Académique Documents
Professionnel Documents
Culture Documents
Imprint
Responsible Care
CONTENTS
PRELIMINARY REMARKS
REQUIREMENTS ON PLANNING
10
10
10
11
11
12
12
12
13
MATERIALS
13
4.1 Primers
13
13
14
14
15
16
16
PRELIMINARY WORK
17
17
8.2
8.3
8.4
8.5
17
18
18
18
18
SUBSTRATE PRE-TREATMENT
19
19
20
20
22
SERVICE PENETRATIONS
24
24
24
JOINTS
25
5.1 In General
25
25
26
CONNECTIONS
27
28
29
31
31
31
31
32
10
26
ANNEX
ANNEX 1: WATERPROOFING WITH PMBC BEYOND DIN 18195
33
33
GENERAL REQUIREMENTS
34
RANGE OF USE
34
34
34
34
35
35
35
36
36
36
36
37
38
ILLUSTRATIONS
Ill.: 1
11
Ill.: 2
11
Ill.: 3
12
13
20
21
21
21
22
Ill.: 10
22
Ill.: 11
23
23
24
25
Ill.: 4
Ill.: 5
Ill.: 6
Ill.: 7
Ill.: 8
Ill.: 9
Ill.: 12
Ill.: 13
Ill.: 14
Ill.: 15
Ill.: 16
Ill.: 17
Ill.: 18
Ill.: 19
Ill.: 20
26
27
28
29
35
36
PRELIMINARY REMARKS
This 3rd edition of the Guideline for Planning and Executing Waterproofing with
Polymer Modified Bituminous Thick Coatings (PMBC) Building Elements with Ground
Contact (abbreviated: PMBC Guideline) issued May 2010 was prepared by representatives of the associations named below and published by these associations:
The 1st edition of the PMBC Guideline issued in June 1997 was revised to integrate
the changes that had been made to parts 1 to 6 of DIN 18195 Waterproofing of
Buildings in August 2000. The result was the 2nd edition of the PMBC Guideline
issued in November 2001. In this 3rd edition, experience gained in the meantime and
changes in the standard (DIN 18195) as well as rules for PMBC issued by the [German]
supervising authority have been incorporated. This 3rd edition of the PMBC Guideline
published in May 2010 replaces the 2nd edition from November 2001.
This PMBC Guideline may be used by anyone, however, whoever uses it must make
sure that it is correctly applied in each individual case. The use of this guideline does
not relieve anyone from responsibility for the work they have executed.
PART A: GENERAL
REQUIREMENTS
Part A of this guideline deals
with the principles for waterproofing building elements with
ground contact using polymer
modified bituminous thick
coatings (PMBC) and is the
basis for part B and Annex 1.
10
2 REQUIREMENTS ON PLANNING
The effect and durability of structural waterproofing depends not only on proper planning and execution of the waterproofing but also on proper planning and execution
of the building and the elements to be waterproofed. The planner of the building
must make sure that the foundation and enclosing walls are designed and executed
according to the state of the art, taking differences in settlement, soil pressure and, if
applicable, a water pressure load into account.
Whenever buildings are waterproofed, the waterproofing must be carefully planned
and taken into account in the overall planning of the building or the part of the building to be waterproofed. Static, structural and physical requirements must also be taken
into account. Before the planner can begin, he must also obtain sufficient information
on the properties of the foundation soil. He must investigate whether the soil is water
permeable (hydraulic conductivity k > 10-4 m/s). If this cannot be determined without
doubt, a soil survey will be required or a higher water load must be assumed.
If waterproofing it to be planned properly, it is essential to know the design water
level. According to DIN 18195-1, the design water level is defined as: The highest
ground water/high-water level determined, if possible, over the course of many years
of observation and, in the case of internal water pressure, the planned water level. If
drainage according to DIN 4095 is planned for poorly permeable soil (k > 10-4 m/s), it
must be clarified in advance how the arising drainage water can be safely led off since,
in Germany for example, the statutes of many communities prohibit the discharge
of drainage water into the sewer system. If drainage water is to seep away on the
property, Work Sheet A 138 issued by the German Association for Water, Waste Water
and Waste (DWA) must also be observed.
11
precipitation
1)
Illustration 1
precipitation
1)
Illustration 2
least 10-4 m/s. This load also exists if drainage according to DIN 4095 is used for less
permeable soil, provided that the drainage functions permanently.
12
precipitation
With less permeable soil 1)
k < 10 -4 m/s
(k < 0.1 mm/s)
Without drainage
Foundation depth up to 3 m below
ground level
<3m
Illustration 3
1)
2)
> 300 mm
13
<3m
1)
Illustration 4
2)
4 MATERIALS
4.1 Primers
Primers ensure that the subsequently applied bituminous thick coating reliably adheres
to the surface and binds dust. Depending on the type of substrate and the primer
selected, they may also penetrate into and strengthen the substrate. Suitable products
for priming may be on a:
Bitumen-emulsion base
Reactive resin base
Plastic dispersion base
Silicate base
Bitumen solution base (only for repairs)
The use of solvent based products should be restricted to an essential minimum (e.g.
repairs) for occupational safety reasons and the environments sake and because the
solvents evaporate slowly. Solvent based primers should never be used in interior areas
because of the risk of explosion if ventilation is insufficient.
14
15
1
German Committee for Reinforced
Concrete (DAfStb) - Guideline for Water
Impermeable Structures made of Concrete
(WU Guideline) issued November 2003
16
17
not suitable for aerated concrete or for building elements of less strength. Absorbent
substrates may be matt damp but not shiny wet. To test this, water that is applied to
the substrate must distribute itself within a short time and may not be repelled. Subconcrete/base course layers to which PMBC is to be applied (e.g. when installing the
waterproofing plane below the floor slab) must be made of concrete at least C 25/30
and sufficiently designed.
8 PRELIMINARY WORK
8.1 General Preliminary Work
During the construction phase, polymer modified bituminous thick coatings may be
damaged if water can act from behind. If it is not possible to keep water away from the
side of the waterproofing that adheres to the structure/element, intermediate waterproofing must be placed. This must be water impermeable and may not be detached
from the substrate by water pressure. Suitable for this purpose are, e.g.:
Mineral waterproofing grouts that do not bridge cracks
Crack-bridging mineral waterproofing grouts
Interior corners and wall/floor connections should be produced with a sealing cove. As
a rule, these can be executed with mortars compatible with the system in a radius of
4 to 6 cm (bottle moulding). The mortar used should be coordinated to the substrate.
As an alternative, if permitted by the manufacturer, the sealing cove can be produced
with the polymer modified bituminous thick coating. In this case, the radius should
not exceed 2 cm.
Remove any unevenness and bevel edges.
18
19
PART B: EXECUTION
OF WATERPROOFING
USING PMBC ACCORDING
TO DIN 18195
Table 1
Load
2 working operations *
3 mm
2 working operations **
A layer of reinforcement on
coves and edges
3 mm
2 working operations **
A layer of reinforcement
4 mm
20
In floor/wall connecting areas with a projecting floor slab, the polymer modified bituminous waterproofing should be led down from the wall area over the floor slab to at
least 100 mm down the face side of the floor slab.
If work is interrupted, the polymer modified bituminous thick coating must be feathered out to zero. When work is continued, the coating is lapped over the feathered out
area. Work should not be interrupted when coating the corners of buildings.
3 WATERPROOFING SCHEME
3.1 Ground Damp and Non-Standing Seepage Water
or:
Concrete according to DIN EN 206
or:
Masonry with standard mortar in horizontal
joints with/without closing cross joints with
mortar according to DIN 1053
Polymer modified
bitumen thick coating (PMBC)
(2 layers, minimum dry layer thickness 3 mm)
*) Drainage according
to DIN 4095 only
necessary for less
permeable soil
Illustration 5
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
Parting layer
Cross-sectional waterproofing made of mineral waterproofing grout or sheet in accordance with DIN 18195-4
Capillary-interrupting layer
or sub-concrete
21
Mineral waterproofing
grout (MWG)
Cavity flashing
(L-shaped waterproofing)
Mineral waterproofing
grout (MWG)
> 10 cm
Illustration 6
> 10 cm
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
Illustration 8
22
or:
Concrete according to DIN EN 206
Polymer modified
bituminous thick coating (PMBC)
(2 layers with a layer of reinforcement,
minimum dry layer thickness 4 mm)
or:
Masonry with standard mortar in the
horizontal joints with/without closing of
cross joints with mortar according to DIN 1053
Polymer modified
bituminous thick coating (PMBC)
(2 layers with a layer of reinforcement,
minimum dry layer thickness 4 mm)
Protective screed
Parting layer
Sub-concrete
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
> 10 cm
Illustration 10
> 5 cm
23
Reinforced
sub-concrete
> 10 cm
Detail: Connection to splash water areas, single leaf masonry, plinth connection
Water load: Standing seepage water DIN 18195-6
> 15 cm
> 5 cm
Mineral waterproofing
grout (MWG)
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
> 10 cm
Mineral waterproofing
grout (MWG)
(adjusted to ground)
External
render
24
4 SERVICE PENETRATIONS
Service penetrations (pipe penetrations) may pass through the waterproofing at all
levels but if possible, they should always be installed in an area where the water load is
only ground damp and non-standing seepage water. The external edges of the flanges
used for pipe penetrations should be at least 30 cm apart.
> 5 cm
Illustration 13
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
25
> 5 cm
Illustration 14
5 JOINTS
5.1 In General
Movement joints: Space between two building elements or building sections that
allows each to have different movements.
The placement and execution of joints requires careful planning. Bitumen compatible
water stops made of plastic waterproofing sheets laminated to a non-woven or woven
fabric for bedding into the polymer modified bituminous thick coating (PMBC) are used
to waterproof joints in surface waterproofing made of polymer modified bituminous
thick coatings (PMBC).
Type II joints are for movements that take place quickly or are often repeated, e.g.
movements through alternating live loads or changes in length caused by differences
in temperature during the day. As a rule, these joints are above ground level and are
therefore not dealt with in this PMBC guideline for building elements with ground
contact.
26
Joint
System-compatible
water stop according to DIN 18195-8,
section 7.2.1
> 5 cm
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
27
Exterior wall
Illustration 16
6 CONNECTIONS
In splash water zones, the waterproofing should be led 30 cm above ground level to
ensure that there is sufficient space for adjusting the surface of the ground. After
the ground has been adjusted, the waterproofing should still be at least 15 cm above
ground level. The exposed PMBC must be protected from UV-light by a bonded thermal
insulation system, curtain facade element or similar. See Illustration 10.
Waterproofing in splash water zones on one-leaf masonry (see Ill. 12) or concrete
walls to which plinth render is to be applied should be waterproofed with a mineral
waterproofing grout. The mineral waterproofing grout is applied first before the render
is applied.
In the case of two-leaf masonry, a cavity flashing (L-shaped waterproofing) is attached
to the load-bearing shell, led downward in the cavity towards the outside and laid
horizontally in the external shell. The connection between the cavity flashing and the
PMBC in the areas in contact with the ground can be executed with a mineral waterproofing grout. See Illustration 6.
The zone in which the mineral waterproofing grout is overlapped by the polymer modified bituminous thick coating is below ground level and should be at least 10 cm high.
Note:
This is a schematic diagram showing
0the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
28
Illustration 17
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
> 15 cm
29
Illustration 18
> 15 cm
Concrete according to
DIN EN 206
The materials used for protective measures and/or protective layers (see Part A, section 4.4) must be compatible with the polymer modified bituminous thick coating.
Protective layers may only be installed after the bituminous thick coating has thoroughly dried. Point and line loads as well as loads that could impair the waterproofing
through compression should be avoided.
30
By taking suitable measures, for example the use of a sliding plane, it should be
ensured that no movements from the ground can be transferred to the waterproofing. Selection of a suitable protective layer depends on the expected loads and local
conditions. The waterproofing should not be damaged when the protective layers are
installed; contaminates on the waterproofing should be carefully removed first.
Horizontal waterproofing with a polymer modified bituminous thick coating, for
example on the sub-layer of concrete, must also be protected by a layer after it has
thoroughly dried. To separate the horizontal waterproofing from the protective layer,
two layers of PE sheets are placed as a sliding plane. When screeds are used as a protective layer, they are placed directly over the PE sheets at least 5 cm thick.
Protective layers on waterproofing above the floor slab can be produced, for example,
as a screed on a parting layer or as a screed on a layer of insulation for the water load
moisture. Movement joints should be continued in the rigid protection layers so that
their capacity to function is not impaired.
Thermally insulating materials (perimeter insulation) as well as drainage layers may
also be used as protective layers provided they are suitable according to DIN 4095.
Care must be taken to ensure that these protective layers do not exert pressure on
the waterproofing at the wall-slab connection. When cementing protective layers to
the substrate, an adhesive must be used that is compatible with the bituminous thick
coating. If perimeter insulation panels are used, additional protective layers may be
necessary. Furthermore, the information given in the proof of usability issued by the
building inspectorate should also be observed.
When removing excavation pit shoring works, for example pulling out planks (sheet
piles), suitable measures should be taken to ensure that the protective layer for the
waterproofing is not moved or damaged.
Relevant guidelines should also be observed when filling the excavated area. The
material used for filling should be placed in layers and carefully compacted so that the
protective layer is not damaged and the load on the walls is not increased. Protective
layers that are connected to the waterproofing should not move when the ground is
being compacted. If necessary, additional protective layers (parting planes) should be
installed.
31
32
The substrate of the reference samples must correspond to the building element that
is waterproofed. Individual reference samples, e.g. single masonry stones, are coated
in the same manner with the same thick coating at the same time the waterproofing
is applied and stored under the same weather conditions in the bottom area of the
excavation pit. If such reference samples have been produced, wedges can be cut out
and the respective state of drying checked and documented accordingly.
According to DIN 18195, when waterproofing according to parts 5 and 6, the results
of monitoring must be documented. Documentation is urgently recommended for all
waterproofing measures. In Annex 3 of this guideline you will find a Documentation
form that can be used for this purpose.
To test waterproofing made of PMBC in areas that connect to water impermeable concrete building elements, the waterproofing should be led down beyond the 15 cm wide
connecting area in some areas for testing purposes. In these areas, destructive testing
of adhesion and thorough drying can be carried out. As opposed to building elements
made of water impermeable concrete, the connection of PMBC waterproofing to floor
slabs is executed only 10 cm wide.
10.3 Documentation
The details of the waterproofing monitored at the building site should be documented
for quality assurance purposes. Records of measurements, check lists and similar
should be used to provide clear and orderly documentation (see Annex 3).
33
ANNEX 1:
34
The contractor is, however, fully responsible for the serviceability of the proposed
material, the proposed construction method and proper execution of the work.
If the owner of the building has called in a planner and a material that does not comply
with DIN is specified in the Bill of Quantities or the plan, it is the responsibility of the
contractor to inform the client of his misgivings.
If it can be proved that the client insisted on these specifications, the contractor cannot be blamed later for having deviated from the recognised state of art.
This should also be recorded in writing in the offer confirmation or in a separate record
and signed by the client.
2 GENERAL REQUIREMENTS
All of the general information given in Part A and Part B of this guideline is applicable.
For quality assurance purposes, the results of monitoring the waterproofing at the construction site should be documented. Records of measurements, check lists and similar
should be used to provide clear and orderly documentation (see Annex 3).
3 RANGE OF USE
PMBC can be used for the following application areas beyond DIN 18195:
35
Illustration 19
Note:
This is a schematic diagram showing
0the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
> 15 cm
36
> 15 cm
Note:
This is a schematic diagram showing
the location of the waterproofing.
Depending on intended utilisation,
additional layers of insulation may be
required, for example.
37
ANNEX 2:
38
ANNEX 3:
Record of execution
Object data
DOCUMENTATION FORM
For the production of waterproofing with polymer modified bituminous thick coatings
(PMBC)
Executing company
Installer/employee
Building project
Client
Date
Weather
Air temperature: C
Substrate temperature: C
Humidity: in %
rainy
sunny
cloudy
Progress in construction
Basement walls
basement floor
ground
storey floor
roof
Soil
Permeable
(e.g. gravel/sand)
less permeable
(e.g. clay/loam)
water management
system
Exists
planned accord.
to Bill of Quant.
non accord.
to Bill of Quant.
Water load
Ground damp/
non-standing seepage water
Ground water *
moisture,
moderate load
moisture,
heavy load *
* Note: For this load, DIN 18 195-5 and 6 does not allow bituminous thick coatings. In accordance with VOB, part C, and
DIN 18 336, an agreement must be made for waterproofing with thick coatings. The client must be expressly informed of
the deviation to DIN 18 195 (in writing).
Substrate
Masonry smooth
porous aggregates
profiled
Age of concrete/days
rendered surface
other
Surfaces cleaned
Indentations > 5 mm
closed with mortar
Foundation projection/
face side cleaned
Edges bevelled
Primer
Designation of product:
Quantity used
Thinner:
Sealing cove
Surface waterproofing
Made of bituminous
thick coating
Produced on:
made of mortar
Produced on:
Layer of reinforcement
yes
no
39
Protective layer
Drainage layer
(vertical drainage)
cemented
installed on:
yes
no
cemented
yes
no
cemented
yes
no
Perimeter insulation
full surface
If applicable, adhesive used:
point-cemented
1st date:
thoroughly dry
yes
no
2nd date:
thoroughly dry
yes
no
3rd date:
thoroughly dry
yes
no
4th date:
thoroughly dry
yes
no
5th date:
thoroughly dry
yes
no
Note: For subsequent tests on the object, the dry layer thickness can be determined by the wedge cut method.
For waterproofing according to DIN 18195-5 and 6, layer thickness controls as well as
thorough drying must be documented.
(At least 20 measurements per object or 20 measurements per 100 m)
1st layer
Measurement No. 1
Measurement No. 2
Measurement No. 3
Measurement No. 4
Measurement No. 5
Measurement No. 6
Measurement No. 7
Measurement No. 8
Measurement No. 9
Measurement No. 10
Measurement No. 11
Measurement No. 12
Measurement No. 13
Measurement No. 14
Measurement No. 15
Measurement No. 16
Measurement No. 17
Measurement No. 18
Measurement No. 19
Measurement No. 20
2nd layer
3rd layer
Deutsche Bauchemie e. V.
Mainzer Landstrasse 55
60329 Frankfurt am Main
Germany
Phone + 49 69 2556 - 1318
Fax
+ 49 69 2556 - 1319
www.deutsche-bauchemie.de