro, en el P3 se obtuvo 6.09 m2/d/
h por la experiencia del operario en
tareas similares y para E-D en canales a un solo muro, para P4 se obtuvo 4.06 m2/d/h; y a doble muro en
P1 se obtuvo 2.4 m2/d/h siendo estos los ms ptimos.
En el Cuadro No 6 se observa los
rendimientos en concreto simple
(C.S.), destacando coincidentemente P1 y P6. Habindose obtenido 0.85m3/d/h en concreto fc =
140 Kg./cm2. En mampostera de
piedra asentada en concreto fc =
140Kg./m2, P3 obtuvo 3.77 m2/d/h
como el ms ptimo. Cabe sealar, que en las mezclas de C.C. fc=
140 Kg/cm2 + 30%PG y C.C.

fc=175Kg/m2 + 30% PG se obtuvo


en P1 0.61 m3/d/h y en P4 se obtuvo 0.57 m3/d/h respectivamente
como los ms ptimos.
En el Cuadro No 7 se detallan los
resultados en acero 3/8, y 5/8
el rendimiento ptimo fue realizado
por P6, logrndose 72.58 Kg/d/h y
56.45 Kg/d/h para los dos primeros
dimetros, mientras en P5 alcanz
para el ltimo nivel de dimetro 34.63
Kg/d/h slo con mano de obra remunerada.
En el Cuadro No 8 los rendimientos
obtenidos en P5 fue de 4.02 m2/d/h
en mortero c/a 1:4 y P3logr 3.51 m2/
d/h utilizando mortero paja-arena ar
cillosa (p/a , 1:10).
En el Cuadro No 9 la instalacin de
Tubera PVC C-5 en el P3 se obtuvo
36 m/d/h como rendimiento ptimo en
a instalacin de tuberas de 4 de dimetro. Debido a la flexibilidad del material que habilit su acople en curvas.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

293

CUADRO No 4. RENDIMIENTOS EN EXCAVACION DE RESERVORIO Y RELLENO


CON MATERIAL PROPIO
Rend. Presupuestado
Proyectos

Cuadrilla

Rend. Ejecutado

Rend.
3

Cuadrilla
3

Rend.
3

Cap

Op

of

Pn

M /d

M /d/h

cap

op

of

fae

m /d

M3/d/h

0.1

3.5

3.18

0.1

310

147.6

EXCAV. RESERVORIO
R Esperanza Suelto Maq. (P6)
R. Cedron. Manual (P1)

No presupuestado

0.1

1*

4.00

3.64

R. Millpo. Manual (P3)

No presupuestado

0.1

2.85

2.59

R. Independencia. Maq. (P5)

0.1

3.5

3.18

0.1

220

70.97

3.2

5.0

1.42

0.1

4.20

3.82

RELLENO CON MATERIAL PROPIO


C. Cedrn (P1)

0.32

C. Millpo (P3)

0.32

3.2

5.0

1.42

0.1

4.50

4.09

C. Taprag (P4)

0.32

3.2

5.0

1.42

0.1

4.55

4.14

3.5

0.64

0.1

2*

4.40

1.42

R. La Esperanza (P6)

CU AD RO No 5. RENDIM IENTOS E N E NCOFRADO Y DES E NCOFR ADO (E -D)


Rend. Presupuestado
P ro yectos

Cuadrilla
cap

op

of

Rend. Ejecutado

Rend.
pn

m 2/d

m 2 /d/h

Cuadrilla
cap

op

of

Rend.
fae

m 2 /d

m 2/d/h

M UROS DE RESE RVO RIO-BO CATOM A


C. Cedrn (P 1 ). Bocat.

12

3.00

0.1

3.6

21.8

3.82

C. Mitotam bo (P 2 ). Bocat.

12

3.00

0.1

4.2

18.9

3.00

C. Millpo (P 3 ). Bocat.

12

3.00

0.1

3.5

22.8

4.07

C. Taprag (P 4 ). Bocat.

12

3.00

0.1

3.0

25.0

4.90

12

4.00

0.1

1*

18.0

4.39

R. Indepen (P 5 ) . Reser.

0.1

12

5.71

0.1

24.0

7.74

A 2.4m

0.1

12

5.71

0.1

20.0

6.45

A 3.6m

0.1

12

5.71

0.1

15.5

5.00

C. Cedrn (P 1 )

0.1

0.7

0.7

5.23

0.1

2.0

16.8

4.10

C. Mitotam bo (P 2 )

0.1

1.0

1.0

12

2.35

0.1

3.0

22.5

4.41

C. Millpo (P 3 )

0.1

0.7

0.7

5.23

0.1

2.0

25.0

6.09

C. Taprag (P 4 )

0.1

0.7

0.7

5.23

0.1

2.5

21.5

4.67

R. Independencia (P 5 )

0.1

0.7

0.7

5.23

0.1

4.0

15.5

2.54

C. Mitotam bo (P 2 ) a 2m uro

0.1

0.7

0.7

5.23

0.1

3.0

15.0

2.94

C. Taprag (P 4 ) a 2 m uro

0.1

0.7

0.7

5.23

0.1

2.5

12.0

2.61

C. Cedrn (P 1 ) a 1 m uro

0.1

0.7

0.7

5.23

0.1

2.0

13.5

3.29

R. Esperanza (P 6 ) . Reser.

OBRAS DE ARTE

CAN ALE S

C. Mitotam bo (P 2 ) a 1m uro

0.1

1.0

1.0

12

2.35

0.1

3.0

20.4

4.00

C. Taprag (P 4 ) a 1 m uro

0.1

0.7

0.7

5.23

0.1

3.2

21.5

4.06

294

Anales Cientficos UNALM

CUADRO No 06. RENDIMIENTOS EN CONCRETO


Rend. Presupuestado
Proyectos

Cuadrilla

Rend. Ejecutado

Rend.
3

Cuadrilla

Rend.
3

cap

op

Of

pn

m /d

m /d/h

cap

op

of

fae

m /d

m /d/h

C. Millpo (P3). Bocat.

0.1

1.6

6.0

0.78

0.2

2.95

0.48

R. La Esperanza (P6). Res.

0.1

1.0

6.0

0.59

0.2

3*

4.45

0.72

0.2

5.2

0.51

0.1

35

8.25

0.22

A 2.4m

0.1

30

7.50

0.23

A 3.6m

0.1

23

6.85

0.26

CONCRETO ARMADO
C.A. fc=175 kg/cm2

C.C. fc=175kg/cm + 30%PG


R. Independencia (P5). Res.

CONCRETO SIMPLE
C.C. fc=175kg/cm2 + 30%PG
C. Taprag (P4). B.

0.1

1.6

6.0

0.78

0.1

4.05

0.57

0.1

6.0

0.59

0.1

4.35

0.61

0.1

6.0

0.59

0.1

4.20

0.59

C. Taprag (P4). Canal

0.1

6.0

0.85

0.1

2.5

2.5

0.54

C. Cedrn (P1) . O.A.

0.1

6.0

0.85

0.1

2.0

3.5

0.85

C. Mitotambo (P2). O.A.

0.1

5.0

0.78

0.1

5.0

4.2

0.59

R. Esperanza (P6). O.A.

0.1

4.2

0.69

0.1

3.5

0.85

0.1

4.0

15.50

2.54

0.1

3.5

16.20

2.89

C.C. fc=140kg/cm + 30%PG


C. Cedrn (P1). B.
C. Mitotambo (P2).B.
2

C. S. fc=140 kg/cm

Mamp. de piedra fc=140kg/cm .


C. Cedrn (P1). Canal
C. Mitotambo (P2). Canal

No presupuestado
0.1

20

6.45

C. Taprag (P4). Canal

No presupuestado

0.1

2.2

15.00

3.49

C. Millpo (P3). O.A.

No presupuestado

0.1

2.2

16.20

3.77

Mampostera de piedra fc=140kf/cm evaluado en m /d/h

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

295

CUADRO No 07. RENDIMIENTOS EN ACERO FY=4200 KG/CM


Rend. Presupuestado
Proyectos

Cuadrilla

Rend. Ejecutado
Rend.

Cuadrilla

Rend.

cap

op

of

pn

kg/d

kg/d/h

cap

op

of

fae

kg/d

kg/d/h

0.01

0.04

0.05

25

25

0.1

2.2

195

45.35

C. Millpo (P3)

1.00

1.00

60

15

0.1

2.5

200

43.48

C. Taprag (P4)

0.01

0.04

0.05

25

25

0.1

2.0

206

50.24

1.00

150

50

0.1

225

72.58

R. Independencia (P5)

180

60

0.1

2.0

162

39.51

R. La Esperanza (P6)

150

50

0.1

175

56.45

180

60

0.1

2.0

142

34.63

Acero =3/8
C. Cedrn (P1)

R. La Esperanza (P6)
Acero =1/2

Acero =5/8
R. Independencia (P5)

CUADRO No 08. RENDIMIENTOS EN REVOQUES Y ENLUCIDOS


Rend. Presupuestados
Proyectos

Cuadrilla
cap

op

of

Rend. Ejecutado

Rend.
pn

Cuadrilla

m2/d

cap

Op

of

Rend.
m2/d

fae

m2/d/h

R. Millpo (P3) a/p

No presupuestado

0.1

25.0

3.51

R. Independen. (P5) a/c

No presupuestado

0.1

3*

20.5

4.02

CUADRO No 09. RENDIMIENTOS EN INSTALACIN DE TUBERA PVC C-5


Rend. Presupuestados
Proyectos

Cuadrilla

Rend. Ejecutado

Rend.

Cuadrilla

Rend.

cap

op

Of

pn

m/d

m/d/h

Cap

op

of

fae

m/d

m/d/h

C. Cedrn (P1)

0.2

22

5.24

0.2

3.3

139

25.3

C. Millpo (P3)

0.2

22

5.24

0.2

3.5

205

36.0

C. Taprag (P4)

0.2

22

5.24

0.2

4.0

185

30.0

R. Independencia (P5)

0.2

22

5.24

0.2

3.0

120

23.1

C. Taprag (P4) = 8

0.2

22

5.24

0.2

3.2

142

26.3

Tubera de =4

Tubera de =6

296

Anales Cientficos UNALM

CUADRO No 10. RENDIMIENTOS EN INSTALA. DE GEOMEMBRANA VINIMANTA DE 1MM


Rend. Presupuestados
Proyectos

Cuadrilla
cap

op

Rend. Ejecutado

Rend.

Of

m2/d

pn

Cuadrilla

m2/d/h

Rend.

Cap

op

of

fae

m2/d

m2/d/h

R. Cedrn (P1)

No presupuestado

0.1

10

162

12.37

R. Millpo (P3)

No presupuestado

0.1

15

190

11.11

0.1

25

230

8.48

R. Independencia (P5)

0.1

270

87.01

CUADRO
11. RRENDIMIENTO
C UA D R O NN
o 11.
E ND IM IE NT O E NEN
O BOBRAS
R A S CO NCONEXAS
E XA S
R end. P resupuestado
Proyectos

C uadrilla
cap

Op

C . C edrn (P 1 ).
C . M itotam bo (P 2 ).

of

R end. E jecutado

R end .
Pn

Pza/d

C uadrilla

Pza/d/h

N o presupuestado
0.1

0.32

R end .

cap

op

of

fae

Pza/d

Pza/d/h

0.1

1.0

0.24

0.1

1.0

0.24

R . Independencia (P 5 )

0.1

0.32

0.1

0.5

0.07

R . Esperanza (P 6 )

0.1

0.32

0.1

1.0

0.48

SE L L A D O D E JU N T A S
C . C edrn (P 1 )
C . M itotam bo (P 2 )
C . Taprag (P 4 )

N o presupuestado
1

60

N o presupuestado

En el Cuadro No 10 se muestra la Impermeabilizacin de reservorio, que comprendi actividades de tendido, tensado


y pegado. Los resultados mostrados son
globales; varan segn la seccin a instalar y la cantidad de aporte comunal.
En P1 se logr los rendimientos ptimos
por el eficiente despliegue de su cuadrilla, obtetenindose 12.37 m2/d/h.
En el Cuadro No 11 las obras conexas
se han agrupado en: Preparacin e Instalacin de compuertas metlicas, Instalacin de Vlvulas y Sellado de Juntas. En Instalaciones de Vlvulas Esfricas de PVC de 3 y 4 de dimetro; en
P1 y P3 se obtuvo 1.4 pza/d/h, ejecutado con una cuadrilla de 0.1 cap., 1 op. y
1 fae. Y en P6 se obtuvo 2.86 pza/d/h,
instalado con 0.1cap., 1 op., y 1 pn.
Fue superior este ltimo por que se

15

2.5

65

14.44

4.0

82

13.67

3.0

75

15.00

remuner la partida. En el Sellado de


Juntas, en P4 se logr el mejor rendimiento, obtenindose 15 m/d/h debido a la destreza de la cuadrilla.
4.2 COSTOS UNITARIOS
En el Cuadro N 12 los resultados
indican que el costo econmico por
trazo, niveles y replanteo en canales
variaron de 2.36 a 2.50 soles/m2. Para
reservorios fluctu entre 0.97 y 1.16
soles/m.
En el Cuadro No 13, el costo econmico por acarreo de hormign y
piedra para P1 fue de 30 y 100 Soles/m3 respectivamente, diferencindose en 233.33% por el flete(40Km).
Por acarreo de cemento con transporte animal, en P1 y P2 lleg a 2.0

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

Soles/bolsa para 1Km y 2.3 Soles/


bls, para 1.5 Km. Y para el transpor
te de tubos PVC C-5 de 4 de dimetro, los costo variaron de 1.14 a 1.52
Soles/unid., debido al poco peso del
material y al aporte comunal de 0.8
a 1.10 Soles/unid.

297

En el Cuadro No 14 , se observa los


menores costos por m3 en excavacin de plataforma y zanjas en material suelto, normal y roca suelta fue
de 4.41, 5.53, 6.00 Soles/m3 y de
4.03, 4.27, 5.76 Soles/m3 respectivamente obtenidos en P4.

CUADRO No 12. COSTOS UNITARIOS EN TRAZO, NIVELES Y REPLANTEO


C.U. Aporte estatal
Proyectos

S/ x m

C.U. Evaluado S/. x m


Costo econmico

Val. Fin. sin apo.

Aporte
comunal

CANALES
C. Cedrn (P1)

1.33

2.47

2.44

0.03

C. Mitotambo (P 2 )

1.58

2.48

2.45

0.03

C. Millpo (P 3)

1.33

2.50

2.47

0.03

C. Taprag (P 4)

1.33

2.36

2.34

0.02

RESERVORIO
R. Cedrn (P1)

No presupuestado

1.16

1.06

0.10

R. Millpo (P 3)

No presupuestado

0.97

0.88

0.09

R. Independen. (P 5)

1.05

1.07

0.89

0.18

R. La Esperanza (P 6)

1.45

1.08

1.08

0.00

CUADRO No 13. COSTOS UNITARIOS EN ACARREO DE MATERIALES


C.U. Evaluados
Proyectos

Hormign S/xm

Piedra S/ x m

Costo

Val. Fi.

C/A

econ.

Sin ap.

Com.

Costo

Val.F.S

econ. /Ap.

Cemento S/x bls

Apor.

Tubos 4 S/xunid

Cost Val. F.

C/A

Costo V Fin.

comu. econ s/apor

com

econ s/apor

A/c

A esfuerzo propio
P1 a 1km

30.00

30.00

0.00

1.52

0.41

1.1

P3 a 0.5km

16.03

4.67

11.3

P1 a 0.3km

30.00

1.25

0.34

0.9

30.00

0.00

P2 a 0.3km

6.91

2.37

4.54

13.44

3.91

10.4

3.5

1.01

2.50

P3 a 0.3km

22.80

6.60

16.2

3.4

0.92

2.50

P4 a 0.3km

9.86

2.90

6.96

15.30

4.50

10.8

4.6

1.23

3.4

1.14

0.31

0.8

P5 a 50m

6.13

1.80

6.43

9.40

2.74

6.7

2.7

0.74

1.96

P1 a 1 km

2.3

2.3

0.0

P2 a 1.5 km

2.0

2.0

0.0

A animales

298

Anales Cientficos UNALM

CUADRO No 14. COSTOS UNITARIOS EN MOVIMIEN. DE TIERRA . PLATAFORMA- ZANJAS


C.U. Evaluado S/ x m3

C.U. Ap.
Proyectos

Estatal
3

S/ x m

Mat. suelto

Mat. Normal seco

Mat. Roca suelta

Costo

Val.F.

Con

Costo

Val.F.

Con

Costo

Val.F.

Apor.

Econ.

s/ap.

a/com

Econ.

s/ap.

a/com

Econ.

s/ap.

Comu

EX. DE PLATAFORMA
C. Cedrn (P1)

1.45

5.32

1.55

3.77

6.00

1.75

4.25

7.63

2.22

5.41

C. Millpo (P3)

1.45

5.04

1.47

3.57

6.41

1.87

4.54

7.05

2.05

4.00

C. Taprag (P4)

1.45

4.41

1.28

3.13

5.53

1.61

3.92

6.00

1.75

4.25

C. Cedrn (P1)

1.45

4.41

1.28

3.13

4.7

1.37

3.33

6.72

1.96

4.76

C. Mitota. (P2)

12.3

4.15

1.21

2.94

6.72

1.96

4.76

C. Millpo (P3)

1.45

4.70

1.37

3.33

4.52

1.32

3.20

4.95

1.44

3.51

C. Taprag (P4)

1.45

4.03

1.17

2.86

4.27

1.24

3.03

5.76

1.68

4.08

EX. DE ZANJAS

En el Cuadro No 15 el costo econmico en E-D de reservorio y bocatoma a 1.2m de altura flucta de


17.40 a 21.50 soles/m2 y para alturas
de 2.4 y 3.6m fue de 22.60 a 24.36 soles/m2 respectivamente por el uso de andamio y escalera (P5).
En el Cuadro No 16 se muestran
los costos unitarios en concreto
armado en funcin a la altura de
vaceado y calidad de concreto. En
C.A. fc=175 kg/cm2 vara de 194.70
a 2 1 9 . 5 3 s o l e s / m 3, e n C . C .
fc=175kg/cm 2 + 30% PG solo se
ejecut en P5 observndose la fluctuacin de 214.89, 212.89, 207.49
soles/m 3 a 1.2 m, 2.4 m y 3.6 m
respectivamente.
En el Cuadro No 17 los costos econmicos aumentan al habilitar aceros
de mayores dimetros. Para acero
3/8 el habilitado ejecutado con apor
te comunal flucta de 1.90 a 2.54

soles/kg y con mano de obra calificada fue de 1.89soles/kg (P6); para


acero de y 5/8 se ejecut solo
con mano de obra calificada variando
el primero de 2.36 a 2.38 soles/kg y
el segundo fue de 2.99 soles/kg.
El Cuadro No 18 nos muestra los
costos econmicos para morteros
difieren debido a la obrabilidad del tipo
de mezcla. El mortero c/a tiene como
finalidad impermeabilizar los taludes
del reservorio. En el P 5 se obtuvo
188.84 soles/m2 y en el P3 con mortero paja/ar para fines de proteccin
de la GV1 cost 26.16 soles/m2 .
En el Cuadro No 19 se muestra
los costos econmicos para la instalacin de tubera PVC C-5 para 4 fluc
tan de 10.23 a 14.22 soles/m para la
instalacin de tubera de 6 y 8 de
dimetro cost 16.98 y 21.54 soles/m
respectivamente, estos costos ascendieron por el flete aplicados a es
tos materiales.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

299

CUADRO No 15. COSTOS UNITARIOS EN ENCOFRADO Y DESENCOFRADO


Proyectos

C.U. Aporte

C.U. Evaluados S/ x m
3

Estatal S/ x m

Costo econmico

Val. F. Sin aporte

Aporte comunal

BOCATOMA
C.Cedrn(P1)B.A1.2m

15.50

17.40

15.75

1.65

C.Mitot..(P2)B.A 1.2m

11.42

19.46

10.13

9.33

C.Taprag (P4)B.A1.2m

15.50

12.99

10.62

2.37

C.Millpo(P3).B.A1.2m

15.50

18.43

16.90

1.53

R.Indep.(P5)B.A1.2m

13.66

21.50

21.50

0.00

R.La Esp.(P6)B.A1.2m

27.71

19.83

19.83

0.00

R. Independ(P5)A2.4m

13.66

22.60

22.60

0.00

R. Independ.(P5) A3.6

13.66

24.36

24.36

0.00

C. Cedrn (P1)

15.74

14.21

13.02

1.19

C. Mito (P2)

11.42

13.47

9.47

4.00

OBRAS DE ARTE

C. Millpo (P3)

15.50

13.50

12.70

0.80

C. Taprag (P4)

15.50

14.08

11.50

2.58

R. Independencia (P5)

15.50

17.59

17.59

0.00

C. Mito.(P2)A 2 muros

11.42

14.40

12.40

2.00

C.Cedrn(P1)A 1muro

15.74

11.13

10.05

1.08

C.Taprag(P4)A 1 muro

15.75

11.79

10.3

1.49

CANALES

En el Cuadro No 20 se observa que


slo se program la instalacin con
GV en P5 con un aporte estatal ascendente a 24.76 soles/m2 sin embargo se ejecut con un costo de
51.15 soles/m2; esta diferencia origin el agotamiento de su financiamiento porque el transporte de ma
teriales en temporadas lluvias encareci los costos . Caso contrario ocurri en P1 y P3 la temporada seca
favoreci el traslado pero se encare
ci por la lejana de traslado fluctuando
sus costos de 56.64 a 62.39 soles/m2.

P5 fue menor en 312.92 soles con respecto al costo econmico debido a


que las medidas y materiales iniciales se cambiaron al finalizar la obra
ocasionando dficit en el financiamiento; para las restantes obras de
riego el costo econmico vari 285.03
a 410.00 soles/pza .

En el Cuadro No 21 respecto a la
instalacin de compuertas metlicas,
se observa que el aporte estatal para

En el Cuadro No 23 los presupuestados difieren significativamente de


los financiados por la variacin en los

En el Cuadro No 22 el costo econmico de Sellado de Juntas vari de


7.81 a 8.18 soles/m debido a que el
costo de asfalto lquido RC250 fue
transportado de Lima.

300

Anales Cientficos UNALM

rendimientos y el costo de transporte. El aporte comunal representa el


9.11%, 11.56%, 13.32%, 7.83% y
7.18% de sus costos en P1, P2, P3,
P4 y P5 respectivamente. En P6 el
aporte comunal fue nulo. Cabe men-

cionar que para el tendido de tubera


PVC C-5 y reservorios impermeabilizados con GV se ha estimado una
vida de 5 aos, para canales de con
creto simple 10 aos y para reservorio de concreto armado 30 aos.

CUADRONo 16. COSTOS UNITARIOSENCONCRETO


Proyectos

C.U. Aporte

C.U. Evaluado S/ x m

Estatal S/ x m3

Costo econmico

Val. Fin. Sin aporte

Aporte comunal

225.45

219.53

205.97

13.56

170.65

194.70

194.70

0.00

R. Indepen (P5)a 1.2m

156.83

214.87

172.45

42.42

a 2.4m

156.83

212.89

173.15

39.74

a 3.6m

156.83

207.49

173.92

33.57

191.21

165.03

152.69

13.34

130.76

119.27

11.49

131.77

189.52

132.05

67.47

C. Cedrn (P1) O.A.

153.68

147.96

5.72

C. Mitotam. (P2) O.A.

161.02

157.91

146.01

11.90

C. Taprag (P4) O.A.

188.11

178.11

10.00

156.18

156.18

0.00

No presupues.

16.22

13.64

2.58

No presupues.

15.72

13.66

2.06

No presupues.

16.19

14.72

1.47

CONCRETO ARMADOC. A. fc=175 kg/cm


C. Millpo (P3). B.
R. Esperanza (P6)
2

C.C. fc=175kg/cm + 30%PG

CONCRETOSIMPLE fc=175kg/cm + 30%PG


C. Taprag (P4). B.
2

C. C. fc=140kg/cm + 30 %PG
C. Cedron (P1) B.
C. Mitotambo (P2) B.
2

C. S. fc=140 kg/cm

R. Esperanza (P6) O.A.


2

Mampostera de piedra asentada en fc=140kg/cm .


C. Cedrn (P1) Canal

I.

Mito.

(P2)

Canal
C. Taprag (P4) Canal

costos en mampostera de piedra asentada en fc=140kg/cm es por m


2.1LosLoscostos
en mapostera de piedra asentada en Fc= 140kc/cm2 es por m2
2

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO
2

CUADRO No 17. COSTOS UNITARIOS EN ACERO FY=4200 KG/CM


Proyectos

C.U. Aporte

Estatal S/ x kg

C.U. Evaluados S/ x kg

Costo econmico

Val. Fin. Sin aporte

Aporte comun.

Acero =3/8
C. Cedrn (P1)

2.20

1.90

1.78

0.12

C. Millpo (P3)

2.15

2.54

2.42

0.12

C. Taprag (P4)

2.20

2.51

2.41

0.10

R. Esperanza (P6)

2.24

1.89

1.89

0.00

R. Independencia (P5)

2.39

2.36

2.36

0.00

R. Espera (P6)

2.24

2.38

2.38

0.00

R. Indep. (P5) =5/8

3.20

2.99

2.99

0.00

Acero =1/2

CUADRO No 18. COSTOS UNITARIOS EN REVOQUES Y ENLUCIDOS


Proyectos

C.U. Evaluados m2

C.U. Aporte
Estatal S/ x m2

Costo econmico

Val. Fin .Sin aporte

No presupuesta.

188.84

187.37

1.47

No presupuesta.

26.16

24.16

2.00

Aporte comun.

Mortero c/a
R. Independ. (P5) 1:4
Mortero p/ar
R. Millpo (P3) 1:10

CUADRO No 19. COSTOS UNITARIOS EN LA INSTALACIN DE TUBERA PVC C-5


Proyectos

C.U. Aporte

C.U. Evaluados S/. M

Estatal S/. X m

Costo econmico

Val. Fin. s/aporte

Aporte comun.

C Cedrn (P1)

15.11

14.22

14.00

0.22

C. Millpo (P3)

11.84

10.78

10.00

0.78

10.23

10.06

0.17

26.72

16.98

16.73

0.25

21.54

21.31

0.23

Tubera de =4

C. Taprag (P4)
Tubera de =6
R. Indepen. (P5)
Tubera de =8
C. Taprag (P4)

301

302

Anales Cientficos UNALM

CUADRO No 20. COSTOS UNITARIOS EN IMPERMEABILIZACIN DE RESERVORIO


Proyectos

C.U. Evaluados S/ x m2

C.U. Aporte
2

R. Cedrn (P1)
R. Millpo (P3)
R. Independencia (P5)

Estatal S/ x m

Costo econmico

Val. Fin. s/aporte

Aporte comunal

56.64

50.46

6.18

62.36

50.52

11.84

24.76

51.15

50.07

1.08

CUADRO No 21. COSTOS UNITARIOS EN INSTALACIN DE COMPUERTAS METLICA


Proyectos

C.U. Aporte

C.U. Evaluado S/. x unid

Estatal S/. m2

Costo econmico

Val. Fin. s/aporte

Aporte comunal

410.00

370.60

39.40

C. Mitotambo (P2)

314.01

285.03

265.03

20.00

R. Independencia (P5)

555.68

868.60

508.68

359.92

R. La Esperanza (P6)

650.00

390.00

390.00

0.00

C. Cedrn (P1)

CUADRO No 22. COSTOS UNITARIOS EN SELLADO DE JUNTAS


Proyectos
C. Cedrn (P1)
C. Mitotambo (P2)
C. Taprag (P4)

C.U. Aporte

C.U. Evaluados S/ x m

Estatal S/. x m

Costo econmico

Val. Fin. s/aporte

Aporte comunal

7.81

7.43

0.38

3.94

8.18

7.69

0.49

7.83

7.43

0.40

CUADRO No 23. PRESUPUESTOS PROGRAMADOS Y EVALUADOS


Presupuestos
Proyecto

Programados

Presupuestos Evaluados
Costo econmico

V. Fin. Sin aporte

Aporte comunal

C. Cedron (P1)

33646.50

46614.94

42366.03

4248.91

C. Mitotambo (P2)

52690.83

54278.69

48001.78

6276.91

C. Millpo (P3)

33650.00

39365.24

34118.14

5247.10

C. Taprag (P4)

45951.00

50228.24

46295.32

3932.92

C. Independencia (P5)

33498.57

36508.18

33887.22

2620.96

C. La esperanza (P6)

16855.96

17305.96

17305.96

0.00

P1, P2, P3 proyectos de zona alta


P4, P5, P6 proyectos de zona media

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

303

V. CONCLUSIONES
1.

Los rendimientos de mano de obra y cuadrillas ptimas fueron:


a) En Zonas Altas
Partida

Rend

Unid

cap

top

op

of

fae

Trazo, niveles y replanteo preliminares

1600

m 2/d

1.0

4.0

Acarreo de tubos PVC C-5 f=4 a 1km

11

unid/d

0.1

1.0

Excav. De reservorio en material roca suelta

2.85

m 3/d

0.1

1.0

Instalacin de tubera PVC C-5 f=4

205

m/d

0.2

3.0

Rend

unid

cap

top

op

of

Fae

3.2

m /d

0.1

1.0

15

m /d

0.1

2.2

Instalacin de tubera de =8

142

m/d

0.2

3.2

Sellado de juntas

75

m/d

1.0

3.0

b) En Zonas Medias
Partida
Excavacin de zanjas en material suelto
Mampos. de piedra asentada en fc=140kg/cm

2. Los rendimientos de mano de obra de cuadrillas con aporte comunal obtenidos


en para zona alta y media se diferenciaron entre 10% a 18%. Y a su vez son inferiores en 26.69% a los rendimientos de obtenidos con cuadrillas totalmente
remuneradas.
3. No hay diferencias significativas en cuanto a la evaluacin de los costos unitarios
para obras construidas en zona alta y media debido a que se desarrollaron a 33km y 31.5km
respecto de la ciudad (excepto P6 , a 5km de la ciudad).
4. El costo por metro lineal en la construccin de canal segn altitud cost:
a) En Zona Alta
Mampostera de piedra asentada en fc=140kg/cm2
Tendido de tubera PVC C-5 de f=4

S/.

U.S. $

20.03
12.61

7.47
4.71

27.34
23.30
22.40

10.20
8.69
8.37

b) En Zona Media
Concreto Simple fc=140kg/cm2
Tendido de tubera PVC C-5 de f=8
Tendido de 2 tubos en paralelo de f=4

304

Anales Cientficos UNALM

El costo por ml de tendido de tubera en zona alta son inferiores en 37.04% respecto al de
mampostera de piedra asentado en fc=140kg/cm2 . En zona media fue la instalacin de
tubera en paralelo aventajando al de C.S. en 17.92 %.5. El costo por metro cubico de construccin de reservorio fue de:
a) Para zona alta

S/.

U.S. ($)

Con geomembrana vinimanta de 1mm de espesor (GV1)

83.49

31.15

81.94

30.57

202.50

75.56

b) Para zona media


Con geomembrana vinimanta de 1mm de espesor(GV1)
En Concreto Armado fc=175kg/cm

La construccin con GV1 en zona alta y media se diferencian en 2% justificando su costo


para ambas altitudes en comparacin con la habilitacin con concreto armado.
VI. RECOMENDACIONES

Para la recopilacin de datos deber incluirse la capacitacin de los miembros del


Comit de Obra, que son comuneros encargados de la administracin del
financiamiento de cada proyecto, ya que
estos ayudaran a obtener la mayor cantidad de informacin conllevando a obtener
resultados con niveles de confianza mucho mayores.
Seguir promoviendo la participacin de la
comunidad desde la gestacin del proyecto hasta su termino, buscando la participacin voluntaria a travs de su aporte de
mano de obra, ya que con ello podrn comprender que las acciones en ejecucin son
necesarias y que estas se traducirn en
beneficios tangibles de su comunidad.
Realizar la evaluacin de rendimientos y
costos unitarios en la construccin de
canales y reservorios con mano de obra
comunal en zonas ubicada en la sierra sur
y sierra norte del pas con el fin de estimar
rendimientos y costos en dichas zonas.
Incrementar los gastos generales de los
proyectos a ejecutar bajo esta modalidad,
en 1.7%, ya que este rubro es suscepti-

ble a agotarse por la prolongacin del plazo de ejecucin.


VII. BIBLIOGRAFIA
1.

CAMARA PERUANA DE LA CONSTRUCCION (1990) Reglamento de metrados para obras de edificacin. Lima,
Fondo editorial CAPECO. Octava edicin.

2.

COTRINA MATOS TITO W. (1995) Relacin de costos entre edificaciones convencionales y no convencionales de
Hunuco y Ambo. Tesis UNIV. NAC.
HEMILIO VALDIZAN.

3.

GRUPO PERMANENTE DE ESTUDIO


SOBRE RIEGO (1993) Gestin del agua
y crisis institucional. Quinta edicin.

4.

MONTALVO TORRES, JUAN (1993).


Determinacin de costos por Ml de construccin y revestimiento de canales de
riego. PRONAMACHCS.

5.

RAMOS SALAZAR, JESUS (1998) Costos y presupuestos en edificacin. Lima,


Editorial Gesco S.R.L. Sptima edicin.

6.

ROCHA FELICES, ARTURO (1993) Re


cursos hidrulicos. Libro 16. Lima. Edicin Captulo de Ingeniera Civil. Primera
edicin.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

305

VIII ANEXO
ANEXO No 1.

EVALUACION DE RENDIMIENTOS DE MANO DE OBRA

ANEXO No 1.1

APORTE COMUNAL (JORNALES ACUMULADOS) DURANTE LA


CONSTRUCCIN DE LAS OBRAS DE RIEGO
ANEXO No 1.1.1 PROYECTO CONSTRUCCIN CANAL CEDRN

Mes
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Total

Julio
97
9*
12
13
15
12
15
18
22
30
12
9
10
14
8
6
205

Agosto
97
4
4
5
8
9
2
4
8
4
1
5
4
1
3
1
2
1
3
3
82

Setiembre
97
8
10
8
6
6
7
10
10
6
8
10
8
10
8
7
7
8
7
8
8
5
4
169

Octubre
97
3
5
4
3
3
3
3
4
7
5
4
3
2
2
4
5
3
4
4
5
4
4
5
91

Noviembre
97
5
5
6
5
5
5
4
5
12
6
4
4
4
3
4
4
15
10
106

Diciembre
97
2
3
4
2
4
2
3
2
4*

24

Total
Diario
12
25
32
32
18
22
28
35
30
45
55
27
20
33
26
26
28
15
18
17
5
13
13
17
14
16
7
18
9
8
11
675

306

Anales Cientficos UNALM

ANEXO No
No 1.1.2
1.1.2 PROYECTO
PROYECTO CONSTRUCCIN
S.P.
MITOTAMBO
ANEXO
CONSTRUCCINCANAL
CANAL
S.P.
MITOTAMBO
Mes

Enero

Febrero

Marzo

Abril

Mayo

Junio

Total

97

97

97

97

97

97

Diario

11

14

18

35

5*

32

15

10

17

10

11

13

12

13

14

15

15

16

10

17

17

11

22

18

10

12

13

34

19
20

16

21

18

28

22

16

14

33

23

10

23

24

19

25

20

10

41

26

15

27

10

27

28

29

6*

16

30

14

31

Total

87

93

93

92

66

71

503

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

ANEXO No 1.1.3 PROYECTO MEJORAMIENTO CANAL MILLPO


Y CONSTRUCCIN RESERVORIO NOCTURNO
Mes

Julio

Agosto

Setiembre

Octubre

Noviembre

Diciembre

Total

97

97

97

97

97

97

Diario

5*

29

10

31

12

10

15

49

12

42

10

10

35

10

10

15

48

18

12

42

12

18

18

58

11

17

36

10

15

37

11

13

17

35

12

13

29

13

15

22

14

15

14

16

17

11

18

10

19

15

20

10

12

29

21

11

10

28

22

14

17

15

50

23

12

15

39

24

16

17

10

4*

55

25

13

10

17

11

26

16

33

27

18

15

49

28

15

10

15

56

29

14

18

40

30

10

12

12

37

31

10

10

Total

221

153

205

214

142

51

69

1004

307

308

Anales Cientficos UNALM

ANEXO No 1.1.4 PROYECTO MEJORAMIENTO CANAL TAPRAG


Mes

Agosto

Setiembre

Octubre

Noviembre

Diciembre

Enero

Total

97

97

97

97

97

98

Diario

12

12

26

12

23

10

15

28

18

29

8*

19

42

18

20

50

23

20

37

25

10

45

22

33

10
11

25

37

12

16

23

13

20

11

42

14

11

29

15

22

16

16

17

12

15

18

19

17

20

21

22

11

35

22

24

18

52

23

25

16

51

24

18

33

25

4*

14

26

15

27

16

28

15

29

13

18

47

30

10

22

40

31

Total

115

315

166

141

86

47

672

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

309

ANEXO No
No1.1.5
1.1.5PROYECTO
PROYECTO CONSTRUCCION
CONSTRUCCIN RESERVORIO
ANEXO
RESERVORIONUEVA
NUEVAINDEPENDENCIA
INDEPENDENCIA
Mes

Enero

Febrero

Marzo

Abril

Mayo

Octubre

Total

97

97

97

97

97

97

Diario

8*

22

35

39

10

11

10

12

13

10

12

14

20

25

15

18

26

16

17

23

23

18

19

20

21

5*

22

23

13

24

12

25

10

26

12

16

27

28

10

18

29

10

15

30

31

TOTAL

20

53

78

15

* Fecha de inicio y finalizacin de las obras

111

268

310

Anales Cientficos UNALM

ANEXO No 2.2 ECUACIONES DE ESTIMACION DE RENDIMIENTOS DE M.O.


ANEXO N 2.2 ECUACIONES DE ESTIMACION DE RENDIMIENTOS DE M.O.
ANEXO N
No2.2.1
2.2.1 PROYECTO
PROYECTO CONSTRUCCIN
CANAL
CEDRON
ANEXO
CONSTRUCCION
CANAL
CEDRON
PARTIDA

Intercepto

Tiempo

Mano de

s/u

(T)

O. (MO)

( C)

. (P)

a1

a2

a3

a4

Temperatura Precipita
o

TRABAJOS PRELIMINARES
- Acarreo de Hormign a 1km

47.731

-0.26

3.09

1.428

- Acarreo de Cemento a 1km

-20.86

-6.94

-0.59

1.44

0.18

-444.32

23.61

20.61

2.187

- Material Normal Seco

24.34

2.50

-0.001

-1.28

- Material Roca Suelta

99.44

-36.03

3.296

3.228

-28.736

2.57

-0.965

2.18

2.198

5.33

2.23

-0.06

0.04

-30.47

-16.02

6.18

4.25

-72.13

4.69

0.419

2.94

0.10

E-D. Bocatoma

11.82

0.798

-1.344

-0.18

26.84

E-D. Obras de artes

-25.56

86.40

88.19

E-D. Canal a 1 muro

-8.87

2.12

1.899

0.08

0.46

1.562

-0.13

-0.0004

0.269

MOVIMIENTO DE TIERRA
Excavaciones de Plataforma
- Material Suelto

Excavaciones de Zanjas
- Material Suelto
- Material Normal Seco
- Material Roca Suelta
Excavacin de Reservorio
- Material Roca Suelta
ENCOFRADO-DESENCOFRADO
-37.80 1090.33

CONCRETO
2

C. C. fc=175kg/cm + 30% PG. Bocatoma


2

C. S. fc=140kg/cm .

-0.427

0.39

-0.28

-0.28

-0.06

Mamp. de piedra en fc=140kg/cm . Canal

32.71

-1.09

-0.87

-0.85

Instalacin de Tubera PVC C-5 4

79.78

1.62

2.18

0.08

-19.93

153.09

16.86

-9.13

4.05

IMPERME. DE RESERVORIO
- Tendido, tensado y pegado de mantas

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

311

ANEXO No 2.2.2 PROYECTO CONSTRUCCIN CANAL S.P. DE MITOTAMBO


PARTIDA

Intercepto Tiempo

M. de

Temperatura Precipitao

s/u

(T)

obra

( C)

cin

a1

(MO)

a3

(P)

a2

a4

TRABAJOS PRELIMINARES
Trazo, niveles y replanteo de canal

233.04

-55.61

382.019

-36.906

-579.07

- Acarreo de Hormign a 300m

-7.62

0.95

-0.107

0.39

0.99

- Acarreo de Piedras a 300m

0.679

0.148

-0.145

0.038

- Material Suelto

11.55

2.819

3.427

-1.45

- Material Normal Seco

-32.51

-2.56

3.85

1.74

2.15

E-D. Canal a 2 muros

1.066

1.92

-0.145

-0.04

E-D. Canal a 1 muro

7.13

0.957

0.157

-0.10

0.657

-0.235

0.002

0.08

0.268

-0.586

0.317

0.309

-0.02

-109.03

9.16

-2.077

7.4

MOVIMIENTO DE TIERRA. Zanjas

ENCOFRADO-DESENCOFRADO

CONCRETO
C. C. fc=140kg/cm + 30%PG.
C. S. fc=140kg/cm .
OBRAS CONVEXAS
Sellado de Juntas seccin de 1x2

312

Anales Cientficos UNALM

ANEXO No
No 2.2.3
MEJORAMIENTO
CANAL
MILLPO
Y CONSTRUCCIN
ANEXO
2.2.3PROYECTO
PROYECTO
MEJORAMIENTO
CANAL
MILLPO
Y CONSTRUCCION
RESERVORIO NOCTURNO
RESERVORIO NOCTURNO

PARTIDA

Intercepto

Tiempo

M. de

Temperatura

s/u

(T)

obra (MO)

( C)

a1

a2

a3

Precipitacin
(P)
a4

TRABAJOS PRELIMINARES
Trazo, niveles y replanteo de canal

-.279E18

323.7

3.98E17

-104.9

1.59E18

Acarreo de Materiales
- Acarreo de Hormign a 500m

0.18

0.37

-0.04

-0.066

- Acarreo de Piedras a 300m

0.329

-0.33

0.0125

-0.03

0.07

- Acarreo de cemento a 300m

-1.68

1.74

-3.62E-15

0.076

0.08

7260.82

-86.36

-243.99

-313.36

125.847

-2.28

-2.17

-4.14

16.56

3.41

0.038

-0.76

-74.159

10.61

0.079

3.25

- Material Suelto

-31.60

0.92

-1.27

3.19

- Material Normal Seco

-11.07

1.23

1.365

0.38

1.41

-1.85

0.98

0.298

0.442

7.27

0.63

-0.4007

0.5495

0.238

-12.746

11.866

-2.87

-0.148

-38.89

-39.24

-1.05

1.727

2.68

- Acarreo de Tubos 4 PVC C-5


MOVIMIENTO DE TIERRA
Excavaciones de Plataforma
- Material Suelto
- Material Normal Seco
- Material Roca Suelta
Excavaciones de Zanjas

- Material Roca Suelta


Excavacin de Reservorio
- Material Roca Suelta
Relleno
- Relleno con material propio
ENCOFRADO-DESENCOFRADO
E-D. Bocatoma
CONCRETO
2

C. A. fc=175kg/cm .

-4.35

0.77

-0.49

0.315

-2.112

Mamp. de piedra en fc=140kg/cm .

-0.61

0.07

0.009

0.09

Instalacin de Tubera PVC C-5 4

-2851.92

81.38

-34.83

155.96

-34.83

150.06

32.05

-18.52

-8.33

REVOQUE Y ENLUCIDO

-286.86

4.56

7.057

14.038

2262.73

-108.79

-80.39

Acero 3/8 fy=4200kg/cm

IMPERME. DE RESERVORIO
- Tendido, tensado y pegado de la manta

-9.50

-78.73

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

313

ANEXO
CANALTAPRAG
TAPRAG
ANEXON
No2.2.4
2.2.4PROYECTO
PROYECTOMEJORAMIENTO
MEJORAMIENTO CANAL
PARTIDA

Intercepto

Tiempo

M. de

Temperatura
o

Precipita

s/u

(T)

obra

( C)

cin (P)

a1

(MO)

a3

a4

a2
TRABAJOS PRELIMINARES
Trazo, Niveles y replanteo. Canal

41067.4

-25581

12768

3316.4

-108.34

18.98

-0.12

0.729

192.05

- Acarreo de Cemento a 300m

18.72

0.41

-1.137

-0.547

- Acarreo de Tubos 8 PVC C-5

32.12

12.82

-7.05

-0.745

-3.29

- Acarreo de Tubos 4 PVC C-5

43.12

2.466

-1.27

-1.45

-0.108

7.40

-4.83

0.209

1.69

- Material Normal Seco

-6.79

2.42

1.008

0.185

- Material Roca Suelta

1.19

9.40E-14

-1.042

1.04

- Material Suelto

-74.08

1.48

-1.52

4.25

- Material Normal Seco

65.385

-0.548

-1.066

-1.95

- Material Roca Suelta

17.80

1.33

0.147

-0.46

-1.23

40.20

0.19

1.04

1.93

0.21

-1.89

1.74

1.46

0.148

Acarreo de Materiales
- Acarreo de Piedras a 300m

MOVIMIENTO DE TIERRA
Excavaciones de Plataforma
- Material Suelto

Excavaciones de Zanjas

Relleno
- Relleno con material propio
ENCOFRADO-DESENCOFRADO
E-D. Bocatoma
E-D. Obras de artes.

25.73

-1.24

-2.67

-0.22

-0.15

E-D. Canal a 2 muros

-31.55

7.175

0.1875

0.70

0.1875

-1.56

-0.13

-0.0004

0.269

-3.03

0.066

0.106

0.195

-69.78

3.491

-6.54

3.52

0.263

Instalacin de Tubera PVC C-5 4

116.68

-2.542

-7.646

2.68

-15.49

Instalacin de Tubera PVC C-5 8

47.11

21.59

14.35

-5.64

20.67

2007

6.66

1.50

-91.66

CONCRETO
2

C.C. fc=175kg/cm +30%PG. Bocatoma


2

C. S. fc=140kg/cm . Cajas
2

Mam. de piedra en fc=140kg/cm .


TUBERIA

Acero 3/8 fy=4200kg/cm

314

Anales Cientficos UNALM

ANEXO No 2.2.5 PROYECTO CONSTRUCCIN RESERVORIO NUEVA INDEPENDENCIA


PARTIDA

Intercepto
b

Tiempo

M. de

Temperatura Precipita-

(T)

obra

( C)

cin (P)

a1

(MO)

a3

a4

a2
TRABAJOS PRELIMINARES
Acarreo de Materiales
- Acarreo de Hormign a 50m

8.07

3.58

-2.0427

-0.47

0.702

- Acarreo de Piedras a 50m

7.55

0.47

-0.34

-0.33

0.17

- Acarreo de Cemento a 50m

-3.05

2.17

-0.969

0.459

-0.55

-403.35

49.186

13.13

13.517

0.482

E-D. Reservorio a 1.2m

97.22

-5.457

-4.83

-1.2449

-0.188

E-D. Reservorio a 2.4m

31.91

6.547

-2.52

-0.806

5.86

1.75

-0.22

-0.104

29.23

6.476

0.586

11.115

334.06

14.88

-14.44

80.77

-0.37

4.6

MOVIMIENTO DE TIERRA
Excavacin de Reservorio
- Material Roca Suelta
ENCOFRADO-DESENCOFRADO

E-D. Reservorio a 3.6m


2

Acero 58 fy=4200kg/cm

Acero 1/2 fy=4200kg/cm

IMPERME. DE RESERVORIO
- Tendido, tensado y pegado de mantas

-2.16

15.135

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

315

ANEXO No 2.2.6 PROYECTO CONSTRUCCIN RESERVORIO VIVERO FORESTAL


LA ESPERANZA
PARTIDA

Intercepto
B

Tiempo

M. de

Temperatura Precipita-

(T)

obra

( C)

cin (P)

a1

(MO)

a3

a4

a2
TRABAJOS PRELIMINARES
Eliminacin de roca

-0.037

0.53

0.53

-0.117

-5.122

0.12

0.369

-891.79

0.8

50

0.40

0.43

-0.007

0.45

3.59

-0.237

0.046

-860.4

329.07

-3.169

7.591

7.30

22.36

0.73

-110.63

MOVIMIENTO DE TIERRA
Relleno
- Relleno con material propio
ENCOFRADO-DESENCOFRADO
E-D. Muros de reservorio
E-D. Obras de artes.
CONCRETO
2

C. C. fc=175kg/cm

C. S. fc=140kg/cm

Acero 1/2 fy=4200kg/cm


Acero 3/8 fy=4200kg/cm

* Rend. = b + a1 T + a2 MO + a3 To + a4 P
Coeficientes

: a1 , a2 , a3 ,a4

316

Anales Cientficos UNALM

ANEXO No 3. EVALUACION DE COSTOS UNITARIOS POR PARTIDAS


ANEXO No 3.01 CONSIDERACIONES PARA CALCULAR EL APORTE DE MATERIALES
CLAVOS

DIMENSIN

TIPOS Y/O No (BWG)

CANT/KG

KG/M

14
13
11
10
9
8

1028
582
272
180
128
94

8
16

0.111
0.017

1.552
0.994
0.559
0.248

1
2
2
3
3
4
ALAMBRE (mm)
4.191
1.691
ACERO
5/8

3/8

DE TUBERIA PVC C-5: FABRICADAS SEGN NORMA ISO 4435 SERIE 25.
ISO 4435 SERIE 25
ISO SERIE 20
PESO APROXIMA.
f NOMINAL f EXTERIOR PESO APROXIMA.

ISO 9971 NOVAFORT


PESO APROXIMA.

(Pulg)

(mm)

POR TUBO EN Kg.

POR TUBO EN Kg.

POR TUBO EN KG.

160

13.939

17.229

11.04

200

21.133

26.537

15.96

10

250

32.020

41.704

23.22

TABLA DE PORCENTAJE DE DESPERDICIOS


DESCRIPCIN

% DE DESPERDICIOS

Mezcla de concreto

Mortero

10

Clavos

15

Madera

10

Acero de refuerzo: f = 5/8

f =

f = 3/8

f =

Pintura /esmalte

15

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

317

3
MATERIALES
MATERIALES PARA
PARA m
m3 DE
DE CONCRETO
CONCRETO ARMADO
ARMADO

MEZCLA TIPO

CEMENTO

PIEDRA f
3

ARENA
3

AGUA

PROPORCIN DE

(kg/cm )

(bls)

(m )

(m )

(m )

AGREGADO

140

7.2

1.01

0.52

0.21

1; 2; 4

175

7.7

0.98

0.46

0.19

1; 2; 3

APORTEPOR
POR m
m3 DE
DE CONCRETO
CONCRETO SIMPLE
APORTE
SIMPLE EQUIVALENTE
EQUIVALENTEAAFc=140Kg/cm
Fc=140Kg-cm2
PROPORCIN

a/c

CEMENTO

HORMIGN
3

PIEDRA MEDIANA
3

AGUA
3

(bls)

(m )

(m )

(m )

1:6

0.8

6.20

1.05

0.21

1:7

0.8

5.50

1.09

0.19

1:8

0.8

5.00

1.13

0.17

1:8 + 25% PM

0.8

3.70

0.85

0.40

0.13

1:10 + 30% PM

0.8

2.90

0.83

0.48

0.10

318

Anales Cientficos UNALM

ANEXO No 3.02 COTIZACIONES DE PRECIOS PERIODO ENERO-DICIEMBRE 97


DESCRIPCIN

DISTRIBUIDORAS

Unid

FERROESTRADA

ATACHAGUA

FERROVISION

Jr. Los Jaminez-Hco

Primer Km de Hco.

Av. V.T. 141-Hco

P. Unitario S/.

P. Unitario S/.

P. Unitario S/.

No

Materiales/Herram.

Alambre No 8

kg

2.5

2.5

2.5

Alambre No 16

kg

2.5

2.5

2.5

Clavos 2

kg

2.5

2.5

2.5

Clavos 3

kg

2.5

2.5

2.5

Clavos 4

kg

2.7

2.7

2.7

Clavos 6

kg

2.7

2.7

2.7

Acero liso

kg

2.8

2.8

2.8

Acero 3/8corrugado

varilla

9.0

10.5

8.5

Acero corrugado

varilla

13.5

15.5

14.5

10

Acero 5/8corrugado

varilla

18.0

18.5

18.5

11

Esmalte

gln

35.0

35.0

35.0

12

Pegamento

gln

48.0

48.0

48.0

13

Bolsa de yeso

kg

1.0

0.80

1.00

14

Cemento andino T-1

bls

15.0

15.0

15.0

15

Wincha 30m

unid

35.0

30.0

35.0

16

Manguera

0.70

0.70

0.70

17

Pala cuchara

pza

30.0

30.0

30.0

18

Pala recta

pza

36.0

36.0

36.0

19

Carretilla buggi

pza

130.0

135.0

138.0

20

Barreta 11/2x 1.8m

pza

65.0

68.0

55.0

22

Zapapico

pza

38.0

36.0

32.0

23

Comba 12 lbs.

pza

36.0

28.0

30.0

* Precios sin considerar flete


ANEXO No 3.03 PROCEDIM IENTO PAR A OBTENER COSTOS UNITARIOS
COEFICIENTE DE APORTE

PRECIO UNITARIO
(P.U)

COSTOS PARCIALES

COSTOS TOTALES

(A)

Materiales

(cantidad)

(P.U.)

Cantidad x P.U.

Sum a de (A)

Mano de obra

(H-H)

(J.H.)

H-H x J.H.

Sum a de (A)

Equipo

(H-M)

(CH)

H-H x C.H.

Sum a de (A)

COSTO UNITARIO

= Total de m ateriales + Total mano de obra + Total equipo

J.H. Jornal horario, C.H. Costo horario,


H-H Hora hombre.

i
0
1
2
2
4
3
3
7
5
6
8
9
9
10
11
12
13
13
14
15
15
16
17
18
19
18
20
20
21
22
23
23
25
26

j
1
2
4
3
7
5
5
8
8
8
9
12
10
11
12
13
14
15
15
16
17
17
18
19
20
20
21
22
22
23
24
25
27
29

SUCESO
INICIAL FINAL

Tiempo de autorizacin del financiamiento al proyecto


Reunin entre la comunidad y residente de obra estrategia de trabajo
Limpieza de terreno
Trazo, Niveles y replanteo del eje de canal
Identificacin de cantera de hormign, piedra, madera
Construccin de almacn
Excavacin al 100% de plataforma de canal
Acarreo de hormign y piedra
Transporte de herramientas y equipos a almacn
Excavacin de zanjas de cimiento para la bocatoma
Vaceado de cimiento izquierdo bocatoma
Vaceado de cimiento izquierdo de bocatoma
Encofrado del muro derecho de la bocatoma
Preparacin y vaceado de concreto del muro dere. de la bocatoma
Desencofrado del muro derecho de la bocatoma
Encofrado del muro izquierdo dela bocatoma
Preparacin y vaceado de concreto del muro izqui. de la bocatoma
Desencofrado del muro derecho de la bocatoma
Encofrado del barraje
Preparacin y vaceado de concreto en el barraje
Desencofrado del barraje
Instalacin de rejilla
Excavacin de zanjas para canal abierto y obras de arte
Encofrado del muro del canal
Preparacin y vaceado del muro de canal
Desencofrado del muro del canal
Encofrado de muros de obras de arte (desarenador, rompe presin)
Preparacin y vaceado de muros de obras de arte
Desencofrado del muro de obras de arte
Excavacin de zanjas instalacin de tubera de 4 de dimetro 50%
Nivelacin de camas de tubera 50%
Excavacin de secciones 1x1m para cajas repartidoras
Encofrado del muro de cajas repartidoras
Prueba hidrulica al 50% de la tubera

DESCRIPCION

2.0
1.0
1.0
1.0
1.0
1.0
18.0
1.0
0.5
1.0
0.5
0.5
0.5
0.5
0.3
0.5
0.5
0.3
0.5
0.5
0.2
0.2
0.5
0.5
0.5
0.3
0.5
0.5
0.3
12.0
1.0
0.5
0.5
0.5

0.0
2.0
3.0
3.0
4.0
4.0
4.0
5.0
5.0
22.0
22.5
22.5
23.0
23.5
24.0
24.3
24.8
24.8
25.3
25.8
25.8
26.3
26.6
27.1
27.6
27.1
28.1
28.1
28.6
28.9
40.9
40.4
41.4
47.9

2.0
3.0
4.0
4.0
5.0
5.0
22.0
22.5
22.5
22.5
24.3
24.3
23.5
24.0
24.3
24.8
25.3
25.8
25.8
26.3
26.6
26.6
27.1
27.6
28.1
28.1
28.6
28.9
28.9
40.9
41.9
41.4
41.9
48.4

0.0
2.0
3.0
3.0
20.5
4.0
4.0
21.5
22.0
22.0
22.5
22.5
23.0
23.5
24.0
24.3
24.8
24.8
25.3
25.8
25.8
26.3
26.6
27.1
27.6
27.1
28.1
28.1
28.6
28.9
40.9
40.9
47.1
47.9

2.0
3.0
20.5
4.0
21.5
22.0
22.0
22.5
22.5
22.5
24.3
24.3
23.5
24.0
24.3
24.8
25.3
25.8
25.8
26.3
26.6
26.6
27.1
27.6
28.1
28.1
28.6
28.9
28.9
40.9
41.9
47.1
47.6
48.3

DURACION TIEMPO OPTIMO TIEMPO PESIMISTA


DIAS
T I
T I
T I
T I
0.0
0.0
16.5
0.0
16.5
17.0
0.0
16.5
17.0
0.0
1.3
1.3
0.0
0.0
0.0
0.0
0.0
0.7
0.0
0.0
0.6
0.1
0.0
0.0
0.0
0.7
0.0
0.3
0.0
0.0
0.0
6.2
5.7
0.0

C
C
N.C.
C
N.C
N.C.
C
N.C.
N.C.
C
N.C.
N.C.
C
C
C
C
C
N.C.
C
C
N.C.
N.C.
C
C
C
N.C.
C
N.C.
C
C
C
N.C.
N.C.
C

HOLGURA DE UNA CONDICION


ACTIVIDAD HA ij

ANEXO No 5.02.02 APLICACION DEL PERT - CPM PARA EL PROYECTO MEJORAMIENTO CANAL MILLPO Y CONSTRUCCIONES RESERVORIO NOCTURNO

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES


Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO
319

320

vienen...
SUCESO
INICIAL FINAL
j
28
29
26
30
31
32
34
35
36
33
36
37
38
39
40
40
41
42
43
44
44
45
46
47
48
49
50
50
50
51
52
53
53
54
55

Preparacin y vaceado del muro de cajas repartidoras


Desencofrado del muro de cajas repartidoras
Instalacin de tubera de 4 de dimetro 50%
Excavacin de zanjas para la insta. tubera de 4 de dimetro 50%
Nivelacin de camas de tubera 50%
Excavacin de secciones 1x1m para cajas reparadoras
Encofrado de cajas repartidoras
Preparacin y vaceado del muro de cajas repartidoras
Desencofrado de cajas repartidoras
Instalacin de tubera de 4 de dimetro de 50%
Prueba hidrulica del 50% de tubera tendida
Relleno con material propio de la tubera de 4 de dimetro 50%
Encofrado de cajas colectoras
Preparacin y vaceado del muro de cajas colectoras
Desencofrado de cajas colectoras
Concreto para tapas
Explanacin de reservorio
Trazo y niveles de plataforma del reservorio
Excavacin de seccin trapezoidal del reservorio 100%
Traslado de herramientas al almacn
Nivelacin de fondo y corona de reservorio
Relleno de arena el fondo del reservorio
Excavacin de zanjas en el permetro del 0.40x0.40m
Tendido y tensado de la geomembrana
Prueba hidrulica del 50% de tubera tendida
Anclage perimtrico de la geomembrana
Supervisin del pegado
Cerco perimtrico
Camino de mantenimiento
Encofrado de caja de vlvulas
Concreto de cajas de vlvulas
Desencofrado de cajas de vlvulas
Instalacin de vlvulas
Limpieza total del terreno
Entrega

DURACION
DIAS

0.5
0.3
6.0
12.00
0.50
0.50
0.50
0.50
0.30
6.00
0.50
1.00
0.50
0.50
0.30
0.30
6.00
0.50
18.00
0.50
0.50
0.25
0.25
0.25
0.50
0.25
0.25
1.00
0.75
0.50
0.50
0.30
0.25
1.00
1.00

TIEMPO OPTIMO
T I
T I

41.9
42.4
41.9
48.4
60.4
60.4
61.4
61.9
62.4
62.4
74.4
74.9
75.9
76.4
76.4
76.0
77.2
83.2
83.2
83.7
101.2
101.5
101.8
102.0
102.0
102.0
102.3
102.3
102.3
103.3
103.6
103.6
103.9
104.1
105.1

42.4
48.4
47.9
60.4
62.4
61.4
61.9
62.4
74.9
74.4
74.9
75.9
76.4
76.9
77.2
77.2
83.2
83.7
101.2
101.5
101.8
101.8
102.0
102.3
102.3
102.3
103.3
103.3
103.3
103.6
103.9
104.1
104.1
105.1
106.1

TIEMPO PESIMISTA HOLGURA DE UNA CONDICION


T I
T I
ACTIVIDAD HA ij

47.6
48.1
41.9
48.4
60.4
60.4
73.6
74.1
74.6
62.4
74.4
74.9
75.9
76.4
76.4
76.9
77.2
83.2
83.2
101.0
101.2
101.5
101.8
102.0
102.0
102.0
103.0
102.3
102.5
103.3
103.6
103.6
103.9
104.1
105.1

48.1
48.4
47.9
60.4
62.4
73.6
74.1
74.6
74.9
74.4
74.9
75.9
76.4
76.9
77.2
77.2
83.2
101.0
101.2
101.5
101.5
101.8
102.0
102.5
103.0
102.3
103.3
103.3
103.3
103.6
103.9
104.1
104.1
105.1
106.1

5.7
5.7
0.0
0.0
1.5
12.7
12.2
12.2
12.2
6.0
0.0
0.0
0.0
0.0
0.5
0.9
0.0
17.3
0.0
17.3
0.0
0.0
0.0
0.3
0.5
0.0
0.8
0.0
0.3
0.0
0.0
0.3
0.0
0.0
0.0

N.C.
N.C.
C
C
N.C
N.C.
N.C.
N.C.
N.C.
N.C.
C
C
C
C
N.C.
N.C.
N.C.
N.C.
C
N.C.
C
C
C
N.C.
C
N.C.
N.C.
C
N.C.
C
C
N.C.
C
C
C

Anales Cientficos UNALM

i
27
28
24
29
30
30
32
34
35
31
33
36
37
38
38
39
40
41
41
42
43
44
45
46
46
46
48
49
47
50
51
51
52
53
54