CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
Finish
150
58%
19-Aug-14 A
15-Jan-15
15-Jan-
150
69.33%
19-Aug-14 A
15-Jan-15
15-Jan-
19-Dec-14
122
100%
19-Aug-14 A
A1000
100%
19-Aug-14 A
A1010
100%
20-Aug-14 A
A1020
100%
20-Sep-14 A
A1030
Fin de Proyecto
0%
0%
29-Sep-14 A
HITOS DE
DEL CONTRATO
HITOS DE INGENIERA
2014
Sep
2015
Oct
Nov
Fin de Proyecto
23-Oct-14 A
100%
29-Sep-14 A
A2030
100%
29-Sep-14 A
0
0
0%
100%
23-Oct-14 A
23-Oct-14 A
100%
23-Oct-14 A
0
0
0%
100%
23-Oct-14 A
23-Oct-14 A
100%
23-Oct-14 A
Entrega d
de Ingeniera Tubera
A1090
Entrega de Ingeniera de Diseo p/Fabricacin APC
0
0
0%
100%
23-Oct-14 A
23-Oct-14 A
100%
23-Oct-14 A
150
69.33%
19-Aug-14 A
15-Jan-15
63
0
100%
100%
29-Sep-14 A
29-Sep-14 A
01-Dec-14
A1060
Entrega d
de Ingeniera Mecnica
A1070
Entrega de Ingeniera para Procura o Diseo p/Fabricacin APC
A1080
A1100
HITOS DE CONSTRUCCIN
HITOS DE INICIO
A1110
Inicio de Obras Civiles
23-Oct-14 A
23-Oct-14 A
23-Oct-14 A
A1120
100%
20-Oct-14 A
A1130
100%
20-Oct-14 A
A1140
100%
28-Oct-14 A
A1150
0%
01-Dec-14*
A1160
0%
01-Dec-14*
150
0
90.53%
0%
19-Aug-14 A
0%
HITOS DE FIN
A1170
Fin de Obras Civiles
Jan
A1040
Entrega d
de Ingeniera Estructuras
A1050
Entrega de Ingeniera de Diseo p/Fabricacin APC
Dec
15-JanFin de Ob
11-Jan-15
Fin de Obra
A1180
A1190
0%
01-Jan-15
A1200
100%
19-Aug-14 A
A1210
0%
15-Jan-15
Fin de O
A1220
0%
01-Jan-15
143
57.34%
24-Aug-14 A
13-Jan-15
31
100%
22-Sep-14 A
22-Oct-14 A
TRABAJOS PRELIMINARES
TRABA
PRELIMINARES
PRELIMIN
A1230
15
100%
22-Sep-14 A
06-Oct-14 A
A1240
15
100%
30-Sep-14 A
14-Oct-14 A
A1250
15
100%
06-Oct-14 A
20-Oct-14 A
A1260
15
100%
08-Oct-14 A
22-Oct-14 A
13-Jan-15
22-Oct-14 A, PRELIMINARES
Planeamiento del Trabajo (solo en trmino contractual)
Reclutamiento de Personal Obrero
Exmenes Mdicos e Induccin de Ingreso
Movilizacin de Equipos a Obra
45
100%
29-Sep-14 A
12-Nov-14 A
A1270
30
100%
29-Sep-14 A
28-Oct-14 A
A1280
30
100%
03-Oct-14 A
01-Nov-14 A
A1290
30
100%
06-Oct-14 A
04-Nov-14 A
A1300
30
100%
10-Oct-14 A
08-Nov-14 A
A1310
30
100%
14-Oct-14 A
12-Nov-14 A
114
47.66%
22-Sep-14 A
13-Jan-15
13-Jan-15
101
48.51%
05-Oct-14 A
13-Jan-15
13-Jan-15
INGENIERA
INGENIER
PROCURA
PROCURA CLIENTE
PROCUR
Actual Work
Remaining Work
Milestone
Summary
Page 1 of 15
12-Nov-14 A, INGENIERA
Revisin de Ingeniera Civil
Revisin de Ingeniera Estructuras
Revisin de Ingeniera Mecnica
Revisin de Ingeniera Tuberas
Revisin de Ingeniera Elctrica & Instrumentacin
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Obras Mecnicas
M
AREA 5000
5
Generales
A1330 Suministro de Filtro de Discos TAG 5000-FL-002/001
A1420
AREA 5100
5
Filtracin de Relaves Detoxificados espesados
A1360 Suministro de Bombas Centrfugas (alimentacin a filtros) Bomba de vaco TAG 5100-VP-0
Original
Duration
Duration %
Complete
Start
Finish
101
39
0
48.51%
100%
100%
05-Oct-14 A
23-Oct-14 A
23-Oct-14 A
2014
Sep
0%
01-Dec-14*
13
0
0%
0%
23-Nov-14
05-Dec-14*
13-Jan-15
01-Dec-14
Oct
2015
Nov
Dec
Jan
13-Jan-15
06-Dec-14
A1370
0%
23-Nov-14*
A1380
0%
06-Dec-14*
A2840
0%
28-Nov-14
A3380
0%
28-Nov-14
A3390
0%
28-Nov-14
A3400
0%
28-Nov-14
A3410
0%
28-Nov-14
A3420
0%
28-Nov-14
0
0
0%
0%
06-Dec-14
06-Dec-14*
AREA 5200
5
Almacenamiento y Dosificacin de Cemento
A1390 Suministro de Silo de Cemento TAG 5200-BN-001/002/003
A1400
0%
06-Dec-14*
A3430
0%
06-Dec-14
A3440
0%
06-Dec-14
A3450
0%
06-Dec-14
A3460
0%
06-Dec-14
11
0
0%
0%
21-Dec-14
01-Jan-15*
0%
21-Dec-14
51
0
100%
100%
03-Nov-14 A
03-Nov-14 A
AREA 5300
5
Preparacin de Relleno en Pasta
A1350 Suministro de Mezcladores Acondicionadores doble eje TAG 5300-MX-001/002/003
A3470
AREA 5400
5
Sistema de Bombeo de Pasta
A1340 Suministro de Bomba de Desplazamiento Positivo TAG 5400-PU-001A/001B
A3480
AREA 5700
5
Espesamiento de relaves Detoxificados
A1320 Suministro de Espesador de Alta Densidad TAG 5700-TH-001 (15m, h=7m)
A2830
AREA 5800
5
Preparacin y Servicios de Reactivos
A5770 Suministro de Bomba de preparacin de floculante TAG 5800-PU-001
24-Dec-14
0%
24-Dec-14
101
0
100%
100%
05-Oct-14 A
05-Oct-14 A
13-Jan-15
0%
13-Jan-15
Bomba de
0
0
0%
0%
02-Dec-14
02-Dec-14
02-Dec-14
13-Jan-15
Suministro de Espesador de Alta Densidad TAG 5700-TH-001 (15m, h=7m)
A5780
0%
02-Dec-14
A5790
0%
02-Dec-14
A5800
0%
02-Dec-14
A5810
0%
02-Dec-14
A5820
0%
02-Dec-14
A5830
0%
02-Dec-14
A5970
0%
02-Dec-14
A6090
0%
02-Dec-14
A6100
0%
02-Dec-14
A6110
0%
02-Dec-14
A6120
0%
02-Dec-14
A6130
0%
02-Dec-14
A6140
0%
02-Dec-14
A6150
0%
02-Dec-14
A6160
0%
02-Dec-14
A6180
0%
02-Dec-14
A6190
0%
02-Dec-14
Actual Work
Remaining Work
Milestone
Summary
Page 2 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
A6220
0%
02-Dec-14
A6230
0%
02-Dec-14
A6240
0%
02-Dec-14
A6250
0%
02-Dec-14
A6270
0%
0
0
0%
100%
09-Oct-14 A
09-Oct-14 A
AREA 5900
5
Servicios Auxiliares Aire (Instrumentacin & Planta)
A1410 Suministro de Compresor de Aire de Alta Presin TAG 5910-CP-001A
02-Dec-14
09-Oct-14 A
A1510
100%
09-Oct-14 A
A1720
100%
09-Oct-14 A
A1840
100%
09-Oct-14 A
A2040
100%
09-Oct-14 A
A2050
100%
09-Oct-14 A
24
0
100%
0%
07-Nov-14 A
01-Dec-14*
Obras E
Elctricas
A1430
Suministro de Switchgear MT/BT
A1450
0%
01-Dec-14*
A1470
0%
01-Dec-14*
A1490
100%
07-Nov-14 A
0
0
0%
100%
10-Oct-14 A
10-Oct-14 A
10-Oct-14 A
108
0
0
50.31%
0%
100%
22-Sep-14 A
11-Oct-14 A
11-Oct-14 A
08-Jan-15
11-Oct-14 A
Obras Instrumentacin
In
A1500
Suministro de Instrumentacin
PROCUR CONTRATISTA
PROCURA
Obras C
Civiles
A1560
Suministro de Geomenbranas HDPE de 1.5mm
A1570
Obras E
Estructuras
A1440
Suministro de Materiales P/Fabricacin de estructuras incluye pernera para Nave de Relle
100%
11-Oct-14 A
105
0
100%
100%
22-Sep-14 A
22-Sep-14 A
A1480
0%
05-Jan-15*
A1540
100%
27-Oct-14 A
A1550
100%
27-Oct-14 A
54
0
0
0%
0%
0%
15-Nov-14
24-Nov-14
Obras Mecnicas
M
AREA 3420
3
Espesamiento de Relaves
A1520 Suministro de Bomba de Alimentacin de Relaves (155.1m3/h-1.0m) TAG 3420-PU-001A
A1530
AREA 5100
5
Filtracin de Relaves Detoxificados espesados
A1850 Suministro de Materiales P/Fabricacin de Tanque de Homonizacin de Relave TAG 5100-
0%
30
0
0%
0%
15-Nov-14
05-Jan-15, Obras
Suministro de Materiales P/Fabricacin de estructuras incluye pernera para Nave de Relleno en Pasta
Suministro de Cob
Suministro de Cerco Perimtrico
Suministro de Poste Proteccin de Seguridad cada 3m
08-Jan-15
24-Nov-14
24-Nov-14
08-Jan-15, Ob
24-Nov-14, AREA 3420 Espesamiento de Relaves
Suministro de Bomba de Alimentacin de Relaves (155.
24-Nov-14
15-Dec-14
15-Nov-14
A1870
0%
28-Nov-14
A1880
0%
28-Nov-14
A1890
0%
28-Nov-14
A1910
0%
28-Nov-14
A1920
0%
15-Dec-14
A1940
0%
15-Dec-14
A1960
0%
15-Dec-14
A1980
0%
15-Dec-14
A2000
0%
28-Nov-14
A2010
0%
28-Nov-14
A2020
0%
26-Nov-14
10
0
0%
0%
AREA 5300
5
A5880 Suministro de Materiales P/ Fabricacin de Tolva de relaves TAG 5300-BN-001
11-Dec-14
21-Dec-14
11-Dec-14
A5890
0%
11-Dec-14
A5910
0%
21-Dec-14
Actual Work
Remaining Work
Milestone
Summary
Page 3 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
A6170
Original
Duration
Duration %
Complete
Start
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
0%
21-Dec-14
AREA 5400
5
A6290 Suministro de Tecle TAG 5400-HS-001
0
0
0%
0%
13-Dec-14
13-Dec-14
13-Dec-14
AREA 5600
5
A5920 Suministro de Materiales P/ Fabricacin de Tanque de agua recuperada TAG 5600-TK-00
10
0
0%
0%
29-Nov-14
09-Dec-14
29-Nov-14
A5940
0%
29-Nov-14
A5960
0%
09-Dec-14
A5980
0%
09-Dec-14
A5990
0%
29-Nov-14
A6010
0%
09-Dec-14
A6020
0%
29-Nov-14
A6040
AREA 5700
5
A6050 Suministro de Materiales P/ Fabricacin Tanque de Alimentacin de Relaves TAG 5700-TK
A6070
AREA 5800
5
A6080 Suministro de Tecle TAG 5800-HS-001
0%
10
0
0%
0%
0%
0
0
0%
0%
09-Dec-14
29-Dec-14
08-Jan-15
29-Dec-14
08-Jan-15, ARE
Suministro de Materiales
02-Dec-14
02-Dec-14
02-Dec-14
08-Jan-15
Suministro de B
A6200
0%
02-Dec-14
A6210
0%
02-Dec-14
A6260
0%
02-Dec-14
A6280
0%
02-Dec-14
Obras T
Tubera
A5710
Suministro Tubera, Accesorios, Empaquetadura y Pernera
0
0
0%
100%
28-Oct-14 A
28-Oct-14 A
28-Oct-14 A
Obras E
Elctricas
A1460
Suministro de Soporte y Bandeja T/Escalera C/Tapa 0.6m x 1.0m
0
0
0%
0%
01-Dec-14
01-Dec-14
01-Dec-14
A1580
0%
01-Dec-14
A1590
0%
01-Dec-14
A1600
0%
01-Dec-14
A1610
0%
01-Dec-14
A1620
0%
01-Dec-14
A1630
0%
01-Dec-14
A1640
0%
01-Dec-14
A1650
0%
01-Dec-14
A1660
0%
01-Dec-14
A1670
0%
01-Dec-14
A1680
0%
01-Dec-14
A1690
0%
01-Dec-14
A1700
0%
01-Dec-14
A1710
0%
01-Dec-14
A1730
0%
01-Dec-14
A1740
0%
01-Dec-14
A1750
0%
01-Dec-14
A1760
0%
01-Dec-14
A1770
0%
01-Dec-14
A1780
0%
01-Dec-14
A1790
0%
01-Dec-14
A1800
0%
01-Dec-14
A1810
0%
01-Dec-14
A1820
0%
01-Dec-14
Actual Work
Remaining Work
Milestone
Summary
Page 4 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
A1830
Original
Duration
INSTALACIN EN OBRA
INSTALAC
Duration %
Complete
Start
Finish
0%
01-Dec-14
136
60.29%
24-Aug-14 A
06-Jan-15
10
100%
24-Sep-14 A
03-Oct-14 A
A3060
Trazo y Replanteo
109
50.46%
20-Sep-14 A
06-Jan-15
A3300
Instalacin de Campamentos
10
100%
24-Aug-14 A
02-Sep-14 A
149
58.39%
19-Aug-14 A
14-Jan-15
Instalacin de Campamentos
14-Jan-1
61.94%
20-Aug-14 A
07-Jan-15
100%
100%
100%
100%
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
26-Aug-14 A
26-Aug-14 A
26-Aug-14 A
26-Aug-14 A
SECTOR 3
AREA 50
5000 Generales
OBRAS CIVILES
A2800 5000 Habilitado de Acero de Refuerzo
141
73
45
45
61.94%
100%
100%
100%
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
07-Jan-15
31-Oct-14 A
03-Oct-14 A
03-Oct-14 A
40
6
6
100%
100%
100%
22-Sep-14 A
25-Sep-14 A
25-Sep-14 A
31-Oct-14 A
30-Sep-14 A
30-Sep-14 A
100%
25-Sep-14 A
28-Sep-14 A
A2370 Barandas
100%
26-Sep-14 A
26-Sep-14 A
Barandas
07-Jan-15, TRA
Parrillas
26-Aug-14 A, SECTOR 2
26-Aug-14 A, AREA 3450 TRANSPORTE DE RELAVES
26-Aug-14 A, OBRAS CIVILES
3450 Habilitado de Acero de Refuerzo
07-Jan-15, SEC
31-Oct-14 A, AREA 5000 Generales
03-Oct-14 A, OBRAS CIVILES
5000 Habilitado de Acero de Refuerzo
31-Oct-14 A, OBRAS ESTRUCTURAS
30-Sep-14 A, FABRICACIN DE ACCESOS A PLANTA Y MISCELNEOS
Estructuras Livianas (<=30KG/M)
Estructuras Medianas (>30KG/M y <=60KG/M)
100%
26-Sep-14 A
27-Sep-14 A
14
14
100%
100%
24-Sep-14 A
24-Sep-14 A
07-Oct-14 A
07-Oct-14 A
10
100%
25-Sep-14 A
04-Oct-14 A
100%
25-Sep-14 A
30-Sep-14 A
100%
25-Sep-14 A
27-Sep-14 A
A2320 Barandas
100%
25-Sep-14 A
25-Sep-14 A
A2330 Escaleras
100%
25-Sep-14 A
26-Sep-14 A
Escaleras
A2340 Parrillas
100%
25-Sep-14 A
27-Sep-14 A
Parrillas
14
11
100%
100%
23-Sep-14 A
23-Sep-14 A
06-Oct-14 A
03-Oct-14 A
100%
23-Sep-14 A
28-Sep-14 A
100%
23-Sep-14 A
27-Sep-14 A
100%
23-Sep-14 A
27-Sep-14 A
A2260 Barandas
100%
24-Sep-14 A
24-Sep-14 A
A2270 Parrillas
12
100%
25-Sep-14 A
06-Oct-14 A
13
13
100%
100%
22-Sep-14 A
22-Sep-14 A
04-Oct-14 A
04-Oct-14 A
12
100%
23-Sep-14 A
04-Oct-14 A
100%
24-Sep-14 A
01-Oct-14 A
100%
25-Sep-14 A
03-Oct-14 A
A2190 Barandas
100%
23-Sep-14 A
23-Sep-14 A
A2200 Escaleras
100%
24-Sep-14 A
27-Sep-14 A
Escaleras
A2210 Parrillas
100%
25-Sep-14 A
28-Sep-14 A
Parrillas
40
40
100%
100%
22-Sep-14 A
22-Sep-14 A
31-Oct-14 A
31-Oct-14 A
17
100%
23-Sep-14 A
09-Oct-14 A
15
100%
24-Sep-14 A
08-Oct-14 A
12
100%
25-Sep-14 A
06-Oct-14 A
FABRI
FABRICACIN
DE SOPORTES PARA EQUIPOS EN TANQUES
A2280 Estructuras Livianas (<=30KG/M)
FABRI
FABRICACIN
DE ESCALERA PARA NAVE
A2220 Estructuras Livianas (<=30KG/M)
FABRI
FABRICACIN
DE PIPE RACK
A2150 Estructuras Livianas (<=30KG/M)
FABRI
FABRICACIN
DE NAVE DE RELLENO EN PASTA
A2080 Estructuras Livianas (<=30KG/M)
Actual Work
Remaining Work
Milestone
Summary
Jan
Trazo y Replante
7
7
7
7
A2380 Parrillas
Dec
06-Jan-15, INST
141
OBRAS ESTRUCTURAS
FABRICACIN DE ACCESOS A PLANTA Y MISCELNEOS
FABRI
A2350 Estructuras Livianas (<=30KG/M)
Nov
SECTOR 2
AREA 3450
34 TRANSPORTE DE RELAVES
OBRAS CIVILES
A2810 3450 Habilitado de Acero de Refuerzo
TRABAJOS EN PLANTA
TRABAJO
2015
Oct
A2060
CONSTRUCCIN
CONST
2014
Sep
Page 5 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
A2120 Barandas
100%
22-Sep-14 A
22-Sep-14 A
A2130 Escaleras
11
100%
22-Sep-14 A
02-Oct-14 A
A2140 Parrillas
100%
22-Sep-14 A
27-Sep-14 A
122
5
5
71.39%
100%
100%
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
20-Dec-14
24-Aug-14 A
24-Aug-14 A
35
11
0%
0%
15-Nov-14
15-Nov-14
20-Dec-14
26-Nov-14
AREA 51
5100 Filtracin de Relaves Detoxificados espesados
OBRAS CIVILES
A2450 5100 Habilitado de Acero de Refuerzo
OBRAS MECNICAS
A1860 Fabricacin de Tanque de Homonizacin de Relave TAG 5100-TK-001 (3.5, h=4.42m)
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
Barandas
Escaleras
Parrillas
20-Dec-14, AREA 5100 Filtraci
24-Aug-14 A, OBRAS CIVILES
5100 Habilitado de Acero de Refuerzo
20-Dec-14, OBRAS MECNICA
Fabricacin de Tanque de Homonizacin de Relave T
A1900
11
0%
28-Nov-14
09-Dec-14
A1930
11
0%
09-Dec-14
20-Dec-14
A1950
11
0%
09-Dec-14
20-Dec-14
A1970
11
0%
09-Dec-14
20-Dec-14
A1990
11
0%
09-Dec-14
20-Dec-14
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
79
7
7
100%
100%
100%
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
06-Nov-14 A
26-Aug-14 A
26-Aug-14 A
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
10
10
10
0%
0%
0%
11-Dec-14
11-Dec-14
11-Dec-14
20-Dec-14
20-Dec-14
20-Dec-14
OBRAS TUBERA
A2850 5100 Fabricacin de Spools
AREA 52
5200 Almacenamiento y Dosificacin de Cemento
OBRAS CIVILES
A2590 5200 Habilitado de Acero de Refuerzo
OBRAS TUBERAS
A5660 5200 Fabricacin de spools
AREA 5300
53
OBRAS MECNICAS
A5870 Fabricacin de Tolva de relaves TAG 5300-BN-001
A5900
10
0%
11-Dec-14
20-Dec-14
AREA 54
5400 Sistema de Bombeo de Pasta
OBRAS CIVILES
A2670 5400 Habilitado de Acero de Refuerzo
25
25
25
100%
100%
100%
29-Sep-14 A
29-Sep-14 A
29-Sep-14 A
23-Oct-14 A
23-Oct-14 A
23-Oct-14 A
AREA 5600
56 Sistema de Almacenamiento de Agua de Planta de relleno en Pasta
OBRAS CIVILES
A2820 5600 Habilitado de Acero de Refuerzo
71
5
5
85.92%
100%
100%
29-Sep-14 A
29-Sep-14 A
29-Sep-14 A
08-Dec-14
03-Oct-14 A
03-Oct-14 A
10
10
0%
0%
29-Nov-14
29-Nov-14
08-Dec-14
08-Dec-14
OBRAS MECNICAS
A5930 Fabricacin de Tanque de agua recuperada TAG 5600-TK-001 (4.6m, h=5.79m)
A5950
10
0%
29-Nov-14
08-Dec-14
A6000
10
0%
29-Nov-14
08-Dec-14
A6030
10
0%
29-Nov-14
08-Dec-14
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
101
35
35
90.1%
100%
100%
29-Sep-14 A
29-Sep-14 A
29-Sep-14 A
07-Jan-15
02-Nov-14 A
02-Nov-14 A
OBRAS MECNICAS
A6060 Fabricacin Tanque de Alimentacin de Relaves TAG 5700-TK-001(5.88m, h=7.35m)
10
10
0%
0%
29-Dec-14
29-Dec-14
07-Jan-15
07-Jan-15
OBRAS TUBERAS
A5690 5700 Fabricacin de Spools
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
39
29
29
100%
100%
100%
29-Sep-14 A
29-Sep-14 A
29-Sep-14 A
06-Nov-14 A
27-Oct-14 A
27-Oct-14 A
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
39
5
100%
100%
29-Sep-14 A
29-Sep-14 A
06-Nov-14 A
03-Oct-14 A
OBRAS TUBERA
A5680 5600 Fabricacin de Spools
AREA 57
5700 Espesamiento de relaves Detoxificados
OBRAS CIVILES
A2690 5700 Habilitado de Acero de Refuerzo
AREA 58
5800 Preparacin y Servicio de Reactivos
OBRAS CIVILES
A2780 5800 Habilitado de Acero de Refuerzo
OBRAS TUBERAS
A5700 5800 Fabricacin de Spools
AREA 59
5900 Servicios Auxiliares (instrumentacin planta)
OBRAS CIVILES
Actual Work
Remaining Work
Milestone
Summary
Page 6 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
A2770
Original
Duration
Duration %
Complete
Start
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
100%
29-Sep-14 A
03-Oct-14 A
10
10
100%
100%
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
79
79
10
10
100%
100%
100%
100%
20-Aug-14 A
20-Aug-14 A
28-Oct-14 A
28-Oct-14 A
06-Nov-14 A
06-Nov-14 A
06-Nov-14 A
06-Nov-14 A
06-Nov-14 A, SECTOR 1
06-Nov-14 A, AREA 3420 Espesamiento de Relaves - Planta de Proces
06-Nov-14 A, OBRAS TUBERAS
3420 Fabricacin de Spools
28
28
100%
100%
20-Aug-14 A
20-Aug-14 A
16-Sep-14 A
16-Sep-14 A
149
58.39%
19-Aug-14 A
14-Jan-15
96
96
89
74
74
18
8
90.94%
90.94%
98.12%
100%
100%
100%
100%
19-Aug-14 A
19-Aug-14 A
19-Aug-14 A
19-Aug-14 A
19-Aug-14 A
19-Aug-14 A
19-Aug-14 A
22-Nov-14
22-Nov-14
15-Nov-14
31-Oct-14 A
31-Oct-14 A
05-Sep-14 A
26-Aug-14 A
10
100%
27-Aug-14 A
05-Sep-14 A
66
20
100%
100%
27-Aug-14 A
27-Aug-14 A
31-Oct-14 A
15-Sep-14 A
100%
16-Sep-14 A
19-Sep-14 A
100%
16-Sep-14 A
19-Sep-14 A
100%
16-Sep-14 A
19-Sep-14 A
100%
11-Sep-14 A
15-Sep-14 A
100%
12-Sep-14 A
15-Sep-14 A
100%
07-Sep-14 A
15-Sep-14 A
100%
12-Sep-14 A
15-Sep-14 A
100%
09-Sep-14 A
15-Sep-14 A
100%
27-Oct-14 A
31-Oct-14 A
14
100%
09-Sep-14 A
22-Sep-14 A
12
100%
09-Sep-14 A
20-Sep-14 A
100%
11-Sep-14 A
18-Sep-14 A
10
100%
06-Sep-14 A
15-Sep-14 A
15
2
100%
100%
16-Sep-14 A
16-Sep-14 A
30-Sep-14 A
17-Sep-14 A
100%
18-Sep-14 A
18-Sep-14 A
100%
19-Sep-14 A
19-Sep-14 A
100%
20-Sep-14 A
20-Sep-14 A
100%
26-Sep-14 A
30-Sep-14 A
100%
21-Sep-14 A
25-Sep-14 A
44
3
1
100%
100%
100%
18-Sep-14 A
18-Sep-14 A
18-Sep-14 A
31-Oct-14 A
20-Sep-14 A
18-Sep-14 A
100%
19-Sep-14 A
19-Sep-14 A
100%
20-Sep-14 A
20-Sep-14 A
OBR
OBRAS
DE CONCRETO SIMPLE
A28 Solado fc=100kg/cm2 (e=10cm) en Losas
1
1
100%
100%
19-Sep-14 A
19-Sep-14 A
19-Sep-14 A
19-Sep-14 A
OBR
OBRAS
DE CONCRETO ARMADO
A29 Habilitado de Acero de Refuerzo fy=4200kg/cm2
14
2
100%
100%
18-Oct-14 A
18-Oct-14 A
31-Oct-14 A
19-Oct-14 A
100%
22-Oct-14 A
23-Oct-14 A
OBRAS TUBERAS
A5650 5900 Fabricacin de Spools
SECTOR 1
AREA 34
3420 Espesamiento de Relaves - Planta de Procesos
OBRAS TUBERAS
A2390 3420 Fabricacin de Spools
OBRAS CIVILES
A2070 3420 Habilitado de Acero de Refuerzo
TRABAJOS EN OBRA
TRABAJO
SECTOR 2
AREA 34
3450 Transporte de Relaves a Planta de Relleno en Pasta
OBRAS CIVILES
CIMENTACIN DE TUBERA
CIMEN
MOVIMIENTO DE TIERRA
MOVI
CANAL RECTANGULAR PARA TUBERA DE TRANSPORTE DE RELAVE (L=200M)
CAN
A27 Cortar terreno para canal de mampostera margen derecha
A27 Vaciado para manpostera de concreto f'c=140kg/cm2 margen derecha
ACC
ACCESO
Y CANAL PARA TUBERA DE TRANSPORTE DE RELAVES (L=400M)
A29 Cortar hasta la Subrasante material suelto c/tractor
PASA
PASARELA
CRUCE DE TUBERA
MOVIMIENTO DE TIERRA
MOV
A28 Excavacin Localizada
Actual Work
Remaining Work
Milestone
Summary
Page 7 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
100%
24-Oct-14 A
27-Oct-14 A
100%
28-Oct-14 A
31-Oct-14 A
100%
27-Oct-14 A
28-Oct-14 A
15
15
88.89%
88.89%
31-Oct-14 A
31-Oct-14 A
15-Nov-14
15-Nov-14
22
22
60.61%
60.61%
31-Oct-14 A
31-Oct-14 A
22-Nov-14
22-Nov-14
148
107
80
17
10
10
58.11%
42.06%
56.25%
52.94%
20%
20%
20-Aug-14 A
30-Sep-14 A
30-Sep-14 A
05-Nov-14 A
12-Nov-14 A
12-Nov-14 A
14-Jan-15
14-Jan-15
18-Dec-14
21-Nov-14
21-Nov-14
21-Nov-14
14-Jan-1
14-Jan-1
18-Dec-14, OBRAS CIVILES
21-Nov-14, MOVIMIENTO DE TIERRAS
21-Nov-14, Plataformado de la Planta de Relleno en Pasta
Corte hasta la Subrasante material suelto c/tractor
OBRA ESTRUCTURAS
OBRAS
A6300 Estructura Metlica Liviana (<=30kg/m)
OBRAS TUBERA
A5730 AREA 3450 Transporte de Relaves a Planta de Relleno en Pasta
SECTOR 3
AREA 50
5000 Generales
OBRAS CIVILES
MOVIMIENTO DE TIERRAS
MOVIM
Plataformado de la Planta de Relleno en Pasta
Plata
A316 Corte hasta la Subrasante material suelto c/tractor
A317 Relleno compactado con material propio c/equipo
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
15-Nov-14, OBRAS ESTRUCTURAS
Estructura Metlica Liviana (<=30kg/m)
0%
19-Nov-14
21-Nov-14
11
4
81.82%
100%
05-Nov-14 A
08-Nov-14 A
15-Nov-14
11-Nov-14 A
66.67%
12-Nov-14 A
14-Nov-14
50%
13-Nov-14 A
14-Nov-14
0%
14-Nov-14
14-Nov-14
100%
10-Nov-14 A
11-Nov-14 A
100%
07-Nov-14 A
11-Nov-14 A
11
81.82%
05-Nov-14 A
15-Nov-14
49
3
2
28.57%
100%
100%
31-Oct-14 A
09-Nov-14 A
10-Nov-14 A
18-Dec-14
11-Nov-14 A
11-Nov-14 A
100%
09-Nov-14 A
11-Nov-14 A
Relleno Localizado
100%
11-Nov-14 A
11-Nov-14 A
12
5
16.67%
40%
12-Nov-14 A
12-Nov-14 A
23-Nov-14
16-Nov-14
CIMEN
CIMENTACIN
PLANTA DE RELLENO EN PASTA
MOVIMIENTO DE TIERRA
MOVI
A325 Excavacin Localizada
0%
17-Nov-14
23-Nov-14
49
24
28.57%
58.33%
31-Oct-14 A
31-Oct-14 A
18-Dec-14
23-Nov-14
0%
24-Nov-14*
30-Nov-14
0%
27-Nov-14
30-Nov-14
Habilitado y Encofrado
0%
15-Dec-14
18-Dec-14
14
0%
01-Dec-14
14-Dec-14
0%
27-Nov-14
30-Nov-14
74
6
3
60.54%
31.58%
60%
30-Sep-14 A
12-Nov-14 A
12-Nov-14 A
13-Dec-14
18-Nov-14
15-Nov-14
0%
15-Nov-14
17-Nov-14
0%
17-Nov-14
18-Nov-14
11
2
0%
0%
17-Nov-14
17-Nov-14
28-Nov-14
19-Nov-14
CIMEN
CIMENTACIN
DE SALA ELCTRICA PREFABRICADA SOLDADA TIPO CONTAINER 1100X
MOVIMIENTO DE TIERRA
MOVI
A510 Excavacin Localizada
0%
19-Nov-14
28-Nov-14
74
11
79.82%
100%
30-Sep-14 A
30-Sep-14 A
13-Dec-14
10-Oct-14 A
0%
28-Nov-14
03-Dec-14
0%
30-Nov-14
04-Dec-14
0%
09-Dec-14
13-Dec-14
Actual Work
Remaining Work
Milestone
Summary
Page 8 of 15
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
Instalacin de Pernos de Anclaje
13-Dec-14, CIMENTACIN DE SALA
18-Nov-14, MOVIMIENTO DE TIERRA
Excavacin Localizada
Relleno Localizado
Eliminacin de Material Excedente (d=2.5km)
28-Nov-14, OBRAS DE CONCRETO SIMPLE
Solado fc=100kg/cm2 (e=10cm) en Zapatas
Solado fc=100kg/cm2 (e=10cm) en Losas
13-Dec-14, OBRAS DE CONCRETO
Habilitado de Acero de Refuerzo fy=4200kg/cm2
Instalacin de Acero de Refuerzo fy=4200kg/cm
Habilitado y Encofrado
Desencofrado y Solaqueado
TASK filter: All Activities
Oracle Corporation
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
0%
05-Dec-14
09-Dec-14
Concreto fy=280kg/cm2
0%
04-Dec-14
05-Dec-14
OBRAS ESTRUCTURAS
A5260 AREA 5000 Generales
17
17
0%
0%
19-Dec-14
19-Dec-14
04-Jan-15
04-Jan-15
04-Jan-15, OBRA
AREA 5000 Gene
OBRAS ELECTRICIDAD
A5500 AREA 5000 Generales
45
45
0%
0%
01-Dec-14
01-Dec-14*
14-Jan-15
14-Jan-15
14-Jan-1
AREA 50
OBRAS INSTRUMENTACIN
A5580 AREA 5000 Generales
2
2
0%
0%
13-Jan-15
13-Jan-15
14-Jan-15
14-Jan-15
14-Jan-1
AREA 50
139
98
98
2
1
61.87%
87.46%
87.46%
100%
100%
20-Aug-14 A
20-Aug-14 A
20-Aug-14 A
12-Nov-14 A
12-Nov-14 A
05-Jan-15
26-Nov-14
26-Nov-14
13-Nov-14 A
12-Nov-14 A
100%
13-Nov-14 A
13-Nov-14 A
Relleno Localizado
100%
13-Nov-14 A
13-Nov-14 A
1
1
0%
0%
14-Nov-14
14-Nov-14
14-Nov-14
14-Nov-14
98
3
88.47%
100%
20-Aug-14 A
20-Aug-14 A
26-Nov-14
23-Aug-14 A
0%
15-Nov-14
18-Nov-14
0%
18-Nov-14
19-Nov-14
0%
25-Nov-14
26-Nov-14
0%
23-Nov-14
24-Nov-14
0%
19-Nov-14
23-Nov-14
OBRAS ESTRUCTURAS
A5270 AREA 5100 Filtracin de Relaves Detoxificados espesados
16
16
0%
0%
26-Nov-14
26-Nov-14*
12-Dec-14
12-Dec-14
OBRAS MECNICAS
A5350 AREA 5100 Filtracin de Relaves Detoxificados espesados
2
2
0%
0%
26-Nov-14
26-Nov-14*
28-Nov-14
28-Nov-14
OBRAS TUBERAS
A5430 AREA 5100 Filtracin de Relaves Detoxificados espesados
65
65
77.95%
77.95%
24-Sep-14 A
24-Sep-14 A
28-Nov-14
28-Nov-14
OBRAS INSTRUMENTACIN
A5590 AREA 5100 Filtracin de Relaves Detoxificados espesados
36
36
0%
0%
01-Dec-14
01-Dec-14*
05-Jan-15
05-Jan-15
05-Jan-15, OBRA
AREA 5100 Filtra
60
11
11
3
1
3.31%
17.65%
17.65%
66.67%
100%
12-Nov-14 A
12-Nov-14 A
12-Nov-14 A
12-Nov-14 A
12-Nov-14 A
11-Jan-15
23-Nov-14
23-Nov-14
14-Nov-14
12-Nov-14 A
50%
13-Nov-14 A
14-Nov-14
Relleno Localizado
Eliminacin de Material Excedente (d=2.5km)
AREA 51
5100 Filtracin de Relaves Detoxificados espesados
OBRAS CIVILES
CIMENTACIN DE EQUIPOS
CIMEN
MOVIMIENTO DE TIERRA
MOVI
A357 Excavacin Localizada
AREA 52
5200 Almacenamiento y Dosificacin de Cemento
OBRAS CIVILES
CIMENTACIN DE ESTRUCTURAS
CIMEN
MOVIMIENTO DE TIERRA
MOVI
A366 Excavacin Localizada
Finish
2014
Sep
Oct
2015
Nov
Dec
Jan
05-Jan-15, AREA
26-Nov-14, OBRAS CIVILES
26-Nov-14, CIMENTACIN DE EQUIPOS
13-Nov-14 A, MOVIMIENTO DE TIERRA
Excavacin Localizada
11-Jan-15, A
23-Nov-14, OBRAS CIVILES
23-Nov-14, CIMENTACIN DE ESTRUCTURAS
14-Nov-14, MOVIMIENTO DE TIERRA
Excavacin Localizada
0%
14-Nov-14
14-Nov-14
1
1
0%
0%
15-Nov-14
15-Nov-14
15-Nov-14
15-Nov-14
10
3
9.68%
30%
13-Nov-14 A
13-Nov-14 A
23-Nov-14
16-Nov-14
30%
13-Nov-14 A
16-Nov-14
0%
16-Nov-14
17-Nov-14
0%
22-Nov-14
23-Nov-14
0%
21-Nov-14
22-Nov-14
Remaining Work
Milestone
Summary
0%
17-Nov-14
21-Nov-14
10
2
9.68%
50%
13-Nov-14 A
13-Nov-14 A
23-Nov-14
14-Nov-14
Page 9 of 15
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
Instalacin de Pernos de Anclaje
23-Nov-14, CIMENTACIN DE EQUIPOS
14-Nov-14, MOVIMIENTO DE TIERRA
TASK filter: All Activities
Oracle Corporation
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
100%
13-Nov-14 A
13-Nov-14 A
0%
14-Nov-14
14-Nov-14
Relleno Localizado
0%
14-Nov-14
14-Nov-14
1
1
0%
0%
15-Nov-14
15-Nov-14
15-Nov-14
15-Nov-14
10
3
9.68%
30%
13-Nov-14 A
13-Nov-14 A
23-Nov-14
16-Nov-14
30%
13-Nov-14 A
16-Nov-14
0%
16-Nov-14
17-Nov-14
0%
22-Nov-14
23-Nov-14
0%
21-Nov-14
22-Nov-14
Finish
2014
Sep
Oct
2015
Nov
Dec
Jan
Excavacin Localizada
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
0%
17-Nov-14
21-Nov-14
OBRAS ESTRUCTURAS
A5280 AREA 5200 Almacenamiento y Dosificacin de Cemento
23
23
0%
0%
23-Nov-14
23-Nov-14
16-Dec-14
16-Dec-14
OBRAS MECNICAS
A5360 AREA 5200 Almacenamiento y Dosificacin de Cemento
26
26
0%
0%
16-Dec-14
16-Dec-14
11-Jan-15
11-Jan-15
11-Jan-15, O
AREA 5200
OBRAS TUBERA
A5440 AREA 5200 Almacenamiento y Dosificacin de Cemento
12
12
0%
0%
16-Dec-14
16-Dec-14
28-Dec-14
28-Dec-14
OBRAS INSTRUMENTACIN
A5600 AREA 5200 Almacenamiento y Dosificacin de Cemento
12
12
0%
0%
28-Dec-14
28-Dec-14
09-Jan-15
09-Jan-15
09-Jan-15, OB
AREA 5200 A
AREA 5300
53 PREPARACIN DE RELLENO EN PASTA
OBRAS MECNICAS
A5340 AREA 5300 Preparacin de Relleno en Pasta
25
10
10
0%
0%
0%
21-Dec-14
21-Dec-14
21-Dec-14
14-Jan-15
30-Dec-14
30-Dec-14
14-Jan-1
30-Dec-14, OBRAS M
AREA 5300 Preparaci
OBRAS INSTRUMENTACIN
A5840 AREA 5300 Preparacin de Relleno en Pasta
15
15
0%
0%
31-Dec-14
31-Dec-14
14-Jan-15
14-Jan-15
14-Jan-1
AREA 53
49
29
24
7
4
0%
0%
0%
0%
0%
14-Nov-14
14-Nov-14
14-Nov-14
14-Nov-14
14-Nov-14
02-Jan-15
13-Dec-14
07-Dec-14
21-Nov-14
17-Nov-14
02-Jan-15, AREA 54
13-Dec-14, OBRAS CIVILES
07-Dec-14, CIMENTACIN DE ESTRUCT
21-Nov-14, MOVIMIENTO DE TIERRA
Excavacin Localizada
0%
18-Nov-14
21-Nov-14
Relleno Localizado
0%
19-Nov-14
21-Nov-14
2
2
0%
0%
21-Nov-14
21-Nov-14
23-Nov-14
23-Nov-14
20
7
0%
0%
18-Nov-14
18-Nov-14
07-Dec-14
24-Nov-14
0%
21-Nov-14
24-Nov-14
0%
25-Nov-14
27-Nov-14
0%
06-Dec-14
07-Dec-14
0%
30-Nov-14
05-Dec-14
0%
28-Nov-14
29-Nov-14
25
7
4
0%
0%
0%
18-Nov-14
18-Nov-14
18-Nov-14
13-Dec-14
24-Nov-14
21-Nov-14
0%
22-Nov-14
24-Nov-14
Relleno Localizado
0%
23-Nov-14
24-Nov-14
2
2
0%
0%
25-Nov-14
25-Nov-14
26-Nov-14
26-Nov-14
22
4
0%
0%
21-Nov-14
21-Nov-14
13-Dec-14
24-Nov-14
AREA 54
5400 Sistema de Bombeo de Pasta
OBRAS CIVILES
CIMENTACIN DE ESTRUCTURAS
CIMEN
MOVIMIENTO DE TIERRA
MOVI
A384 Excavacin Localizada
CIMEN
CIMENTACIN
DE EQUIPOS
MOVIMIENTO DE TIERRA
MOVI
A393 Excavacin Localizada
Actual Work
Remaining Work
Milestone
Summary
Page 10 of 15
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
Instalacin de Pernos de Anclaje
13-Dec-14, CIMENTACIN DE EQUI
24-Nov-14, MOVIMIENTO DE TIERRA
Excavacin Localizada
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
Finish
0%
25-Nov-14
28-Nov-14
0%
28-Nov-14
01-Dec-14
0%
11-Dec-14
13-Dec-14
0%
05-Dec-14
11-Dec-14
2014
Sep
Oct
2015
Nov
Dec
Jan
0%
01-Dec-14
05-Dec-14
OBRAS ESTRUCTURAS
A5290 AREA 5400 Sistema de Bombeo de Pasta
3
3
0%
0%
08-Dec-14
08-Dec-14
10-Dec-14
10-Dec-14
OBRAS MECNICAS
A5370 AREA 5400 Sistema de Bombeo de Pasta
11
11
0%
0%
13-Dec-14
13-Dec-14
24-Dec-14
24-Dec-14
OBRAS INSTRUMENTACIN
A5610 AREA 5400 Sistema de Bombeo de Pasta
9
9
0%
0%
24-Dec-14
24-Dec-14
02-Jan-15
02-Jan-15
02-Jan-15, OBRAS
AREA 5400 Sistema
72
52
42
2
1
37.5%
51.92%
64.29%
50%
100%
18-Oct-14 A
18-Oct-14 A
18-Oct-14 A
13-Nov-14 A
13-Nov-14 A
28-Dec-14
08-Dec-14
28-Nov-14
14-Nov-14
13-Nov-14 A
AREA 56
5600 Sistema de Almacenamiento de agua de planta de relleno en pasta
OBRAS CIVILES
CIMENTACIN DE EQUIPOS ELECTROMECNICOS
CIMEN
Movimiento de Tierra
Movim
A422 Excavacin Localizada
0%
14-Nov-14
14-Nov-14
2
2
0%
0%
14-Nov-14
14-Nov-14
15-Nov-14
15-Nov-14
42
29
64.29%
93.1%
18-Oct-14 A
18-Oct-14 A
28-Nov-14
15-Nov-14
0%
16-Nov-14
19-Nov-14
0%
20-Nov-14
21-Nov-14
0%
27-Nov-14
28-Nov-14
0%
22-Nov-14
26-Nov-14
51
1
1
50.98%
0%
0%
19-Oct-14 A
14-Nov-14
14-Nov-14
08-Dec-14
14-Nov-14
14-Nov-14
0%
14-Nov-14
14-Nov-14
2
2
0%
0%
15-Nov-14
15-Nov-14
16-Nov-14
16-Nov-14
51
29
50.98%
89.66%
19-Oct-14 A
19-Oct-14 A
08-Dec-14
16-Nov-14
12
0%
17-Nov-14
28-Nov-14
0%
29-Nov-14
30-Nov-14
0%
07-Dec-14
08-Dec-14
CIMEN
CIMENTACIN
DE TANQUES
Movimiento de Tierra
Movim
A433 Excavacin Localizada
A435 Eliminacin de Material Excedente (d=2.5km)
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
Habilitado y Encofrado
Desencofrado y Solaqueado
0%
01-Dec-14
06-Dec-14
OBRAS MECNICAS
A5720 AREA 5600 Sistema de Almacenamiento de agua de planta de relleno en pasta
16
16
0%
0%
09-Dec-14
09-Dec-14
24-Dec-14
24-Dec-14
OBRAS TUBERA
A5670 AREA 5600 Sistema de Almacenamiento de Agua de Planta de Relleno en Pasta
53
53
15.09%
15.09%
06-Nov-14 A
06-Nov-14 A
28-Dec-14
28-Dec-14
OBRAS INSTRUMENTACIN
A5850 AREA 5600 Sistema de Almacenamiento de Agua de Planta de Relleno en Pasta
13
13
0%
0%
09-Dec-14
09-Dec-14
21-Dec-14
21-Dec-14
82
82
47
7
3
25.71%
25.71%
44.81%
0%
0%
23-Oct-14 A
23-Oct-14 A
23-Oct-14 A
15-Nov-14
15-Nov-14*
13-Jan-15
13-Jan-15
09-Dec-14
21-Nov-14
17-Nov-14
13-Jan-15
13-Jan-15
09-Dec-14, CIMENTACIN DE EQUIPO
21-Nov-14, Movimiento de Tierra
Excavacin Localizada
0%
18-Nov-14
21-Nov-14
Relleno Localizado
0%
21-Nov-14
21-Nov-14
AREA 57
5700 Espesamiento de relaves Detoxificados
OBRAS CIVILES
CIMENTACIN DE EQUIPOS ELECTROMECNICOS
CIMEN
Movimiento de Tierra
Movim
A444 Excavacin Localizada
Actual Work
Remaining Work
Milestone
Summary
Page 11 of 15
Concreto fy=280kg/cm2
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Obra de Concreto Simple
Obras
A447 Solado fc=100kg/cm2 (e=10cm) en Zapatas
A448 Solado fc=100kg/cm2 (e=10cm) en Losas
Original
Duration
Duration %
Complete
Start
Finish
2
1
0%
0%
22-Nov-14
22-Nov-14
23-Nov-14
22-Nov-14
0%
23-Nov-14
23-Nov-14
47
28
44.81%
75.4%
23-Oct-14 A
23-Oct-14 A
09-Dec-14
20-Nov-14
0%
23-Nov-14
28-Nov-14
0%
29-Nov-14
29-Nov-14
0%
09-Dec-14
09-Dec-14
0%
02-Dec-14
08-Dec-14
2014
Sep
Oct
2015
Nov
Dec
Jan
0%
30-Nov-14
01-Dec-14
82
25
17
25.71%
0%
0%
23-Oct-14 A
18-Nov-14
18-Nov-14
13-Jan-15
13-Dec-14
04-Dec-14
0%
05-Dec-14
09-Dec-14
0%
10-Dec-14
13-Dec-14
4
2
0%
0%
10-Dec-14
10-Dec-14
13-Dec-14
11-Dec-14
CIMEN
CIMENTACIN
DE TANQUES
Movimiento de Tierra
Movim
A455 Excavacin Localizada
0%
12-Dec-14
13-Dec-14
82
42
25.71%
50.27%
23-Oct-14 A
23-Oct-14 A
13-Jan-15
04-Dec-14
13-Jan-15
Habilitado de Acero de Refuerzo fy=4200kg/cm
12
0%
12-Dec-14
23-Dec-14
0%
24-Dec-14
30-Dec-14
0%
08-Jan-15
13-Jan-15
0%
04-Jan-15
07-Jan-15
Habilitado y Encofrado
Desencofr
Concreto fy=28
0%
31-Dec-14
03-Jan-15
Instalacin de Pern
OBRAS ESTRUCTURAS
A5300 AREA 5700 Espesamiento de relaves Detoxificados
11
11
0%
0%
30-Nov-14
30-Nov-14
10-Dec-14
10-Dec-14
OBRAS MECNICAS
A5380 AREA 5700 Espesamiento de relaves Detoxificados
6
6
0%
0%
08-Jan-15
08-Jan-15
13-Jan-15
13-Jan-15
13-Jan-15
AREA 570
OBRAS TUBERA
A5460 AREA 5700 Espesamiento de relaves Detoxificados
32
32
0%
0%
13-Dec-14
13-Dec-14
13-Jan-15
13-Jan-15
13-Jan-15
AREA 570
OBRAS INSTRUMENTACIN
A5620 AREA 5700 Espesamiento de relaves Detoxificados
15
15
0%
0%
24-Dec-14
24-Dec-14
07-Jan-15
07-Jan-15
07-Jan-15, OBR
AREA 5700 Esp
57
46
43
23
10
0%
0%
0%
0%
0%
15-Nov-14
15-Nov-14
18-Nov-14
18-Nov-14
18-Nov-14*
11-Jan-15
30-Dec-14
30-Dec-14
10-Dec-14
27-Nov-14
11-Jan-15, A
30-Dec-14, OBRAS C
30-Dec-14, CIMENTAC
10-Dec-14, Movimiento de Tierra
Excavacin Localizada
13
0%
28-Nov-14
10-Dec-14
Relleno Localizado
0%
07-Dec-14
10-Dec-14
8
3
0%
0%
11-Dec-14
11-Dec-14
18-Dec-14
13-Dec-14
0%
14-Dec-14
18-Dec-14
43
7
0%
0%
18-Nov-14
18-Nov-14*
30-Dec-14
25-Nov-14
0%
14-Dec-14*
20-Dec-14
0%
21-Dec-14
22-Dec-14
0%
29-Dec-14
30-Dec-14
Desencofrado y Solaqu
0%
28-Dec-14
28-Dec-14
Concreto fy=280kg/cm2
0%
23-Dec-14
27-Dec-14
Instalacin de Pernos de A
AREA 58
5800 Preparacin y Servicio de Reactivos
OBRAS CIVILES
CIMENTACIN DE EQUIPOS ELECTROMECNICOS
CIMEN
Movimiento de Tierra
Movim
A466 Excavacin Localizada
Actual Work
Remaining Work
Milestone
Summary
Page 12 of 15
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
33
6
2
0%
0%
0%
15-Nov-14
28-Nov-14
28-Nov-14
18-Dec-14
03-Dec-14
29-Nov-14
0%
30-Nov-14
03-Dec-14
Relleno Localizado
0%
02-Dec-14
03-Dec-14
4
2
0%
0%
30-Nov-14
30-Nov-14
03-Dec-14
01-Dec-14
CIMEN
CIMENTACIN
DE TANQUES
Movimiento de Tierra
Movim
A477 Excavacin Localizada
Finish
2014
Sep
Oct
2015
Nov
Dec
Jan
18-Dec-14, CIMENTACIN DE T
03-Dec-14, Movimiento de Tierra
Excavacin Localizada
0%
02-Dec-14
03-Dec-14
33
10
0%
0%
15-Nov-14
15-Nov-14*
18-Dec-14
25-Nov-14
10
0%
22-Nov-14*
02-Dec-14
0%
03-Dec-14*
05-Dec-14
0%
16-Dec-14*
18-Dec-14
0%
13-Dec-14*
16-Dec-14
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
0%
06-Dec-14*
13-Dec-14
ESTRU
ESTRUCTURAS
A5310 AREA 5800 Preparacin y Servicio de Reactivos
23
23
0%
0%
19-Dec-14
19-Dec-14*
11-Jan-15
11-Jan-15
11-Jan-15, E
AREA 5800
OBRAS MECNICAS
A5390 AREA 5800 Preparacin y Servicio de Reactivos
30
30
0%
0%
02-Dec-14
02-Dec-14*
01-Jan-15
01-Jan-15
01-Jan-15, OBRAS M
AREA 5800 Preparac
OBRAS INSTRUMENTACIN
A5630 AREA 5800 Preparacin y Servicio de Reactivos
18
18
0%
0%
14-Dec-14
14-Dec-14
01-Jan-15
01-Jan-15
01-Jan-15, OBRAS I
AREA 5800 Preparac
75
23
23
3
1
19.51%
64.71%
64.71%
100%
100%
30-Oct-14 A
30-Oct-14 A
30-Oct-14 A
10-Nov-14 A
12-Nov-14 A
13-Jan-15
21-Nov-14
21-Nov-14
13-Nov-14 A
12-Nov-14 A
100%
13-Nov-14 A
13-Nov-14 A
Relleno Localizado
100%
10-Nov-14 A
13-Nov-14 A
2
1
0%
0%
14-Nov-14
14-Nov-14
15-Nov-14
14-Nov-14
AREA 59
5900 Servicios Auxiliares (instrumentacin planta)
OBRAS CIVILES
CIMENTACIN DE EQUIPOS ELECTROMECNICOS
CIMEN
Movimiento de Tierra
Movim
A488 Excavacin Localizada
13-Jan-15
21-Nov-14, OBRAS CIVILES
21-Nov-14, CIMENTACIN DE EQUIPOS ELECTROME
13-Nov-14 A, Movimiento de Tierra
Excavacin Localizada
0%
15-Nov-14
15-Nov-14
23
3
69.12%
100%
30-Oct-14 A
30-Oct-14 A
21-Nov-14
02-Nov-14 A
0%
15-Nov-14
15-Nov-14
0%
16-Nov-14
17-Nov-14
0%
21-Nov-14
21-Nov-14
0%
19-Nov-14
20-Nov-14
0%
18-Nov-14
18-Nov-14
OBRAS ESTRUCTURAS
A5320 AREA 5900 Servicios Auxiliares (instrumentacin planta)
3
3
0%
0%
08-Jan-15
08-Jan-15
11-Jan-15
11-Jan-15
11-Jan-15, O
AREA 5900
OBRAS MECNICAS
A5400 AREA 5900 Servicios Auxiliares (instrumentacin planta)
5
5
0%
0%
08-Jan-15
08-Jan-15
13-Jan-15
13-Jan-15
13-Jan-15
AREA 590
OBRAS INSTRUMENTACIN
A5640 AREA 5900 Servicios Auxiliares (instrumentacin planta)
6
6
0%
0%
26-Dec-14
26-Dec-14
01-Jan-15
01-Jan-15
01-Jan-15, OBRAS I
AREA 5900 Servicios
10
10
0%
0%
05-Jan-15
05-Jan-15
14-Jan-15
14-Jan-15
14-Jan-1
Apoyo al
APOYO A COMISIONAMIENTO
A5740
Apoyo al comisionamiento - electro/instrumentacin
A5860
SECTOR 1
AREA 5500
55 - DISTRIBUCIN DE PASTA A MINA
OBRAS CIVILES
Actual Work
Remaining Work
Milestone
Summary
10
0%
05-Jan-15
14-Jan-15
91
91
52
52.54%
52.54%
92.9%
27-Sep-14 A
27-Sep-14 A
27-Sep-14 A
27-Dec-14
27-Dec-14
17-Nov-14
Page 13 of 15
Apoyo de
27-Dec-14, SECTOR 1
27-Dec-14, AREA 5500 17-Nov-14, OBRAS CIVILES
TASK filter: All Activities
Oracle Corporation
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
Original
Duration
Duration %
Complete
Start
52
52
20
92.9%
92.9%
100%
27-Sep-14 A
27-Sep-14 A
27-Sep-14 A
17-Nov-14
17-Nov-14
16-Oct-14 A
100%
27-Sep-14 A
04-Oct-14 A
100%
01-Oct-14 A
04-Oct-14 A
100%
05-Oct-14 A
08-Oct-14 A
100%
01-Oct-14 A
06-Oct-14 A
100%
28-Sep-14 A
01-Oct-14 A
100%
28-Sep-14 A
04-Oct-14 A
100%
01-Oct-14 A
05-Oct-14 A
100%
27-Sep-14 A
05-Oct-14 A
26.67%
12-Nov-14 A
17-Nov-14
20
81.67%
28-Oct-14 A
17-Nov-14
20
100%
08-Oct-14 A
28-Oct-14 A
14
100%
06-Oct-14 A
20-Oct-14 A
12
100%
05-Oct-14 A
16-Oct-14 A
9
1
100%
100%
17-Oct-14 A
17-Oct-14 A
25-Oct-14 A
17-Oct-14 A
100%
18-Oct-14 A
18-Oct-14 A
100%
18-Oct-14 A
18-Oct-14 A
100%
19-Oct-14 A
19-Oct-14 A
100%
21-Oct-14 A
25-Oct-14 A
100%
20-Oct-14 A
24-Oct-14 A
15
15
0%
0%
12-Dec-14
12-Dec-14*
27-Dec-14
27-Dec-14
43
26
23
3
2
58.14%
96.15%
100%
100%
100%
20-Oct-14 A
20-Oct-14 A
20-Oct-14 A
20-Oct-14 A
20-Oct-14 A
01-Dec-14
14-Nov-14
11-Nov-14 A
22-Oct-14 A
21-Oct-14 A
100%
22-Oct-14 A
22-Oct-14 A
Relleno Localizado
100%
22-Oct-14 A
22-Oct-14 A
1
1
100%
100%
23-Oct-14 A
23-Oct-14 A
23-Oct-14 A
23-Oct-14 A
MOVIM
MOVIMIENTO
DE TIERRAS
ACCESO Y CANAL PARA TUBERA DE TRANSPORTE DE PASTA (L=700M)
ACCE
A402 Cortar hasta la Subrasante material suelto c/tractor
OBRAS TUBERA
A5450 AREA 5500 Distribucin de Pasta a Mina
AREA 34
3420 Espesamiento de Relaves - Planta de Procesos
OBRAS CIVILES
CIMENTACIN DE ESTRUCTURAS
CIMEN
Movimiento de Tierra
Movim
A257 Excavacin Localizada
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
100%
23-Oct-14 A
23-Oct-14 A
20
15
100%
100%
23-Oct-14 A
23-Oct-14 A
11-Nov-14 A
06-Nov-14 A
100%
03-Nov-14 A
06-Nov-14 A
100%
07-Nov-14 A
08-Nov-14 A
100%
11-Nov-14 A
11-Nov-14 A
100%
09-Nov-14 A
10-Nov-14 A
100%
07-Nov-14 A
08-Nov-14 A
12
2
1
100%
100%
100%
22-Oct-14 A
22-Oct-14 A
22-Oct-14 A
02-Nov-14 A
23-Oct-14 A
22-Oct-14 A
100%
23-Oct-14 A
23-Oct-14 A
Relleno Localizado
100%
23-Oct-14 A
23-Oct-14 A
2
1
100%
100%
24-Oct-14 A
24-Oct-14 A
25-Oct-14 A
24-Oct-14 A
CIMEN
CIMENTACIN
DE EQUIPOS MECNICOS
Movimiento de Tierra
Movim
A240 Excavacin Localizada
Actual Work
Remaining Work
Milestone
Summary
Page 14 of 15
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
Instalacin de Pernos de Anclaje
02-Nov-14 A, CIMENTACIN DE EQUIPOS MECNICOS
23-Oct-14 A, Movimiento de Tierra
Excavacin Localizada
OT 006-2014
CRONOGRAMA REV.B
CONSTRUCCION DE PLANTA DE RELLENO EN PASTA
Activity ID
Activity Name
A244 Solado fc=100kg/cm2 (e=10cm) en Losas
Original
Duration
Duration %
Complete
Start
Finish
2014
Sep
2015
Oct
Nov
Dec
Jan
100%
25-Oct-14 A
25-Oct-14 A
11
2
100%
100%
23-Oct-14 A
23-Oct-14 A
02-Nov-14 A
24-Oct-14 A
100%
26-Oct-14 A
28-Oct-14 A
100%
29-Oct-14 A
30-Oct-14 A
100%
02-Nov-14 A
02-Nov-14 A
100%
01-Nov-14 A
01-Nov-14 A
100%
31-Oct-14 A
31-Oct-14 A
24
1
1
95.83%
100%
100%
22-Oct-14 A
22-Oct-14 A
22-Oct-14 A
14-Nov-14
22-Oct-14 A
22-Oct-14 A
100%
22-Oct-14 A
22-Oct-14 A
Relleno Localizado
100%
22-Oct-14 A
22-Oct-14 A
2
1
100%
100%
23-Oct-14 A
23-Oct-14 A
24-Oct-14 A
23-Oct-14 A
CIMEN
CIMENTACIN
DE TANQUES
Movimiento de Tierra
Movim
1
Excavacin Localizada
100%
24-Oct-14 A
24-Oct-14 A
10
2
90%
100%
05-Nov-14 A
07-Nov-14 A
14-Nov-14
08-Nov-14 A
100%
05-Nov-14 A
08-Nov-14 A
100%
09-Nov-14 A
10-Nov-14 A
0%
14-Nov-14
14-Nov-14
100%
12-Nov-14 A
13-Nov-14 A
Habilitado y Encofrado
Desencofrado y Solaqueado
Concreto fy=280kg/cm2
100%
11-Nov-14 A
11-Nov-14 A
OBRAS ESTRUCTURAS
A5250 AREA 3420 Espesamiento de Relaves
12
12
16.67%
16.67%
12-Nov-14 A
12-Nov-14 A
23-Nov-14
23-Nov-14
OBRAS MECNICA
A5330 AREA 3420 Espesamiento de Relaves
8
8
0%
0%
24-Nov-14
24-Nov-14
01-Dec-14
01-Dec-14
OBRAS TUBERAS
A5410 AREA 3420 Espesamiento de Relaves
15
15
0%
0%
17-Nov-14
17-Nov-14
01-Dec-14
01-Dec-14
18
13
0%
0%
01-Dec-14
06-Dec-14
18-Dec-14
18-Dec-14
COBERT
COBERTURA
TR-4 0.5MM PRECOR
A5750
Cobertura TR-4 0.5MM PRECOR
A5760
18
0%
01-Dec-14
18-Dec-14
A6310
0%
07-Dec-14
14-Dec-14
PRUEBA Y PROTOCLOS
PRUEBAS
A6320
Pruebas y Protocolos
30
30
0%
0%
19-Nov-14
19-Nov-14
18-Dec-14
18-Dec-14
PLANOS AS BUILT
A6330
Planos As built
18
18
0%
0%
01-Dec-14
01-Dec-14
18-Dec-14
18-Dec-14
TRABAJO ADICIONALES
TRABAJOS
OBRA CIVIL
C
AREA 5000
5
GENERALES
ORDEN DE CAMBIO N XXXX - AREA SECA & HMEDA
ORDE
A6370 Excavacin Masiva
44
44
44
44
14
63.64%
63.64%
63.64%
63.64%
100%
17-Oct-14 A
17-Oct-14 A
17-Oct-14 A
17-Oct-14 A
17-Oct-14 A
29-Nov-14
29-Nov-14
29-Nov-14
29-Nov-14
30-Oct-14 A
0%
22-Nov-14
29-Nov-14
10
100%
21-Oct-14 A
30-Oct-14 A
100%
08-Nov-14 A
13-Nov-14 A
100%
31-Oct-14 A
07-Nov-14 A
0%
14-Nov-14
21-Nov-14
7
7
100%
100%
19-Oct-14 A
19-Oct-14 A
25-Oct-14 A
25-Oct-14 A
AREA 3450
3
A3370 Desbroce de topsoil (35cm)
Actual Work
Remaining Work
Milestone
Summary
Page 15 of 15